N°
SONATRACH MLEG-00-AQ-T-00OO43
First Calgary Petroleums 001411-00-CBQB-03453
JOB N° DOC. N° REV.
032076 00-ZA-E-03453 0
MENZEL LEDJMET EAST PROJECT
QCP – Telecommunications DATE 02 Novembre 2009 SHEET 1 OF 47
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
COMPANY’S DOC. N°
SONATRACH MLEG-00-AQ-T-00OO43
First Calgary Petroleums 001411-00-CBQB-03453
JOB N° DOC. N° REV.
032076 00-ZA-E-03453 0
MENZEL LEDJMET EAST PROJECT
QCP – Telecommunications DATE 02 November 2009 SHEET 2 OF 47
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
COMPANY’S DOC. N°
SONATRACH MLEG-00-AQ-T-00OO43
First Calgary Petroleums 001411-00-CBQB-03453
JOB N° DOC. N° REV.
032076 00-ZA-E-03453 0
MENZEL LEDJMET EAST PROJECT
QCP – Telecommunications DATE 02 November 2009 SHEET 3 OF 47
CONTENTS
1. GENERAL 4
1.1. Scope and field of application 4
1.2. Terms and definitions 4
3. APPLICABLE DOCUMENTATION 8
3.1. Specification, Codes and Standards 8
3.2. Applicable revision 8
7. ATTACHMENTS 16
7.1. List of applicable ITP 16
7.2. List of applicable inspection and test report forms 16
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
COMPANY’S DOC. N°
SONATRACH MLEG-00-AQ-T-00OO43
First Calgary Petroleums 001411-00-CBQB-03453
JOB N° DOC. N° REV.
032076 00-ZA-E-03453 0
MENZEL LEDJMET EAST PROJECT
QCP – Telecommunications DATE 02 November 2009 SHEET 4 OF 47
1 GENERAL
3 This document provides guidance and minimum requirements for inspecting, checking
and testing related to the installation of Telecommunication to be performed during
construction of of Menzel Ledjmet East Project.
6 The following terms and definitions are applicable to all Saipem specifications related
to quality requirements for Construction SubContractors.
Construction
SubContractor(s) Organisation(s), including its sub-contractors to whom any part of
the Works has been subcontracted by Saipem/Client;
Saipem Organization appointed by Client to perform the Works;
Company Organization that receives the services related to the Works
provided by Saipem and by its Construction SubContractor(s).
TPI Third Party Inspection: any organization, authority, person or
persons, to which Construction SubContractor has subcontracted
the execution of inspection and or laboratory testing related
activities.
Works Means the permanent new facilities constituting the Project,
including all the construction services, materials and equipment to
be provided by Saipem/Client to satisfy its obligations pursuant to
the Contract undertaken with the Client.
QMS Quality Management System: part of the organization’s
management system that focuses on achievement of results, in
relation to the quality objectives, to satisfy the needs, expectations
and requirements of Saipem/Client and of any other interested
parties, as appropriate.
QAS Quality Assurance Specification: Saipem document 000-ZA-E-09609
&000-ZA-E-09610 specifying the minimum requirements related to
Construction SubContractor’s QMS and QA/QC Manual specific for the
Works.
QCS Quality Control Specification: Saipem specification for quality control
requirements.
QCP Quality Control Plan: Construction SubContractor plan containing all
quality control requirements. This plan complement and compiles all
applicable ITP(s).
ITP Inspection and Test Plan: Construction SubContractor plan of
inspection and tests required by engineering and vendors
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
COMPANY’S DOC. N°
SONATRACH MLEG-00-AQ-T-00OO43
First Calgary Petroleums 001411-00-CBQB-03453
JOB N° DOC. N° REV.
032076 00-ZA-E-03453 0
MENZEL LEDJMET EAST PROJECT
QCP – Telecommunications DATE 02 November 2009 SHEET 5 OF 47
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
COMPANY’S DOC. N°
SONATRACH MLEG-00-AQ-T-00OO43
First Calgary Petroleums 001411-00-CBQB-03453
JOB N° DOC. N° REV.
032076 00-ZA-E-03453 0
MENZEL LEDJMET EAST PROJECT
QCP – Telecommunications DATE 02 November 2009 SHEET 6 OF 47
10 This document includes the ITP(s) and forms, listed under paragraph 5.2 and 5.1, for
performing as minimum the inspection, tests and certification to be carried out during
site activities related to installation of telecommunications.
11 The enclosed ITP(s) are specific and they include inspection and tests which are
directly related to specific project items and/or are part of the Works that can be
identified and traceable through engineering documentation.
13 Construction SubContractor has issued this document “Quality Control Plan” (QCP)
same as the approved “Quality Control Specification” (QCS), improving the enclosed
ITPs in accordance to the project requirements and completing the information
requested on clause 3.1 and the ITPs columns “Reference document” & “Acceptance
Criteria”
Construction SubContractor will number the QCP in accordance to the project
numbering system provided by Saipem.
14 If during Works Construction SubContractor will need additional ITP/ ITP phase for
further test and checks with the relevant QC Codes, the same shall be numbered
adding an alphanumeric suffix to the preceding available QC Code. New QC Codes
shall be submitted and approved by Saipem.
15 Construction SubContractor during the execution of the Works shall revise and update,
as and when required, the QCP(s) and relevant ITP(s) to incorporate any other
pertinent requirements set forth in engineering specifications, standards, design codes,
recommended practices, safety design, referred hereafter or included elsewhere in the
contractual and vendors documents.
16 Before starting of Works, the QCP containing the ITPs applicable for the project items
and works, shall be submitted by the Construction SubContractor for Saipem review
and approval.
