I. Objective
V. Timetable of work
VI.
I. Objective
To keep the river clean and avoid further contamination of the water,
which could emit foul odor and affects the surrounding community.
b. 2) Boiler area
b. 3) Dumpsite area
Scraping of sludge
d) Disposal method
Placed in a bin to
Collected waste
prevent water
materials stored in Dump at mill
spillage during
sack
transportation
Feed to boiler as
Prepare for drying
fuel
IV. Estimated Schedule of Cleaning
a) Station 5 to Station 4 (1st km)
b) Station 4 to
Station 3 (2nd
km)
Estimated timeframe of cleaning would take about 10 days
c) Station 3 to
Station 2 (3rd
Km)
Estimated
timeframe of cleaning would
take about 7 days
V. Timetable of work
ITE
M ACTIVITES WHEN
NO.
1 Survey of the area Jan. 23-25, 2023
2 Planning
Jan. 26-28, 2023
3 Hiring, purchasing of materials (tools, PPEs, etc.)