WEEKLY REVIEW – 11.1.

19

Lakshmi Project -Work Schedule - for completion

S.No. Nature of Work Date of completion Remarks

1 Second floor Blockwork to be completed 24.11.18 Completed

Second floor - Inner beam and column plastering to be


2 8.12.18 Completed
completed

3 External column and beam plastering work - all sides 2.12.18 Progress

4 Firsrt floor - Toilet wall tiles laying work 30.11.18 Completed

5 Second floor Toilet wall - Tiles laying work 15.12.18

6 First floor - General flooring tiles laying work 8.12.18


Second floor - General flooring tiles laying work to be
7 22.12.18
completed
8 Terrace floor - weathering course work 15.12.18 Progress

9 First floor to Terrace floor - steel staircase work 22.12.18 Progress

Plumbing outer and Terrace Ringmain system pipe line


10 31.12.18 Progress
work

11 Compound wall construction completion work 31.12.18

12 Inner and External painting work 15.1.19 Progress

Parapet - Glass railing and 2nd floor open Terrace


13 22.1.19
pergola work

14 CP and Sanitary fitting fixing work 30.1.19

15 Paving block laying work 30.1.19