250600dlsad0269 Exde00 15
250600dlsad0269 Exde00 15
ISSUED FOR
EX-DE 00 20/10/16 M.Hijazi M.Hijazi H.Hammami C. Ialenti R. Dellacecca
APPROVAL
Validity Rev.
Status number Prepared Checked Contractor Contractor Company
Date Description
by by Checked Approval Approval
Revision Index
Company logo and business name Project name Company Identification
OGI002-PL-0270-00
Drake & Scull International PJSC
Contract N. 5000008451
Vendor logo and business name Vendor Identification
Order N.
Facility Name Location Scale Sheet of Sheets
ZUBAIR OIL FIELD – WATER
ONSHORE n. a. 1 of 16
INJECTION NETWORK INSTALLATION
Document Title Supersedes N. XXX (SOC NUMBER)
REVISION HISTORY
INDEX
1 General............................................................................................................................................ 4
1.1 Scope of the Document.......................................................................................................... 4
2 Abbreviations and Glossary........................................................................................................ 4
3 Reference Documents.................................................................................................................. 6
3.1 Previous Zubair EPC Phase Documents................................................................................6
3.2 Company Standard................................................................................................................. 8
3.3 International Rules, Codes and Standard...............................................................................8
4 Scope of Work Overview............................................................................................................ 10
4.1 General................................................................................................................................. 10
4.2 North Complex and Hammar Mishrif Area............................................................................11
4.3 Upper Medial Complex and Hammar Area...........................................................................11
4.4 Lower Medial, South Complex and Zubair Mishrif Area........................................................12
4.5 Installation activities.............................................................................................................. 12
4.6 Engineering........................................................................................................................... 16
1 General
A. The contractor shall design, furnish and install all materials and equipment and provide all
labor necessary to complete the work in accordance with the typical drawings and/or listed
below and all other work and miscellaneous items. Work design and execution including both
temporary and permanent cathodic protection for 11 water injection flow lines.
For the purpose of this specification, the following definitions shall apply:
3 Reference Documents
Design and installation of cathodic protection systems shall be carried out in compliance
with Iraqi normative documents. In case of conflict with local rules the matter shall be
investigated in detail.
In case of conflict between the content of Project documents and other documents, other
than local rules, the order of preference is as follows:
1. Project documents
2. Company standards
3. International rules, codes and standards
4. Manufacturer’s technical documentation.
European Standards
4.1 General
Work included in this section consists of the design, supply and installation of all components of the
cathodic protection system, including anodes, pin brazing, cables, test stations, coating repair,
joint bonds, and any other work necessary to complete the installation.
This section describes for each area, the flowlines in project and the relevant documentation
produced during the previous phase, that shall be used as references for the new
design phase to be realised by Subcontractor.
The new water injection flowlines in project have the scope to complete and finalize the general
pipelines, trunklines and flowlines (oil and water) system already installed during the
previous phase. For this reason, Subcontractor shall:
analyse and fully understand the relevant documentation already issued (see cap.
5.2);
perform a field survey in order to verify the existing CP systems (from previous
Zubair phase or derived by other project in the same area);
design the temporary and permanent cathodic protection system for the new water
injection flowlines in project in accordance with codes, philosophy and input
data (as soil resistivity values) already used in the previous phase and listed in
the issued documentation (see cap. 5.2);
Since the existing CP network (realized with different CPS) was built taking into account the
future system expansion, Subcontractor main scope is to protect the new water
injection flowlines maximizing the use of existing CPS in the different project areas.
It has to verify if the existing CPS are able to protect also the new flowlines through simple
connection without other modification of the system.
In case of existing CP systems are not able to protect the new flowlines in project, the design of
new system shall be foreseen, according to the actual configuration, available spaces
and existing constraints.
In his design, Subcontractor shall take into account and mitigate the mutual possible
interferences between existing and new cathodic protection system.
For technical characteristics of the new water injection flowlines in project, see ref. Error:
Reference source not found
and Error: Reference source not found.
