EP Wells Operations Summary Report


Well: LEKHWAIR-688
Project: Lekhwair Site: LEKHWAIR-688 Rig Name No: Z_Historical PDO Rig 68/,
Wireline Unit 9/
Event: Drilling only Actual Start Date: 12/23/2009 End Date: 2/2/2010 Original Spud Date: 12/27/2009
Active Datum: DFE @116.14m (above Mean Sea Level) UWI (SAP PSN#): 410000009655
Date Time Hrs Phase Op WSOP Depth Description
Start-End Code (m)
12/23/2009 12:00 - 18:00 6.00 RM PMO 0.00 Rig down rig miscellaneous equipments.Moved mud tanks, poor boy degaser, Choke
& kill manifold, BOP and rig equipments to new location AS-OP-WF23New.Lowered
dog house and sub structure @ 17:30 hrs. R/dn drawworks.
18:00 - 00:00 6.00 RM NOA 0.00 Waiting on day light.

12/24/2009 00:00 - 06:00 6.00 RM NOA 0.00 Waiting on day light.


06:00 - 18:00 12.00 RM PMO 0.00 Prepare to lower mast.Lowered mast at 0830Hrs.Moved and spot mini camp.Moved
and spot rig camp.Moved mast at (1530hrs),substructure,draw works,mud pumps
generator,diesel tank and all miscellenous rig equipments.All equipment on location
at 1800 Hrs.
18:00 - 06:00 RM NOA 0.00 Waiting on day light.

12/25/2009 00:00 - 06:00 6.00 RM NOA 0.00 Waiting on day light.


06:00 - 00:00 18.00 RM RUD 0.00 Spot substructure and mast.Spot generator, mud pumps,koomy unit,dog house and
other miscellenous rig equipments.Prepared to raise mast.Raised mast at 1700
Hrs.R/up draw works and raised substructure at 2030 hrs and dog house
2045Hrs.R/up mud pumps and mud tanks.

12/26/2009 00:00 - 00:00 24.00 RM RUD 0.00 Connected electrical cables with draw works,mud pump and other rig
equipments.Spot poor boy degesser.M/up mud pump HP lines and stand
pipe.Connected fast end of drill line with draw works.Released travelling block from
its shelf.R/up ladders,inclined walk,catwalk and pipe racks.M/up swivel kelly and
kelly hose.Repaired air winches.Welded conductor.R/up rig floor equipments.
Remarks : GWDC forklift not working.

12/27/2009 00:00 - 02:00 2.00 RM RUD 0.00 M/up flow line.M/up PDO water line with the conductor for filling well in case of
loss.
02:00 - 08:00 6.00 RM REP 0.00 During testing of HP lines found leakage from stand pipe connection.Repaired the
same.Test the HP line,kelly etc at 21000kpa.O.K.
08:00 - 10:30 2.50 RM RUD 0.00 M/up 17 1/2 bit and BHA and spud well of location AS-OP-WF29 at 1030 Hrs.
10:30 - 00:00 13.50 D17 DRR 120.00 Drill 17 1/2" hole from 09 m to 120m.Pump high vis in every two connection.No loss.
For initial 50m took return from celler pit to shale shaker to avoid communication with
rat hole.After 50m taking return directly from flow line to shale shaker.
Drilling Parameters :
WOB : 2-4-16 Ton RPM :40- 80-100
Flow : 1.4-1.8m-3.0m3/min
SPP : 1.4 - 2-5.4Mpa.
Drilling Time : 9.50Hrs Connection Time : 3.00Hrs
Reaming and hi vis time : 1.00Hrs

12/28/2009 00:00 - 00:00 24.00 D17 DRR 500.00 Drill 17 1/2" hole from 120 m to 500m.Pump high vis every two connection.No loss.
Taking return directly from flow line to shale shaker.
Drilling Parameters :
WOB : 20-25 Ton RPM :100 Flow : 3.4m3/min
SPP : 9.80pa.
Drilling Time : 18.25Hrs Connection Time : 3.75Hrs
Reaming and hi vis time : 2.00Hrs
ROP : 20.82 m/hr.

4/11/2011 12:24:16PM Report Version: 3.2.901 1


PDO

EP Wells Operations Summary Report


Well: LEKHWAIR-688
Project: Lekhwair Site: LEKHWAIR-688 Rig Name No: Z_Historical PDO Rig 68/,
Wireline Unit 9/
Event: Drilling only Actual Start Date: 12/23/2009 End Date: 2/2/2010 Original Spud Date: 12/27/2009
Active Datum: DFE @116.14m (above Mean Sea Level) UWI (SAP PSN#): 410000009655
Date Time Hrs Phase Op WSOP Depth Description
Start-End Code (m)
12/29/2009 00:00 - 02:30 2.50 D17 DRM 516.00 Drill 17 1/2" hole from 500 m to 516m.(Section TD confirmed by town
geologist).Pump high vis every two connection.No loss.
Taking return directly from flow line to shale shaker.
Drilling Parameters :
WOB : 20-25 Ton RPM :100 Flow : 3.4m3/min
SPP : 9.80pa.
Drilling Time : 1.50Hrs Connection Time : 0.50Hrs
Reaming and hi vis time : 0.50Hrs
ROP : 10.67 m/hr.
02:30 - 03:00 0.50 D17 PCD 516.00 Circulation to clean hole prior to wiper trip
03:00 - 12:00 9.00 D17 DRT 516.00 Pooh.During pooh observed overpull more then 20 ton at 327m,320m ,278m and
265m.Try to clear tight spot by reciprocation,but could not.Clear all tight spots with
reaming.
Also tight spot from 260m to 221m cleared by reciprocation.Pooh to surface.From
221m to surface well was smooth.After pooh found the stablizer and bit is balled
up.
12:00 - 15:45 3.75 D17 DRT 516.00 Cleaned bit and stablizer and rih to 500m.Wash down to bottom.During rih no held
up.
15:45 - 19:00 3.25 D17 PCD 516.00 Circulation to clean hole.Pump high vis two time to clean hole.Observed lot of cutting
on shale shaker.Spot 20m3 High vis at bottom.Drop EMMS.
19:00 - 00:00 5.00 D17 DRT 516.00 Pooh to 30m.L/dn of 8" drill collar in progress.

12/30/2009 00:00 - 01:30 1.50 D17 DRT 516.00 Pooh and L/dn 8" drill collar and shock sub.Recover EMMS.Max angle 1.10 degree at
331m.B/off Bit .
Dull Grade : 1-1-WT-A-E-I-NO-TD.
01:30 - 03:30 2.00 C17 RUD 516.00 R/dn flow line.Cut and l/dn conductor.
03:30 - 04:30 1.00 C17 RUD 516.00 R/D hyd tong. R/U casing tong & make arrangment to run
13 3/8" casing
04:30 - 07:00 2.50 C17 CLR 516.00 PJSM.During M/Up float shoe found all thread of 13 3/8" casing pipe not going inside
float shoe(Last 4-5 thread left).Decided to change shoe.Arranged shoe from GWDC
lekhwair store.L/Dn casing joint with float shoe.
07:00 - 15:00 8.00 C17 CLR 516.00 M/Up float shoe and float collar (1 joint above shoe).Check
floats.O.K.Rih 38 joints of 13 3/8" 54.5 # NT55HE BTC casing to 504m.Wash down
to bottom(514.70).Fill casing every joint.
Shoe at 514.70m Float coller at 500.60m.
15:00 - 17:00 2.00 C17 CLR 516.00 Circulate 120% casing content.Meanwhile install base clamp
17:00 - 18:00 1.00 C17 CLC 516.00 R/dn circulating head.M/up cementing head ( Top plug loaded) and cementing
lines.PJSM
18:00 - 20:30 2.50 C17 CLC 516.00 Flush cementing lines and P/T cementing lines at 15000KPA.O.K. Pump 5 m3 fresh
water followed by 60m3(75% OH excess) Pozzmix slurry of 16.1 kpa/m.Drop top
plug.Displace cement with 1.5m3 fresh water followed by 38.95m3 WSW.Bump
plug (pressure before bump 4200 kpa).Tested casing at 10500kpa.Hold pressure
for 10
min.Pressure holding.Bleed off.Float holding.
During displacement observed 10m3 cement return to surface.
Shoe at 514.70 Float coller at 500.60m
20:30 - 22:00 1.50 C17 CLC 516.00 L/D cement lines,cement head and Landing joint.
22:00 - 00:00 2.00 PR BPR 516.00 N/Up of BOP stack in progress.