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
COMPANY’S DOC. N°
SONATRACH MLEG-00-AQ-T-00OO43
First Calgary Petroleums 001411-00-CBQB-03453
JOB N° DOC. N° REV.
032076 00-ZA-E-03453 0
MENZEL LEDJMET EAST PROJECT
QCP – Telecommunications DATE 02 November 2009 SHEET 7 OF 47
18 Construction SubContractor will prepare and update any other necessary QCP(s) and
ITP(s), and quality procedures to include all inspections, examinations and tests
required to verify the quality of the Works. The above documents will be timely
submitted to Saipem for review and approval in order to ensure their availability in
approved status prior to starting of the activities related to the inst allation of
telecommunications.
19 Construction SubContractor will perform and record all inspections, examinations and
tests required and shall carry out all the works necessary for the preparation of
inspections, examinations and tests, including adequate scaffolding for safely
witnessing the inspection.
20 Construction SubContractor will provide, for the execution of testing, inspection and
measurements all necessary equipment, tools and shall make available the applicable
international Standards and Codes.
21 Construction SubContractor will issue inspections, examinations and tests reports
immediately after the completion of each inspection activity. All reports will be
approved and signed off by Construction SubContractor authorized personnel prior to
submission to Saipem for review or approval, as appropriate.
22 Saipem or other Parties signature on inspection, examination and test reports does not
release the Construction SubContractor from his responsibilities.
23 Construction SubContractor shall have at his own charge the filing of the relevant QCP
form certificate on dedicated Dossiers as specified on SPC. 000-ZA-E-09609 and SPC.
000-ZA-E-09610, at the time required for the mechanical completion phases the
Construction SubContractor will deliver to Saipem hard copies and PDF file of the
dossiers.
24 Local regulations
25 Inspections and tests required by Algerian law and regulation shall be strictly adhered
to, documented by Construction SubContractor and shall take precedence over this
specification
26 When Algerian law and local regulations are different from the applicable design
codes, Construction SubContractor shall inform SAIPEM for the necessary actions.
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
COMPANY’S DOC. N°
SONATRACH MLEG-00-AQ-T-00OO43
First Calgary Petroleums 001411-00-CBQB-03453
JOB N° DOC. N° REV.
032076 00-ZA-E-03453 0
MENZEL LEDJMET EAST PROJECT
QCP – Telecommunications DATE 02 November 2009 SHEET 8 OF 47
27 APPLICABLE DOCUMENTATION
29 Contractual Specification:
- J8328A-J-SD-16071 Telecommunication System Specification
30 Project specifications:
- 00-HA-E-49000; MLEG-00-SP-T-86OO00 , GENERAL SPC. for TELECOMMUNICATION
System (ITP0112)
- 00-HA-E-49012; MLEG-00-SP-T-86TS12, SPC. for VSAT System(ITP0107)
- 00-HA-E-49014; MLEG-CPF-SP-T-86TV14, SPECIFICATION for VHF AIRBAND
System(ITP0107)
- 00-HA-E-49015; MLEG-00-SP-T-86TU15, SPC. for TETRA System(ITP0107)
- 00-HA-E-49023; MLEG-00-SP-T-86TP23, SPC. for TELECOM HOTLINE System(ITP0102)
- 00-HA-E-49041; MLEG-00-SP-T-86TJ41, SPC. for FO CABLE (ITP0101)
- 00-HA-E-49043; MLEG-00-SP-T-86TJ43, SPC. for SPLICING AND TERMINATION OF FO
CABLE (ITP0101)
- 00-HA-E-49061; MLEG-00-SP-T-86TM61, SPC. for MULTIPLEXER (ITP0112)
- 00-HA-E-49066; MLEG-00-SP-T-86TM66, SPC. for SDH (ITP0112)
- 00-HD-A-49144; MLEG-00-DE-T-86TJ01, TYPICAL FO CABLE LAYING AND CROSSING
(ITP0101)
- 00-HL-E-49154; MLEG-00-SP-T-86TJ54, SPECIFICATION for FOC INSTALLATION
WORKS (ITP0101)
- 15-HA-E-49021; MLEG-CPF-SP-T-86TP21, SPC. for PABX (ITP0102)
- 15-HA-E-49081; MLEG-CPF-SP-T-86TC81, SPECIFICATION for CCTV System(ITP0105)
- 15-HA-E-49082; MLEG-CPF-SP-T-86TA82, SPECIFICATION for PAGA System(ITP0104)
- 15-HA-E-49088; MLEG-CPF-SP-T-86TL88, SPECIFICATION for I.T. SYS. LAN (EDMS-
EDP ETC.) (ITP0106)
- 000-ZA-E-09609 - MLEG-00-AS-MC-00OO09 Quality Assurance Requirements for
Construction SubContractors
- 000-ZA-E-09610 - MLEG-00-AS-MC-00OO10 Quality Control Requirements for
Construction SubContractors
32 Applicable revision
33 Unless otherwise specified in the contract documents, the applicable revision or edition
of applicable Specification and Standards is the last valid at the time when the contract
or agreement is entered into.
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
COMPANY’S DOC. N°
SONATRACH MLEG-00-AQ-T-00OO43
First Calgary Petroleums 001411-00-CBQB-03453
JOB N° DOC. N° REV.
