WEEKLY REVIEW - 11.1.

19
MANDHAGINI PROJECT SCHEDULE (PILE FOUNDATION)

Duration
Sl.No Description Start Date Finish Date Remarks
in days
PROJECT START DATE / EARTH WORK
1 02-Jan-18
EXCAVATION

2 FOUNDATION 68 02-Jan-18 10-Mar-18 Completed

3 STRUCTURE
ROOF
Stilt floor 20 11-Mar-18 30-Mar-18 Completed

First floor 20 31-Mar-18 19-Apr-18 Completed

Second floor 20 19-Apr-18 08-May-18 Completed

Third floor 20 09-May-18 28-May-18 Completed

Fourth Floor 20 29-May-18 17-Jun-18 Completed

4 SUB STRUCTURE
POROTHERM BLOCK WORK &
BRICKWORK
First floor 20 09-May-18 28-May-18 Completed

Second floor 20 29-May-18 17-Jun-18 Completed

Third floor 20 18-Jun-18 07-Jul-18 Completed


Fourth Floor 20 08-Jul-18 27-Jul-18 Completed

5 CEILING & INTERNAL PLASTERING

First floor 21 03-Jul-18 23-Jul-18 Completed

Second floor 21 24-Jul-18 13-Aug-18 Completed


MANDHAGINI PROJECT SCHEDULE (PILE FOUNDATION)

Duration
Sl.No Description Start Date Finish Date Remarks
in days

Third floor 21 14-Aug-18 03-Sep-18 Completed

Fourth Floor 21 04-Sep-18 24-Sep-18 Completed

6 INTERNAL PLUMBING WORK 58 14-Aug-18 10-Oct-18 Completed

7 WATERPROOFING 60 28-Aug-18 26-Oct-18 Completed

Putty work
8 INTERNAL PAINTING 60 16-Aug-18 14-Oct-18
completed

EXTERNAL PLASTERING & ELEVATION


9 60 15-Sep-18 13-Nov-18 Completed
WORK

TOILET WALL DADO & GENERAL


10 62 15-Oct-18 15-Dec-18 Progress
FLOORING TILE

11 ELECTRICAL WORK 50 15-Nov-18 03-Jan-19

PAVING BLOCK LAYING,COMPOUND Septic tank


12 WALL WORKS, FINAL PAINTING AND 62 15-Dec-18 15-Feb-19 work
FINISHING WORKS progress

13 HANDING OVER 28-Feb-19