12/31/2009 00:00 - 09:30 9.50 PR BPR 516.00 N/U BOP stack . Tightened the BOP & CHH joint.M/up bell nipple and flow line.N/up kill
line ,chokeline and choke manifold .

4/11/2011 12:24:16PM Report Version: 3.2.901 2


PDO

EP Wells Operations Summary Report


Well: LEKHWAIR-688
Project: Lekhwair Site: LEKHWAIR-688 Rig Name No: Z_Historical PDO Rig 68/,
Wireline Unit 9/
Event: Drilling only Actual Start Date: 12/23/2009 End Date: 2/2/2010 Original Spud Date: 12/27/2009
Active Datum: DFE @116.14m (above Mean Sea Level) UWI (SAP PSN#): 410000009655
Date Time Hrs Phase Op WSOP Depth Description
Start-End Code (m)
09:30 - 12:00 2.50 PR BPT 516.00 Mup test plug.Function test BOP from both remote panel and from koomy
unit.Pressure Test BOP connection of BOP stack with CHH and choke manifold at
3500/21000 KPA.O.K.Pressure test of BOP stack was already done on stump.L/Dn
test plug.Install wear bushing
12:00 - 13:00 1.00 PR SAF 516.00 Super tuesday safety meeting with both crew.Safety meeting could no be done on
tuesday as tuesday was crew change day.
13:00 - 16:30 3.50 PR PRE 516.00 L/Dn test plug.M/up Cup tester and test SOV at 15000kpa.L/dn cup tester .Install
wear bushing
16:30 - 17:00 0.50 D12 SAF 516.00 H2S drill.Response good.
17:00 - 21:30 4.50 D12 DRT 516.00 M/up 12 1/4" bit ,motor and m/up MWD tool .Shallow test MWD tool and motor.O.K.
21:30 - 00:00 2.50 D12 DRT 516.00 M/up BHA and rih to 249m.

1/1/2010 00:00 - 02:15 2.25 D12 DRT 516.00 Continue rih tag cement at 499.50m.Test casing at 10500Kpa.O.K.
02:15 - 04:00 1.75 D12 DRT 516.00 L/dn 9 joints of 5" drill pipe.
04:00 - 06:30 2.50 D12 DCM 516.00 Drill top plug and float collar.Drill and cleared cement in shoe track to 514m.Drill float
shoe and clear pocket to 516m.Record GR from 491m.
06:30 - 15:30 9.00 D12 DRM 610.00 Drill 12 1/4" hole from 516m to 610m.Pump high vis
every two connection.No loss.
15:30 - 16:00 0.50 D12 SAF 610.00 Fire and First aid drill.
16:00 - 00:00 8.00 D12 DRM 705.00 Drill 12 1/4" hole from 610m to 705m.Pump high vis
every two connection.No loss.
Drilling Parameters :
WOB : 10-12 Ton Surface RPM : 50 Flow : 2.80m3/min
SPP on bottom / off bottom: 14.50 / 13.5 Mpa.
Drilling Time : 12 Hrs Connection Time : 2.00Hrs
Reaming and hi vis time : 2.00Hrs. Survey time : 1.00
Rop : 15.75/hr.

1/2/2010 00:00 - 00:00 24.00 D12 DRM 927.00 Drill 12 1/4" hole from 610m to 927m.Pump high vis
every two connection.No loss.
Drilling Parameters :
WOB : 10-14Ton Surface RPM : 50 Flow : 2.85m3/min
SPP on bottom / off bottom: 15.20 / 14.20 Mpa.
Drilling Time : 17.50 Hrs Connection Time : 2.25Hrs
Reaming and hi vis time : 2.25Hrs. Survey time : 2.00
Rop : 12.69/hr.

1/3/2010 00:00 - 19:00 19.00 D12 DRM 1,114.00 Drill 12 1/4" hole from 927m to 1114m.Pump high vis
every two connection.KOP 935m.
No loss till 1049m.Loss started at 1049m.Loss rate 5m3/hr.It gone to 20m3/hr and
then reduced to 10m3/hr at 1080m.Again total loss encountered at 1103m.Filling
hole with naith line,but no return to surface.
Drilling Parameters :
WOB : 10-14Ton Surface RPM : 0-50 Flow : 2.85m3/min
SPP on bottom / off bottom: 15.20 / 14.20 Mpa.
19:00 - 21:30 2.50 D12 PCD 1,114.00 As total loss observed started filling hole with one Naith line.The other naith line is
filling mud tanks.Also one pump in water pit filling the tanks,but one pump and naith
line is not able to keep water level in mud tanks for drilling.M/up another pump in
water pit.Meanwhile circulation with low pump rate(1.7m3/min).No return.

4/11/2011 12:24:16PM Report Version: 3.2.901 3


PDO

EP Wells Operations Summary Report


Well: LEKHWAIR-688
Project: Lekhwair Site: LEKHWAIR-688 Rig Name No: Z_Historical PDO Rig 68/,
Wireline Unit 9/
Event: Drilling only Actual Start Date: 12/23/2009 End Date: 2/2/2010 Original Spud Date: 12/27/2009
Active Datum: DFE @116.14m (above Mean Sea Level) UWI (SAP PSN#): 410000009655
Date Time Hrs Phase Op WSOP Depth Description
Start-End Code (m)
21:30 - 00:00 2.50 D12 DRM 1,125.00 Drill 12 1/4" hole from 1114m to 1125m.Pump high vis
every connection.Total loss.Filling hole with naith line,but no return to surface.
Drilling Parameters :
WOB : 10-14Ton Surface RPM : 0-50 Flow : 2.65m3/min
SPP on bottom / off bottom: 11.30 / 10.50 Mpa.
Drilling Time : 15.75 Hrs Connection Time : 2.00Hrs
Reaming and hi vis time : 1.75 Hrs. Survey time : 2.00
Rop : 12.57/hr.

1/4/2010 00:00 - 00:00 24.00 D12 DRM 1,181.00 Drill 12 1/4" hole from 1125m to 1181m.Pump high vis
every connection.Total loss.Filling hole with naith line,but no return to surface.
Drilling Parameters :
WOB : 12-16Ton Surface RPM : 0-50 Flow : 2.80m3/min
SPP on bottom / off bottom: 14.50 / 13.50 Mpa.
Drilling Time : 19.50 Hrs Connection Time : 1.00Hrs
Reaming and hi vis time : 1.50 Hrs. Survey time : 2.00
Rop : 2.87/hr.