032076 00-ZA-E-03453 0
MENZEL LEDJMET EAST PROJECT
QCP – Telecommunications DATE 02 November 2009 SHEET 9 OF 47
35 Incoming inspection
37 Material handling
38 All telecommunication material will be stored in an area separately from other project
material. Contractor QC inspector will visually inspect all telecommunication material
received from the store, prior to installation. He will ensure that all materials comply
with the materials take-off lists and construction drawings, and that all materials are
properly tagged and identified with relevant Stock Numbers. Damaged equipment shall
not be used.
41 General
The design and installation of underground conduits and duct banks shall be in
accordance with the project documentation. Before commencing the installations, the
Subcontractor Telecommunications QC Inspector shall verify that the materials
conform to the standard specifications and are free from damage and deformities. All
materials shall be kept away from excessive heat, flames and direct sunlight.
Before installing, the trench shall be checked to verify that the trench bottom is leveled
and free from stones and foreign materials.
Correct bending radius shall be observed during the installation. Cold field bending is
allowed for radius of 10-45 meters only. The number of bends permitted to the conduit
lateral shall not have more than the equivalent of two 90° turns.
The maximum length of the main conduit section containing bends or curves shall
depend upon the angle between the straight conduit run on each side of the curve and
the radius of the curve.
43 Conduit installation
Approved conduit spacers shall be installed between conduits. These shall be applied
in all concrete encased conduit sections. Conduit spacers shall be placed at 1.5 – 2.5m
intervals along the conduit. There shall be a sufficient number of spare conduits in a
duct-bank.
Installed conduits shall be mandrel tested prior to pouring of concrete, after pouring
and before doing any paving work in the conduits.
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
COMPANY’S DOC. N°
SONATRACH MLEG-00-AQ-T-00OO43
First Calgary Petroleums 001411-00-CBQB-03453
JOB N° DOC. N° REV.
032076 00-ZA-E-03453 0
MENZEL LEDJMET EAST PROJECT
QCP – Telecommunications DATE 02 November 2009 SHEET 10 OF 47
44 Encasement
The minimum amount of concrete encasement using forms shall be 75mm along the
top, sides and bottom of the conduit formation. Whenever the trench walls are used in
lieu of forms, the same 75 mm minimum thickness of concrete on each side of conduit
bank shall be considered.
When required by the project, communication duct banks shall be identified by their
orange color.
It shall be accomplished by
b) mixing orange dye with the top layer of the concrete encasement of 5mm
thickness;
c) placing an orange warning tape 30cm on top of the conduit encasement and
located minimum of 30cm below the grade.
Telecommunication conduits crossing other sub-structures like pipeline, etc. shall have
adequate separation as per project documentation.
Prior to backfilling the duct-bank, spare conduits shall be closed with approved plugs.
Concrete encasement and trench backfilling shall be carried on only after Client review
and approval all of the installations.
45 Responsibility
Subcontractor Telecommunications QC Inspector shall closely monitor the installation
of telecommunication duct banks to verify and certify that it is in accordance with the
standards. He shall witness and document all tests performed during the installation.
The Client’s representative will check the installation and witness the testing.
46 Manhole construction
47 General
Manholes shall be designed and constructed in accordance with the project
documentation.
48 Pre-cast inspection
Company shall inspect pre-cast manholes to be in compliance with the standard during
the fabrication, construction and placing in the ground. A minimum of 24 hours written
notice before casting shall be provided to allow sufficient time for the Client to inspect.
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
COMPANY’S DOC. N°
SONATRACH MLEG-00-AQ-T-00OO43
First Calgary Petroleums 001411-00-CBQB-03453
JOB N° DOC. N° REV.
032076 00-ZA-E-03453 0
MENZEL LEDJMET EAST PROJECT
QCP – Telecommunications DATE 02 November 2009 SHEET 11 OF 47
50 Internal racking
Cables and completed splices shall be properly supported with cable rack hooks at
each cable rack location. Cable rack hook positions shall be numbered from top to
bottom of the uprights. The number one shall be at the uppermost cable hook rack
space. Double racking of cables is allowed to obtain maximum use of available
manhole wall space. There shall be no more than two cables racked side by side at
any racking level.
51 Responsibility
Subcontractor Telecommunications QC Inspectors will verify that the manholes design
and construction meets the minimum requirement of the standard. He will verify and
check that approved materials were used. He will verify that the cable-rack is securely
attached and the spacing is correct. Subcontractor Telecommunications QC Inspector
will notify the Client through RFI in advance, as agreed with the Client for final
inspection of the completed manhole. Grounding tests will be witnessed by Client.
53 Conduits system
Conduits shall be of rigid galvanized steel. There will be no more than 2-90 bends
allowed in one run of conduit.
The maximum continuous section shall not exceed 30m; whenever this value is
exceeded, a pull-box or pull point shall be inserted. The direct buried entrance conduit
shall be encased in concrete. All building entrance conduits shall be plugged or sealed
in accordance with project documentation. The correct bending radius shall be
observed especially when Fibre Optic cables are involved. It shall have at least 10
times the internal diameter of the conduit.
1) Cantilever brackets
2) Trapeze supports
Supports shall be placed in strategic locations so that the connectors between sections
of the cable trays lie between the support point and the quarter section of the span.
They shall be within 2ft (0.6m) on each side of any connection to a fitting.
The system shall be designed so that the cables installed within will have a correct
bending radius. Trays shall be bonded together and securely connected to a reliable
grounding system.
In order to avoid electromagnetic interference (EMI), cables shall be installed meeting
the correct spacing requirement towards adjacent installations, such as power cables
and equipment. Spacing shall be in accordance with project requirements and the
referenced codes.
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
COMPANY’S DOC. N°
SONATRACH MLEG-00-AQ-T-00OO43
First Calgary Petroleums 001411-00-CBQB-03453
JOB N° DOC. N° REV.
