Professional Documents
Culture Documents
QQS Valuation No 8 - 22-08-2016
QQS Valuation No 8 - 22-08-2016
3.0 Security Adjustment [14.7.1 (Retention), 31.8] (yes/no) No (If yes) 0.0% R - R 78,085,393.28
15.0 CERTIFIED AMOUNT DUE FOR PAYMENT TO THE (Contractor / Employer) R 24,394,932.06
16.0 Contract Sum execution % (Variable construction guarantee only) (D7.0 ÷ A11.0 × 100) 47.2%
√ Practical x Final x
Security Status [Mark each box with a √ or ×] 16.0 < 50% √ 16.0 > 50%
Completion Completion
Signed by the Principal Agent who, as agent for the employer, certifies that the positive or
Signed :
negative amount stated in D 15.0 above is due and payable
Date 22-Aug-16
652787964.xlsx 1
Payment Certificate
Recovery Statement Certificate N° 8
The following amounts, as detailed in the supplementary documentation where required, are recovered in the current Payment Certificate :
A B C
Signed by the Principal Agent who, as agent for the employer, certifies that the amounts stated above
Signed :
are included in the current payment certificate
652787964.xlsx 2
Recovery Statement
Date : 22-Aug-16
652787964.xlsx 3
Recovery Statement
VALUATION SUMMARY Valuation 8 22-Aug-16
PREVIOUS BALANCE TO
ITEM DESCRIPTION BOQ CURRENT VALUATION TOTAL DUE
VALUATION COMPLETE
. DESCRIPTION UNIT Rate QTY AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
1 610mm Diameter pile No 821.74 125 R 102,717.50 131.00 R 107,647.94 131.00 R 107,647.94 131.00 R 107,647.94
2 520mm Diameter pile No 717.06 80 R 57,364.80 80.00 R 57,364.80 77.00 R 55,213.62 77.00 R 55,213.62
New/QQS 410mm Diameter pile No 612.38 37.00 R 22,658.06 14.00 R 8,573.32 14.00 R 8,573.32
3 Allow for risk of collapse to battered sides of "in bulk" Item 20935.98 1 R 20,935.98 1.00 R 20,935.98 1.00 R 20,935.98 1.00 R 20,935.98
excavations or filling.
4 Keeping excavations free of water Item 8897.79 1 R 8,897.79 1.00 R 8,897.79 1.00 R 8,897.79 1.00 R 8,897.79
5 Keeping excavations free of seepage and subterranean water Item 0 1 R 0.00 R 0.00 R 0.00 R 0.00
Dewatering H3
6 Dewatering system for removal of seepage water and water Item 214728 1 R 214,728.00 1.00 R 214,728.00 1.00 R 214,728.00 1.00 R 214,728.00
from other subterranean sources in the bulk excavations
designed and executed by the contractor
New/QQS Excavations average 5m deep (Ross Rate as agreed) m3 65 1,000.00 R 65,000.00 1,000.00 R 65,000.00 1,000.00 R 65,000.00
New/QQS Surplus material from excavations and/or stock piles on site to m3 155 1,000.00 R 155,000.00 1,000.00 R 155,000.00 1,000.00 R 155,000.00
a dumping site to be located by the contractor (Ross Rate as agreed)
8 Trenches for ground beams m3 125.62 102 R 12,813.24 1,094.63 R 137,507.67 121.00 R 15,200.02 121.00 R 15,200.02
10 Sump holes m3 130.85 20 R 2,617.00 23.00 R 3,009.55 0.00 R 0.00 0.00 R 0.00
11 Holes including working around piles m3 151.79 371 R 56,314.09 563.00 R 85,457.77 561.00 R 85,154.19 561.00 R 85,154.19
12 Lift pits m3 130.85 63 R 8,243.55 6.95 R 909.41 0.00 R 0.00 0.00 R 0.00
13 Exceeding 0,50m and not exceeding 1,50m deep for erection m2 141.32 732 R 103,446.24 149.00 R 21,056.68 0.00 R 0.00 0.00 R 0.00