1/5/2010 00:00 - 02:30 2.50 D12 DRM 1,192.00 Drill 12 1/4" hole from 1181m to 1192m.Section TD confirmed by town
geologist.Pump high vis every connection.Total loss.Filling hole with naith line,but no
return to surface.
Drilling Parameters :
WOB : 12-16Ton Surface RPM : 0-50 Flow : 2.80m3/min
SPP on bottom / off bottom: 14.50 / 13.50 Mpa.
Drilling Time : 2.00 Hrs Connection Time : 0.00Hrs
Reaming and hi vis time : 0.25 Hrs. Survey time : 0.25
Rop : 5.5/hr.
02:30 - 04:00 1.50 D12 PCD 1,192.00 Circulation to clean hole.Spot 15m3 high vis at bottom.
04:00 - 12:00 8.00 D12 DRT 1,192.00 Pooh and .l/dn MWD tools and mud motor.B/off bit.
Bit IADC Dull : 7-8-BT-A-F-1-NO-TD
12:00 - 13:00 1.00 D12 SAF 1,192.00 Super Tuesday safety meeting with both crew.
13:00 - 14:30 1.50 C12 RUD 1,192.00 Retrieve wear bushing.R/Up 9 5/8" casing handling tools
14:30 - 00:00 9.50 C12 CLR 1,192.00 Pjsm.M/U shoe track & check floats.Ok.
RIH 9 5/8" CSG K55 40# LTC to 1132m.
-Fill every 3-4joints.
-Break circulation at 13 3/8" casing shoe.

1/6/2010 00:00 - 02:00 2.00 C12 CLR 1,192.00 Continue rih 9 5/8" CSG K55 40# LTC to 1179m.Wash down to bottom 1191 m.
-Fill every 3-4joints.
-Break circulation at 13 3/8" casing shoe.
-Shoe at 1191m. F/C at 1171.11m.L/C at 1176.89m
MSIPC at 492.70m
02:00 - 03:00 1.00 C12 PCD 1,192.00 Circulated 120% of casing content
03:00 - 04:30 1.50 C12 RUD 1,192.00 R/Up cement head and cementing lines.PJSM
04:30 - 07:00 2.50 C12 CLC 1,192.00 Flush lines and pressure test cement lines at 21000kpa.O.K.
First Stage Cementaion :
Pumped 5 m3 fresh water as pre flush. Pumped 22.70 m3(100% exceess of open
hole) Lead cement slurry of 13.8 kpa/m & 18.10 m3 ( 100%excess of open hole) tail
slurry of 18.6 kpa/m.Dropped plug .Displaced cement slurry with 1.5 m3 fresh water
& continue displacement with 45.10m3 of WSW.Bumped plug at 2.8Mpa.Continue to
increase pressure in stages to 12Mpa & inflated ACP.Further increased pressure to
15 mpa & tested casing at 15 Mpa.OK.Released pressure Float holding.OK.

4/11/2011 12:24:16PM Report Version: 3.2.901 4


PDO

EP Wells Operations Summary Report


Well: LEKHWAIR-688
Project: Lekhwair Site: LEKHWAIR-688 Rig Name No: Z_Historical PDO Rig 68/,
Wireline Unit 9/
Event: Drilling only Actual Start Date: 12/23/2009 End Date: 2/2/2010 Original Spud Date: 12/27/2009
Active Datum: DFE @116.14m (above Mean Sea Level) UWI (SAP PSN#): 410000009655
Date Time Hrs Phase Op WSOP Depth Description
Start-End Code (m)
07:00 - 08:00 1.00 C12 CLC 1,192.00 Dropped opening Bomb. Port open at 8Mpa.Established circulation through stage
tool.Circulate out annulus volume.No cement return to surface
08:00 - 08:15 0.25 C12 RUD 1,192.00 M/up cementing line for seconed stage cementaion.PJSM.Flush cementing lines and
tested at 21000kpa.O.K
08:15 - 09:30 1.25 C12 CLC 1,192.00 Second Stage cementation :
Pumped 5 m3 fresh water as pre flush. Pumped 18.26m3 cement slurry of 13.8
kpa/m.Dropped second stage
plug Displaced cement with 1.5M3 fresh water & continue
displacement with 17.99m3 of WSW.Bumped plug at
3.2Mpa.Continue increase pressure in stages to 8.5mpa to close the stage tool
ports.Ports closed.Increased pressure to 15Mpa and tested casing at 15
Mpa.OK.Released pressure .Float holding.
1.5m3 cement return to surface
09:30 - 11:30 2.00 C12 RUD 1,192.00 L/dn cementing lines and cementing head.Flush BOP.Dropped casing slip from rig
floor thru BOP.Set Slip.
11:30 - 16:00 4.50 PR PRE 1,192.00 N/Dn BOP.Final cut and redress stump.Install THS.Tested
THS slip and seal at 8500KPa.O.K
16:00 - 23:30 7.50 PR BPR 1,192.00 N/up BOP.Function test BOP.O.K.M/up test plug and pressure test BOP at
3500/21000Kpa.O.K. L/Dn Test plug.M/Up cup tester and pressure test SOV at
15000Kpa.O.K.Install wear bushing
23:30 - 00:00 0.50 D09 DRT 1,192.00 Prepare to m/up 8 1/2" hole BHA.M/up 8 1/2" bit with mud motor.

1/7/2010 00:00 - 05:30 5.50 D09 DRT 1,192.00 M/up 8 1/2" bit,Mud motor and FEWD tools.Shallow test.O.K.PJSM.Install source in
FEWD tools
05:30 - 08:30 3.00 D09 DRT 1,192.00 Rih to 491m.Taged stage tool at 491m.
08:30 - 09:15 0.75 D09 DCM 1,192.00 Drill stage tool.Reamed stage tool area three times
09:15 - 12:00 2.75 D09 DRT 1,192.00 Continue rih to 1176m.Tag landing collar at 1176m.Pressure test casing at
15Mpa.O.K.
12:00 - 17:00 5.00 D09 DCM 1,192.00 Drill plugs and landing collar.Clear shoe track to 1190m.Pump high vis during drilling
shoe track.Record gamma ray during drilling shoe track.
Drilling parameter:
WOB : 1-2 Ton Surface Rpm : 25 Flow : 1.8m3
SPP : 7.6Mpa
17:00 - 18:45 1.75 D09 PCD 1,192.00 Prepare to change over to XED polymer mud.Changeover to XCD polymer mud.
18:45 - 19:30 0.75 D09 DCM 1,192.00 Drill float shoe and clear pocket to 1192m
19:30 - 00:00 4.50 D09 DRM 1,232.00 Drill 8 1/2" hole from 1192 m to 1232m.
Drilling Parameter.
WOB : 8-12Kdan Rpm : 40 Flow : 1.8-1.9m3/min
SPP on/off bottom : 8.5/7.9Mpa
Drilling Time : 3.00 Hrs Connection Time : 0.50Hrs
Survey Time : 0.50Hr Reaming and high Vis Time : 0.50hrs
ROP : 13.33m/Hr
Slide : 30% Rotating : 70%
No Loss.

