ABSTRACT

ESTIMATION FOR CONSTRUCTION OF KUINGAI BAPTIST CHURCH

Rate Amount
Sl No. Description UOM Quantity Remarks
(INR) (INR)

1.0 Earth work in excavation


1.1 Earth work in excavation by mechanical means(Hydraulic
excavator)/ manual means over areas (Exceeding 30Cm in
depth, 1.5m as width as well as 10 sqm as on plan) including Reference-
getting out disposal of excavated earth lead upto 50m & lift upto Cum 205.45 220.20 45240.09 DSR-2021, Vol-1, Code
1.5m, as directed by Engineer-in-charge. No. 2.6.1
2.6.1 All kinds of soil

1.2 Extra for every additional lift of 1.5m or part thereof in


Reference-
excavation banking excavated or stacked materials. Cum 104.50 44.04 4602.18 DSR-2021, Vol-1,
2.26.1 All Kinds of Soil.
Code No. 2.26.1
2.0 Earth work in Back filling
2.1 Filling available excavated earth (excluding rock) in trenches,
plinth, sides of foundations etc. in layers not exceeding 20 cm in
depth, consolidating each deposited layer by raming and Cum 253.95 169.70 43095.57 Reference-DSR-2021,
Vol-1,Code No. 2.25
watering, lead up to 50 m and lift upto 1.5 m.

2.2 Extra for every additional lift of 1.5m or part thereof in Reference-
excavation/banking excavated or stacked materials. Cum 104.50 0.34 35.11 DSR-2021, Vol-1,
2.26.1 All Kinds of Soil. Code No. 2.26.1

Page 1 of 31
ABSTRACT

ESTIMATION FOR CONSTRUCTION OF KUINGAI BAPTIST CHURCH

Rate Amount
Sl No. Description UOM Quantity Remarks
(INR) (INR)

3.0 PCC M15


Providing and Laying in position cement concrete of specified
grade excluding the cost of centering, shuttering. All work upto
plinth level. Reference - DSR-2021, Vol-1,
Cum 7365.15 70.23 517232.39
4.1.3 1:2:4 (1 Cement : 2 Coarse sand (Zon-III) : 4 graded Code No. 4.1.3
stone aggregate 20mm nominal size)

4.0 RCC M25


Providing & laying in position machine batched & machine Mixed
design mixed M-25 grade cement concrete for reinforcement
cement concrete work, using cement content as per approved
design mix, including pumping of concrete to site of laying but
excluding the cost of centering, shuttering, finishing &
reinforcement, including admixture as per recommended
porportion IS:9103 to accelerate, retard setting of concrete, Reference - DSR-2021, Vol-1,
improve workability without impairing strength & durability as per Code No. 5.33
direction of Engineer-in-charge. (Note: Cement content
considerd in this item @330kg/Cum, exess/Less cement used as
per design mix payble/recoverable saperatly)

4.1 5.33.1 All work upto plinth level


Cum 8683.80 53.60 465460.36

4.2 5.33.2 All work above plinth level upto floor-v level
Cum 10306.20 93.49 963480.26

5.0 Shuttering Work


Centering & shuttering including struting, propping etc. and
5.1 removal of form for
5.9.1 Foundation, footing, base of columns etc. for mass Reference - DSR-2021,
concrete Sqm. 307.95 92.33 28431.48
Vol-1, Code No 5.9.1

Page 2 of 31
ABSTRACT

ESTIMATION FOR CONSTRUCTION OF KUINGAI BAPTIST CHURCH

Rate Amount
Sl No. Description UOM Quantity Remarks
(INR) (INR)

5.9.3 Suspended floors, roofs, landings, balconies and access Reference - DSR-2021,
platform Sqm. 766.55 243.84 186915.55
Vol-1, Code No 5.9.3
5.9.5 Lintels, beams, plinth beams, girders, bressumers and
cantilevers Sqm. 608.35 480.40 292251.34 Reference - DSR-2021,
Vol-1, Code No 5.9.5
5.9.6 Columns, Pillars, Piers, Abutments, Posts and Struts
Sqm. 804.25 545.60 438798.80 Reference - DSR-2021,
Vol-1, Code No 5.9.6
5.9.7 Stairs, (excluding landings) except spiral-staircases Reference - DSR-2021,
Sqm. 657.75 18.00 11839.50 Vol-1, Code No 5.9.7
5.9.16 Edges of slabs and breaks in floors and wall

