Professional Documents
Culture Documents
Claim Management
Claim Management
Outcomes
Learn
• Why Construction companies often do not submit claims
• Common Reasons for rejection of claims
• Types of variation claims
Overview
What is a claim?
► A request for a benefit which a claimant believes or contends he is entitled to
Breach of
Obligation
Damage to
Other Party
Claim
Construction Claims-underlying Principle
• Acceleration claims
Forms of Claims
► Excusable delay
a. Non compensable
b. Compensable
Two types:
► NON COMPENSABLE- this delay normally encompasses such things as strikes- unusually severe
weather, acts of god, fires, floods, etc..
► Compensable
Forms of Claims-excusable
Compensable delay
For a contractor to request both a time extension and compensation for it, he must
demonstrate that the client was the cause of that delay & consequent financial loss.
Or
It should be mentioned as an Employer Risk Event in the contract
Forms of Claims-inexcusable
Entitlement?
► For an inexcusable delay, the contractor receives neither a time
extension nor additional compensation;
CONCURRENCY
• TRUE CONCURRENCY AS DEFINED BY SCL PROTOCOL : TWO OR MORE EVENTS OCCURING AT
THE SAME TIME WHERE PARTIES TO THE CONTRACT ARE EACH RESPONSIBLE INDEPENDENTLY
FOR DIFFERENT EVENTS AND WITH EQUAL EFFECT ON CRITICAL PATH- RARE CASE.
• OTHER CASES
• DELAYS BY CONTRACTOR AND EMPLOYER OVERLAP
• EVENTS AT DIFFERENT TIMES BUT EFFECTS FELT AT SAME TIME
• IF EMPLOYER’S EVENT OCCURS AFTER COMMNENCEMENT OF CONTRACTOR’S DELAY UT
CONTINUES IN PARALLEL
• DELAY DUE TO EMPLOYER OCCURING DURING A PERIOD WHEN DELAY IS ALREADY OCCURING
FOR A CAUSE WHICH DOES NOT GIVE RISE TO ENTITLEMENT , THEN PROLONGATION COSTS
CANNOT BE RECOVERED
• PRINCIPLE – CONTRACTOR CANNOT RECOVER DAMAGES FOR DELAY IN CIRCUMSTANCES
WHERE EXACTLY THE SAME LOSS WOULD HAVE OCCURRED DUE TO CAUSES WHICH ARE THE
RESPONSIBILTY OF THE CONTRACTOR. “THE BUS WAS GOING THERE ANYWAY:
• CONVENTIONAL APPROACH – EOT ONLY IF EMPLOYER RESPONSIBLE EVENT HAD AN EFFECT
WHICH LASTED MORE THAN CONTRACTOR RESPONSIBLE DELAY
EXAMPLE
LABOUR - 40%
MATERIAL - 40%
INDIRECT COSTS - 10%
OH - 5%
PROFIT - 5%
TOTAL -100%
Week 1 2 3 4 5 6
Zone A(Mh) planned 2000 2000 2000
Zone A production (Ton) 10 10 10
Zone A productivity 200 200 200
Zone B(Mh) planned 2000 2000 2000
Zone B production (Ton) 10 10 10
Zone B productivity 200 200 200
Zone A performed(Mh) 2100 2000 2200
Zone A production Tons 10 10 10
Zone B Performed (Mh) 3000(site access 3000 (site access blocked 2800
blocked by by Employer) (Rainfall)
Employer)
Calculate additional labour costs assuming per hour cost of labour is Rs 120
On the above information and the following simplistic analysis, the Contractor is entitled to
be paid …..in additional costs that it incurred, as illustrated in the following formula:
Actual North Cross
Taxiway Production
Actual South Cross
Taxiway Production
Hours 10,116.00 51,969.00
Square Metres Produced 102,256.00 281,746.60
Hours/Square Metre .099 .184
Increase in Unit Labour Rate 0.086
Quantity Affected by Blockout and Light Change 281,746.60
Increased Rate 0.086
Manhour Increase Due to Change 24230.20
Labour Cost per Manhour 120
Total Additional Labour Cost 2,907,624.91
Workshop – Calculating Disruption Costs- Example
Variation Claims
Variation Claims
• Additional item
• Substitute item
• Extra item
• Change in specifications
• Change in sequence
• Omissions
• Changes in law
• Changes in contract conditions
• Changes in working conditions
• Force Majeure/Neutral Events
• Any other instructions issued by Employer
Negative Variations
Some contracts may entitle contract to loss of profit for negative variations
Nil Impact Varaitions
Example – Contractor has given rate of 2800 per m2 for formwork for retaining wall
Qty – 576m2 – 24 bays – 3 m high
Engineer issued variation order reducing retaining wall to 16 bays- 384 m2 after shuttering had been ordered but before