1/8/2010 00:00 - 09:15 9.25 D09 DRM 1,282.00 Drill 8 1/2" hole from 1232 m to 1282m.
Drilling Parameter.
WOB : 8-12Kdan Rpm : 40 Flow : 1.8-1.9m3/min
SPP on/off bottom : 8.5/7.9Mpa
09:15 - 10:15 1.00 D09 PCD 1,282.00 Send data to duty geologist to confirm next plan.Meanwhile circulation.As per
geologist drill ahead to 1325m and then log well Run #1 SFT-GR on TLC

4/11/2011 12:24:16PM Report Version: 3.2.901 5


PDO

EP Wells Operations Summary Report


Well: LEKHWAIR-688
Project: Lekhwair Site: LEKHWAIR-688 Rig Name No: Z_Historical PDO Rig 68/,
Wireline Unit 9/
Event: Drilling only Actual Start Date: 12/23/2009 End Date: 2/2/2010 Original Spud Date: 12/27/2009
Active Datum: DFE @116.14m (above Mean Sea Level) UWI (SAP PSN#): 410000009655
Date Time Hrs Phase Op WSOP Depth Description
Start-End Code (m)
10:15 - 18:45 8.50 D09 DRM 1,325.00 Drill 8 1/2" hole from 1282m to 1325m.Section TD confirmed by town duty geologist.
Drilling Parameter.
WOB : 10-12Kdan Rpm : 45 Flow : 1.8-1.9m3/min
SPP on/off bottom : 10.50 / 9.5Mpa
Drilling Time : 13.50 Hrs Connection Time : 1.25Hrs
Survey Time : 1.50Hr Reaming and high Vis Time : 1.75hrs
ROP : 6.89m/Hr
No Loss.
18:45 - 20:00 1.25 D09 PCD 1,325.00 Circulation to clean hole.Flow check.Well static.
20:00 - 21:45 1.75 D09 DRT 1,325.00 Wiper trip to 9 5/8" casing shoe(1191m).
21:45 - 23:15 1.50 D09 PCD 1,325.00 Circulation to clean prior to pooh for logging.
23:15 - 00:00 0.75 D09 DRT 1,325.00 Pooh to 9 5/8" casing shoe(1191m)

1/9/2010 00:00 - 04:00 4.00 D09 DRT 1,325.00 Pooh to surface.


04:00 - 09:00 5.00 D09 DRT 1,325.00 Pjsm.Retrieve source.Down load memory data..L/dn FEWD tools and mud
motor.B/off bit.
IADC Dull grade of Bit : 1-6-BT-A-E-I-PB-TD
09:00 - 11:30 2.50 D09 ELO RUD 1,325.00 Clean the rig floor and prepare CNLC tools for Run #1
SFT-GR.Pjsm.
11:30 - 16:30 5.00 D09 ELO ELE 1,325.00 Rih Run #1 SFT-GR CNLC tool with drill pipe to 1095m.
During rih drifted drill pipes,filled mud every 10 stand and break circulation every 20
stands
16:30 - 18:00 1.50 D09 ELO RUD 1,325.00 Circulation prior to latch tool.R/up CNLC sheaves
18:00 - 19:00 1.00 D09 ELO RUD 1,325.00 M/up SES.Rih.Pump down head and latch tool.Latch sucessful.Test SFT-GR
tool.O.K.
19:00 - 00:00 5.00 D09 ELO ELE 1,325.00 Pjsm.Rih with SFT-GR tool to first point.Record pressure at one point at 1208.9m.

1/10/2010 00:00 - 08:30 8.50 D09 ELO ELE 1,325.00 Run #1 SFT-GR.Record presure at 7 points(From 109.77m to 1238.74m.Total 8
points).Send data to town reservoir engineer to confirm quality of data.
08:30 - 09:00 0.50 D09 ELO NOA 1,325.00 Waiting for reservoir engineer confirmation.
09:00 - 11:15 2.25 D09 ELO RUD 1,325.00 Pooh to 1095m.Unlatch tool.R/dn SES and CNLC sheaves.
11:15 - 15:30 4.25 D09 ELO RUD 1,325.00 Contiue pooh.CNLC tool on surface.L/dn CNLC logging tool.
15:30 - 17:15 1.75 C09 RUD 1,325.00 Prepare to rih 7" liner.PJSM.
17:15 - 20:00 2.75 C09 CLR 1,325.00 M/up float shoe joint and float coller,landing coller joint of 7" 23# K-55 LTC(Shoe
float collar and landing joint bakerlocked at BOT workshop) .Check floats.O.K.Rih 13
joints of 7" #23 K-55 LTC liner(Total joints 15).M/up HF3 packer and HF3
hanger.Circulate for 10 min.
Record up / Down wt 13t
20:00 - 00:00 4.00 C09 CLR 1,325.00 Pjsm.Rih liner with running string to 1211m.
-Fill every 5 stands.
-Drifted string prior to RIH.
-Break circulation at shoe

1/11/2010 00:00 - 01:15 1.25 C09 CLR 1,325.00 continue rih 7" liner with running string to 1308m.Observed held up at 1308m
01:15 - 04:30 3.25 C09 CLR 1,325.00 Wash down to bottom(1324m).Circulate 120%
casing & string contents.Record up wt 52t and down wt 44t. Turn string 2 times to
the left & set HF-3 hanger with 15 Ton slack off weight. Turn string 12 turns to the
right & release running tool. Pick up string . Observed 04 Ton
weight loss (liner weight). Slack off 10Ton for cement job.
7" Liner Shoe at 1324m.Landing coller at 1313.17m and Liner Hanger Top 1144.03m.

4/11/2011 12:24:16PM Report Version: 3.2.901 6


PDO

EP Wells Operations Summary Report


Well: LEKHWAIR-688
Project: Lekhwair Site: LEKHWAIR-688 Rig Name No: Z_Historical PDO Rig 68/,
Wireline Unit 9/
Event: Drilling only Actual Start Date: 12/23/2009 End Date: 2/2/2010 Original Spud Date: 12/27/2009
Active Datum: DFE @116.14m (above Mean Sea Level) UWI (SAP PSN#): 410000009655
Date Time Hrs Phase Op WSOP Depth Description
Start-End Code (m)
04:30 - 06:00 1.50 C09 CSR 1,325.00 R/up cement lines.PJSM.
Pump 3 m3 fresh water P/T cement lines to 21000
kpa. Ok.
- Mix & pump 5.5m3 of G cement slury 18.6kpa (50% Excess) .Released dart.
-Pump 1.0 m3 fresh water as post flush.
-Displace cement by 11.70m3 of mud
-Shear Wiper plug at 2200 KPA.
-Bump plug At 3200Kpa & raised pressure to 15000kpa.Test liner at
15000kpa.OK.Bleed off.Float holding
06:00 - 08:00 2.00 C09 CSR 1,325.00 P/up 2m and slack off 25Ton to set Hyflow-3 packer.Apply pressure of 3000kpa
and swab out.Pressure dropped to zero.Circulate& dump 1.5m3 of neat cement
slurry
-P/T liner lap at 15000kpa.O.K
- L/d cement head.
08:00 - 00:00 16.00 D06 DRT 1,325.00 POOH and laydown 5 " D/p.L/Dn of drill collar in progress.

1/12/2010 00:00 - 01:00 1.00 D06 DRT 1,325.00 Cont L/D extra 2 stands of 5" DP from mast.
01:00 - 07:00 6.00 D06 BPR 1,325.00 HPJSM.Changed upper 5" Pipe ram with variable ram.
07:00 - 12:30 5.50 D06 BPT 1,325.00 Pressure test Annular @ 2 & 10.5 Mpa & variable ram & blind ram @ 2 & 21
Mpa,with test plug & cup tester.
12:30 - 19:00 6.50 D06 DRT 1,325.00 Pick up new 6 1/8" bit & m/u with slick bore & Lobe.Adjusted the bend angle to
1.5d..Shallow test motor ok. Added FEWD tools & tested ok. HPJSM.Loaded RA
source.
19:00 - 00:00 5.00 D06 DRT 1,325.00 COnt RIH 3.5" HWDPs & DPs in singles,from 35 m to 421m conts.

