Indonesia Batam-Bintan Bridge Project ES Consultant ToR - May 2022

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 27

*OFFICIAL USE ONLY

INDONESIA BATAM-BINTAN BRIDGE PROJECT – E&S Consultant Terms of Reference

INDONESIA BATAM-BINTAN BRIDGE PROJECT


Environmental and Social Consultant – Terms of Reference

1. Introduction
The Ministry of Public Works and Housing of Indonesia (the Ministry) is preparing the Batam-Bintan Bridge
Project (the Project). The project consists of the construction of a fixed road crossing between the Batam and
Tanjung Sauh Islands. This crossing would be a segment of the proposed Batam-Bintan inter-island road
crossing which consists of: (i) a road access to a fixed bridge crossing between Batam Island and Tanjung
Sauh Island; (ii) a fixed bridge crossing between Batam Island to Tanjung Sauh Island; (iii) a road
connecting the Batam-Tanjung Sauh Bridge, on Tanjung Sauh Island, to a bridge connecting Tanjung Sauh
Island to Bintan Island; (iv) a fixed bridge crossing between Tanjung Sauh Island to Bintan Island; and (v) a
road access on Bitan Island to the fixed bridge crossing between Tanjung Sauh Island and Bintan Island.
This crossing will be the only fixed permanent crossing between Batam and Tanjung Sauh Islands. The
Ministry is seeking Asian Infrastructure Investment Bank’s (AIIB) financing the Batam-Tanjun Sauh
segment of the crossing. The following picture shows the indicative alignment and the scope of AIIB’s
proposed financing in the red circle.

Figure 1 Indicative Alignment of Batam-Bintan Bridge Project

The AIIB seeks to engage an experienced Environmental and Social Consultant (“the Consultant”) to bring
the Project and related environmental and social documentation into compliance with the AIIB’s
Environmental and Social Policy (“ESP1”) and corresponding Environmental and Social Standards (ESS) 1
(Environment and Social Assessment and Management), ESS 2 (Involuntary Resettlement), and ESS3
(Indigenous Peoples).

2. Scope of Work
Overview
The Ministry, with the provincial government of Riau Islands, has prepared a Feasibility Study for this
Project and been conducting the engineering detailed design for the bridge and the approach roads. An
Environmental Impact Assessment (hereinafter “AMDAL”) has been prepared by a local consultant engaged
by the provincial government. The AMDAL is meant to satisfy the environmental requirements of Indonesia.
The provincial government has also prepared a Land Acquisition Planning Document (LAPD). However,
certain components of the ESP and ESSs are not addressed in the AMDAL and the LAPD. The purpose of
the assignment is to prepare an Environmental and Social Impact Assessment (ESIA) and a Resettlement or
Livelihood Restoration Plan that fully addresses AIIB’s ESP and ESSs with consideration to existing
information and assessments found in the AMDAL and LAPD.

1
The ESP is available at https://www.aiib.org/en/policies-strategies/_download/environment-framework/Final-
ESF-Mar-14-2019-Final-P.pdf

1
*OFFICIAL USE ONLY
INDONESIA BATAM-BINTAN BRIDGE PROJECT – E&S Consultant Terms of Reference

Most of the baseline information required to develop the ESIA and address the ESP and ESSs are contained
in the existing AMDAL (to be finalized). Apart from AMDAL, a separate Biodiversity Baseline Study is
commissioned to another consultant (herein after Biodiversity Consultant), which will provide inputs to the
preparation of the ESIA. However, certain complements will be required, particularly in regards of
biodiversity assessment in accordance with international standards. In addition, documents typically required
by international standards, including Cumulative Impact Assessment (CIA), Environmental and Social
Management Plan (ESMP) and a Stakeholder Engagement Plan (SEP) will also need to be prepared to fully
meet the ESP. Similarly, a social impact assessment needs to be conducted on (i) the identified affected
persons in the LAPD and (ii) other potentially affected persons not captured in the LAPD.
The scope of work includes the following five tasks:
- Task A – Familiarization with the Project, site visit and review of documentation
- Task B – Biodiversity assessment and Critical Habitat Assessment with the input of biodiversity
baseline provided by other party
- Task C – Cumulative Impact Assessment
- Task D – Preparation of ESIA with Executive Summary (ES) and ESMP
- Task E – Additional Stakeholder Consultations and Preparation of SEP
- Task F – Census and socio-economic survey covering 100% of affected households and
preparation of a Resettlement and/or Livelihood Restoration Plan (RLRP) with Executive
Summary (including translation in local language)
Given the specific environmental and social (E&S) aspects of the location and length of the bridge and the
approach roads, it requires an in-depth analysis and consideration of all aspects, from engineering to E&S
and financial aspects, all in a coordinated fashion. Thus, the early and continuous integration between all
parties involved in the preparation of the project is extremely important. In particular, the Consultant is
expected to work closely with other consultants such as the Biodiversity Consultant and the engineering
design team. These tasks are presented in further detail in succeeding sections of the present ToRs.

Task A – Familiarization with the Project, site visit and review of documentation
The Consultant shall:
- Review all available documentation, including the Feasibility Study report, the draft engineering
detailed design for the bridge and the approach roads, the draft AMDAL, the LAPD, provincial and
regional planning and any other relevant documentation available from the Ministry and the
provincial government;
- Liaise with provincial government and obtain relevant permitting documentation available at the
time of the Consultant’s assignment;
- Prepare a Scoping Report identifying gaps based on existing documents and action needed to meet
AIIB ESP and ESSs requirements and propose methodology to fill in the gaps;
- Scope the supplemental baseline monitoring based on a detailed review of existing information and
data
- Review and provide comments on the scoping/ proposal of the biodiversity baseline study to be
conducted by the Biodiversity Consultant;
- Carry out primary monitoring to supplement the environmental baseline if there was any gap in the
existing data, except the biodiversity baseline;
- Review socio-economic data and available data regarding land acquisition;
- Review available social surveys, consultations and other due diligence activities carried out and
determine gaps against ESS2 requirements.
- Visit the Project sites and Project area;
- Conduct preliminary consultations with major project stakeholders

2
*OFFICIAL USE ONLY
INDONESIA BATAM-BINTAN BRIDGE PROJECT – E&S Consultant Terms of Reference

- Conduct Socio-economic Baseline (sex-disaggregated male/female data on economic conditions,


demography, accommodation types, local services available; socio-cultural; vulnerable groups –
including persons with disabilities). These should include gender-based violence related data at the
country level and project area level (i.e. whether project site are near places frequented by women
and/or girls) and description of relevant stakeholders regarding this concern. The socio-economic
baseline should confirm absence or presence of Indigenous Peoples in the community.
- Collect baseline information and conduct necessary surveys within the scope of cumulative impact
assessment (Task C).
All technical, engineering, and environmental and social (E&S) documentation produced to-date is in the
Bahasa language.