032076 00-ZA-E-03453 0
MENZEL LEDJMET EAST PROJECT
QCP – Telecommunications DATE 02 November 2009 SHEET 12 OF 47
56 Responsibility
Contractor is responsible for daily inspecting and testing activities on cables laying,
routing and termination. This procedure is applied to all Fiber Optics and Copper Wires
(signal and power) cables, utilized at the installation sites during the implementation of
the plants.
57 Cutting plan
Before starting the cable pulling operations and in order to optimize the utilization of
cables lengths on each reel, a general site cutting plan should be drawn up. For
traceability purposes every portion of cable shall be recorded on the Drum Record
Card.
58 Cables routing
Contractor shall verify that every cable interconnected to the System under his control
be routed according to contractual engineering documents and/or civil drawings. If due
to practical reasons this is not possible, the Contractor shall notify the Employer in
order to define an alternative route.
59 Cables laying
Contractor shall verify that the cables are correctly placed on the applicable supports
(trench, open conduit, PVC pipe, cable duct, cable tray, etc.) without dangerous
bending, properly fastened (together and/or to the ladder, as applicable, using cable
ties made of polyamide or suitable material) and far from sharp edges. During handling
and laying, care shall be taken to observe the minimum-bending radius recommended
by the cable manufacturers. Tools for cable laying (where necessary) shall be those
recommended by the cable manufacturers. A 25 cm minimum of clearance between
power and signal cables shall be left. Cables shall be laid according to instructions
provided by the project documents (Telecommunications Cables Laying Instructions).
Underground cables shall be tested for continuity and insulation resistance/attenuation
before backfilling the cable trench. When laying has been completed, cables shall be
cleaned from inert dry lubricants that were added during pulling activities and/or
existing under the sheath.
60 Cables identification
Each cable shall be provided with suitable identification tags or labels showing the
cable number as per the applicable Cable List and in accordance with applicable
engineering drawings. Tags shall be placed on both ends of cables, at both sides of
road crossings and at both sides of building entry. For underground cabling, the
spacing between cable numbers along the roads should be 5 to 15 m. Such cables
shall also be numbered where they branch-off from a main route. Each conductor shall
be provided with plastic rings numbered according to the tables and cable diagrams for
identification or other agreed cable identification media.
61 Cable glands
Proper sizes of cable glands suitable for the cables shall be utilized. Contractor shall
ensure that the load of the cables does not derive from the cable gland.
62 Cables termination
The cable laying must be made in such a way to reduce shorts of cable. Suitable
slacks shall be left available (below false floors, inside wells, etc.), to avoid that wires
are pulled off from terminals and/or for possible future intervention. Any cable shall be
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
COMPANY’S DOC. N°
SONATRACH MLEG-00-AQ-T-00OO43
First Calgary Petroleums 001411-00-CBQB-03453
JOB N° DOC. N° REV.
032076 00-ZA-E-03453 0
MENZEL LEDJMET EAST PROJECT
QCP – Telecommunications DATE 02 November 2009 SHEET 13 OF 47
joined end-to-end, run and connected according to the cable schedule and relevant
interconnection diagrams. Terminations shall be done as per contract specifications.
64 Unused cables
All unused cables shall be returned to the store wound on reels or as windings. Cable
ends shall be sealed for waterproofing.
66 General
The Equipment shall be completely unpacked (but left on relevant pallets, if any)
before entering the rooms where they will be installed. Light protections (plastic film,
packaging cartoons, etc.) should be placed over pieces of equipment to preserve them
from dust, moisture, paint and other agents which could cause electrical and/or
mechanical damages. Equipment shall be visually inspected before its installation.
67 Cabling
Before starting the equipment installation activities, all the subfloor cables should be
installed and inspected, as per relevant procedure. Inter-cabinet and internal cabling
shall be installed at the end of the mechanical assembly activities, together with signal,
power and ground cables.
68 Mechanical assembly
Before moving equipment to their final position all mechanical hardware should be
installed inside racks and cabinets (unless it makes the unit too heavy). Adjacent
cabinets shall be joined together, if so specified by relevant drawings, only after their
final positioning and anchoring. Fixing bolts (where applicable) have to be located as
per the contract installation drawings. Cable trays shall also be fixed to the top of
racks, if applicable, after their mechanical assembly completion. The absence of
loosened hardware items (screws, bolts, etc.) shall be carefully checked.
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
COMPANY’S DOC. N°
SONATRACH MLEG-00-AQ-T-00OO43
First Calgary Petroleums 001411-00-CBQB-03453
JOB N° DOC. N° REV.
032076 00-ZA-E-03453 0
MENZEL LEDJMET EAST PROJECT
QCP – Telecommunications DATE 02 November 2009 SHEET 14 OF 47
All the equipment specified in the documents, spec.s etc. should be inspected;
Supplier’s identification of cards, equipment, etc. must be maintained;
Good presentation of equipment (cards, racks, cabinets, wiring, cables, etc.) has been
assured;
Overall documentation has been submitted and accepted, and fits the hardware
delivered.
032076 00-ZA-E-03453 0
MENZEL LEDJMET EAST PROJECT
QCP – Telecommunications DATE 02 November 2009 SHEET 15 OF 47
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
COMPANY’S DOC. N°
SONATRACH MLEG-00-AQ-T-00OO43
First Calgary Petroleums 001411-00-CBQB-03453
JOB N° DOC. N° REV.