5.9.19 Weather shade, Chajjas, corbels etc., including edges Reference - DSR-2021,
Sqm. 766.75 26.64 20426.22
Vol-1, Code No 5.9.19
Extra for additional height in centering, shuttering where ever
required with adequate bracing, propping etc., including cost of
de-shuttering and decentering at all levels, over a height of 3.5
5.2 m, for every additional height of 1 metre or part thereof (Plan
area to be measured).

5.11.1 Suspended floors, roofs, landing, beams and balconies


(Plan area to be measured) Sqm. 319.25 161.84 51667.42 Reference - DSR-2021,
Vol-1, Code No 5.11.1
6.0 Scaffolding Work

Page 3 of 31
ABSTRACT

ESTIMATION FOR CONSTRUCTION OF KUINGAI BAPTIST CHURCH

Rate Amount
Sl No. Description UOM Quantity Remarks
(INR) (INR)

6.1 Providing & fixing double Scaffolding system (Cup lock type) on
the upto exterior side, upto seven story hight made with 40mm
dia MS tube 1.5 meter center to center, Vertical & horizontal tube
joining with cup & lock system with MS tube, MS tube challies,
MS clamps & MS staircase system in the scaffolding for working
platform etc. maintaining it in a serviceable condition for the
required condition as approved and removing it there after. The
scaffolding system shall be stiffened with bracing, Runneres
connection with the building etc, wherever required for inspection Reference- DSR-2021,
of work at required location with essential safety features for sqm. 285.00 1921.20 547542.00
Vol-2, Code No 14.72
workmen etc. complete as per direction & approval Engineer- in-
charge. The elevational area of scaffolding shall be measured for
the payment purpose. The payment will be made once
irrespective dration of scaffolding.

Page 4 of 31
ABSTRACT

ESTIMATION FOR CONSTRUCTION OF KUINGAI BAPTIST CHURCH

Rate Amount
Sl No. Description UOM Quantity Remarks
(INR) (INR)

7.0 Reinforcement work


Steel reinforcement of RCC work including straightening, cutting,
bending and placing in position and binding all complete upto
plinth level. Reference - DSR-2021,
kg 89.65 14554.89 1304845.89
5.22.6 Thermo- Mechanically treated bars of grade Fe-500 or more Vol-1, Code No. 5.22.6

8.0 Brick work


8.1 Brick work with common burnt clay F.P.S. (non modular) brick of
class designation 7.5 in superstructure above plinth level upto
floor level V level in all shape & size in; Reference - DSR-2021,
Cum 8512.10 170.40 1450443.11
6.4.1 Cement Mortar (1 Cement : 4 Coarse Sand) Vol-1, Code No 6.4.1

9.0 Plaster
9.1 12mm Cement Plaster of mix
Reference - DSR-2019,
Sqm. 276.15 1770.36 488884.91
Vol-2, Code No 13.4.1
13.4.1 1:4 (1Cement : 4 coarse Sand)
10.0 Structural steel work
10.1 Structural steel work in single section with or without connecting
plate, including cutting, hoisting, fixing in position and applying a Reference -DSR-2021,
priming coat of approved steel primer all complete. Kg 111.95 11736.00 1313845.20
Vol-1, Code No 10.2

Page 5 of 31
ABSTRACT

ESTIMATION FOR CONSTRUCTION OF KUINGAI BAPTIST CHURCH

Rate Amount
Sl No. Description UOM Quantity Remarks
(INR) (INR)

11.0 Anchor fastener


11.1 Drilling suitable holes in reinforced or plain cement concrete with
power driven drill machine to a minimum depth of 100mm upto
200mm in RCC beams. Lintels, columns and slabs to introduce
steel bars for sunsades/balconies including fixing the steel bars
in position using epoxy resin anchor grout of approved make but
excluding the cost of reinforcement, all complete as per direction Reference- DSR-2021,
Nos. 121.95 104.00 12682.80
Vol-2, Code No 26.30.1
of Engineer-in-charge.
26.30.1 Upto and including 12mm dia

