Development (B-09) S.No. Name of Activity Start Date Finish Date No. of Days
Development (B-09) S.No. Name of Activity Start Date Finish Date No. of Days
Development (B-09) S.No. Name of Activity Start Date Finish Date No. of Days
A Sewer line
1 Sewer line Excavation 11-Jan-23 16-Jan-23 6
2 sewer pipe line 12-Jan-23 17-Jan-23 6
3 sewer line Manhole Pcc and Brick work 13-Jan-23 20-Jan-23 8
4 Manhole Plaster and Cover Fixing 15-Jan-23 21-Jan-23 7
5 Sewer line conection 22-Jan-23 25-Jan-23 4
B Cable Trench
1 Cable Trench Excavation 20-Jan-23 24-Jan-23 5
2 Cable Trench PCC and Brick work 24-Jan-23 29-Jan-23 6
3 Cable Trench root conection (Hume pipe) 29-Jan-23 2-Feb-23 5
4 Cable laying 28-Feb-23 5-Mar-23 6
C Drain work
1 Drain Excavation 22-Jan-23 29-Jan-23 8
2 Drain Pcc and Brick work 28-Jan-23 5-Feb-23 9
3 Drain conection 6-Feb-23 10-Feb-23 5
4 Drain cover Fixing 4-Mar-23 10-Mar-23 7
F Parking Work
1 Parking solling 30-Jan-23 7-Feb-23 9
2 Parking Layout and Pcc 31-Jan-23 8-Feb-23 9
G Road work
1 WBM road 15'' 9-Feb-23 19-Feb-23 11
2 Paver fixing 20-Feb-23 2-Mar-23 11
3 Plinth Protaction 3-Mar-23 9-Mar-23 7
PART - B (Tower B 09 Back and RHS)
B Sewer line
1 Sewer line Excavation 12-Feb-23 16-Feb-23 5
2 sewer pipe line 16-Feb-23 21-Feb-23 6
3 sewer line Chamber Pcc and Brick work 21-Feb-23 2-Mar-23 10
4 Manhole Plaster and Cover Fixing 2-Mar-23 5-Mar-23 4
5 sewer line conection 6-Mar-23 10-Mar-23 5
C Drain work
1 Drain Excavation 14-Feb-23 18-Feb-23 5
2 Drain Pcc and Brick work 17-Feb-23 25-Feb-23 9
3 Drain conection 25-Feb-23 27-Feb-23 3
Drain cover Fixing 28-Feb-23 1-Mar-23 2
F Parking Work
1 Parking solling 22-Feb-23 3-Mar-23 10
2 Parking Layout and Pcc 26-Feb-23 5-Mar-23 8
G Road work
1 WBM road 15'' 27-Feb-23 9-Mar-23 11
2 Paver fixing 10-Mar-23 18-Mar-23 9
3 Plinth Protaction 19-Mar-23 25-Mar-23 7