032076 00-ZA-E-03453 0
MENZEL LEDJMET EAST PROJECT
QCP – Telecommunications DATE 02 November 2009 SHEET 16 OF 47
77 ATTACHMENTS
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
COMPANY’S DOC. N°
SONATRACH MENZEL LEDJMET EAST PROJECT MLEG-00-AQ-T-00OO43
First Calgary Petroleums 001411-00-CBQB-03453
JOB N° DOC. N° REV.
SPC 00-HA-E-49043;
SPC 00-HD-A-49144
SPC 00-HL-E-49154
SPC 00-HA-E-49061
SPC 00-HA-E-49023
-SPC 15-HA-E-49021
REPORT N°
MENZEL LEDJMET EAST PROJECT JCC-TL-0002
DOCUMENT/SPECIFICATION: PAGE OF
TAG/ITEM:
1. Trenches are of correct depth, cleaned & with the proper sand bedding
2. Ducts & sub-ducts are of correct type, number, colour and free from damages
3. Cables are routed according to applicable drawings
4. Correct procedure & proper tools were used in laying and pulling
5. Visual inspection for proper identification & labelling has been made
6. Cables glands compatibility & tightness were verified
7. Cables termination are executed in standard manner & properly identified
8. Armoured cables are suitably grounded
9. Not used cables are sealed and wounded after cutting
10. Installed cables were tested in accordance with the project/standard procedure
NOTES INSPECTION NOTIFICATION REFERENCE
RFI N°
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
JOB UNIT
SONATRACH 032076
First Calgary Petroleums
QC CODE
TL-0101-02
REPORT N°
MENZEL LEDJMET EAST PROJECT JCC-TL-0002
DOCUMENT/SPECIFICATION: PAG OF
C NC C NC NA
C NC C NC NA
C NC C NC NA
C NC C NC NA
C NC C NC NA
C NC C NC NA
C NC C NC NA
C NC C NC NA
C NC C NC NA
C NC C NC NA
C NC C NC NA
C NC C NC NA
C NC C NC NA
C NC C NC NA
C NC C NC NA
C NC C NC NA
C NC C NC NA
C NC C NC NA
C NC C NC NA
C NC C NC NA
C NC C NC NA
RFI N°
SNAMPROGETTI CLIENT
QC CONSTRUCT. SUBCONTR.
NAME NAME NAME NAME
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
JOB UNIT
SONATRACH 032076
First Calgary Petroleums
QC CODE
TL-0101-02
REPORT N°
MENZEL LEDJMET EAST PROJECT JCC-TL-0002
DOCUMENT/SPECIFICATION: PAGE OF
TAG/ITEM:
End to End
FIBER ACCEPTANCE
ATTENUATION (dB)
No
A÷B B÷A EXPECTED VALUE AT 1,300nm 1,550nm :
1 P F
2 P F Δ x Δ1 =…………....dB
Ψ x Ψ1 =…………....dB
3 P F
C x C1 =………..…..dB
4 P F ________________
5 P F
6 P F EXPECTED VALUE =……dB
7 P F
8 P F
Δ IS THE CABLE TOTAL LENGTH IN KM
9 P F
Δ1 IS THE FIBRE ATTENUATION IN DB/KM
10 P F Ψ IS THE NUMBER OF SPLICES
11 P F Ψ1 IS THE AVERAGE SPLICE LOSS IN DB
12 P F C IS THE NUMBER OF CONNECTORS
13 P F C1 IS THE CONNECTORS LOSS
14 P F
REQUIREMENTS:
15 P F TESTS SHALL BE PERFORMED ON 100% OF FIBERS IN BOTH
16 P F DIRECTIONS AND 100% OF FIBERS SPLICES AND
CONNECTORS.
TEST INSTRUMENT :
MANUFACTURER :
CALIBRATIONE DATE :
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
JOB UNIT
SONATRACH 032076
First Calgary Petroleums
QC CODE
TL-0101-02
REPORT N°
MENZEL LEDJMET EAST PROJECT JCC-TL-0002
DOCUMENT/SPECIFICATION: PAGE OF
TAG/ITEM:
CHECKED
CHECK AND TEST DESCRIPTION COMPLY
CHECKED N. A.
NOT COMPLY
1. Cabling completed
RFI N°
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
JOB UNIT
SONATRACH 032076
First Calgary Petroleums
QC CODE
TL-0101-02
REPORT N°
MENZEL LEDJMET EAST PROJECT JCC-TL-0002
DOCUMENT/SPECIFICATION: PAGE OF
TAG/ITEM:
1. Equipment, racks & accessories did not suffer for abuse in transportation
and installation activities
2. Equipment racks are positioned according to the project documentation,
space between rows is respected, ventilation is not obstructed
3. Cabinet doors are closed, blank panels were fixed after installation &
cabling
4. Keys for locks are available (when required)
5. Equipment racks or cabinets are clean from dust and any other material.
Dust to be removed only by vacuum
6. Paint is intact or touched up where necessary
7. The operator set(s) are properly installed and connected, the cables
connectors are mechanically fixed
8. All cables connections including the power supply are properly done
9. Connections to the grounding are according to the project documents
RFI N°
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
JOB UNIT
SONATRACH 032076
First Calgary Petroleums
QC CODE
TL-0101-02
REPORT N°
MENZEL LEDJMET EAST PROJECT JCC-TL-0002
DOCUMENT/SPECIFICATION: PAGE OF
TAG/ITEM:
CHECKED
CHECKED
CHECK AND TEST DESCRIPTION NOT N. A.
