F - ABCD - 43FLBLDG - 40

ABC Construction Corporation


TYPE YOUR PROJECT NAME
Project :

Date Prepared BRI No.


REQUEST OF INSTALLATION OF
MISCELLANEOUS METALS
REQUESTED BY : Name/ Designation :
Contractor : Signature :

Note : All signatories should print their name and sign.

Balcony Railings Ladder Rungs

Column Guards

Stairway Handrails Others

AREA (Pls. enclose key plan) GRIDLINE/LOCATION LEVEL STRUCTURE

PREPARED BY CHECKED BY INSPECTED BY


CHECK ITEMS
CONTRACTOR PROJECT SUPERVISOR QC

LINE and GRADE


ELECTRICAL
PLUMBING
ARCHITECTURAL
WATERPROOFING

OTHERS

REMARKS :

CHECKED BY : RECOMMENDING APPROVAL :

PROJECT SUPERVISOR QC

APPROVED BY : NOTED BY:

VP-CONSTRUCTION OPERATIONS

NOTE : This form must be submitted to The QC TEAM, duly accomplished and signed by the corresponding
Contractor's Personnel-in-charge at least 24 hours before actual installation.

Rev. 0 August 27,2019