12.0 Paint
12.1 White washing with lime to give an even shade : Reference - DSR-2021,
13.37.1 New work (three or more coats) Sqm 32.45 1761.36 57156.13
Vol-2, Code No 13.37.1

12.2 Finishing walls with Acrylic Smooth exterior paint of required


shade :
13.46.1 New work (Two or more coat applied @ 1.67 ltr/10 sqm Reference - DSR-2021,
Sqm 166.85 1761.36 293882.92
over and including priming coat of exterior primer applied @ 2.20 Vol-2, Code No 13.46.1
kg/10 sqm)

Page 6 of 31
ABSTRACT

ESTIMATION FOR CONSTRUCTION OF KUINGAI BAPTIST CHURCH

Rate Amount
Sl No. Description UOM Quantity Remarks
(INR) (INR)

13.0 Flooring
13.1 Marble stone flooring with 18 mm thick marble stone, as per
sample of marble approved by Engineer-in-charge, over 20 mm
(average) thick base of cement mortar 1:4 (1 cement : 4 coarse
sand) laid and jointed with grey cement slurry, including rubbing Reference - DSR-2021,
and polishing complete with : Sqm 3377.45 876.40 2959997.18
Vol-1, Code No 11.23.1
11.23.1 Makrana white second quality

14.0 Sheet Roofing


14.1 Providing corrugated G.S. sheet roofing including vertical /
curved surface fixed with polymer coated J or L hooks, bolts and
nuts 8 mm diameter with bitumen and G.I. limpet washers or with
G.I. limpet washers filled with white lead, including a coat of
approved steel primer and two coats of approved paint on
overlapping of sheets complete (up to any pitch in horizontal/
vertical or curved surfaces), excluding the cost of purlins, rafters Reference - DSR-2021,
Sqm 1135.45 733.20 832511.94
and trusses and including cutting to size and shape wherever Vol-1, Code No 12.1.2
required.
12.1.2 0.80 mm thick with zinc coating not less than 275 gm/m²

14.2 Providing ridges or hips of width 60 cm overall width plain G.S.


sheet fixed with polymer coated J or L hooks, bolts and nuts 8
mm dia G.I. limpet and bitumen washers complete.
m 822.15 40.00 862.15 Reference - DSR-2021,
12.4.1 0.80 mm thick with zinc coating not less than 275 gm/m² Vol-1, Code No 12.4.1

Page 7 of 31
ABSTRACT

ESTIMATION FOR CONSTRUCTION OF KUINGAI BAPTIST CHURCH

Rate Amount
Sl No. Description UOM Quantity Remarks
(INR) (INR)

15.0 Providing and fixing false ceiling at all height including providing and
fixing of frame work made of special sections, power pressed from
M.S. sheets and galvanized with zinc coating of 120 gms/sqm (both
side inclusive) as per IS : 277 and consisting of angle cleats of size 25
mm wide x 1.6 mm thick with flanges of 27 mm and 37mm, at 1200
mm centre to centre, one flange fixed to the ceiling with dash fastener
12.5 mm dia x 50mm long with 6mm dia bolts, other flange of cleat
fixed to the angle hangers of 25x10x0.50 mm of required length with
nuts & bolts of required size and other end of angle hanger fixed with
12.45.1
intermediate12.5
G.I.mm thick45x15x0.9
channels taperedmm edge gypsum
running plain board
at the spacing of
conforming to IS: 2095- (Part I) : 2011 (Board
1200 mm centre to centre, to which the ceiling section 0.5 mm with BIS
thick Reference - DSR-2021,
Sqm 1145.95 720.00 825084.00
certification
bottom wedge marks)
of 80 mm with tapered flanges of 26 mm each having Vol-1, Code No 12.45.1
lips of 10.5 mm, at 450 mm centre to centre, shall be fixed in a
direction perpendicular to G.I. intermediate channel with connecting
clips made out of 2.64 mm dia x 230 mm long G.I. wire at every Sub Total (INR) 13,157,215
junction, including fixing perimeter channels 0.5 mm thick 27 mm high
having flanges of 20 mm and 30 mm long, the perimeter of ceiling
fixed to wall/partition with the help of rawl plugs at 450 mm centre,
with 25mm long dry wall screws @ 230 mm interval, including fixing of
Overhead @ 15% 1,973,582
gypsum board to ceiling section and perimeter channel with the help
of dry wall screws of size 3.5 x 25 mm at 230 mm c/c, including
jointing and finishing to a flush finish of tapered and square edges of
Grand Total (INR) 15,130,797
the board with recommended jointing compound , jointing tapes ,
finishing with jointing compound in 3 layers covering upto 150 mm on
both sides of joint and two coats of primer suitable for board, all as
per manufacturer's specification and also including the cost of making
openings for light fittings, grills, diffusers, cutouts made with frame of
perimeter channels suitably fixed, all complete as per drawings,
specification and direction of the Engineer in Charge but excluding the
cost of painting with