COMPLY
COMPLY
- the call setting facilities (internal call, group call, direct lines, block dialling) operate correctly
- the call answering facilities (call with or without ring tone, call on hold, pick-up busy override)
operate correctly
- the call pick-up facilities (call group pick-up, call pick-up, switchboard pick-up, general call
pick-up, recovering a parked call) operate correctly
- during a conversation the facilities of conference calls, call forwarding, general and individual
call hold, DTMF signal transmission, rate information, malicious call recording, restriction
external transfer, call parking and parked call retrieval operate correctly
- the mobility facilities (follow me, call parking and parked call retrieval, substitution) operate
correctly
- the system facilities (integrated voice messaging, remote programming – isdn, virtual private
network, general call, day/night key, alarm switch & alarm key, monitoring of operator calls)
operate correctly
- the euro-isdn system facilities (connected line identification presentation [colp], calling line
identification presentation [clip], multiple subscriber numbers [msn], block dialling, log of
missed calls, direct inward dial [did], user to user signalling, telesecretary services,
identification of malicious calls) operate correctly
- theVOIP facilities operate correctly
4. PABX versus interfaces equipment operational tests
- the communication access from/to any authorized user radio system operate correctly
- the communication access from any authorized public address user system operate correctly
- the communication access from/to any connected public/private switching system operate
correctly
- the communication access from /to any central office line operate correctly
NOTES INSPECTION NOTIFICATION REFERENCE
RFI N°
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
JOB UNIT
SONATRACH 032076
First Calgary Petroleums
QC CODE
TL-0101-02
REPORT N°
MENZEL LEDJMET EAST PROJECT JCC-TL-0002
DOCUMENT/SPECIFICATION: PAGE OF
TAG/ITEM:
CHECKED
CHECKED
CHECK AND TEST DESCRIPTION NOT N. A.
COMPLY
COMPLY
- the version of the loaded switching system software comply with the project documents
- the system has built-in capabilities to be locally and remotely updated.
- all final software plus manuals are delivered at site
RFI N°
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
JOB UNIT
SONATRACH 032076
First Calgary Petroleums
QC CODE
TL-0101-02
REPORT N°
MENZEL LEDJMET EAST PROJECT JCC-TL-0002
DOCUMENT/SPECIFICATION: PAGE OF
TAG/ITEM:
1. Equipment racks & accessories did not suffer for abuse in transportation
and installation activities
3. Cabinet doors are closed, blank panels were fixed after installation &
cabling
5. Equipment racks or cabinets are clean from dust and any other material.
dust to be removed only by vacuum
7. The operator set(s) are properly installed and connected, the cables
connectors are mechanically fixed
8. All cables connections including the power supply are properly done
RFI N°
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
JOB UNIT
SONATRACH 032076
First Calgary Petroleums
QC CODE
TL-0101-02
REPORT N°
MENZEL LEDJMET EAST PROJECT JCC-TL-0002
DOCUMENT/SPECIFICATION: PAGE OF
TAG/ITEM:
10. The loudspeakers, the intercom sets, the junction boxes and the accessories
are certified for the installation area. material classification and cables entry
mechanical protection to be checked
12. field equipment are properly installed and well fixed to the relevant supports
13. Field equipment are correctly located according to the layout drawings
14. The field equipment cables are properly connected and mechanically
protected
15. The field equipment cables entry not used are carefully plugged
16. The loudspeakers are well oriented and not interfered by other plant
structures
18. Field equipment connections to the grounding are according to the project
documents
RFI N°
QC CONSTRUCT. SUBCONTR. SAIPEM CLIENT
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
JOB UNIT
SONATRACH 032076
First Calgary Petroleums
QC CODE
TL-0101-02
REPORT N°
MENZEL LEDJMET EAST PROJECT JCC-TL-0002
DOCUMENT/SPECIFICATION: PAGE OF
TAG/ITEM:
CHECKED
CHECKED
CHECK AND TEST DESCRIPTION COMPLY NOT N. A.
COMPLY
1. Power supply check: V / hz to the cabinet(s) main equipment (pmx or intercom
exchange)
2. Power supply check: V / hz to the amplifier cabinet(s) for the loudspeaker
system
3. Operational test from field equipment (c.b. or intercom set) to the operator set
- optical and acoustical indication are operating on an incoming call
- ringing bell is automatically off at the answer
- communication is operational on both way
- end of communication check
4. Operational test from operator set to the field equipment (c.b. or intercom set)
- the optical indications relevant to the outgoing call operate correctly
- the calling tone is available
- ringing tone is automatically off at the answer
- communication is operational on both way
- end of communication check
5. Operational test on the loudspeakers network
- the single zone and the general call functionality operate correclty from any operator set
- the s/n ratio required on project documents for messages intelligibility is reached
- network and equipment diagnostic facilities operate correctly from the system management
unit
- loudspeakers power setting is available from system management unit
- remote equipment configuration is available from system management unit
6. Software compliance
- the version of the system software, comply with the project documents
- the system has built-in capabilities to be locally and remotly upadated
- all final software plus manuas are delivered at site
NOTES INSPECTION NOTIFICATION REFERENCE
RFI N°
SAIPEM CLIENT
QC CONSTRUCT. SUBCONTR.
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
JOB UNIT
SONATRACH 032076
First Calgary Petroleums
QC CODE
TL-0101-02
REPORT N°
MENZEL LEDJMET EAST PROJECT JCC-TL-0002
DOCUMENT/SPECIFICATION: PAGE OF
TAG/ITEM:
CHECKED
CHECKED
CHECK AND TEST DESCRIPTION NOT N. A.