For details about flowlines routing and well head position, see ref. Error: Reference source not
found.
APPROX.
ITEM DESCRIPTION NOTE
LENGTH (m)
10” new UG flowline from NCS to The existing 6”
connection area with existing 6” flowline flowline was not
(connecting well ZB-075 to ZB-099) included in the
1 100
design performed
during the previous
phase.
10” UG flowline connecting the existing
2 120
10” line to well ZB-272
3 10” new UG flowline from NCS to well 4496 NEW FLOW LINE
WI-4
APPROX.
ITEM DESCRIPTION NOTE
LENGTH (m)
10” UG flowline from existing flowline Well ZB-278 was
1 (that connect UMCS to well ZB-278) to 150 named WI AH23 in
well ZB-219 the previous phase
10” new UG flowline from well ZB-105 to Well ZB-234 was not
2 well ZB-234 3300 included in the
previous phase
3 WI-2 to ZB-223 1866
4 AH-21 to ZB-223 1962
5 ZB-094 to UMCS 4554
6 WI-1 to ZB-094 1619
APPROX.
ITEM DESCRIPTION NOTE
LENGTH (m)
10” new UG flowline from well ZB-207 to Well ZB-280 was not
well ZB-280 included in the
previous phase. Well
1 693
ZB-207 was named
WI 120S in the
previous phase
10” new UG flowline from wSCS to well
2 189
ZB-082
10” new UG flowline from LMCS to well .
3 3199
ZB-074
4 10” new UG flowline from LMCS to well
5990
ZB-221
5 10’’ new flowline from SCS to well WI-3 2004
4.5.1 Underground
Underground cable-to- pipe connections shall be carried out by using pin brazing
equipment.
Once pin brazing has been executed, Contractor shall check the cable
connection by means of:
This document is property of eni Iraq B.V.
It shall neither be shown to Third Parties nor used for purposes other than those for which it has been sent.
Owner Logo and business name Company Identification Owner Identification Revision Index Sheet of Sheets
of document Owner
Validity Rev.
Status N. 13 / 16
250600DLSAD0269 OGI002-PL-0270-00
EX-DE 00
visual check;
pull out test, having the purpose to verify the good mechanical outcome of the
connection. It shall be carried out by applying traction parallel to pipe direction
not less than 1500 N to the connected cable;
electrical check.
Once the connection has been executed, Contractor shall check the cable
connection by means of:
visual check;
pull out test, having the purpose to verify the good mechanical outcome of the
connection. It shall be carried out by applying traction parallel to pipe direction
not less than 1500 N to the connected cable;
electrical check.
Upon positive results of required checks and tests, every bolted connection shall
be sealed with epoxy resin.
Cables shall be handled and laid with extreme care because any damage to the
insulation and/or sheathing may result in premature cable failure. During
installation the cable reel shall be supported so that cable may be pulled from the
reel without causing twisting.
Once cables have been laid, Contractor shall check cables for electrical
continuity.
One end of each cable shall be connected to the pipe, to the reference electrode
cable or to the zinc ribbon for earthing. The second end shall be connected to the
respective terminal block, installed into junction boxes or TPs or directly to T/R.
When necessary, cables ends shall be provided with copper compression lugs
Each cable end shall be suitably identified by a coloured heat shrinkable sleeve
and by a plastic tag with its identity and origin written on.
Electrodes location shall be checked to comply with the design. The electrodes
shall be installed according to Manufacturer’s instructions and TP installation
drawing details.
Fixed CSE shall be laid inside a backfill groundbed composed by gypsum and
bentonite (previously mixed with water) and placed at about 500 mm apart from
the lateral pipeline lateral border for ZSE add to mixture Sodium Sulphate as
indicated.
After installation the cables and the electrodes shall be protected from any
damage due to on-going construction work.
The electrode cable tails and the test cable to the structure shall be terminated in
a terminal block.
4.6 Engineering