Page 8 of 31
Name of the Project :

QUANTITY
1.0 EARTHWORK - QUANTITY
Sl. No. Description No. Length Width Depth Quantity Remarks
(m) (m) (m) (Cum)
1.1 EARTH WORK IN EXCAVATION
Refer the foundation drawing
Excavation - from 0 to 1.5 m depth

a Footing type- F1 19 2.10 1.60 1.500 95.76

b Footing type- F2 6 1.90 1.90 1.500 32.49

c Footing type- F3 2 2.10 2.10 1.500 13.23

d Footing type- F4 8 1.70 1.70 1.500 34.68

Sub- Total 176.16


Excavation - from 1.5 m to 3.0 m depth

a Footing type- F1 19 2.10 1.60 0.375 23.94

b Footing type- F2 6 1.90 1.90 0.375 8.12

c Footing type- F3 2 2.10 2.10 0.375 3.31

d Footing type- F4 8 1.70 1.70 0.375 8.67

Sub- Total 44.04

Total 220.20
Name of the Project : Construction of Kuingai Baptist Church

QUANTITY

Sl. No. Description No. Length Width Depth Quantity Remarks

(m) (m) (m) (Cum)

2.0 EARTH WORK IN BACK FILLING

Refer the foundation drawing

2.1 Back filling - from 0 to 1.5 m depth

a Footing type- F1 19 2.10 1.60 1.50 95.76

b Footing type- F2 6 1.90 1.90 1.50 32.49

c Footing type- F3 2 2.10 2.10 1.50 13.23

d Footing type- F4 8 1.70 1.70 1.50 34.68

Deduction for volumn covered by structure (6.80)

Net Qty 169.37

2.2 Back filling - from 1.5 m to 3.0 m depth


a Footing type- F1 19 2.10 1.60 0.375 23.94

b Footing type- F2 6 1.90 1.90 0.375 8.12

c Footing type- F3 2 2.10 2.10 0.375 3.31

d Footing type- F4 8 1.70 1.70 0.375 8.67

Deduction for volumn covered by structure (43.70)


