Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 8

Cascades Enterprises, Inc.

Gov’s Drive Barrio Tanauan Tanza, Cavite

Work Program:
Rehabilitation of river along Pasinaya to Cascades

Prepared by:

John Phillip A. Queliope


Pollution Control officer
Cascades Enterprises, Inc.

Noted by:

Levy T. Bergoña
Papermill Head
Cascades Enterprises, Inc.
Parts of report

I. Objective

II. Surveying the area

III. Cleaning Method

IV. Estimated Schedule of cleaning

V. Timetable of work

VI.
I. Objective
 To keep the river clean and avoid further contamination of the water,
which could emit foul odor and affects the surrounding community.

II. Surveying of the area


This will determine the following:
 Length of the area to be clean.
 What areas will be accessible for cleaning?
 What cleaning materials will be required?
 How many persons would be required to thoroughly clean it quickly?
 The amount of time required to properly clean the area.

III. Cleaning Method


a) Separation of area into different stations

Station 1 – Pasinaya Central


Station 2 – Ciudad Nuevo Bridge
Station 3 – Sta. Lucia area
Station 4 – Sta. Lucia bridge
Station 5 – Cascades Enterprises, Inc.
b) Station 5 (Cascades Enterprises, Inc.)
b.1) Discharge location (exit of the culvert)

Siphon using Collected sludge


Collected water will
submersible pump will under go drying
be treated at
and stored in tote and use as fuel to
inhouse WTP
bin boiler

b. 2) Boiler area

To reduce the temperature,


Blocking of hole, cleaning of
discharge water will be mixed
canals
with effluent.

b. 3) Dumpsite area

Plastics will be process using our


Sorting of different solid waste plastic extruder machine which
materials (ex. plastics to metals) converts plastics into plastic pellets
that can be use as fuel to boiler
c) Station 1,2,3, & 4

Manual collection of garbage

will be placed in sack

Scraping of sludge

To minimize disruption and avoid flowing to lower areas:


We will install screen mesh at down side allowing the water only
to pass through and blocking the sludge

All collected garbage, sludge, etc. stored in sack


will be brought back to the mill and will undergo
drying and will be use as fuel to boiler

d) Disposal method

Placed in a bin to
Collected waste
prevent water
materials stored in Dump at mill
spillage during
sack
transportation

Feed to boiler as
Prepare for drying
fuel
IV. Estimated Schedule of Cleaning
a) Station 5 to Station 4 (1st km)

Estimated timeframe of cleaning would take about 7 days

b) Station 4 to
Station 3 (2nd
km)
Estimated timeframe of cleaning would take about 10 days

c) Station 3 to
Station 2 (3rd
Km)

Estimated
timeframe of cleaning would
take about 7 days

d) Station 2 to Station 1 (4th km)


Estimated timeframe of cleaning would take about 10 days

V. Timetable of work

ITE
M ACTIVITES WHEN
NO.
1 Survey of the area Jan. 23-25, 2023

2 Planning
Jan. 26-28, 2023
3 Hiring, purchasing of materials (tools, PPEs, etc.)

4 Cleaning of 1st km (station 5-4) Jan 30-Feb. 4, 2023

5 Cleaning at 2nd km (station 4-3) Feb. 6-16, 2023

6 Cleaning at 3rd km (station 3-2) Feb. 17-24, 2023


Feb. 25-Mar. 7,
7 Cleaning at 4th km (station 2-1)
2023