Task B – Biodiversity assessment and Critical Habitat Assessment with the input of biodiversity baseline
provided by other party
A Rapid Assessment of Crab Fauna in the project area was carried out in Jan-Mar 2022, the report of which
is available for the consultant’s reference. The Biodiversity Consultant will conduct a comprehensive
biodiversity baseline survey and provide inputs to the Critical habitat Assessment (CHA). The biodiversity
baseline study report will be ready prior to the CHA. Based on the inputs from the Biodiversity Consultant
and existing baseline information as reflected in the AMDAL, the Consultant shall in accordance with IFC
Performance Standard 6 (PS 6):
- Identify any threatened species and compare against the IUCN Red list and the protected plant and
animal species based on government regulations in Indonesia (jenis tumbuhan dan satwa yang
dilindungi berdasarkan Peraturan Pemerintah);
- Carry out critical habitat screening against the criteria as defined in PS6; if triggered, conduct a
Critical Habitat Assessment (CHA) according to PS6 and its guidance note;
- Use satellite imagery and GIS data for analysis of ecosystem at landscape level;
- Review and update the existing assessment on ecological environment in AMDAL to a
comprehensive biodiversity impact assessment as part of the ESIA that covers all potential impacts
at landscape, ecosystem and species levels;
- Analyze the loss of ecosystem services but quantitative analysis is not mandatary.
- Incorporate the conclusions and recommendations of the rapid assessment report for crab fauna into
this biodiversity impact assessment; Review the existing designs of the bridge and the approach
roads and evaluate if sufficient facilities (e.g. culverts, bridges) have been provided for wildlife
crossings or protection to the habitats and ecosystems, and inform the design with suggested
changes/measures;
- Provide mitigation measure for any impacts on biodiversity that could not be avoided;
- Prepare a holistic Biodiversity Management Plan (BMP) to address impacts of this project and
potential cumulative impacts (Task C). The BMP shall ensure the “net gain” if critical habitat is
triggered; otherwise “no net loss” of biodiversity shall be demonstrated, in accordance with AIIB
ESP and IFC PS6. The BMP will establish a mechanism of inclusion of stakeholders in biodiversity
management, including government agencies, local communities, and NGOs. A Biodiversity
Monitoring Plan will also be developed as part of the BMP for the monitoring in preconstruction and
construction phases and long-term monitoring. The budget and resources required for the
implementation of the BMP will be discussed in the BMP.

Task C – Cumulative Impact Assessment


The Consultant will carry out the CIA following the six-step methodology defined in IFC’s Handbook 2:
- Step 1: Determine spatial and temporal boundaries;
2
https://www.ifc.org/wps/wcm/connect/58fb524c-3f82-462b-918f-0ca1af135334/
IFC_GoodPracticeHandbook_CumulativeImpactAssessment.pdf?MOD=AJPERES&CVID=kbnYgI5

3
*OFFICIAL USE ONLY
INDONESIA BATAM-BINTAN BRIDGE PROJECT – E&S Consultant Terms of Reference

- Step 2: Identify the Valued Environmental Components (VEC) based on inputs from stakeholders;
and identify all developments and external natural and social stressors affecting the VECs;
- Step 3: Determine present conditions of VECs;
- Step 4 and 5: Assess cumulative impacts of the project and multiple other development activities
identified in Step 2 and evaluate their significance over VEC’s predicted future conditions;
- Step 6: Design and implement: (a) adequate strategies, plans, and procedures to manage cumulative
impacts, (b) appropriate monitoring indicators, and (c) effective supervision mechanisms.
Based on preliminary information, the planned and ongoing development activities that might be considered
in the CIA include but not limited to:

- A general cargo and container port at Batu Ampar (north Batam Island) ;
- The Tj. Uncang Industrial Park ;
- An International Convention Center ;
- Kabil container port on Tj. Sauh island ;
- A new international hospital and a polytechnic college ;
- A waste water treatment system ;
- The Bintan Intelligent Island; and
- The Batam Public Gas Facility.
Special attention shall be given to the cumulative impacts on the biodiversity values. Thus, biodiversity-
related values should be considered important VECs in the CIA. The Consultant shall conduct the
assessment of cumulative biodiversity impacts at landscape and ecosystem levels with the support of GIS
and quantitative or semi-quantitative analysis is preferred. Analysis on ecosystem services is required but
quantitative analysis is not mandatary. The Consultant is also expected to assess the cumulative impacts on
key species identified in the biodiversity impact assessment. The CIA on biodiversity will serve as inputs for
the preparation of the BMP (Task B).
Task D –Preparation of ESIA with Executive Summary (ES) and ESMP
The Consultant shall prepare an ESIA to fill in the gaps and meet the requirements of the ESP. Large
sections of the AMDAL can be reused with minimal amendments. Annex 1 provides the proposed indicative
structure of the ESIA. The Consultant shall prepare one consolidated ESIA for all three components of the
Project.
While the AMDAL is still under preparation, the gaps between the AMDAL and AIIB ESP and ESS1 are not
clear at this stage. The Consultant shall pay attention to the following aspects where gaps often exist in
previous similar projects.
- The project description should include construction features such as quarries, borrow pits and
disposal areas, approach roads established for construction purpose if any, etc., and a brief
description of construction activities, including methods and timelines.
- A list of national environmental and social legislation, a comparison with AIIB’s ESP and ESSs and
measures to fill the gaps should be discussed.
- The analysis of alternatives should be presented in an E&S perspective to the comparison. The
alternatives that the consultant could analyze may include with and without project scenario,
alignment alternatives, various bridge type, approach road alignment alternatives, as well as
alternative construction methods (e.g. pavement, quarries) if any. E&S criteria should be considered
in the comparison.
- Noise modelling should be carried out for operation phase based on the design traffic.
- Quantitative calculation of greenhouse gas (GHG) is needed for operation phase.
- A climate risk assessment is required to identify the major climate risks to the Project, via external
tools and climate change models.
- Analysis of climate adaption/ resilience will be carried out to elaborate how the climate risks to the
projects are addressed in the Project design.

4
*OFFICIAL USE ONLY
INDONESIA BATAM-BINTAN BRIDGE PROJECT – E&S Consultant Terms of Reference

- This is a Project with special requirements on Occupational Health and Safety (OHS) given that it is
a large bridge project. Thus, the Consultant should pay special emphasis to assessment of OHS and
road safety risks (e.g. risks to road users/communities due to the traffic) during construction and
operation and maintenance (O&M). Mitigation measures and OHS management should be proposed
in the ESIA.
- The biodiversity impact assessment as described in Section 2.3 (Task B).
- Cumulative impact assessment as described in Section 2.4 (Task C).
- The social impact assessment will need to be developed. Impacts to consider include those arising
from land acquisition (permanent and/or temporary limited economic and/or physical displacement
to those who have formal and informal land users) and other project activities. These include
changes in population, accommodation requirements, demand for local services, traffic disruption,
restriction of community access, and presence of workforce, which will be summarized in the ESIA.
Other social impacts due to the construction and operation of the Project will also be assessed in the
ESIA, e.g. impacts on public utilities, disturbance to the accesses and the traffic, and community
health and safety. The social impact assessment should also identify impacts on livelihood arising
from other project activities apart from land acquisition i.e. impacts on fishing communities or other
livelihood sources that may be impacted by project activities.
- Conduct labor influx risk assessment, specifically whether labor influx may lead to social conflict,
illicit behavior and crime, bring in additional population (e.g. family members), impacts on
community dynamics; increase burden on competition and public service provision; increase risk of
communicable diseases and burden on local health services; gender-based violence; child labor;
inflation on price; impact on accommodation and rent; traffic and related accidents.
- Gender and social inclusion assessment. Based on the socio-economic baseline and social impact
assessment, determine whether bridge/road designs include measures for ensuring application of the
concept of universal access for persons with disabilities and any other vulnerable persons with
limited accessibility; access of women, poor and other vulnerable individuals/groups to opportunities
generated by the project activities.
The ESIA will include an Executive Summary and an ESMP. The ESMP will build and broaden the
environmental protection measures proposed in the existing AMDAL, design documents, for both the
construction and operation phases. In particular, the ESMP will include an OHS Management Plan and an
Adaptive Management Plan in the case of project/design change. The ESMP shall also set out measures to
address social-related impacts identified in the assessment specifically but not limited to labor influx, GBV,
and gender and social inclusion. The ESMP will also include grievance redress mechanism (GRM) for
project-affected people and workers with provisions on concerns regarding gender-based violence. The
ESMP should also include description of AIIB’s Project-Affected People Mechanism and how this can be
accessed.
The structure of ESIA is provided in Annex 1. The ESIA report including the ESMP shall be prepared in the
English and Bahasa languages; the Executive Summary will be prepared in the English and Bahasa
languages.