Net Qty 0.34

Total 169.70
Name of the Project : Construction of Kuingai Baptist Church

QUANTITY
3. PCC M15 GRADE

Sl No. Description Unit Nos Length Width Depth Quantity Remarks

a PCC M15 grade below footing

Footing type- F1 Cum 19 2.10 1.60 0.075 4.79

Footing type- F2 Cum 6 1.90 1.90 0.075 1.62

Footing type- F3 Cum 2 2.10 2.10 0.075 0.66

Footing type- F4 Cum 8 1.70 1.70 0.075 1.73


b PCC M15 grade for Plinth Beam

Plinth beam type- PB1 Cum 1 98.20 0.35 0.075 2.58

Plinth beam type- PB2 Cum 1 32.10 0.35 0.075 0.84

Plinth beam type- PB3 Cum 1 28.90 0.35 0.075 0.76

c PCC M15 grade for Flooring

Floor - Internal Cum 1 40.00 18.00 0.075 54.00

Floor - External/Front side Cum 1 10.80 4.00 0.075 3.24

TOTAL 70.23
Name of the Project : Construction of Kuingai Baptist Church

QUANTITY
4.0 - RCC M25 GRADE

Sl No. Description Unit Nos Length Breadth Depth/ Quantity Remarks


Height

4.1 Upto plinth level

a Footing

Footing type- F1 Cum 19 2.00 1.80 0.30 20.52


Footing type- F2 Cum 6 1.80 1.80 0.30 5.83
Footing type- F3 Cum 2 2.00 2.00 0.30 2.40
Footing type- F4 Cum 8 1.60 1.60 0.30 6.14

b Plinth Beam -

Plinth beam type- PB1 Cum 1 98.00 0.25 0.30 7.35


Plinth beam type- PB2 Cum 1 32.00 0.25 0.30 2.40
Plinth beam type- PB3 Cum 1 28.80 0.25 0.30 2.16

c Column -

Column type- C1 Cum 2 0.30 0.30 1.50 0.27


Column type- C2 Cum 10 0.30 0.30 1.50 1.35
Column type- C3 Cum 4 0.50 0.30 1.50 0.90
Column type- C4 Cum 19 0.50 0.30 1.50 4.28
Total 53.60
4.2 Above plinth level upto floor-v level

a Column

Column type- C1 Cum 2 0.30 0.30 6.75 1.22


Column type- C2 Cum 6 0.30 0.30 6.75 3.65
Column type- C2 Cum 4 0.30 0.30 10.25 3.69
Column type- C3 Cum 4 0.50 0.30 6.75 4.05
Column type- C4 Cum 19 0.50 0.30 6.75 19.24

b Tie Beam -

All around tie beam Cum 1 176.80 0.25 0.25 11.05

c Roof Beam -

Roof beam type- RB1 Cum 1 36.00 0.30 0.25 2.70


Roof beam type- RB2 Cum 1 140.80 0.30 0.25 10.56

d Slab -

Slab type - S1 Cum 1 12.40 8.00 0.15 14.88


Slab type - S2 Cum 1 12.40 4.80 0.15 8.93
Slab type - S3 Cum 1 4.00 4.00 0.15 2.40
Top Roof Slab for Parapet Cum 1 80.00 0.50 0.15 6.00
Chajja Cum 16 1.50 0.80 0.15 2.88
Stair Cum 2 5.00 1.50 0.15 2.25

Total RCC M-25 grade Cum 93.49


Name of the Project : Construction of Kuingai Baptist Church

QUANTITY
5.0 - SHUTTERING WORK

Sl No. Description Unit Nos Set Length Breadth Quantity Remarks

1 Shuttering (Footing PCC)

Footing type- F1 Sqm 19 2.00 2.10 0.075 5.99


Footing type- F1 Sqm 19 2.00 1.60 0.075 4.56
Footing type- F2 Sqm 6 4.00 1.90 0.075 3.42
Footing type- F3 Sqm 2 4.00 2.10 0.075 1.26
Footing type- F4 Sqm 8 4.00 1.70 0.075 4.08

Total 19.31

2 Shuttering (Footing RCC)

Footing type- F1 Sqm 19 2 2.00 0.30 22.80


Footing type- F1 Sqm 19 2 1.50 0.30 17.10
Footing type- F2 Sqm 6 4 1.80 0.30 12.96
Footing type- F3 Sqm 2 4 2.00 0.30 4.80
Footing type- F4 Sqm 8 4 1.60 0.30 15.36

Total 73.02

3 Shuttering (Plinth Beam)

Plinth beam type- PB1 Sqm 1 2 98.00 0.25 49.00


Plinth beam type- PB2 Sqm 1 2 32.00 0.25 16.00
Plinth beam type- PB3 Sqm 1 2 28.00 0.25 14.00

Total 79.00
4 Shuttering (Mid Tie Beam)

