Development (B-09) S.No. Name of Activity Start Date Finish Date No. of Days

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

Development (B-09)

S.No. Name of Activity Start Date Finish Date No. of Days


PART - A (Tower B 09 Front and LHS)

1 De-scaffolding 8-Jan-23 17-Jan-23 10


2 Excavation 16-Jan-23 18-Jan-23 3

A Sewer line
1 Sewer line Excavation 11-Jan-23 16-Jan-23 6
2 sewer pipe line 12-Jan-23 17-Jan-23 6
3 sewer line Manhole Pcc and Brick work 13-Jan-23 20-Jan-23 8
4 Manhole Plaster and Cover Fixing 15-Jan-23 21-Jan-23 7
5 Sewer line conection 22-Jan-23 25-Jan-23 4

B Cable Trench
1 Cable Trench Excavation 20-Jan-23 24-Jan-23 5
2 Cable Trench PCC and Brick work 24-Jan-23 29-Jan-23 6
3 Cable Trench root conection (Hume pipe) 29-Jan-23 2-Feb-23 5
4 Cable laying 28-Feb-23 5-Mar-23 6

C Drain work
1 Drain Excavation 22-Jan-23 29-Jan-23 8
2 Drain Pcc and Brick work 28-Jan-23 5-Feb-23 9
3 Drain conection 6-Feb-23 10-Feb-23 5
4 Drain cover Fixing 4-Mar-23 10-Mar-23 7

D Street Light 10-Feb-23 18-Feb-23 9

E Pcc and Kerb Stone 24-Jan-23 5-Feb-23 13

F Parking Work
1 Parking solling 30-Jan-23 7-Feb-23 9
2 Parking Layout and Pcc 31-Jan-23 8-Feb-23 9

G Road work
1 WBM road 15'' 9-Feb-23 19-Feb-23 11
2 Paver fixing 20-Feb-23 2-Mar-23 11
3 Plinth Protaction 3-Mar-23 9-Mar-23 7
PART - B (Tower B 09 Back and RHS)

1 De-scaffolding 30-Jan-23 10-Feb-23 12


2 Excavation 11-Feb-23 13-Feb-23 3

A Rain water Harvesting 25-Jan-23 13-Feb-23 20

B Sewer line
1 Sewer line Excavation 12-Feb-23 16-Feb-23 5
2 sewer pipe line 16-Feb-23 21-Feb-23 6
3 sewer line Chamber Pcc and Brick work 21-Feb-23 2-Mar-23 10
4 Manhole Plaster and Cover Fixing 2-Mar-23 5-Mar-23 4
5 sewer line conection 6-Mar-23 10-Mar-23 5

C Drain work
1 Drain Excavation 14-Feb-23 18-Feb-23 5
2 Drain Pcc and Brick work 17-Feb-23 25-Feb-23 9
3 Drain conection 25-Feb-23 27-Feb-23 3
Drain cover Fixing 28-Feb-23 1-Mar-23 2

D Street Light 25-Feb-23 2-Mar-23 6

E Pcc and Corve Stone 22-Feb-23 27-Feb-23 6

F Parking Work
1 Parking solling 22-Feb-23 3-Mar-23 10
2 Parking Layout and Pcc 26-Feb-23 5-Mar-23 8

G Road work
1 WBM road 15'' 27-Feb-23 9-Mar-23 11
2 Paver fixing 10-Mar-23 18-Mar-23 9
3 Plinth Protaction 19-Mar-23 25-Mar-23 7