Task E – Additional Stakeholder Consultations and Preparation of Stakeholder Engagement Plan (SEP)
The local consultant has already carried out public consultations per the requirements of Indonesia during the
process of AMDAL preparation. The stakeholder engagement will need to be strengthened to meet AIIB’s
ESP requirement of meaningful consultations with views and concerns of the potentially affected
communities adequately addressed.
The Consultant shall conduct additional stakeholder consultations during the supplemental surveys (e.g. with
communities/entities to be affected) and document the outcomes. The documentation of consultations
conducted during the biodiversity baseline study will be provided to the Consultant. The Consultant will also
facilitate one public consultation meeting to be organized by the implementation agency in the project area
after the draft E&S documentation (ESIA and RLRP) is disclosed. The feedback received at the
consultations shall be incorporated into the ESIA. The consultant shall conduct separate consultations/focus
group discussions among women in the community and vulnerable groups especially people with disability.

5
*OFFICIAL USE ONLY
INDONESIA BATAM-BINTAN BRIDGE PROJECT – E&S Consultant Terms of Reference

A concise Stakeholder Engagement Plan during implementation of the Project will be prepared, taking
consideration of activities already undertaken and objectives and requirements of AIIB’s ESP. At a
minimum, it should address:
- The identification of key stakeholders (stakeholder mapping);
- The description of past consultation activities, their outcomes (including the ones to be conducted by
the Consultant);
- A commensurate consultation plan during the implementation of the Project, involving consultation
methods suitable in the social and administrative context of the Project. Special consideration will be
given to enable participation of vulnerable project affected people, such as elderly people, who may
otherwise face barriers to participate.
- A disclosure plan specifying where and how Project E&S documentation will be available to the
public;
- A description of the GRM for the community and workers;
- Roles and responsibilities of key entities.

The structure of this SEP is provided in Annex 2. The document should be concise. The document will be
prepared in the Bahasa and English languages.

Task F – Preparation of Resettlement or Livelihood Restoration Plan


The consultant shall prepare a Resettlement and/or Livelihood Restoration Plan depending on the identified
impacts. In preparing the document the consultant shall (i) review prevailing national and local laws and
regulations, administrative arrangements and requirements, and budgetary processes relevant to land
acquisition and involuntary resettlement against AIIB and ESS 2 requirements and recommend gap-filling
measures as needed to be applied in the proposed project; (ii) conduct and fully document meaningful
consultations with affected households and other relevant stakeholders including CSOs/NGOs, work closely
with government agencies/departments responsible for land acquisition and resettlement; (iii) assess the
potential resettlement and other impacts and determine whether measures were taken to avoid or minimize
such potential impacts; (iv) conduct the necessary surveys to update and/or determine the scope and
magnitude of land acquisition impacts and impacts arising from other activities of the proposed project
including census to obtain socioeconomic data of project-affected households; (v) collect an inventory of
types and extent of losses of each affected household, including a detailed inventory of loss or detailed
measurement survey of affected assets for all project affected persons to establish loss of fixed assets such
as structures and trees, livelihood or access to community resources as a result of project implementation on
the road or bridge influence area; (vi) determine the replacement costs of all categories of losses; (vii)
identify severely affected households, including those losing 10% or more of total affected assets and
relocating households, and also vulnerable affected households including those without secure tenure to the
land they are using, including workers if any, and ensure that additional assistance is provided for these
households; (viii) map social and cultural characteristics of displaced communities and other vulnerable
groups affected by the project including a description of formal and informal institutions that may be
relevant to the consultation strategy and to designing and implementing the resettlement activities; (ix) carry
out necessary additional need assessment on livelihood restoration program of the affected
persons/households and assess; (x) assess institutional capacity and propose the institutional arrangement for
the approval and implementation of the resettlement plan/livelihood restoration plan. Please refer to Annex 3
for detailed guidance on Task E.

3. Deliverables
As identified in section 2, the Consultant shall prepare the following documentation:
- Scoping Report. The document will be in the English.
- Environmental and Social Impact Assessment for Batam-Bintan Bridge Project (including the
ESMP). The document will be in the English and Bahasa languages.
6
*OFFICIAL USE ONLY
INDONESIA BATAM-BINTAN BRIDGE PROJECT – E&S Consultant Terms of Reference

- A Land Acquisition and Resettlement/Livelihood Restoration Plan with Executive Summary. The
document will be in both the Bahasa and English languages.
- A Stakeholder Engagement Plan. The document will be in both Bahasa and English languages.
- An Executive Summary of the Environmental and Social Impact Assessment for Batam-bintan
Bridge Project. The document will be in both Bahasa and English languages.

4. Team Required and Implementation Schedule


4.1 Team
The Consultant’s team should include Bahasa-speaking experts with significant experience in Indonesia. The
required qualification and experience of key experts are shown in the table below.

No. Key Expert Minimum Qualification


And Experience
1 Team Leader - Senior The candidate should have master’s degree or equivalent in
environmental Specialist/ environmental engineering/science with minimum 15 years of
engineer experience of which at least 10 years on environmental impact
assessment of infrastructure projects particularly road projects and
experience of preparing environmental management plans. The
candidate must have full knowledge of MDB’s E&S Policies.
Experience in Indonesia is essential. Experience of working as
environmental expert in MDB (World Bank, ADB or IFC) funded
projects with similar level of complexity (for E&S assessment and
management) is required. Fluent in the English language. Fluent
Bahasa is preferred.
2 Deputy Team Leader - At least 15 years of experience working on social development
Senior Social Development issues and Social Impact Assessments and Management Plans.
Specialist Some experience should also be in infrastructure projects and labor
issues. Experience of working on development projects in Riau
Islands Province will be preferred will be preferred. Experience of
working on MDB funded projects will be essential. S/he should
have a post-graduate degree in a relevant social science
(development studies, sociology, urban studies, anthropology, etc.)
Fluent in the Bahasa and English languages.
3 Environmental Specialist/ The candidate should have bachelor’s degree in environmental
Engineer science or engineering or related area with minimum 7 years of
experience of which at least 5 years on environmental impact
assessment of infrastructure projects particularly road projects and
experience of preparing environmental management plans for the
same. Experience in Indonesia is essential. Experience of working
on MDB funded projects will be advantageous. Fluent in the Bahasa
language. Fluent English is preferred.
4 Senior Biodiversity An advanced degree in ecology or any other biological field. At
Experts / Ecologist least 10 years of extensive working experience of marine and
coastal ecological surveys and biodiversity management; knowledge
in freshwater and or marine ecology is preferred. S/he should be
familiar with IFC Performance Standard 6. Experience of Critical
Habitat Assessment against PS6 is essential. Fluent in the English
language.
5 OHS Specialist The candidate should hold a Certificate issued by recognized OHS
qualification, such as NEBOSH / IOSH / OSHA or other regionally
recognized qualification or degree in OHS, public health or related
field. Minimum 10 years of relevant professional experience, of
which 5 years of experience as an OHS practitioner for

