Distribution List
MA COM PM SR/ ED FA CW FI SDCI -
ITS LOG QEHS
√
MA
AUT SAS
MA
AUT NMS
MA
SALES
MA COM PR
SERVICE-ISJ
PT ALSTOM GRID : PLAZA ALSTOM Lantai 6, 7, 8, 9, Jl. TB Simatupang Kav IS-1 Pondok Pinang, Kebayoran Lama,
Jakarta Selatan – 12310 Indonesia
Total or partial reproduction and/or utilization of this document are forbidden without prior written authorization of the owner.
Affectivity of paper copy should be checked prior to use. Think before print, as your responsibility and commitment with the ENVIRONMENT.
Operating Instruction Title: Site Quality Plan Doc . No : A-FA-I-001, Rev. A Page: 1/8
CONTENTS PAGE REVISION
1 OBJECTIVE
2 SCOPE OF APPLICATION
3 REFERENCE DOCUMENT
4 SITE DESCRIPTION
8 INSTALLATION EQUIPMENT
9 COMMISSIONING EQUIPMENT
Operating Instruction Title: Site Quality Plan Doc . No : A-FA-I-001, Rev. A Page: 2/8
1. OBJECTIVE
The main objective of this document is to give guidance for the preparation of the site and will
assure Quality of Construction throughout the opening of Site, installation, commissioning up to
Closing of Site to our customer and to The Company.
It may be useful to standardize or harmonize a mode of operation and its associated basic
documents to control the site works.
2. Scope of Application
3. Reference Document
4. Site Description
Project Name :
Customer :
Customer Number :
Project Location :
Signature :
Date :
Signature :
Date :
Signature :
Date :
Operating Instruction Title: Site Quality Plan Doc. No : A-FA-I-001, Rev.A Page: 3/8
Applicable Procedure List
No. Procedures to be applied Document Reference Remark(s)
1 Receive Packing List(P/L) and Materials Receiving Report(MRR) from Project Manager Transmittal form
/ Logistic Department
2 Receive Drawings with status for ‘Execution/Construction’ (Construction drawing), and
specific procedures if any.
3 Prepares the Construction procedures required by your site :
1. Erection Guide procedures.
2. Test and Commissioning procedures.
3. Quality Control Procedure
4. Health Safety and Environment (HSE)
5. Erection File Management forms
6. Commissioning Management forms
7. PPMS
This document is the property of PT. Alstom Grid and cannot be used, reproduced or transmitted to thirds without
Operating Instruction Title: Site Quality Plan Doc. No : A-FA-I-001, Rev.A Page: 7/8
DRAWING LIST FOR CONSTRUCTION
Operating Instruction Title: Site Quality Plan Doc. No : A-FA-I-001, Rev.A Page: 7/8
LIST OF CASE /EQUIPMENT
Operating Instruction Title: Site Quality Plan Doc. No : A-FA-I-001, Rev.A Page: 7/8
INSTALLATION EQUIPMENT
No Material Designation Qty Location Document Title Document Rev. Remark(s)
Code number
Operating Instruction Title: Site Quality Plan Doc. No : A-FA-I-001, Rev.A Page: 7/8
COMMISSIONING EQUIPMENT
This document is the property of PT. Alstom Grid and cannot be used, reproduced or transmitted to thirds without