1/13/2010 00:00 - 08:15 8.25 D06 DRT 1,325.00 Cont RIH from 421 m to 1144m. Reciprocated with circulation while entering inside
7" liner.No obstructions.Cont RIH from 1144m to 1270m.Tagged cement @ 1270.
08:15 - 09:15 1.00 D06 PRE 1,325.00 Circulated btms up.Pr test liner @ 15 mpa.OK.
09:15 - 12:00 2.75 D06 PCD 1,325.00 Washed down & recorded GR inside 7" liner from 1270m to 1307m.
12:00 - 13:00 1.00 D06 SAF 1,325.00 Conducted super tuesday work stoppage safety meeting.
13:00 - 16:30 3.50 D06 DCP 1,325.00 Cont drill cement,top plug,L/C,F/C & cement & cleared up to 1323 m.WOB-1-23
kdn,rpm-10+,f/rate-0.85 m3/min,STPP-9.6/11 mpa.
16:30 - 18:15 1.75 D06 PCD 1,325.00 Pump 6 me of LV & HV at tandem. changed over to new 10.8 kpa/m XCD polymer
mud.Drill out c/s & pocket to 1325m,with previous parameters.
18:15 - 18:30 0.25 D06 PCD 1,325.00 Recorded SCR of both MPs @ 20 & 30 SPM.F/check OK.
18:30 - 00:00 5.50 D06 DRM 1,364.00 Drill new 6 1/8" hole from 1325 m to 1364 m.

WOB- 5-10 ,RPM-50+, F/rate--0.85 m3/min,STPP- 9.6-10.4 Kpa,Drill hrs- 3.75, Av


ROP--10.4 m/hr.

1/14/2010 00:00 - 01:00 1.00 D06 NOA 1,364.00 Sent data to town geologist.waiting for his instructions.
01:00 - 04:00 3.00 D06 DRM 1,387.00 Cont slide/rotary drill 6 1/8" hole from 1364 m to 1387 m.
WOB-8-10kdn,rpm-50+,f/rate-0.85 m3/min.STPP-9-11 kpa.
04:00 - 05:00 1.00 D06 NOA 1,387.00 Sent data to town geologist.waiting for his instructions.
05:00 - 22:00 17.00 D06 DRM 1,529.00 Cont slide/rotary drill 6 1/8" hole from 1387 m to 1529 m.
WOB-8-10kdn,rpm-50+,f/rate-0.85 m3/min.STPP-9-11 kpa.
Pumped HV each joint.
Drill hrs--12.75
Mtg-- 165
AV ROP-- 29.41

4/11/2011 12:24:16PM Report Version: 3.2.901 7


PDO

EP Wells Operations Summary Report


Well: LEKHWAIR-688
Project: Lekhwair Site: LEKHWAIR-688 Rig Name No: Z_Historical PDO Rig 68/,
Wireline Unit 9/
Event: Drilling only Actual Start Date: 12/23/2009 End Date: 2/2/2010 Original Spud Date: 12/27/2009
Active Datum: DFE @116.14m (above Mean Sea Level) UWI (SAP PSN#): 410000009655
Date Time Hrs Phase Op WSOP Depth Description
Start-End Code (m)
22:00 - 00:00 2.00 D06 WCP 1,529.00 While drilling at 1529 m,observed a lot of foam coming .flow check positive.Shut in
the well.Waited for 30 mins. NO SIDP & SICP.Decided to circulate through choke
.MW in-10.9,MW out 10.4Kpa/m.
After one cycle MW in-10.9kpa/m,But MW out- full with foam.
Arrangement to arrange more chemicals from base camp.
Mean while circulation though choke conts.

1/15/2010 00:00 - 01:30 1.50 D06 WCP 1,529.00 Cont circulation through choke with increased MW of 11.15 Kpa/m .After one
cycle,the return MW foam only.After shut in the well Dp & Csg pr read zero.
01:30 - 14:00 12.50 D06 WCP 1,529.00 Shut in the well.Monitored pressures.Decided to prepare kill mud .Arranged
chemicals from base camp.From 0215 hrs,the SIDP & DICP both recorded
2400kpa.After 0500hrs It start increasing from 2400kpa to 3500kpa.
While heavy kill mud preperation was going on. SICP in the range of 3-5 mpa.
14:00 - 14:30 0.50 D06 SAF 1,529.00 HPJSM with whole of crew.Touched upon operational safety matters.
14:30 - 16:30 2.00 D06 WCP 1,529.00 Pumped 3 m3 of water spacer ahead.Pumped 12.56 kpa/m mud using drillers
method.Dumped the foamed mud in w/pit.
By the end of one full cycle +300extra strokes,the return mud was 12.16 kpa/m.
Shut in the well.
Observed 2800kpa pressure on both DP & casing Pr gauges. Monitored for 30 mins
& it starts increasing .
16:30 - 00:00 7.50 D06 WCP 1,529.00 Decided to inctrease the MW from 12.16 kopa to 12.56 kpa/m again.Mean got
approval of bleeding the well L-595.
Mean while keep pumping 10 strokes of mus in the string in well shut condition,to
avoid nozzle plugging& maintaining the BHP constant.
M/A for bleeding L-595.

1/16/2010 00:00 - 10:00 10.00 D06 WCP 1,529.00 Cont to mix new kill mud of 12.65 kpa/m.Also bled off well Wi L-595,from 8 to 1
mpa.Mean while pumped 10 stks of mud every 30 mins to keep nozzles clean.
10:00 - 12:00 2.00 D06 WCP 1,529.00 HPJSM.Start well killing with 12.65 kpa/m mud.End of cycle.Shut in the well.Mud
return last was 12.00 kpa/m.
12:00 - 16:45 4.75 D06 WCP 1,529.00 Decided to bled of L-626 & L-649 also.Mean mixed the sueface mud & made it
homogenous of 12.75 kpa/m.
16:45 - 19:00 2.25 D06 WCP 1,529.00 HPJSM.Start killing again with 12.75 kpa/m mud.Return mud Weight from 10.79
kpa-12.36 kpa/m.Shut in the well.Observed DP P -3 mpa,CP-4.5 mpa. No rise further
in 15 mins. Bled off trap pressure.Both gauge rea zero.Conducted flow check.Well
was flowing very marginally.Decided to open the well & work on string.Opened the
well circulated & worked on string free.Observed mud return.
19:00 - 20:00 1.00 D06 WCP 1,529.00 During btms up circulation,observed return mud again gas cut & MW fall from 12.36
kpa/m ro 10.79 kpa/m. Stopped mud pump. Shut in the well. Well flowing with 1.5
m3/hr. SHut in the well.
20:00 - 00:00 4.00 D06 WCP 1,529.00 Observed the pressure on Dp & Casing gauges.Stablised SIDPP-2000 kpa
,SICp-2000kpa.Asked GWDC mud dept to prepare kill mud of 13.5+ kpa/m,after
discussion with WE & FSWE.
Mud mixing on.
Mean while no further rise in pressures.
Pumped 10 stks every 1 hr,by holding csg pr constant& during waiting maintained
SIDPP constant.