7
*OFFICIAL USE ONLY
INDONESIA BATAM-BINTAN BRIDGE PROJECT – E&S Consultant Terms of Reference

No. Key Expert Minimum Qualification


And Experience
constructions. Experience in OHS of bridge project is preferred.
Fluent in the English language.
6 Social Development At least 10 years of experience working social development issues
Specialists and Social Impact Assessments and Management Plans. Some
experience should also be in infrastructure projects and labor issues.
Experience of working on development projects in Riau Islands
Province will be preferred. Experience of working on MDB funded
projects will be advantageous. S/he should have a post-graduate
degree in a relevant social science (development studies, sociology,
urban studies, anthropology, etc.)
7 Gender Specialist/Social At least 10 years of experience working on gender issues and/or
Inclusion Specialist social inclusion. Experience of working on development projects in
Riau Islands Province will be preferred. Experience of working on
MDB funded projects will be advantageous. S/he should have a
post-graduate university degree in a relevant social science (gender
studies, development studies, sociology, etc.)

The Consultant’s offer will include a clear description of all proposed specialists’ credentials, as well as their
CVs and exact time inputs for the job. Experience in Indonesia should be stressed in the description of
credentials.

4.2 Implementation Schedule


The services should be implemented over a period of four months from Signature of Contract to submission
of the draft package.

8
*OFFICIAL USE ONLY
INDONESIA BATAM-BINTAN BRIDGE PROJECT – E&S Consultant Terms of Reference

ANNEX 1 – PROPOSED ESIA STRUCTURE

1. Executive Summary
The Executive Summary (ES) should provide a general summary of the ESIA and ESMP
contents and key findings, in a vocabulary that is easily understood by the public at large. It
should be clear and concisely discusses significant findings and recommended actions. The ES
should succinctly describe the process and outputs of ESIA and ESMP.
2. Introduction
This chapter will introduce the ESIA describing its background, objectives, principles, process
and methodology. This chapter should introduce the project proponents, the study team, and
provide other relevant information. The layout of the ESIA report should also be described to
facilitate its use. A project map should be presented in this chapter.
3. Legal and Administrative Framework and Gap Analysis

This will discuss the policy, legal, and administrative framework within which the ESIA is
carried out and identifies relevant international environmental agreements to which the country
is a party. It will also discuss the AIIB ESP applicable to the project, the World Bank Group
Environmental, Health and Safety Guidelines (ESHGs), and other relevant Good International
Industry Practice (GIIP). This section will compare the country’s existing environmental and
social framework and AIIB ESP and ESSs and identifies the gaps between them. The consultant
will do this by review legal and administrative framework section in the AMDAL and update
them as needed.
4. Description of Project
This chapter will provide a brief description of the project to place the ESIA in the relevant
context. This would include a summary of the background to the project, its various
components, construction activities, temporary and permanent facilities to be established as part
of the project, manpower requirements and labor camps, machinery and plant to be used for
construction, requirements of various supplies including water and fuels, borrowing materials,
and wastes streams generated. The cost and implementation schedule of the project should be
also introduced. All phases of the proposed project including design and engineering,
construction, and operation and maintenance will be covered in this Chapter. A map with
sufficient detail, showing the project site and the area that may be affected by the project’s
direct, indirect, and cumulative impacts should also be included.
5. Analysis of Alternatives
This section should systematically compare feasible alternatives to the proposed design, and
operation–including the “without project” situation—in terms of their potential environmental
impacts. In addition to the no-project scenario, feasible alternatives to design and operation shall
be systematically compared and summarized in the chapter. Particular attention will be given to
the environmental and social consideration of each alternative. It should assess the alternatives’
feasibility of mitigating the environmental and social impacts; the capital and recurrent costs of
alternative mitigation measures, and their suitability under local conditions; and the
institutional, training, and monitoring requirements for the alternative mitigation measures. For
each of the alternatives, the environmental impacts should be quantified to the extent possible
and attaches economic values where feasible. The summary of evaluation will be presented in
tabular form also.

9
*OFFICIAL USE ONLY
INDONESIA BATAM-BINTAN BRIDGE PROJECT – E&S Consultant Terms of Reference

6. Associated Facilities
Describe activities that are not included in the description of the Project set out in the agreement
governing the Project, but that the Bank determines, following consultation with the Client, are:
(a) directly and materially related to the Project; (b) carried out or planned to be carried out,
contemporaneously with the Project; and (c) necessary for the Project to be viable and would
not be constructed or expanded if the Project did not exist. Identify and assess the potential
environmental and social risks and impacts of Associated Facilities and assess level of control
or influence of the project sponsor/implementing entity over the associated facility. If no
associated facilities are identified, this section can be omitted.
7. Environmental and Social Baseline Analysis
This chapter of the ESIA will assess the dimensions of the study area and present findings of the
literature review, environmental instrument monitoring, field surveys, social and economic
surveys and data collection conducted at the proposed study areas. The environmental and
socioeconomic baseline data will be collected from secondary as well as primary sources to
establish an environmental and socioeconomic baseline for the proposed project area. The
description will cover relevant physical, biological and socio-economic conditions of the project
area, including any changes anticipated before the project commences, taking into account
current and proposed development activities within the project area but not directly connected to
the project. The biodiversity baseline will be provided by the Biodiversity Consultant.
Data and description should be relevant to decisions about project location, design, operation, or
mitigatory measures. Furthermore, the trends in the key environmental parameters of the area
should also be described. The sensitive receptors will be identified in this chapter.
8. Impact Assessment and Mitigation Measures
This chapter will first present the process and outcome of the scoping carried out early during
the study and identify which impacts are significant and the criteria used to make this judgment.
This will be followed by describing the methodology and outcome of detailed impact
assessment carried out during the assignment.
The chapter will present impact assessment during design phase, construction phase and
operation phase respectively, on physical, biological, social‐economic environment and the
climate. The analysis will cover issues of the proposed works and associated on-site and off-site
facilities (e.g., link and access roads, borrow pits, batching plant, labor camps if any,
transportation and storage of construction equipment and materials) if relevant. All generic and
site-specific impacts should be assessed.
The chapter will also include analysis of occupation and community health and safety (OHS and
CHS) related risks and impacts associated with civil work and potential labor influx including
GBV, VAC and SEA incidences. It will identify mitigation measures to prevent and address
such potential risks and impacts.
Appropriate impact avoidance, minimization, mitigation, and/or compensatory measures will be
detailed for each impact. The potential impacts, their significance, associated mitigation
measures will also be presented in a tabular form.
9. Cumulative Impact Assessment
This chapter will present the methodology, process and the findings of the Cumulative Impact
Assessment. This section will identify current and proposed activities and potentially induced
strip development within the project area, other foreseeable developments, analyze effects of