work commencement on retaining wall. Contractor informed Engineer that in pricing the item he had allowed for a
purpose built steel shutter 8x3 m at capital cost of 600000
Assume – 8% site OHs and 10% HOOH and Profit
BoQ rate- based on 576 m2 = 2800
Less 10% HOOH and profit =
(2800/110) X 100 = 2545
Less 8% site OH =
(2545/108) X 100 = 2356
Material – purpose built steel shutter – 600000 /576 =1042
Remaining costs – labour, plant, erection , cranage= 1314
Calculating for variation
Labour, plant , erection , cranage – 1314
Material – purpose built shutter
Contractor entitled to recover full cost = 600000/384 = 1563
Total – 2877
Add 8% site OH = 3107
Add 10 % HOOH and profit = 3418 /m2
Variation costs
• Demolition
• Labour, machinery
• Loading and transportation
• Protection of nearby works
• Services
• Supervision and management costs
• Subcontractor and suppliers costs
• Additional drawings preparation and vetting costs
• Temporary works
• Additional security
Acceleration Claims
Acceleration Claims
• On Employer’s instructions
• Completing same work in shorter time
• Employer grants EOT and then asks contractor to complete in original
time period
• Contractor delayed due to Force majeure?
• Contractor delayed due to own fault?
• Employer refuses contractor’s requests for EOT?
Acceleration Claims
• Ensure new schedule is submitted and accepted by the Employer
• Failure to achieve new completion date may lead to LD even if the
project is completed before the original scheduled date of completion
• Submit both original and accelerated schedule
How is acceleration achieved?
• Working longer shifts
• Working on holidays
• Using more equipment
• Using better or larger equipment
• Changing construction methodology(eg use of precast components)
• More labour
• Different material- rapid hardening cement
Acceleration Claims
Cost to include
• Mobilization of additional equipment, people, transport, non-
productive time
• OHs for additional equipment and employees- shelters, garages,
lighting
• Overtime costs
• Loss of productivity due to
• Congested work areas
• Employees working longer shifts
• Disruption in continuity of work
• Additional costs to change methods of construction
• Subcontractor and supplier costs
• Additional supervision and management costs
Claims for contractor termination
Termination Due to Contractor’s Fault
Employer’s Entitlement
• Encashment of Performance Guarantee
• Using Retention money of contractor
• Risk and Cost for completion of balance work
• Any losses and damages suffered by the Employer
• Delay damages
• Confiscation of contractor’s material and tools and plant at site
Termination for Convenience
When done:
• Employer no longer desirous of balance work
• Balance work incapable of execution
• Can the Employer do TFC anytime?
• What if Employer wants to execute balance work later on?
Termination for Convenience
Claim of Contractor
• Cost of works executed
• Any other cost or liability reasonably incurred in expectation of
completion of work
• Cost of removal and equipment and return to contractor’s ordinary
place of business
• Cost of repatriation of staff and labour
• Loss of profit?
Escalation Clause
Escalation Clause
• For increase /decrease of cost of items
• During the period of construction
• From last date of submission of tender
• Upto completion date of work
• Contractor submits bids considering rates of items on day of
submission of tender
• Employer fixes last date of tender submission
• Basis considered by Employer
• Last date of tender submission even if contractor had submitted earlier
Escalation Clause
• Works contracts has 100s of items
• Only limited Nos considered individually
• Rest may be grouped
• Some may not be considered
Major components
• Labour
• Skilled , unskilled , semiskilled
• Steel
• Rft bars
• Structural steel
• FOL
• Bitumen
• Sand, aggregate
Escalation Clause