and removal of formwork to bases, etc against excavated face
14 Under floors etc m3 272.17 189 R 51,440.13 103.00 R 28,033.51 0.00 R 0.00 0.00 R 0.00
New/QQS Under floors etc ( Between Gridline 3/4 & D/H) m3 272.17 0 R 0.00 240.00 R 65,320.80 240.00 R 65,320.80 240.00 R 65,320.80
15 Behind retaining walls m3 251.23 889 R 223,343.47 14.00 R 3,517.22 14.00 R 3,517.22 14.00 R 3,517.22
16 Under floors, steps and pavings, etc m3 518.17 522 R 270,484.74 580.00 R 300,538.60 415.00 R 215,040.55 350.00 R 181,359.50
20 Surplus material from excavations and/or stock piles on site to m3 204.13 785 R 160,242.05 1,957.00 R 399,482.41 740.00 R 151,056.20 740.00 R 151,056.20
a dumping site to be located by the contractor
21 Sides of trench and hole excavations not exceeding 1,5m deep m2 15.7 926 R 14,538.20 310.00 R 4,867.00 306.00 R 4,804.20 306.00 R 4,804.20
22 Keeping excations free of water Item 5234 1 R 5,234.00 1.00 R 5,234.00 1.00 R 5,234.00 1.00 R 5,234.00
Compaction of surfaces H3
23 Compaction of ground surface under floors etc including m2 14.66 3257 R 47,747.62 2,070.00 R 30,346.20 2,070.00 R 30,346.20 2,070.00 R 30,346.20
scarifying for a depth of 150mm, breaking down oversize
material, adding suitable material where necessary and
compacting to 95% Mod AASHTO density to top 125mm
24 Backfilling to trenches, holes, etc (Rate Only) m3 68.04 0 R 0.00 210.00 R 14,288.40 0.00 R 0.00 0.00 R 0.00
25 Backfilling behind retaining walls (Rate only) m3 68.04 0 R 0.00 R 0.00 0.00 R 0.00 0.00 R 0.00
26 Backfilling to trenches, holes, etc m3 251.23 128 R 32,157.44 0.00 R 0.00 R 0.00 R 0.00
BOQ CONTRACTOR'S CLAIM QUANTELL VALUATION PREVIOUS AMOUNT CERT
. DESCRIPTION UNIT Rate QTY AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
27 Backfilling behind retaining walls m3 251.23 3103 R 779,566.69 2,050.00 R 515,021.50 2,050.00 R 515,021.50 2,050.00 R 515,021.50
28 Under floors, steps, pavings, etc m3 251.23 209 R 52,507.07 0.00 R 0.00 R 0.00 R 0.00
29 Allow for compacting ground surfaces to bottom of trenches m2 14.66 387 R 5,673.42 378.00 R 5,541.48 295.00 R 4,324.70 295.00 R 4,324.70
30 Allow for compacting surfaces to bottom of bases, etc m2 14.66 270 R 3,958.20 435.00 R 6,377.10 434.00 R 6,362.44 434.00 R 6,362.44
Soil tests H3
31 DCP test on bases as per Engineers requirements No 78.51 137 R 10,755.87 36.00 R 2,826.36 0.00 R 0.00 0.00 R 0.00
15Mpa/10mm concrete H3
32 Surface blinding under footings and bases m3 1128.32 24 R 27,079.68 15.00 R 16,924.80 0.00 R 0.00 0.00 R 0.00
25 Mpa/19 mm concrete H3
33 Strip footings m3 995.38 100 R 99,538.00 70.00 R 69,676.60 58.00 R 57,732.04 58.00 R 57,732.04
34 Pile caps m3 1002.15 299 R 299,642.85 388.00 R 388,834.20 369.00 R 369,793.35 369.00 R 369,793.35
New/QQS Pile caps (Shear wall Bases) m3 1002.15 192.00 R 192,412.80 192.00 R 192,412.80 192.00 R 192,412.80
REINFORCED CONCRETE H2
30Mpa/19mm concrete H3
36 Ground beams m3 1061.14 102 R 108,236.28 101.00 R 107,175.14 73.00 R 77,463.22 73.00 R 77,463.22
New/QQS Capping Beam (All included with ground beams) m3 1061.14 0 R 0.00 26.00 R 27,589.64 49.00 R 51,995.86 49.00 R 51,995.86
New/QQS Lift Walls m3 1061.14 0 R 0.00 37.00 R 39,262.18 1.00 R 1,061.14 1.00 R 1,061.14