10
*OFFICIAL USE ONLY
INDONESIA BATAM-BINTAN BRIDGE PROJECT – E&S Consultant Terms of Reference

those development and activities and the incremental effects, estimate cumulative impacts and
provide recommendations for managing the cumulative impacts.
10. Environmental and Social Management Plan
ESMP will be the most important element of the ESIA. The key elements of ESMP will include
the following:
 Institutional Mechanism. An institutional mechanism for the implementation and monitoring
of ESMP shall also be formulated in the ESIA and the mechanism should clearly identify
the role of all the agencies involved in the Project implementation. The Consultant shall
assess the institutional capacity of Client pertaining to the projects. Based on the assessment,
the Consultant shall propose appropriate Institutional arrangement for effective
environmental and social management of the Project, i.e. organizational setup from the
Ministry, provincial department down to the implementation level, their respective
responsibilities, staffing for environmental and social management, and other resources
needed. A detailed institutional capacity building strategy shall be proposed for the Client,
Consultants and contractors.
 Mitigation plans, including measures for managing and mitigating various risks and impacts
of each proposed project activity identified, with responsibilities assigned for their
implementation and monitoring/supervision, along with monitoring indicators.
 Project-level management plans include not be limited to Occupation Health and Safety
Management Plan, Community Health and Safety Management Plan, Labor Management
Plan, Accommodation Management plan and Environmental Code of Practice, as well as
requirements on Contractor’s ESMPs and Code of Conduct. Include Adaptive Management
Plan in case of changes in design during project implementation.
 Internal monitoring and external monitoring arrangements with roles and responsibilities,
monitoring methodology and frequency, and documentation requirements. Two types of
monitoring will be described: compliance monitoring and effects monitoring.
 Capacity building requirements for various entities of the project.
 Documentation and reporting system.
 Cost of ESMP implementation.
11. Stakeholder Engagement
This chapter of the ESIA should present the objective, process, and outcome of the stakeholder
consultations carried out during the preparation of AMDAL, the ESIA and other associated
activities (i.e., RLRP preparation). Particular emphasis should be given on documenting the
views and comments of all categories of stakeholders including PAPs (men, women, young,
those with disabilities, old people, individual ethnic people intermarried and integrated into the
mainstream communities, and members of other population groups) and other stakeholders
(presentative of government officials, and civil society organizations, etc.). This chapter will
also explain how these comments have been or will be addressed. The record of consultation
and participation should be attached as an annex to the final ESIA. The chapter shall also refer
to the standalone Stakeholder Engagement Plan (SEP) that describes the stakeholder
engagement during the implementation.
As part of this chapter, the consultants will also develop a program for the disclosure of the
ESIA to facilitate the work of the client on this matter. The responsibility for both the disclosure
and dissemination however lies with the client.
12. Grievance Redress Mechanism.
This chapter describes an arrangement for receiving, evaluating and facilitating the resolution of
workers and affected people’s concerns, complaints, and grievances about the borrower/client’s

11
*OFFICIAL USE ONLY
INDONESIA BATAM-BINTAN BRIDGE PROJECT – E&S Consultant Terms of Reference

social and environmental performance on a project. A GRM is important for development


projects where adverse impacts or risks are ongoing or anticipated. GRMs for affected people
and workers respectively, the setups, operating modalities and procedures, taking into account
availability of judicial recourse and traditional community dispute settlement mechanisms as
well as how to ensure equitable access for men and women and different groups of population.

13. Conclusion and Recommendations


This chapter provides the conclusions drawn from the assessment and provides
recommendations, limits of study and further plans needed during project implementation.

14. Appendices

 List of the individuals or organizations that prepared or contributed to the environmental


and social assessment.
 Biodiversity Management Plan
 References: setting out the written materials both published and unpublished, that have
been used.
 Record of meetings, consultations and surveys with stakeholders, including those with
affected people and other interested parties. The record specifies the means of such
stakeholder engagement that were used to obtain the views of affected people and other
interested parties.
 Record of primary environmental monitoring reports
 Tables presenting the relevant data referred to or summarized in the main text.
 List of associated reports or plans.

12
*OFFICIAL USE ONLY
INDONESIA BATAM-BINTAN BRIDGE PROJECT – E&S Consultant Terms of Reference

ANNEX 2 – PROPOSED SEP STRUCTURE

Introduction and brief Project description


- Scope of the document
- Summary Project description

Legal requirements
- Legal requirements pertaining to public consultation and disclosure per Indonesian legislation,
particularly ESIA legislation; international conventions
- AIIB requirements: ESP

Stakeholder identification

The stakeholder identification should present a list of identified stakeholders in tabular form with the precise
identification of the stakeholder (if organization: name, legal status, address and contact information) and the
nature of their interest in the Project.

- Affected parties:
o Neighboring communities
o People and businesses potentially affected by the Project land acquisition
o Others (if any)
- Interested parties:
o Government institutions and agencies at national, provincial and local levels
o Local media (means of mass information)
o Conservation NGOs
o Other NGOs
o Others (if any)

Past consultation
- Consultation carried out as part of the Project Documentation and AMDAL preparation:
o Dates, outcomes
o Annex with relevant protocols

Engagement plan
- Present in tabular form the consultation measures for each of the phases of the Project (design,
construction, operations), including:
o Stakeholders targeted
o Description of measure
o Timeline

13
*OFFICIAL USE ONLY
INDONESIA BATAM-BINTAN BRIDGE PROJECT – E&S Consultant Terms of Reference

o Responsibility for implementation of consultation


o Documentation requirement
- Provide details on certain measures as warranted

Disclosure plan
- Present in tabular form the disclosure measures for each of the phases of the Project (design,
construction, operations), including:
o Stakeholders targeted
o Document or information disclosed
o Avenue where available (web, Project offices, local administration, local library, etc.)
o Timeline
- Provide details on certain measures as warranted

Grievance redress mechanisms (for PAPs and workers)


- Present the proposed mechanisms for grievance management, including
o At least two tiers of the GRM and its institutional arrangement
o Logging process
o Resolution process
o Feedback to aggrieved person
o Appeal mechanism
o Timeline
o Documentation

Roles and responsibilities


- Present respective roles and responsibilities for the implementation of the various measures in the
SEP (consultation, disclosure, grievance management)
- Present resources allocated to stakeholder engagement and reporting line (CLO reporting to E&S
manager for Project)

14
*OFFICIAL USE ONLY

ANNEX 3 – Comparison of Land Acquisition Planning Document and Resettlement/Livelihood Plan

Land Acquisition Planning National Requirements – References: Law No. 2 of 2012, AIIB Environment and Social Policy and
Document Government Regulation (GR) No. 19 of 2021 Standard