COMPLY
COMPLY
1. Equipment racks & accessories did not suffer for abuse in transportation and
installation activities
2. Equipment racks are positioned according to the project documentation, space
between rows is respected, ventilation is not obstructed
3. Cabinet doors are closed, blank panels were fixed after installation & cabling
4. Keys for locks are available (when required)
5. Equipment racks or cabinets are clean from dust and any other material. dust to be
removed only by vacuum
RFI N°
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
JOB UNIT
SONATRACH 032076
First Calgary Petroleums
QC CODE
TL-0101-02
REPORT N°
MENZEL LEDJMET EAST PROJECT JCC-TL-0002
DOCUMENT/SPECIFICATION: PAGE OF
TAG/ITEM:
CHECKED
CHECKED
CHECK AND TEST DESCRIPTION NOT N. A.
COMPLY
COMPLY
18. Field equipment connections to the grounding are according to the project
documents
20. CCTV monitors are properly installed according to the layout and to the ergonomic
requirements
RFI N°
SAIPEM CLIENT
QC CONSTRUCT. SUBCONTR.
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
JOB UNIT
SONATRACH 032076
First Calgary Petroleums
QC CODE
TL-0101-02
REPORT N°
MENZEL LEDJMET EAST PROJECT JCC-TL-0002
DOCUMENT/SPECIFICATION: PAGE OF
TAG/ITEM:
CHECKED CHECKED
CHECK AND TEST DESCRIPTION COMPLY NOT COMPLY N. A.
- by the use of key board, joy stick or touch screen select a remote camera and
check the correctly operated of the zoom pan & tilt and glass cleaning system
- cctv monitor(s) show(s) the area operating in pip/freeze frame mode
- the recorded video is viewed from the operator console
- fixed sequential or random video pictures are suitable displayed
- system parameters are settable by the operator position
- video recording system operate correctly
- equipment failure alarms are correctly displayed
5. Software compliance
- the version of the system software comply with the project documents
- the system has built-in capabilities to be locally and remotely updated
- all final software plus manuals are delivered at site
NOTES INSPECTION NOTIFICATION REFERENCE
RFI N°
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
JOB UNIT
SONATRACH 032076
First Calgary Petroleums
QC CODE
TL-0101-02
REPORT N°
MENZEL LEDJMET EAST PROJECT JCC-TL-0002
DOCUMENT/SPECIFICATION: PAGE OF
TAG/ITEM:
CHECKED CHECKED
CHECK AND TEST DESCRIPTION N. A.
COMPLY NOT COMPLY
1. Equipment racks & accessories did not suffer for abuse in transportation
and installation activities
2. Equipment racks are positioned according to the project documentation,
space between rows is respected, ventilation is not obstructed
3. Cabinet doors are closed, blank panels were fixed after installation &
cabling
8. All cables connections including the power supply are properly done
RFI N°
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
JOB UNIT
SONATRACH 032076
First Calgary Petroleums
QC CODE
TL-0101-02
REPORT N°
MENZEL LEDJMET EAST PROJECT JCC-TL-0002
DOCUMENT/SPECIFICATION: PAGE OF
TAG/ITEM:
CHECKED CHECKED
CHECK AND TEST DESCRIPTION N. A.
COMPLY NOT COMPLY
13. The hand-portable radios and the accessories are certified for the use in
the operation area.
14. Equipment did not suffer of mechanical damages , especially for the whip
antenna
15. Battery chargers are correctly installed and connected to the mains
supply
16. The mobile radio are correctly installed on the car/truck defined with the
client
17. Fixed antennas system did not suffer of mechanical damages
18. Fixed antennas system with the associated supporting structure is
properly installed and located according to the layout requirements
RFI N°
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
JOB UNIT
SONATRACH 032076
First Calgary Petroleums
QC CODE
TL-0101-02
REPORT N°
MENZEL LEDJMET EAST PROJECT JCC-TL-0002
DOCUMENT/SPECIFICATION: PAG OF
TAG/ITEM
CHECKED CHECKED
CHECK AND TEST DESCRIPTION N. A.
COMPLY NOT COMPLY
1. Power supply check: V / HZ to the central cabinet(s) main
equipment
2. Power supply check: V / HZ to the remote radio stations
3. Test on the fixed radio
- RF transmitter output at antenna connector (dbm……..)
- transmitter deviation (+/- …….khz)
- VSWR ≤ 1.5 : 1
- receiver sensitivity (dbm……..)
4. Test on the portable/mobile radio
- RF transmitter output at antenna connector (dbm……..)
- transmitter deviation (+/- …….khz)
- VSWR ≤ 1.5 : 1
- receiver sensitivity (dBm……..)
5. Functional tests from operator position
- by the use of key board, joy stick or touch screen select a radio user, push the
“transmit” button and check that calls and message are correctly received
- test in a) repeated for a group of users
- demonstrate ability to set system parameters by the operator position
6. Functional test mobile/portable to mobile/portable
RFI N°
QC CONSTRUCT. SUBCONTR. SAIPEM CLIENT
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
JOB UNIT
SONATRACH 032076
First Calgary Petroleums
QC CODE
TL-0101-02
REPORT N°
MENZEL LEDJMET EAST PROJECT JCC-TL-0002
DOCUMENT/SPECIFICATION: PAGE OF
TAG/ITEM:
- the version of the system software comply with the project documents
- the system has built-in capabilities to be locally and remotely updated
- all final software plus manuals are delivered at site
RFI N°
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
JOB UNIT
SONATRACH 032076
First Calgary Petroleums
QC CODE
TL-0101-02
REPORT N°
MENZEL LEDJMET EAST PROJECT JCC-TL-0002
DOCUMENT/SPECIFICATION: PAG OF
TAG/ITEM:
CHECKED CHECKED
CHECK AND TEST DESCRIPTION N. A.