Mid Tie beam type- TB (Side) Sqm 1 2 176.80 0.25 88.40


Mid Tie beam type- TB (Bottom) Sqm 1 1 176.80 0.25 44.20

Total 132.60

5 Shuttering (Roof Beam)

Roof beam type- RB1 (Side) Sqm 1 2 36.00 0.25 18.00


Roof beam type- RB1 (Bottom) Sqm 1 1 36.00 0.30 10.80
Roof beam type- RB2 Sqm 1 3 140.80 0.25 105.60

Total 134.40

6 Shuttering (Slab)

Slab type - S1 soffit Sqm 1 1 12.40 8.00 99.20


Slab type - S1 side Sqm 1 2 20.40 0.15 6.12
Slab type - S2 soffit Sqm 1 1 14.40 4.00 57.60
Slab type - S2 side Sqm 1 2 16.40 0.15 4.92
Slab type - S3 soffit Sqm 1 1 4.00 4.00 16.00
Slab type - S3 side Sqm 1 4 4.00 0.15 2.40
Total 186.24

7 Shuttering (column)

Column type- C1 Sqm 2 4.00 8.25 0.30 19.80


Column type- C2 Sqm 6 4.00 8.25 0.30 59.40
Column type- C2 Sqm 4 4.00 11.75 0.30 56.40
Column type- C3 (Side-1) Sqm 4 2.00 8.25 0.50 33.00
Column type- C3 (Side-2) Sqm 4 2.00 8.25 0.30 19.80
Column type- C4 (Side-1) Sqm 19 2.00 8.25 0.50 156.75
Column type- C4 (Side-2) Sqm 19 2.00 8.25 0.30 94.05
Total 439.20
8 Chajja
Chajja - base Sqm 16 1.00 1.50 0.80 19.20
Chajja - side Sqm 16 1.00 3.10 0.15 7.44

Total 26.64

9 Stairs
Base Sqm 2 1.00 5.00 1.50 15.00
Sides Sqm 2 2.00 5.00 0.15 3.00

Total 18.00

10 Extra for height above 3.5 m

Column type- C1 Sqm 2 4.00 1.75 0.30 4.20


Column type- C2 Sqm 6 4.00 1.75 0.30 12.60
Column type- C2 Sqm 4 4.00 5.25 0.30 25.20
Column type- C3 (Side-1) Sqm 4 2.00 1.75 0.50 7.00
Column type- C3 (Side-2) Sqm 4 2.00 1.75 0.30 4.20
Column type- C4 (Side-1) Sqm 19 2.00 1.75 0.50 33.25
Column type- C4 (Side-2) Sqm 19 2.00 1.75 0.30 19.95
Roof beam type- RB1 (Side) Sqm 1 2 36.00 0.25 18.00
Roof beam type- RB1 (Bottom) Sqm 1 1 36.00 0.30 10.80
Roof beam type- RB2 Sqm 1 3 140.80 0.25 105.60
Slab type - S2 soffit Sqm 1 1 14.40 4.00 57.60
Slab type - S2 side Sqm 1 2 16.40 0.15 4.92
Slab type - S3 soffit Sqm 1 1 4.00 4.00 16.00
Slab type - S3 side Sqm 1 4 4.00 0.15 2.40

Total 321.72

1430.13
Name of the Project : Construction of Kuingai Baptist Church

QUANTITY

6 Work Description UOM Nos. Length Hight/ Depth Qty.

Scaffolding for Internal side


Sqm 2 40.00 6.75 540.00
along the length

Scaffolding for Internal side


Sqm 2 18.00 6.75 243.00
along the Breadth

Scaffolding for External side


Sqm 2 42.00 6.75 567.00
along the Length

Scaffolding for External side


6.1 Sqm 2 20.00 6.75 270.00
along the Breadth

Scaffolding for Front side upto


Sqm 1 12.80 6.75 86.40
slab level

Scaffolding for Front side upto Sqm 2 12.80 6.75 172.80


slab level

Scaffolding for Front side


above slab level Sqm 3 4.00 3.50 42.00

Total qty. 1921.20


Name of the Project : Construction of Kuingai Baptist Church

QUANTITY
8.0 - BRICK WORK
Depth/
Sl No. Description Unit Nos Length Height Thickness Quantity Remarks