Participation, In accordance to land acquisition for public interest The client is required to engage with project-
consultation, and process in preparation stage, there are different definition affected people through meaningful
announcement and approaches for participation – consultation, and consultation. To fulfill this requirement the
client should:
(Disclosure) announcement:
1. i) Notification of the development plans to the (a) provide details of the all the consultations
communities at the development area by having information conducted in the preparation stage of the
spread by: socialisation, face to face, by letter or email and, or Project
by media (electronic and or printed); ii) The contents of
information should be including: a. the aims and objectives of (b) conduct stakeholder engagement analysis
the development plan; b. the location of the land and the to ensure that all relevant parties have a voice
in consultation, including national and
required land area; c. stages of the Land Procurement plan; d.
subnational governments, the private sector,
estimated time period for the implementation of Land nongovernmental organizations and people
Procurement; e. estimated timeframe for development affected by the Project, including, as
implementation; f. other information. applicable, Indigenous Peoples;
2. Consultation: i) definition: Public Consultation (PC) means
any communication process by a dialogue and consultation (c) describe the consultation and participation
among parties in interest to achieve understanding and mechanisms to be used during the different
stages of this project cycle to ensure
agreement in the planning of acquisition of land for
consultation is carried out on an ongoing
development in the public interest; ii) The PC would be held basis throughout the implementation and life
during the Land Acquisition Preparation. The Agency needing cycle of the Project;
land together with the provincial government shall under the
Land Acquisition planning documentation: a. Make notification (d) include and provide additional support as
of the development plan; b. Perform preliminary data collection needed so that women, elderly, young,
of the location of the development plan; and c. Hold a Public disabled, minorities and other vulnerable
groups to participate in consultation;
Consultation on a development plan; iii) PC is aimed to
achieve agreement on the location of the development plan (e) (summarize the results of consultations
with the Entitled Parties or people have land rights. with affected persons (including host
3. Announcement: i) the information to announce is of communities), and discuss how concerns
location confirmation for the development for the Public raised and recommendations made were
Interest; ii) the aims to inform and notify the community that addressed in the resettlement plan
the relevant location is affected by development in the Public

15
*OFFICIAL USE ONLY

ANNEX 3 – Comparison of Land Acquisition Planning Document and Resettlement/Livelihood Plan

Land Acquisition Planning National Requirements – References: Law No. 2 of 2012, AIIB Environment and Social Policy and
Document Government Regulation (GR) No. 19 of 2021 Standard

Interest
The client is required to:
Gap in the document: (a) provide timely disclosure of relevant
1. No information about any materials, schedules and or report and adequate information of the resettlement
on any notification, consultation and announcement that has plan and/or livelihood restoration plan,
including availability of the Project’s GRMs
been and to be undertaken in the Project
and of the PPM or other Bank-approved IAM,
2. The document missing the list of Project’s stakeholders, and in a form and language(s)
including affected persons (altogether with the host understandable to the Project-affected;
communities) (b) Disclose: (i) in English, together with
summaries incorporating elements of this
documentation that are relevant to
stakeholders, including the Project-affected
people, in language(s) understandable to
them; and (ii) on the Client’s website, with the
summaries also disclosed in an accessible
manner in the Project area.
(c) Describe the planned information
disclosure measures (including the type of
information to be disseminated and the
method of dissemination) and the process for
consultation with affected persons during
project implementation

Objection The mechanism described in the Preparation Stage: In addition to the general function of the GRM,
handling 1. Handling of objections in determining the location (according AIIB also requires GRM to be designed to
mechanism to Law No. 2/2012) address affected people’s concerns and
/Grievance 2. Handling of objections to the results of the identification and complaints promptly, including gender-related
Redress inventory of land acquisition objects (according to Law No. concerns and complaints relating to GBV,
Mechanism 2/2012) using an understandable and transparent
3. Handling of objections in the matter of compensation process that is gender sensitive, culturally
(according to Law No. 2/2012) appropriate and readily accessible to all
affected people; (d) includes provisions: (i) to

16
*OFFICIAL USE ONLY

ANNEX 3 – Comparison of Land Acquisition Planning Document and Resettlement/Livelihood Plan

Land Acquisition Planning National Requirements – References: Law No. 2 of 2012, AIIB Environment and Social Policy and
Document Government Regulation (GR) No. 19 of 2021 Standard

protect complainants from retaliation, grant


LA document has all points explained, with addition of Handling of them confidentiality and enable them to
Objections Post Land Acquisition section. No gap on this section, remain anonymous, if requested; and (ii) to
however suggest to add information of person in charge for protect those who defend the rights of
objection handling in the mechanism, and the specific actual not complainants to make such complaints; (e)
generic name of each institution related to the topic provides for maintenance of a publicly
accessible case register and reports on
grievance redress and outcomes, which are
disclosed in accordance with the applicable
ESS; and (f) is required to be operational by
the time implementation of the relevant
Project activities commences and for the
duration of the Project.

Land Land Procurement Policy The chapter needs to incorporate AIIB ESS 2
procurement 1. Principles: humanity, justice, utility, certainty, openness, on Involuntary Resettlement
policy and transparency, agreement, participation, welfare, sustainability,
entitlement matrix and harmony
2. Pillars: i) availability of land and funding by government; ii)
obligation to release the land by the entitled party upon
release of compensation or under a final and binding court
decision; iii) assurance that the acquisition of land for the
public interest be performed by government, and aligned with
regional spatial planning, national or regional development
plan, strategic plan and annual or regular working plan of the
agency needs the land; iv) involvement of all the guardians
and stakeholders and has the land acquisition planning; and v)
balance between the interest of development and the interest
of the public of during all stages of the LA process with giving
reasonable and fair compensation.

17
*OFFICIAL USE ONLY

ANNEX 3 – Comparison of Land Acquisition Planning Document and Resettlement/Livelihood Plan

Land Acquisition Planning National Requirements – References: Law No. 2 of 2012, AIIB Environment and Social Policy and
Document Government Regulation (GR) No. 19 of 2021 Standard

Land Entitlement Policy


1. Entitlement Table, contains: impact – loss category, eligible
party, project entitlement and legal basis
2. Entitlement Parties with list of the parties entitled for
compensation

The LA document has a chapter explained the Indonesian


Laws reference that would be applied for this project.
There are some gaps as detailed below:
a. the entitlement table missing a more complete list with
reference to the applicable laws, for example, on the
compensation for the rest of the land re. to the Article 70 of GR
19 of 2021
b. there was no alignment between the Entitlement Parties Table
with the Entitlement Table, no same terminology nor clear
definition of each entitled party
c. the section missing a flow chart of the LA process with
explanation, and usable selection of Laws
d. The section has mixed parts of general usage of the law, with
the specific ones that actually applied in the project

Estimated Land Law’s requirement: This should include the methodology to be


Value 1. The compensation appraisal by a professional used in valuing losses to determine their
independent appraiser that has permit from the Minister of replacement cost; and a description of the
Finance and a license from the Land Agency (BPN) proposed types and levels of
2. The Feasibility Study to have: an estimated land value compensation under local law and such
– to produce an estimate of the value of compensation for supplementary measures as are necessary to
land acquisition objects achieve replacement cost for lost assets.
3. The LA doc should have an estimated land value,
including: a. land; b. above and under the surface; c.
building; d. plants; e. land -related objects; and f. other In addition to the estimated land value, where
physical displacement results in loss of