1/17/2010 00:00 - 12:30 12.50 D06 WCP 1,529.00 Cont to prepare new KMW of 13.7 kpa/m.Mean while keep pumping 10 stks through
choke & maintained BHP constant.
SIDPP--2100 kpa & SICP--2100kpa.NO rise in thes pressures.

4/11/2011 12:24:16PM Report Version: 3.2.901 8


PDO

EP Wells Operations Summary Report


Well: LEKHWAIR-688
Project: Lekhwair Site: LEKHWAIR-688 Rig Name No: Z_Historical PDO Rig 68/,
Wireline Unit 9/
Event: Drilling only Actual Start Date: 12/23/2009 End Date: 2/2/2010 Original Spud Date: 12/27/2009
Active Datum: DFE @116.14m (above Mean Sea Level) UWI (SAP PSN#): 410000009655
Date Time Hrs Phase Op WSOP Depth Description
Start-End Code (m)
12:30 - 15:30 3.00 D06 WCP 1,529.00 HPJSM.Try to kill well with 13.73 kpa/m mud.Return mud Wt varied from 12.36--9.81,
13.34 kpa/m.After pumping full cycle stks+ 300 extra.Shut in the well.
Just after shut in DPP-3.2 mpa,Cp--3.1 mpa.Observed for 30 mins. No change.Bled
off .Both pressures read zero.
Flow check through choke .Well flowing with 1.5 m3/hr.
Shut in again.
15:30 - 17:15 1.75 D06 WCP 1,529.00 Observed pressures. No change.
17:15 - 18:00 0.75 D06 WCP 1,529.00 Opend choke for flow check . Well still flowing 1.0m3/hr.Observed for 30 mins.
Shut in the well again.
18:00 - 20:15 2.25 D06 WCP 1,529.00 Well remained shut in.observed no rise in pressure.
20:15 - 21:30 1.25 D06 WCP 1,529.00 Flow check through choke .starts from 1.0 m3/hr ,0.9, 0.6, 0.7, 0.9,1.0, 1.5
m3/hr.recorded every 5 mins.After 30 mins flow tends to increase.Shut in the choke
.
21:30 - 22:30 1.00 D06 WCP 1,529.00 No pressure on both gauges.Consulted WE & convinced GWDC rig team to try
reciprocate string once.
22:30 - 23:15 0.75 D06 WCP 1,529.00 No pressure.Checked flow through. starts with 01.0 m3/hr. Opened BOP. Started
MP & worked on string. Found string stuck. Jarred up 8-9 times & string became
free. Hada nice rotation & circulated for 900 stks.Returned MW starts to fall from
13.43 kpa/m to 11.18 kpa/m,very quickly.
Shut in the well again.
23:15 - 00:00 0.75 D06 WCP 1,529.00 Observed pressures .Discussed WE & followed ,program of pumping mud every
one hr ,10 stks.

1/18/2010 00:00 - 08:00 8.00 D06 WCP 1,529.00 Observed both pr zero.Pumped 10 stks every 1 hr. Conducted f/check every 2
hr.Flow rate-1.5 m3/hr to 0.5 m3/hr.
08:00 - 11:00 3.00 D06 REP 1,529.00 While pumping 10 stks,found manual choke got stuck.Opened & found it's lock
screw slipped.
Repaired the same.
Mean while received more chemicals from Fahud. kept making more Kmud of 13.7
kpa/m.
11:00 - 12:30 1.50 D06 SWF 1,529.00 Dp & CP both read zero. Flow check 1.0m3/hr -0.7 m3/hr.
Opened the BOP Found the string stuck.Circulated btms up & jarred up the string
.Mud return became foamy. stopped circulation & shut in the well.Shut in the well
with Annular BOP with low closing pressure.
12:30 - 14:00 1.50 D06 WCP 1,529.00 Waited for kill mud to be ready. Recorded both pr zero.Kept string moving every 15
mins with annular closed.
14:00 - 15:45 1.75 D06 WCP 1,529.00 HPJSM.Circulated with 13.65 kpa/m mud .The manual choke became
defunct,towards the end of cycle.Shut in the well.Kept string moving with annular
BOP closed.
15:45 - 16:30 0.75 D06 WCP 1,529.00 Recorded both pr zero. opened choke & found flow 0.6 m3/hr & dying slowly.
16:30 - 20:30 4.00 D06 SWF 1,529.00 Opened Annular BOP .Found string stuck again.Work on string ,with circulation for 2
cycle to make mud homgenous without addition of weighin material on fly.&
recording in & out mud weight same-13.43 kpa/m.
20:30 - 21:00 0.50 D06 INT 1,529.00 Conducted extended flow check for 30 mins. Well static.
21:00 - 23:00 2.00 D06 SWF 1,529.00 Called on GWDC cement team for conducting mud acid job.
mean while worked on string to releas .No success.
23:00 - 00:00 1.00 D06 SAF 1,529.00 Discussed the acid job plan with cement engineer & agreeed to a plan.
Connected cementing lines.HPJSM.

4/11/2011 12:24:16PM Report Version: 3.2.901 9


PDO

EP Wells Operations Summary Report


Well: LEKHWAIR-688
Project: Lekhwair Site: LEKHWAIR-688 Rig Name No: Z_Historical PDO Rig 68/,
Wireline Unit 9/
Event: Drilling only Actual Start Date: 12/23/2009 End Date: 2/2/2010 Original Spud Date: 12/27/2009
Active Datum: DFE @116.14m (above Mean Sea Level) UWI (SAP PSN#): 410000009655
Date Time Hrs Phase Op WSOP Depth Description
Start-End Code (m)
1/19/2010 00:00 - 02:00 2.00 D06 SWF 1,529.00 HPJSM.Pumped 1.5 m3 of fresh water. Pr test c/lines @ 21 Mpa. OK. Pumped 1/0
m3 of fresh water ahead. Pumped 4.5 m3 of 15% HCl.Pumped 1.0 m3 of fresh
water after.
Changed over to mud line. Pumped & displaced acid by 3.3 m3 of mud.( Under
displaced by 2 m3).
Worked on string. Freed the string.
02:00 - 05:30 3.50 D06 PCD 1,529.00 Displaced acid out of system & circulated through choke & dumped in w/pit.COnt to
circulate .Just after acid was out,no return for 10 mins,& slowly start getting mud
return of low mw.Kept on circulating till in & out MW is homogenous 13.03
kpa/m.SHut in & found no pressures.COnducted flow check.neg.
05:30 - 07:00 1.50 D06 DRT 1,529.00 POOH from 1529 m to 1320m.Inside 7" c/s.Filled hole with mud.Added kelly.
07:00 - 17:30 10.50 D06 PCD 1,529.00 Start circulation to condition the mud under the guidance of UIK FHD.In & out MW in
normal mud balance--12.55 kpa/m & by pressrised mud balance --13.93 kpa/m.
17:30 - 18:30 1.00 D06 INT 1,529.00 Conducted extended flow check.Found a flow of 0.6 m3/hr to 0.72 m3/hr & not
decreasing.Consulted UIK & FSWE & suggested to use barite .Resumed circulation
for adding barite.
18:30 - 21:30 3.00 D06 PCD 1,529.00 Added 7.5 T barite,but return mud not getting weighed up .In MW-12.55 kp/m & out
mud 12.45 kpa/m.Consulted FSWE. decided to prepare a new barite mud of 14
kpa,& keep ciculation with existing mud.
21:30 - 00:00 2.50 D06 WCP 1,529.00 Dumped contaminated mud from 2 tanks.Kept circulation on with existing mud.
Preperation for new Barite mud conts.