Wall along the length Cum 2 37.00 5.90 0.23 100.42


Wall back side Cum 1 17.10 5.90 0.23 23.20
Wall Front side Cum 1 17.10 5.90 0.23 23.20
Wall for roof truss enclosure Cum 2 18.00 3.50 0.23 28.98
Wall for cubical below cross Cum 3 3.60 3.50 0.23 8.69
Stage Cum 1 18.00 0.50 0.23 2.07

Deduction

Wall along the length


window Cum (16) 1.20 1.50 0.23 -6.62
8.1
Ventilator Cum (16) 1.20 0.80 0.23 -3.53
Wall back side
Door Cum (2) 1.20 2.10 0.23 -1.16
Ventilator Cum (4) 1.20 0.80 0.23 -0.88
Wall Front side
window Cum (2) 1.20 1.50 0.23 -0.83
Door Cum (3) 1.20 2.10 0.23 -1.74
Wall for cubical below cross
Door Cum (1) 1.20 2.10 0.23 -0.58
window Cum (2) 1.20 1.50 0.23 -0.83

Total - Brick work Cum 170.40


Name of the Project : Construction of Kuingai Baptist Church

QUANTITY
9.0 - PLASTER

Sl No. Description Unit Nos Set Length Depth/ Height Quantity Remarks

Wall along the length sqm 2 2 40.00 6.75 1,080.00


Wall back side sqm 1 2 18.00 6.75 243.00
Wall Front side sqm 1 2 18.00 6.75 243.00
Wall for roof truss enclosure sqm 2 2 18.00 3.50 252.00
Wall for cubical below cross sqm 3 2 4.00 3.50 84.00
Stage sqm 1 1 18.00 0.50 9.00

Deduction

Wall along the length


window sqm (16) 2 1.20 1.50 -57.60
9.1
Ventilator sqm (16) 2 1.20 0.80 -30.72
Wall back side
Door sqm (2) 2 1.20 2.10 -10.08
Ventilator sqm (4) 2 1.20 0.80 -7.68
Wall Front side
window sqm (2) 2 1.20 1.50 -7.20
Door sqm (3) 2 1.20 2.10 -15.12
Wall for cubical below cross
Door sqm (1) 2 1.20 2.10 -5.04
window sqm (2) 2 1.20 1.50 -7.20

Total - Plaster sqm 1770.36


Name of the Project : Construction of Kuingai Baptist Church

QUANTITY
10.0 - Structural Steel
Plan area Unit Weight
Structural Steel works Unit Nos. Length Width
(sqm) (kg/sqm)
Weight Remarks

10.1 As per SP-38- 1987, A -type roof


truss with tubular section with wind kg 1 40.00 18.00 720.00 16.30 11736.00
zone of 200kg/m2 and span of 18 m

Total 11736.00

11.0 - Anchor Fastener

Item Derscription Unit Nos. Sets Qty. Remarks


11.1
Anchor Fastener 16 mm dia Nos 26 4 104
Name of the Project : Construction of Kuingai Baptist Church

QUANTITY
12.0 - PAINT

Sl No. Description Unit Nos Set Length Depth/ Height Quantity Remarks

Wall along the length sqm 2 2 40.00 6.75 1,080.00


Wall back side sqm 1 2 18.00 6.75 243.00
Wall Front side sqm 1 2 18.00 6.75 243.00
Wall for roof truss enclosure sqm 2 2 18.00 3.50 252.00
Wall for cubical below cross sqm 3 2 4.00 3.50 84.00

Deduction

Wall along the length


window sqm (16) 2 1.20 1.50 -57.60
12.1 Ventilator sqm (16) 2 1.20 0.80 -30.72
Wall back side
Door sqm (2) 2 1.20 2.10 -10.08
Ventilator sqm (4) 2 1.20 0.80 -7.68
Wall Front side
window sqm (2) 2 1.20 1.50 -7.20
Door sqm (3) 2 1.20 2.10 -15.12
Wall for cubical below cross
Door sqm (1) 2 1.20 2.10 -5.04
window sqm (2) 2 1.20 1.50 -7.20