18
*OFFICIAL USE ONLY

ANNEX 3 – Comparison of Land Acquisition Planning Document and Resettlement/Livelihood Plan

Land Acquisition Planning National Requirements – References: Law No. 2 of 2012, AIIB Environment and Social Policy and
Document Government Regulation (GR) No. 19 of 2021 Standard

shelter, replacement cost must at least be


assessable losses, and preference for compensation. sufficient to enable purchase or construction
of housing that meets acceptable minimum
The LA document has a dedicated chapter for the community standards of quality and safety.
This should include transaction costs for
Estimated Land Value in the document. The gaps in the
administrative charges, registration or title
doc were: fees, reasonable moving expenses and any
1. Not all regulations to be used to estimate land value, including similar costs imposed on affected persons.
the appraisal method were listed (suggest the regulations to be
moved to the regulation section or chapter, and place in this In order for compensation to be made at
section the application of the regulation in this project); replacement cost, planned compensation
2. The information about the appointed independent appraiser, rates may require updating in Project areas
including the activities done, with the timeline and other info, where inflation is high or the period of time
and report result between calculation of compensation rates
3. Missing the summarised information from the Table of and delivery of compensation is extensive.
Preferred Form of Compensation (recently was in Chapter IX),
on how many prefer what type of compensation, in number
and percentage sex aggregated data (suggest to place the
complete list of the name in an appendix)

Scope and Law requirement are about: This section should include describe physical
Impact of Land  Land location – refer to the specific village, district, regency or and/or economic displacement including
Procurement city, and province where the development would be done; nature and severity of loss. Include those
 Land size needed; without title to land description of associated
 General description of the land status – including data of facilities if any
control, ownership, use, and utilization of land;
 Feasibility Study, including: (–) location feasibility – to produce
an analysis of the physical suitability of the location with the
development plan to be implemented for the Public Interest as
outlined in the map of the development location plan; and (–)
analysis of development costs and benefits for the region and

19
*OFFICIAL USE ONLY

ANNEX 3 – Comparison of Land Acquisition Planning Document and Resettlement/Livelihood Plan

Land Acquisition Planning National Requirements – References: Law No. 2 of 2012, AIIB Environment and Social Policy and
Document Government Regulation (GR) No. 19 of 2021 Standard

the community – to produce an analysis of the costs required


and the benefits of development obtained for the region and
the community;

The LA document has the description of the parcels of


land with ownership information in a section. However,
there were some gaps of information should be added
and/or redrafted in accordance with the law, as detailed:
1. In the feasibility study there was no location feasibility and
analysis in accordance with land ownership (suggest to
develop the study so the result could be used in this LA
doc as references)
2. The LA and FS docs missing any discussion on the
project’s potential impacts, and maps of the areas or zone
of impact of project components or activities (suggest to
integrate the maps in this section, before description of
each landowners)
3. The doc has no summarised land location presumably in
a table, with reference to the specific village, district,
regency or city, and province where the development
would be done (suggest to add, also to describe the
scope of land acquisition (provide maps) and explains
why it is necessary for the main investment project)
4. The doc missing the general description of the land status
– including data of control, ownership, use, and utilization
of land; the key effects in terms of assets acquired and
displaced persons and details of any common property
resources that will be acquired
5. The placement of the affected land parcels and owners,
and land utilisation now would make confusion for
readers, suggest to locate it at an early part of the chapter

20
*OFFICIAL USE ONLY

ANNEX 3 – Comparison of Land Acquisition Planning Document and Resettlement/Livelihood Plan

Land Acquisition Planning National Requirements – References: Law No. 2 of 2012, AIIB Environment and Social Policy and
Document Government Regulation (GR) No. 19 of 2021 Standard

and developing a summarised table.

Socio-economic Requirement: This should include the poor, indigenous


profile of entitled A feasibility study (FS) with the: and/or ethnic minorities, persons with
parties and 1) Socio-economic survey – a study on the socio- disabilities other vulnerable groups; including
affected economic conditions of the community to be affected by those without title to land.
communities the Land Acquisition;
2) Environmental and social analysis of the impacts that
may arise as a result of Land Acquisition and
development – these are carried out to produce an
analysis of environmental impacts or other environmental
documents in accordance with the provisions of laws and
regulations
3)) Other study if needed – studies that are specifically
needed can be in the form of community culture studies,
political and security studies, or religious studies, as an
anticipation of specific impacts due to development in the
Public Interest

Gaps of the project documents:


1. The FS and LA docs missing the socio-economic survey
2. There has been no social impacts analysis (please visit
comments on the above section of Scope and Impact of Land
Procurement)

Resettlement Law requirement: This section should include a description of


Measures – 1. The LA for Public Interest Principles of humanity, benefit, the packages of compensation and other
missing from the welfare, sustainability, and harmony resettlement measures that will assist each
category of eligible displaced persons
document 2. The compensation for land acquired could be made in the form
affected by: (a) land acquisition; and (b)

21
*OFFICIAL USE ONLY

ANNEX 3 – Comparison of Land Acquisition Planning Document and Resettlement/Livelihood Plan

Land Acquisition Planning National Requirements – References: Law No. 2 of 2012, AIIB Environment and Social Policy and
Document Government Regulation (GR) No. 19 of 2021 Standard

of: changes in land use rights, including


a. Money (most suggested); customary rights;
b. Substitute land;
This should include support for host
c. Relocation settlement;
community in case applicable.
d. Shareholding; or
e. Other form as agreed upon both party Livelihood restoration measures should
The compensation could also be possible by combining improve, or at least restore, the livelihoods of
two of the above options. all persons displaced by the Project through:
(a) where feasible, land-based
The LA doc has section Estimated Land Value (on above resettlement strategies when affected
section), with gaps noted as reference livelihoods are land-based or where land is
collectively owned; or cash compensation at
Livelihood Indonesian Law for this term is also with reference to the replacement value for land, including
Restoration and section above (of Resettlement Measures) transitional costs, when the loss of land does
Rehabilitation not undermine livelihoods; (b) prompt
replacement of assets with assets of equal or
Measures – The LA doc has no section discussing this aspect
higher value; (c) prompt compensation at full
missing from the replacement cost for assets that cannot be
document restored; and (d) capacity-building programs
to support improved use of livelihood
resources and enhance access to alternative
sources of livelihood. Make equally available
to all Project-affected people and in a manner
adapted to their respective needs, assistance
for livelihood improvement or restoration,
such as skills training, access to credit,
entrepreneurship and job opportunities and
improvement of existing agricultural activities.
Include transaction costs in determining
compensation. Examine the opportunities for
provision of additional revenues and services
through benefit-sharing, as the nature and
objectives of the Project may allow

22
*OFFICIAL USE ONLY

ANNEX 3 – Comparison of Land Acquisition Planning Document and Resettlement/Livelihood Plan

Land Acquisition Planning National Requirements – References: Law No. 2 of 2012, AIIB Environment and Social Policy and
Document Government Regulation (GR) No. 19 of 2021 Standard

Resettlement assistance should include: (a) if


there is relocation, security of tenure (with
tenure rights that are at least as strong as the
rights the displaced persons had to the land
or other assets from which they have been
displaced) of relocation land (and/or other
assets, as applicable), adequate housing at
resettlement sites with comparable access to
employment and production opportunities,
integration of resettled persons economically
and socially into their host communities and
extension of Project benefits to host
communities to facilitate the resettlement
process; (b) transitional support and
development assistance, such as land
development, credit facilities, training or
employment opportunities; (c) civic
infrastructure and community services, as
required; and (d) special assistance to
woman-headed households and vulnerable
households.