COMPLY NOT COMPLY
1. The cables conduits, cables trays and cables supports are well fixed to
the structures, faraway from the heat sources and the electrical cables
2. The cables entries through the building walls are well sealed
RFI N°
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
JOB UNIT
SONATRACH 032076
First Calgary Petroleums
QC CODE
TL-0101-02
REPORT N°
MENZEL LEDJMET EAST PROJECT JCC-TL-0002
DOCUMENT/SPECIFICATION: PAG OF
TAG/ITEM:
CHECKED
CHECK AND TEST DESCRIPTION CHECKED NOT N. A.
COMPLY COMPLY
1. Field tests on the category 5, cat 5e, cat 6 and cat 6e cabling installation
- Every cabling link in the installation has been tested in accordance with the
telecommunications industry association (tia) standard ansi/tia/eia-568-b and the
following parameters have been verified:
wire map
length
insertion loss (attenuation)
next loss
psnext loss
elfext loss, pair-to-pair
pselfext loss
return loss
acr (attenuation to crosstalk ratio)
psacr
propagation delay
delay skew
- Tthe test equipment (tester) are comply with or exceed the accuracy requirements for
enhanced level ii (level ii-e) field testers as defined in IEC Norma
- The tester is within the calibration period recommended by the vendor in order to
achieve the vendor-specified measurement accuracy
- The test results information for each link are recorded in the memory of the field tester
upon completion of the test
- The test results records saved by the tester have been transferred into a windows™-
based database utility that allows for the maintenance, inspection and archiving of these
test records
- The database for the completed job has been stored and delivered on cd-rom including
the software tools required to view, inspect and print any selection of test reports
RFI N°
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
JOB UNIT
SONATRACH 032076
First Calgary Petroleums
QC CODE
TL-0101-02
REPORT N°
MENZEL LEDJMET EAST PROJECT JCC-TL-0002
DOCUMENT/SPECIFICATION: PAG OF
TAG/ITEM:
CHECKED
CHECKED
CHECK AND TEST DESCRIPTION COMPLY
NOT N. A.
COMPLY
- a paper copy of the test results has been provided that lists all the links that have been
tested with the following summary information
the identification of the link in accordance with the naming convention defined
in the overall system documentation
the test results information contain information on each of the required test
parameters that are listed in section 1d
the overall pass/fail evaluation of the link-under-test
the name of the standard selected to execute the stored test results
the brand name, model and serial number of the tester
- Every cabling link in the installation has been tested in accordance with the
Telecommunications Industry Association (TIA) standard IEC 50346 or by the appropriate
network application standard(s).
- Field test instruments for multimode FIBRE cabling meet the requirements of IEC 50346
- Field test instruments for SINGLE MODE FIBRE cabling meet the requirements of IEC
50346
- The tester is within the calibration period recommended by the vendor in order to achieve
the vendor-specified measurement accuracy.
- The horizontal link (multimode) has been tested at 850 nm or 1300 nm in one direction in
accordance with IEC 50346
- Multimode backbone links have been tested at 850 nm and 1300 nm in one direction in
accordance with IEC 50346
- SINGLE MODE backbone links have been tested at 1310 nm and 1550 nm in accordance
with IEC 50346
NOTES INSPECTION NOTIFICATION REFERENCE
RFI N°
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
JOB UNIT
SONATRACH 032076
First Calgary Petroleums
QC CODE
TL-0101-02
REPORT N°
MENZEL LEDJMET EAST PROJECT JCC-TL-0002
DOCUMENT/SPECIFICATION: PAG OF
TAG/ITEM:
CHECKED CHECKED
CHECK AND TEST DESCRIPTION COMPLY NOT COMPLY N. A.
3. The test results information for each link are recorded in the memory of the
field tester upon completion of the test.
4. The test results records saved by the tester have been transferred into a
Windows™-based database utility that allows for the maintenance,
inspection and archiving of these test records.
5. The database for the completed job haS been stored and delivered on CD-
ROM including the software tools required to view, inspect and print any
selection of test reports.
6. A paper copy of the test results haS been provided that lists all the links that
have been tested with the following summary information:
RFI N°
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
JOB UNIT
SONATRACH 032076
First Calgary Petroleums
QC CODE
TL-0101-02
REPORT N°
MENZEL LEDJMET EAST PROJECT JCC-TL-0002
DOCUMENT/SPECIFICATION: PAG OF
TAG/ITEM:
CHECKED
CHECK AND TEST DESCRIPTION CHECKED N. A.
NOT COMPLY
COMPLY
- the version of the network software comply with the project documents
- the system has built-in capabilities to be locally and remotely updated
- all final software plus manuals are delivered at site
DOCUMENT/SPECIFICATION: PAG OF
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc
JOB UNIT
SONATRACH 032076
First Calgary Petroleums
QC CODE
TL-0101-02
REPORT N°
MENZEL LEDJMET EAST PROJECT JCC-TL-0002
TAG/ITEM:
CHECKED
TEST TO BE PERFORMED AT SITE IN ACCORDANCE TO CHECKED
NOT N. A.
THE SAT VENDOR PROCEDURE COMPLY
COMPLY
1. Voice communication between the PABx and to/over the PSTN and back up
System
3.Link test
NOTES: SAT Reports of will be as per SAT vendor Procedure INSPECTION NOTIFICATION REFERENCE
RFI N°
This document is the property of Sonatrach and First Calgary Petroleums who will safeguard its rights according to the civil and penal provisions of the law.
Data file: 651824065.doc