Total - PAINT sqm 1761.36


Name of the Project : Construction of Kuingai Baptist Church

QUANTITY

13.0 - FLOORING
13.1
Description UoM Length Breadth Quantity

Stage Sqm 18.00 6.00 108.00

Public area Sqm 34.00 18.00 612.00

Inner platform Sqm 17.50 4.00 70.00

Balcony Sqm 10.80 4.00 43.20

Front entry Sqm 10.80 4.00 43.20

Total Qty (In sqm.) 876.40


Name of the Project : Construction of Kuingai Baptist Church

QUANTITY

14.0 - Roofing
Description UoM Nos. Length Breadth Quantity

14.1 Surface area Sqm 2 40.00 9.17 733.20

14.2 Ridges m 1 40.00 1.00 40.00


Name of the Project : Construction of Kuingai Baptist Church

QUANTITY

15.0 - False Ceiling


Description UoM Nos. Length Breadth Quantity

15.1 Surface area Sqm 1 40.00 18.00 720.00

Total 720.00
LIST OF MATERIALS REQUIRED FOR CONSTRUCTION OF CHURCH
(FOR BUDGET PURPOSE)

Sr. No. Materials Unit Quantity Rates Amount

1 Cement Bags 2111

2 Sand (Zone-II) Cum 111

3 Aggregates (10 mm) Cum 70

4 Aggregates (20 mm) Cum 105

5 Plywood for shuttering (1.2*2.4m2) No. 497

6 Reinforcement steel (Fe500) - 8mm dia kg 3936

7 Reinforcement steel (Fe500) - 12mm dia kg 7317

8 Reinforcement steel (Fe500) - 16mm dia kg 3302

9 Bricks (Non Modular) No. 96276

10 Steel for roof truss (as per SP38 - 18 m span) Kg 11736

11 Anchor Fastener (12mm dia, 200 mm length) No. 104

12 Paint (Interior) Sqm 1761

13 Paint (Exterior) Sqm 1761

14 Roof Sheet Sqm 733.2

15 Ridge for roof sheet M 40

16 Floor Area (Marble) Sqm 876

17 False ceiling area (Gypsum board) Sqm 720


PCC Cement Sand Aggregates

Ratio 1 2 4

Concrete volume=1.54m3

Total of ratio = 1+2+4 = 7

Cement Density of cement = 1440kg/m3 Sand

Cement part = 1/7*1.54 0.22 Sand part=

Cement weight = Density x cement part = 316.8 Kg Sand in 1m3 of concrete=

PCC

Cement = 444.97728 445 Bags

Sand = 30.9012 31m3

Aggregates (20mm)= 24.72096 25m3

Aggregates (10mm)= 37.08144 37m3

RCC Cement Sand Aggregates

Ratio 1 2 4

Concrete volume=1.54m3

Total of ratio = 1+1+2 = 4

Cement Density of cement = 1440kg/m3 Sand

Cement part = 1/4*1.54 0.385 Sand part=

Cement weight = Density x cement part = 554.4 Kg Sand in 1m3 of concrete=

RCC 147.09

Cement = 1630.93392 1631Bags Brick size


Sand = 56.62965 57m3

Aggregates (20mm)= 45.30372 45m3 No. of bricks in 1m3 =

Aggregates (10mm)= 67.95558 68m3

Plastering

Area= 1 m2
Thickness= 0.012
Volume= 0.01

Dry volume of mortar= 0.02


Cement part= 0.00324
Cement bags= 4.6656

Total cement = 1775.0256 35.500512

Sand 0.01296
22.9438656 23
1550Kg/m3 Aggregates

2/7*1.54 0.44 Aggregates part = 4/7*1.54 0.88

Sand in 1m3 of concrete= 0.44m3 Aggregates in 1m3 of concrete= 0.88m3

10mm 40% 0.352

20mm 60% 0.528

1550Kg/m3 Aggregates

1/4*1.54 0.385 Aggregates part = 2/4*1.54 0.77

Sand in 1m3 of concrete= 0.385m3 Aggregates in 1m3 of concrete= 0.77m3

10mm 40% 0.308

20mm 60% 0.462

230mm*110mm*70mm
0.001771

No. of bricks in 1m3 = 564.652739

1770.36