40Mpa/19mm concrete H3
37 Stub columns m3 1471.09 7 R 10,297.63 5.00 R 7,355.45 5.00 R 7,355.45 5.00 R 7,355.45
38 Shear walls in foundations m3 1278.16 3 R 3,834.48 4.00 R 5,112.64 4.00 R 5,112.64 4.00 R 5,112.64
39 Lift pit base m3 1522.11 21 R 31,964.31 21.00 R 31,964.31 0.00 R 0.00 0.00 R 0.00
40 Lift pit walls m3 1507.06 8 R 12,056.48 8.00 R 12,056.48 0.00 R 0.00 0.00 R 0.00
41 Retaining walls m3 1489.67 374 R 557,136.58 315.00 R 469,246.05 305.00 R 454,349.35 305.00 R 454,349.35
FORMWORK ETC. H2
42 Bases (200mm Wide concrete added to all bases & ground beams instead of
m2working space &177.15
formwork) 909 R 161,029.35 0.00 R 0.00 0.00 R 0.00 0.00 R 0.00
43 Stub columns m2 391.88 81 R 31,742.28 51.00 R 19,985.88 51.00 R 19,985.88 51.00 R 19,985.88
45 Retaining walls m2 295.25 3268 R 964,877.00 2,800.00 R 826,700.00 2,676.00 R 790,089.00 2,676.00 R 790,089.00
NEW Retaining walls exc. 3.5m High and n.e 5m High m2 332.83 0 R 0.00 475.00 R 158,094.25 0.00 R 0.00 0.00 R 0.00
46 Shear walls in foundations m2 295.25 25 R 7,381.25 27.00 R 7,971.75 27.00 R 7,971.75 27.00 R 7,971.75
New/QQS Inner face of lift foundation walls m2 348.93 0 R 0.00 4.00 R 1,395.72 4.00 R 1,395.72 4.00 R 1,395.72
New/QQS Outer face of lift foundation walls m2 295.25 0 R 0.00 4.00 R 1,181.00 4.00 R 1,181.00 4.00 R 1,181.00
47 Inner face of lift pit walls m2 348.93 37 R 12,910.41 5.00 R 1,744.65 0.00 R 0.00 0.00 R 0.00
48 Outer face of lift pit walls m2 295.25 31 R 9,152.75 6.00 R 1,771.50 0.00 R 0.00 0.00 R 0.00
49 25 x 25mm Horizontal rebate in lift pit walls m 24.16 18 R 434.88 176.00 R 4,252.16 R 0.00 R 0.00
50 10mm Joints not exceeding 300mm high m 28.23 5264 R 148,602.72 1,880.00 R 53,072.40 1,880.00 R 53,072.40 1,880.00 R 53,072.40
51 One brick walls m2 291.89 137 R 39,988.93 20.00 R 5,837.80 R 0.00 R 0.00
52 280mm Hollow retaining wall of two half brick skins, the cavity m2 382.68 18 R 6,888.24 62.00 R 23,726.16 62.00 R 23,726.16 62.00 R 23,726.16
filled with 25MPa/19mm reinforced concrete including butterfly
wall ties to SABS 28 every fourth course vertically and at
500mm centres horizontally staggered (Reinforcement
elsewhere)
53 Cavity wall of two half brick skins, the cavity filled with m2 382.68 22 R 8,418.96 8.00 R 3,061.44 R 0.00 R 0.00
25MPa/19mm reinforced concrete including butterfly wall ties to
SABS 28 every fourth course vertically and at 500mm centres
horizontally staggered (Reinforcement elsewhere)
Brickwork reinforcement H3
54 75mm Wide reinforcement built in horizontally m 1.85 494 R 913.90 368.00 R 680.80 R 0.00 R 0.00
55 150 mm Wide reinforcement built in horizontally m 1.98 539 R 1,067.22 216.00 R 427.68 0.00 R 0.00 0.00 R 0.00
. DESCRIPTION UNIT Rate QTY AMOUNT QTY AMOUNT QTY AMOUNT QTY AMOUNT
56 On brick surfaces m2 16.64 10 R 166.40 62.00 R 1,031.68 62.00 R 1,031.68 62.00 R 1,031.68
SUBSOIL DRAINAGE H2
59 Vertically against retaining walls m2 68.04 1616 R 109,952.64 1,660.00 R 112,946.40 1,211.00 R 82,396.44 1,211.00 R 82,396.44
60 Under stone layer including laps, joints, all cutting and m2 20.94 3498 R 73,248.12 2,970.00 R 62,191.80 2,955.00 R 61,877.70 2,955.00 R 61,877.70
protection.