1/20/2010 00:00 - 08:15 8.25 D06 PCD 1,529.00 Cont to circulate with existing CaCl2 mud,mean while kept mixing Barite mud of 14
kpa/m.
08:15 - 10:25 2.17 D06 WCP 1,529.00 Try to kill the well with 14 kpa/m Barite mud.After end of cycle.shut in the well.No
pressure .
10:25 - 11:15 0.83 D06 WCP 1,529.00 Flow check 0.7 m3/hr to 0.36m3/hr.
Decided to increase the MW to 14.5 kpa/m & circulate open hole .
11:15 - 15:00 3.75 D06 PCD 1,529.00 Increased MW uniform to 14.5 kpa/m.
15:00 - 16:00 1.00 D06 INT 1,529.00 Conducted flow check .Negative.
16:00 - 00:00 8.00 D06 DRT 1,529.00 Advised to POOH to change MWD tools & RIH to resume drilling with same mud.Rig's
Hydraulic tong not working.
POOH from 1324 m to 1238m. Pumped slug & cont POOH from 1238 m to
surface.Maintained accurate trip sheet.well static.HPJSM & retreived RA source.L/D
M/Motor. Downloaded memory data.

1/21/2010 00:00 - 14:00 14.00 D06 DRT 1,529.00 Cont to record memopry data .L/D M/Motor & bit.Pick up new bit & m/motor .Shallow
test m/motor Ok.Added FEWD tools & shallow test ok. HPJSM Loaded RA
source.Changed jar with new one.
Conducted BOP function test.
break circulation at 7" c/s.Cont RIH to 1529 m. Added kelly & established circulation.
14:00 - 16:00 2.00 D06 PCD 1,529.00 Circulated one cycle.MW in-14.5 out 14.2 kpa/m.Even out mud 14.5 kpa/m.
16:00 - 00:00 8.00 D06 DRM 1,601.00 Resume slide/rotary drill ahead from 1529 m to 1601 m.
WOB-8-10Kdn,RPM-60+,F/rate-0.85 m3/min.STPP-13.4-15 mpa.
Drill hrs--6
Mtg--72
Av ROP---12.0m/hr.

1/22/2010 00:00 - 10:00 10.00 D06 DRM 1,672.00 Cont slide/rotary drill 6 1/8" hole ahead from 1601 m to 1672
m.WOB-8-10kdn,RPM-50+,F/rate-0.85 m3/min,STPP-15 mpa.
10:00 - 14:30 4.50 D06 DRT 1,672.00 Circulated out Btms up. F/check .Neg.POOH 12 singles of 5" DP.RIH 12 singles of 6
1/2" DC.Added kelly.

4/11/2011 12:24:16PM Report Version: 3.2.901 10


PDO

EP Wells Operations Summary Report


Well: LEKHWAIR-688
Project: Lekhwair Site: LEKHWAIR-688 Rig Name No: Z_Historical PDO Rig 68/,
Wireline Unit 9/
Event: Drilling only Actual Start Date: 12/23/2009 End Date: 2/2/2010 Original Spud Date: 12/27/2009
Active Datum: DFE @116.14m (above Mean Sea Level) UWI (SAP PSN#): 410000009655
Date Time Hrs Phase Op WSOP Depth Description
Start-End Code (m)
14:30 - 00:00 9.50 D06 DRM 1,736.00 Cont drill ahead from 1672 m to 1736 m.
WOB-6-11 kdn,RPM-60+,F/rate-0.85 m,3/min,STPP-15-17 mpa.
Drill hrs--8
Mtg--135
AvROP--16.85 m/hr

1/23/2010 00:00 - 00:00 24.00 D06 DRT 1,915.00 Cont slide/rotary drill 6 1/8" hole from 1736 m to 1915 m.
WOB--8-10kdn,RPM-50-60+,F/rate--0.85 m3/min,STPP-15300 kpa.
Drill hrs---17
Mtg--179
Av ROP--10.52

1/24/2010 00:00 - 01:15 1.25 D06 DRM 1,925.00 Cont slide/rotary drill & geo steer 6 1/8" hole from 1915 m to 1925 m.
WOB-8-10kdn,RPM-50-60+,F/rate-0.85 m3/min,STPP-16-17.5 mpa,Pumped LV & HV
at tandem every joint.
01:15 - 03:00 1.75 D06 REP 1,925.00 Repaired MP by charging Nitrigen in Dampner.
03:00 - 00:00 21.00 D06 DRM 2,059.00 Cont slide/rotary drill & geo steer 6 1/8" hole from 1925 m to2059 m.Prepare for final
circulation at mid night for POOH & change bit due to hrs on Bit.
WOB-8-10kdn,RPM-50-60+,F/rate-0.85 m3/min,STPP-16-17.5 mpa,Pumped LV & HV
at tandem every joint.
Drill Hrs-- 11
Mtg-- 144
Av ROP-- 13.09

1/25/2010 00:00 - 04:30 4.50 D06 PCD 2,059.00 Started final circulation prior to POOH for bit change. Homogenise the mud In & Out
MW 14.5 kpa/m.Flow check,neg.Slug the string.
04:30 - 15:00 10.50 D06 DRT 2,059.00 POOH from 2059 m to 50m.Hole condition ok.
15:00 - 16:00 1.00 D06 DRT 2,059.00 HPJSM. Retreived RA source from FEWD tool.
16:00 - 17:30 1.50 D06 DRT 2,059.00 Changed m/motor & FEWD pulser.
17:30 - 21:30 4.00 D06 DRT 2,059.00 M/U new bit & m/motor.Shallow test.Ok.Shallow test FEWD tools ok. HPJSm.Loaded
RA source.
21:30 - 00:00 2.50 D06 DRT 2,059.00 Cont to RIH to 660m.Conts.

1/26/2010 00:00 - 07:00 7.00 D06 DRT 2,059.00 Cont RIH from 660 m to 2029 m.Established circulation.
07:00 - 08:30 1.50 D06 PCD 2,059.00 Wash down from 2029 m to 2059 m,.Observed return MW reduced from 14.5 kpa/m
to 10.79 kpa/m.
08:30 - 09:30 1.00 D06 DRM 2,059.00 No signal.Repaired MP #2.Pre charge pressure restored.
09:30 - 00:00 14.50 D06 DRM 2,135.00 Cont slide/rotary drill ahead from 2059 m to 2135 m.WOB-8-10
kdn,RPM-50+,F/rate-0.85 m3/min,STPP- 16000 Kpa.
Drill hrs---10
Mtg--76
AvROP- 7.6 m/hr.

1/27/2010 00:00 - 03:00 3.00 D06 DRM 2,145.00 Cont Slide/rotary drill 6 1/8" hole from 2135 m to 2145m.
WOB-8-10kdn,RPM-50+,F/rate-0.825 m3/min,STPP-16.0mpa
Observed a seepage loss @ 1.5 m3/hr.Start reducing MW from 14.5 kpa/m to
14.0kpa/m.
03:00 - 04:30 1.50 D06 REP 2,145.00 Poor detection from tools.repaired Mp.

