PRE-COMMISSIONING GENSET-PC-R
415V GENERATOR
INSPECTION & TEST REPORT
1. GENERAL DATA
PROJECT NAME: PROJECT NO.:
WC P.O. / CONTRACT NO.: LINE / ITEM NO.:
2. MOTOR DATA
MAKE: KW/KVA:
SERIAL NO.: VOLTAGE:
TYPE/MODEL : CURRENT:
FRAME: FREQUENCY:
ENCLOSURE PROTECTION: SPEED:
COOLING: BATTERY VOLTAGE:
INSULATION CLASS: ENGIN TYPE:
DONE
3. TEST PROCEDURE /YES
NO N/A COMMENTS/DETAILS
Record cold winding and engine
1
temperatures - confirm as expected.
Magger Generator including a
2
Polarisation Index – confirm acceptable.
Check all switches and indicators on
3
switchboard function correctly.
After running 4hour record winding temp
4
and engine tamp.
Confirm ATS connection and delay
5
settings( phase sequence).
Test oil pressure fault and water
6
temperature fault.
Test Failure to start, over speed and low
7
fuel level warning fault.
8 Confirm ATS functional test.
Test general alarm, general fault and
9
charging alternator fault.
Run Generator no-load one hour.
Record Volts, Amps, Power and
10
bearing/winding temperatures – confirm
as expected.
Run Generator no-load one hour.
Record Volts, Amps, Power and
11
bearing/winding temperatures – confirm
as expected.
5. TESTS
5.1 Test Equipment
Megger
Manufacturer: Model:
Serial No.: Last Calibration Date:
Multimeter
Manufacturer: Model:
Serial No.: Last Calibration Date:
6. SIGNOFFS
NAME (PRINT) COMPANY / ROLE SIGNATURE DATE