61 Vertically against sand layer including laps, joints, all cutting m2 20.94 1959 R 41,021.46 810.00 R 16,961.40 810.00 R 16,961.40 810.00 R 16,961.40
and protection.
Subsoil Drainage H3
62 Pipeless subsoil of 19mm crushed stone size 300 x 300mm m 157.02 130 R 20,412.60 236.00 R 37,056.72 130.00 R 20,412.60 130.00 R 20,412.60
and 'Bidem Grade A2' geotextile filter blanket wrapped around
stone with 300mm side and end laps, including stitching
63 110mm Slotted uPVC 'Drainex DN 110' agriculture pipes, m 193.66 384 R 74,365.44 384.00 R 74,365.44 384.00 R 74,365.44 384.00 R 74,365.44
including 19mm crushed stone encasing size 300 x 300mm
and 'Bidem Grade A4' geotextile filter blanket wrapped around
encasing with 300mm side and end laps, including stitching
under solid floors
64 160mm Slotted uPVC 'Drainex DN 110' agriculture pipes, m 209.36 115 R 24,076.40 118.00 R 24,704.48 115.00 R 24,076.40 115.00 R 24,076.40
including 19mm crushed stone encasing size 300 x 300mm
and 'Bidem Grade A4' geotextile filter blanket wrapped around
encasing with 300mm side and end laps, including stitching
under solid floors
65 Extra over for 110mm bend No 125.62 89 R 11,180.18 54.00 R 6,783.48 54.00 R 6,783.48 54.00 R 6,783.48
66 Extra over for 160mm reducing bend No 361.15 4 R 1,444.60 13.00 R 4,694.95 13.00 R 4,694.95 13.00 R 4,694.95
67 Extra over for 160mm reducing junction No 151.79 45 R 6,830.55 28.00 R 4,250.12 28.00 R 4,250.12 28.00 R 4,250.12
68 Extra over for 110mm double Y junction No 308.81 1 R 308.81 8.00 R 2,470.48 8.00 R 2,470.48 8.00 R 2,470.48
69 Extra over for 110mm cast iron rodding eye No 329.74 44 R 14,508.56 25.00 R 8,243.50 25.00 R 8,243.50 25.00 R 8,243.50
Sub-Soil Pumps
New/QQS Sub-Soil Pumps as per quotation from Platinum Pumps No 68200 0 R 0.00 0.00 R 0.00 0.00 R 0.00 0.00 R 0.00
B.7 FLOOR COVERINGS, PLASTIC LININGS, ETC R 35,921.75 R 0.00 R 0.00 R 0.00
Contract UCT 1
Site Quantell
Variation Contractor Quantell
Instruction Date Description Previously Status Comments PQS Comments
No Value Approved Value
No. Approved Value
1 33903 12/1/2015 A Flow rate and water pressure test done on main water supply R 3,887.00 R 3,887.00 R 3,887.00 Pending Agreed
Pile cap S/5 if off centre - A deep ground beam 1mx1m will be
2 33904 1/25/2016 connected to the existing retaining wall footing R 2,248.17 R 0.00 R 0.00 Part of re-measurement in Fnds
Pile Caps off centre P.Q/4 - New Ground beam created 1mx1mx1m
3 33905 2/10/2016 and additional rebar installed R 2,248.17 R 0.00 R 0.00 Part of re-measurement in Fnds
4 33906 2/10/2016 Pile Cap Base To High - to be trimmed still to be quantified
Gunite wall to be trimmed and Franke Pile Tension Plate to be
5 33907 2/1/2016 chopped to accommodate size R 23,391.14 R 23,391.14 R 23,391.14 Pending Projected - To be finalised Breakdown Required
6 Ramp Removal (Included with Foundations - See Qty Certified) R 0.00 R 0.00 R 0.00 Pending Projected - To be finalised Part of re-measurement in Fnds