4/11/2011 12:24:16PM Report Version: 3.2.901 11


PDO

EP Wells Operations Summary Report


Well: LEKHWAIR-688
Project: Lekhwair Site: LEKHWAIR-688 Rig Name No: Z_Historical PDO Rig 68/,
Wireline Unit 9/
Event: Drilling only Actual Start Date: 12/23/2009 End Date: 2/2/2010 Original Spud Date: 12/27/2009
Active Datum: DFE @116.14m (above Mean Sea Level) UWI (SAP PSN#): 410000009655
Date Time Hrs Phase Op WSOP Depth Description
Start-End Code (m)
04:30 - 17:00 12.50 D06 DRM 2,203.00 Cont slide/rotary drill ahead from 2145 m to 2203m.Well TD.
WOB-8-10kdn,RPM-50+,F/rate-0.825 m3/min,STPP-16.0mpa.
Reduced MW from 14 kpa/m to 13.6 kpa/m.Well shows seapage loss @ 0.7
m3/hr.Pumped LV & HV at tandem every single.
Drill hrs--10.5
Mtg-- 68
Av ROP-- 6.47 m/hr.
17:00 - 21:00 4.00 D06 PCD 2,203.00 Conditioned & circulated mud prior to POOH.Pumped LV & HV at tandem.
21:00 - 00:00 3.00 D06 DRT 2,203.00 F/check Neg.Slug the string. POOH from 2203 m to 1662m.Conts.

1/28/2010 00:00 - 10:30 10.50 D06 DRT 2,203.00 Cont POOH from 1662 m to 35 m. HPJSM,Retreived RA source.L/D all sperrysun
tools.,jar & Bit.Cleared rig floor.
10:30 - 12:00 1.50 E06 RUD 2,203.00 R/U for TLC logging. HPJSM.
12:00 - 19:00 7.00 E06 DRT 2,203.00 Tested logging tools.Lowered them in well.Connected XO & added 3 1/2" DP on top
& RIH to 1263m.Drifted each stands & RIH slow as desired by Logging engineer.
19:00 - 20:30 1.50 E06 PCD 2,203.00 Circualtion for one cycle for conditoning.F/rate-0.85 m3/min,STPP-5 mpa.
20:30 - 00:00 3.50 E06 PCD 2,203.00 M/U SES.hanged the sheeve.Pumped down the latch ,but no success.Increased the
flow rate to 1 m3/min.try again to latch.Conts.

1/29/2010 00:00 - 18:15 18.25 E06 ELO INT 2,203.00 Successfully latched the tool in second attempt.Cont RIH from 1213 m to 2190m.
Recorded pressure in given 23 points.
pressure MWE 15 kpa/m.
Sent data to town for QC.
18:15 - 20:30 2.25 E06 DRT 2,203.00 Waiting for confirmation from town.Mean while slowly start POOH .
20:30 - 00:00 3.50 E06 ELO INT 2,203.00 Town asset team asked for repeat log at 3 points.Recorded at one point.Recording
of second repeat point conts.

1/30/2010 00:00 - 02:00 2.00 E06 ELO INT 2,203.00 Finished recording pressure in 2 & 3rd repeat points.Sent data to town .
02:00 - 05:00 3.00 E06 RUD 2,203.00 Unlatched the tool & reeved the logging cable.R/D sheeve.
05:00 - 06:00 1.00 E06 PCD 2,203.00 Circulated for gel breaking.
06:00 - 07:00 1.00 E06 DRT 2,203.00 POOH & L/D tubalars from 1265 m to 1065m.
07:00 - 18:00 11.00 E06 REP 2,203.00 Noticed some damage in the drilling line.Removed all the damaged line .Changed the
whole of drilling line with new spool.Tested twin stop device .OK.
18:00 - 00:00 6.00 E06 DRT 2,203.00 Cont POOh & l/D tubalars from 1065 m to 20m.R/U for L/D TLC SFTT logging tools .

1/31/2010 00:00 - 01:00 1.00 E06 ELO RUD 2,203.00 L/D TLC logging tool.
01:00 - 18:30 17.50 CU DRT 2,203.00 Cont L/D all excess Dp & DC stands from derrick.
Joints found to be too tight.
18:30 - 22:00 3.50 CU DRT 2,203.00 L/D kelly & rat hole conductor.Rtreived w/bushing,Jet clean WH. Function test BP.
22:00 - 23:00 1.00 IC RUD 2,203.00 R/U for lowering 3 1/2" completion.HPJSM.
23:00 - 00:00 1.00 IC LSR 2,203.00 Lowered POP with 4 tubings.Filled every tubing initially.Lowered 3 1/2" completion
to 40m.Conts.

2/1/2010 00:00 - 13:00 13.00 IC LSR 2,203.00 Cont to lower 3 1/2" completion with GLM with Dummy valves ,POP XN nipple &
SSDfrom 40m to 1323.5m.Filled tubing every 5 jonts.
13:00 - 18:00 5.00 IC LSR 2,203.00 Recorded up & Down weights.Landed the string in THS.Screwed in Tie down
bolts.Pr test T/H seals @ 21 mpa.OK.Unscrewed Tie down bolts.Pick up 13 cms.
Pressurise tubing to 10 mpa ok raised to 13 mpa to set PHL PKR.Good indication of
set. Further raised to 15 mpa & tested string @ 15mpa for 30 mins.ok.
18:00 - 18:30 0.50 IC LSR 2,203.00 Released pressure .Landed the T/H in THS.Screwed tie down bolts.
18:30 - 20:30 2.00 IC PRE 2,203.00 Pr test T/H from top @ 21 mpa.OK.Pressurised annulus & tested for 7.5 mpa.OK.

4/11/2011 12:24:16PM Report Version: 3.2.901 12


PDO

EP Wells Operations Summary Report


Well: LEKHWAIR-688
Project: Lekhwair Site: LEKHWAIR-688 Rig Name No: Z_Historical PDO Rig 68/,
Wireline Unit 9/
Event: Drilling only Actual Start Date: 12/23/2009 End Date: 2/2/2010 Original Spud Date: 12/27/2009
Active Datum: DFE @116.14m (above Mean Sea Level) UWI (SAP PSN#): 410000009655
Date Time Hrs Phase Op WSOP Depth Description
Start-End Code (m)
20:30 - 22:30 2.00 IC PRE 2,203.00 R/U MB W/Line lubricator . Pr test @ 15 mpa.OK.
22:30 - 00:00 1.50 IC MDE 2,203.00 Run the gauge cutter with 2.84".Second run with SSD opening tool conts.

2/2/2010 00:00 - 01:00 1.00 IC MDE 2,203.00 Cont & opened SSd with MB w/l .
01:00 - 03:00 2.00 IC PCD 2,203.00 Displaced mud with 13.5 Kpa/m Brine ,above SSD.F/rate-0.5m3/min,STPP-5.0mpa.
03:00 - 06:30 3.50 IC MDE 2,203.00 tried to close SSD .No success. Again circulated for 30 mins.Tried & successfullt
closed SSD.
06:30 - 07:15 0.75 IC PCD 2,203.00 Kept open SOV.Pr test Tubing @ 10 mpa to ensure closure of SSD.OK.
07:15 - 08:00 0.75 IC PRE 2,203.00 Installed TWCV.Pr test from above @ 21 mpa.OK.
08:00 - 18:00 10.00 IC BPR 2,203.00 N/D BOP stack.N/U X-mass tree.Pr test joint @ 21 mpa.OK.Pr test Body @ 21
mpa.OK.retreived TWCV.Installed BPV.
Rig released @ 1800 hrs for AN-H-OP-03.
Mean while cleared all ud tanks .Ready to Tpt to new location.

4/11/2011 12:24:16PM Report Version: 3.2.901 13

You might also like