Dubai Engineering Qualifications (DEQ- Exam Questions for Unlimited Grade)11-01-2021

DIGITAL EXAM

1. Density of Steel
a. 6000 kg/m3
b. 5800 kg/m3
c. 7800 kg/m3
d. 8500 kg/m3

2. Density of Concrete
a. 1000 kg/m3
b. 3800 kg/m3
c. 2500 kg/m3
d. 1500 kg/m3

3. If the bolts are located outside the flanges of UC column close to web, then it is a
a. Hinge
b. Fixed
c. Sliding
d. None

4. If the bolts are located between flanges of the UC column far from the web then this
is a
a. Hinge
b. Fixed
c. Sliding
d. None

5. What are the common type of slab/s?


a. Ribbed
b. Flat
c. Solid
d. All of the above

6. Which of the below mentioned are Beam repair technique.


a. Steel Plates
b. All
c. Carbon Fibre Laminates
d. Carbon Fibre rods

7. Proper curing should be continued for


a. 7 days
b. 28 days
c. 14 days
d. 4 days

8. Durability of concrete is
a. It’s the resistance to all surroundings that causes detoriation
b. Decrease in duration required for hardening the concrete
c. Increase in Duration required to harden the concrete
d. Workability of concrete

9. Apex connection is the connection between


a. Beam to Column
b. None
c. 2 Columns
d. 2 Beams
10. The distance between C.G of compression & C.G of tension flanges for a plate girder
is called
a. Effective depth
b. None
c. Overall Depth
d. Clear Depth

11. Minimum distance between Bolts


a. 4dia
b. 3.5dia
c. 1.5dia
d. 2.5dia

12. As per DM circular 141, maximum shoring deflection under design loads as per
following is
a. 10mm if spacing between the shoring and road is less than 5m
b. 20mm if spacing between the shoring and road is less than 5m
c. 30mm if spacing between the shoring and road is less than 5m
d. 50mm if spacing between the shoring and road is less than 5m

13. As per DM circular 141, maximum shoring deflection under design loads as per
following is(QUESTION REPEATED)
a. 10mm if spacing between the shoring and road is less than 5m
b. 20mm if spacing between the shoring and road is less than 5m
c. 30mm if spacing between the shoring and road is less than 5m
d. 50mm if spacing between the shoring and road is less than 5m

14. As per DM circular 141, soldier piles shoring system without tie anchors can be used
when excavation depth does not exceed a distance of
a. 8 m
b. 6 m
c. 4 m
d. 5 m

15. As per DM circular 141, which shoring system is recommended


a. Secant
b. Contiguous
c. None
d. Soldier

16. As per DM circular 141,open excavation angle is


a. 40 degree
b. 60 degree
c. 30 degree
d. 25 degree

17. Difference Between Secant and Contiguous Shoring system


a. Contiguos are over lapped
b. Secant are over lapped
c. Other
d. All secant piles are reinforced piles
18. What below a water tight shoring system
a. Contiguous
b. Soldier
c. Other
d. Secant

19. Percentage of piles should be tested by static load test is


a. 100%
b. 1%
c. 10%
d. 5%

20. Minimum diameter of micro Pile is


a. 250mm
b. 300mm
c. 400mm
d. 500mm

21. The level of shoring RC piles for the road should be below G.L by
a. 1 m
b. 1.5 m
c. 2 m
d. None

22. Liquefaction induced effect is/are


a. Loss of bearing capacity for shallow foundation
b. All the answer
c. Land sliding
d. Loss of lateral soil stiffness
e. Settlement

23. Select Bending Moment & Shear Force Diagram For following (3 Questions were
asked)

Simple beam with


Simple beam with
Distributed load
Concentrated load

fixed cantliver beam


fixed cantliver beam with
with Concentrated load
Distributed load