7 33908 2/15/2016 Y32 Holes to be cored into the existing ground on grid J-L/5 R 2,772.00 still to be quantified
a) Backfilling behind retaining walls must be done with a selected G7
filling material compacted to 98% mod AASHTO density (100% for
sand) b) Other than general backfill Projected - To be finalised
Part of re-measurement in Fnds
the 500mm wide drainage layer behind all retaining walls is to be (832m3*R411.20)
constructed as per issued drawings C-004 A&B (Signed by Rikus
8 33909 2/16/2016 Steyn) R 342,118.40 R 0.00 R 0.00
Pile Cap of Centre - Rebard core drilled 7No top and Bottom and Part of re-measurement in Fnds - drilling cost to
9 33911 2016/02/25 1mx1m strip footing provided R 4,218.78 be determined
Grid T-U/5-7 Existing ground trimmed to suite, to receive bidum &
10 33912 2016/02/24 200mm aggregate stone & DPC Sheet - As per Rikus Steyn R 12,090.54 77m2*R157.02
2 Alterations R -
-
3 Earthworks R -
-
-
4 Concrete, formwork & reinforcement R -
-
5 Masonry R 139,004.83
NFX MAXI Bricks m2 600.00 228.32 136,992.00
90 x 90mm Lintels in lengths not
m 62.00 32.47 2,012.83
exceeding 3m
-
6 Waterproofing R -
-
-
7 Carpentry & Joinery R 163,542.27
90x70mm Hardwood Door Frames No 186.00 806.95 150,092.70
90x45mm Hardwood Door Frames No 22.00 379.00 8,338.00
Type M double door 1219 x 2135mm
-
high with rebated frame
suitable for 230mm cavity wall No 1.00 5,111.57 5,111.57
652787964.xlsx
7
Materials Schedule "Annex A"
MILTON CONSTRUCTION Valuation No 8
ANNEXURE A: MATERIALS ON SITE CLAIM SCHEDULE
-
11 Metalwork
-
-
12 Plastering R -
-
-
13 Tiling R 121,752.00
Wall and Floor Tiling (500 x 500) m2 700.00 80.33 56,231.00
Wall Tiling (300 x 550) m2 350.00 87.71 30,698.50
Shower Floor tiles (100 x 100) m2 300.00 90.00 27,000.00
Tile adhhesive 20kg bags bags 150.00 52.15 7,822.50
14 Paintwork
15 Glazing R -
16 External Works R -
1 Electrical Installation R -
-
-
2 Heat Pump R 2,118,500.00
Tank 12000L Item 1.00 653,000.00 653,000.00
Heat Pumps & Cold water Tanks Item 1.00 1,465,500.00 1,465,500.00
Lift Installation R -
9 Biometric Locks R -
652787964.xlsx
8
Materials Schedule "Annex A"
MILTON CONSTRUCTION Valuation No 8
ANNEXURE A: MATERIALS ON SITE CLAIM SCHEDULE
-
TOTAL CARRIED TO VALUATION STATEMENT R 9,357,734.61
652787964.xlsx
9
Materials Schedule "Annex A"
SUMMARY OF AMOUNTS CERTIFIED
WORKS: PROPOSED NEW STUDENT BOARDING HOUSE
VALUATION DATE: August 2016
CERTIFICATE NO: 8
0.0%
1 MAIN CONTRACTOR (PTY) LTD 50,452,762.61 1,766,753.58 R 52,219,516.19 R 0.00 R 52,219,516.19 R 0.00 R 52,219,516.19
Main Contractor
4 TEKNIHEAT (CAPE) (PTY) LTD 2,118,500.00 R 2,118,500.00 R 0.00 R 2,118,500.00 R 0.00 R 2,118,500.00
Heat Pump Installation
6 GOOD HOPE INITIATIVES (PTY) LTD 493,419.50 R 493,419.50 R 0.00 R 493,419.50 R 0.00 R 493,419.50
Airconditioning & Ventilation
8 PLOTZ & MULLER 1,706,388.56 828,145.55 R 2,534,534.11 R 0.00 R 2,534,534.11 R 0.00 R 2,534,534.11
Aluminium Windows & Doors
11 KEEP ELECTRONICS (PTY) LTD 2,985.00 1,657,755.00 R 1,660,740.00 R 0.00 R 1,660,740.00 R 0.00 R 1,660,740.00
Biometric Locks