Improve the standards of living of the poor


and other vulnerable groups displaced by the
Project, including women, children and
persons with disabilities, to at least national
minimum standards, including access to
social protection systems. In rural areas
provide them with legal and affordable access
to land and resources, and in urban areas
provide them with appropriate income sources
and legal and affordable access to adequate
housing.

23
*OFFICIAL USE ONLY

ANNEX 3 – Comparison of Land Acquisition Planning Document and Resettlement/Livelihood Plan

Land Acquisition Planning National Requirements – References: Law No. 2 of 2012, AIIB Environment and Social Policy and
Document Government Regulation (GR) No. 19 of 2021 Standard

Pay compensation and provide other


Involuntary Resettlement entitlements before
any related physical or economic
displacement takes place under the Project.
Take gender issues into account in
determining and paying compensation and
providing other entitlements. Under
circumstances in which national law and
tenure systems do not recognize the rights of
women to hold or exchange property, make
provision, to the extent feasible, for women to
gain security of tenure. Include provisions to
address loss of livelihood during Project
implementation.

Implementing To note that under Indonesia Law the LA for public This section should
Mechanism interest the stages are:
a) Planning – with activities like, but not limited to: FS, LA (i) describes institutional arrangement
Plan, Determination of LA doc plan (DPT), and hand over responsibilities and mechanisms for carrying
the DPT to the provincial government; out the measures of the resettlement plan;
b) Preparation – with activities like, but not limited to: (ii) includes institutional capacity building
socialization to community, initial survey, public program, including technical assistance, if
consultation, land determination, and activities related to required;
any objection (if any); (iii) describes role of NGOs, if involved,
c) Implementation – with activities like, but not limited to: and organizations of affected persons in
inventory and measurement, data collection, resettlement planning and management; and
announcement and determination of inventory results, (iv) describes how women’s groups will
determination and announcement of independent be involved in resettlement planning and
appraiser, compensation assessment and result, management
community deliberation, compensation payment and
release of land right activities, and activities related to any

24
*OFFICIAL USE ONLY

ANNEX 3 – Comparison of Land Acquisition Planning Document and Resettlement/Livelihood Plan

Land Acquisition Planning National Requirements – References: Law No. 2 of 2012, AIIB Environment and Social Policy and
Document Government Regulation (GR) No. 19 of 2021 Standard

objection (if any); and


d) Result Handover – with activities like, but not limited to:
hand over results, land registration or certification.

The implementation mechanism here is in accordance


with the institutional arrangement and responsibility as in
the law, which are including, but not limited to, in each
stage:
1. Planning stage: the project implementing agency (the agency
needs land)
2. Preparation stage: governor and provincial government,
designated preparatory team and task force, the agency needs
land, and state court
3. Implementation stage: the agency needs land, land agency,
independent appraiser, and state court
4. Result handover: the agency needs land and land agency

The LA doc has a chapter on the institutional arrangement


that missing the structural or organisational chart of the
project and the flow chart of the LA steps (with tasks and
related responsible agency for each task) for guidance

Implementation Law requirement: This section should include a detailed, time


Schedule – 1. Estimated period of the implementation of Acquisition of bound, implementation schedule for all key
missing from the Land – this describes the estimated time required for each resettlement and rehabilitation activities. The
document stage of the implementation of the Land Acquisition; implementation schedule should cover all
2. Estimated period of the implementation of construction aspects of resettlement activities
synchronized with the project schedule of civil
The LA doc has a chapter on the implementation works construction, and provide land
schedule, only for the land acquisition. The document

25
*OFFICIAL USE ONLY

ANNEX 3 – Comparison of Land Acquisition Planning Document and Resettlement/Livelihood Plan

Land Acquisition Planning National Requirements – References: Law No. 2 of 2012, AIIB Environment and Social Policy and
Document Government Regulation (GR) No. 19 of 2021 Standard

missing: acquisition process and timeline.


1. Estimated period of the implementation of construction
2. The actual schedule on implementing land acquisition for
this Project
3. The timeline of the LA implementation (refer to Table 9.1
in the document)

Budget Law requirement: This section should


Budget plan, with outlining the amount of funds, sources (i) provide an itemized budget for all
of funds, and details of the allocation of funds for resettlement activities, including for the
planning, preparation, implementation, and delivery of resettlement unit, staff training, monitoring
results and evaluation, and preparation of
resettlement plans during loan
The LA document has a dedicated chapter for LA budget implementation.
in the document. The gap to meet are: (ii) describe the flow of funds (the annual
1. Sources of funds resettlement budget should show the budget-
2. Details on disbursement of funds for each allocation scheduled expenditure for key items).
(budget timeline) (iii) include a justification for all
3. Attention for the resettlement unit, staff training, assumptions made in calculating
monitoring and evaluation, and preparation of compensation rates and other cost estimates
resettlement plans during loan implementation to be (taking into account both physical and cost
reflected in the budget contingencies), plus replacement costs.
(iv) include information about the source
of funding for the resettlement plan budget.

Monitoring and Law requirement: This section should describe the mechanisms
Reporting (1) Monitoring and evaluation of the performance of and benchmarks appropriate to the project for
acquisition of land in the Public Interest in the planning, monitoring and evaluating the implementation
preparation, implementation, and result delivery stages of the resettlement plan. It specifies
shall be made by the government. arrangements for participation of affected

26
*OFFICIAL USE ONLY

ANNEX 3 – Comparison of Land Acquisition Planning Document and Resettlement/Livelihood Plan

Land Acquisition Planning National Requirements – References: Law No. 2 of 2012, AIIB Environment and Social Policy and
Document Government Regulation (GR) No. 19 of 2021 Standard

persons in the monitoring process. This


(2) Monitoring and evaluation of the results of the section will also describe reporting
handover of the acquisition of land in the public interest as procedures
the results of delivery of land acquisition shall be made by
the land agency

The LA doc has a chapter on the monitoring and evaluation,


specifically for the LA during preparation and implementation. The
chapter gaps is a timelines planned monitoring and evaluation
table with related stakeholders and agency(s) or person(s) in
charge which specifically responsible for the activity(s).

Other Comments:

The report should also have the following sections to aid in reading the document: project description, executive summary, glossary,
abbreviation. The following writing style guide would also be helpful: (i) document should also spell out the complete terminology
when used for the first time before making any abbreviation, for example P12 of PPK, SPPK and PL; (ii) use gender neutral or
gender sensitive wordings, like: workforce, human-made, police office or humanity rather than manpower, man-made, policeman or
mankind respective; (iii) make all tables and information with sex-aggregated data when applied, for example on the information
about land owners, or training or workshop participants. Regarding compatibility with spatial plan, please provide the reference years
in the main text as well as reference map.

27

You might also like