The document provides assembly steps for BG series valves, beginning with spot welding the valves to the pipeline for preliminary fixation. It then instructs to fully open the ball valve, disassemble bolts, and remove the valve body to clean. Next, the document details fully welding the flanges to the pipeline, cooling them, and reassembling the valve body with bolts before closing the ball valve.
The document provides assembly steps for BG series valves, beginning with spot welding the valves to the pipeline for preliminary fixation. It then instructs to fully open the ball valve, disassemble bolts, and remove the valve body to clean. Next, the document details fully welding the flanges to the pipeline, cooling them, and reassembling the valve body with bolts before closing the ball valve.
The document provides assembly steps for BG series valves, beginning with spot welding the valves to the pipeline for preliminary fixation. It then instructs to fully open the ball valve, disassemble bolts, and remove the valve body to clean. Next, the document details fully welding the flanges to the pipeline, cooling them, and reassembling the valve body with bolts before closing the ball valve.
1. Take out fully assembled BG series valves from packing bag;
Spot welding the valves to pipeline. ***Notes*** The purpose is preliminary fix, three or four spots should be enough; Normally, slightly spot welding only produce small amount of heat and won’t hurt flange seal. 2. Fully turn on the ball valve ( the handle direction should as follow figure shown), disassemble all bolts(Part#1,#2,#3,#4); 3. Take away the valve body(Part#6) to clean and safety place; Take necessary measures to ensure no scratch or pollution happens to the flange face (Part#5) & flange seal surface (Part#6); 4. Fully welding Part#5 to pipeline. 5. Assemble valve body(Part#6) with bolts after two flanges cool down (The right direction of bolts should as follow figure shown); Turn off the ball valve.