Timeline
Timeline
Implementation Plan
SN.
Name of Activity
1 Excavation
Compaction Piles
Piles
Raft Founfation with Column
Roof of Raft Slab
2 GF FF SF
RCC of Column
RCC of Beam
RCC of Slab
3 3rd 4th 5th
RCC of Column
RCC of Beam
RCC of Slab
Brickwork of GF FF SF
4 6th 7th 8th
RCC of Column
RCC of Beam
RCC of Slab
Brickwork of 3rd 4th 5th
Electrical & Plumbing of GF FF SF
Internal Plaster of GF FF SF
5 9th 10th 11th
RCC of Column
RCC of Beam
RCC of Slab
Brickwork of 6th 7th 8th
Electrical & Plumbing of 3rd 4th 5th
Internal Plaster of 3rd 4th 5th
Tiling of GF FF SF
6 12th 13th 14th
RCC of Column
RCC of Beam
RCC of Slab
Brickwork of 9th 10th 11th
Electrical & Plumbing of 6th 7th 8th
Internal Plaster of 6th 7th 8th
Tiling of 3rd 4th 5th
Internal painting of GF FF SF
7 15th 16th 17th
RCC of Column
RCC of Beam
RCC of Slab
Brickwork of 12th 13th 14th
Electrical & Plumbing of 9th 10th 11th
Internal Plaster of 9th 10th 11th
Tiling of 6th 7th 8th
Internal painting of 3rd 4th 5th
Fixing Doors and Windows GF FF SF
8 18th 19th 20th
RCC of Column
RCC of Beam
RCC of Slab
Brickwork of 15th 16th 17th
Electrical & Plumbing of 12th 13th 14th
Internal Plaster of 12th 13th 14th
Tiling of 9th 10th 11th
Internal painting of 6th 7th 8th
Fixing Doors and Windows 3rd 4th 5th
9 Above Roof Slab
RCC of Column
RCC of Beam
RCC of Slab
Brickwork of 18th 19th 20th
Electrical & Plumbing of 15th 16th 17th
Internal Plaster of 15th 16th 17th
Tiling of 12th 13th 14th
Internal painting of 9th 10th 11th
Fixing Doors and Windows 6th 7th 8th
12/1/2021 1/9/2022
1/15/2022 4/1/2022
4/1/2022 6/15/2022
6/15/2022 9/15/2022
9/15/2022 1/1/2023
1/1/2023 3/15/2023
1/1/2023 3/15/2023
3/15/2023 6/1/2023
6/1/2023 9/15/2023
9/15/2023 1/1/2024
1/1/2024 3/15/2024
3/15/2024 6/1/2024
6/1/2024 9/15/2024
9/15/2024 3/1/2025
10
11
12
13
yakLuxuria
on Plan
Start Date End Date of
of Activity Activity
12/1/2021 1/9/2022
1/15/2022 4/1/2022
4/1/2022 6/15/2022
6/15/2022 9/15/2022
9/15/2022 1/1/2023
1/1/2023 3/25/2023
Brickwork of 9th 3/25/2023
Brickwork of 11th 4/9/2023
22
3/25/2023 4/16/2023 22
4/16/2023 5/8/2023 22
5/8/2023 5/30/2023 22
Brickwork of 12th 4/24/2023
Brickwork of 13th 5/9/2023
Brickwork of 14th 5/24/2023
5/30/2023 6/21/2023 22
6/21/2023 7/13/2023 22
7/13/2023 8/4/2023 22
Brickwork of 15th 6/8/2023
Brickwork of 16th 6/23/2023
Brickwork of 17th 7/8/2023
25
8/4/2023 8/29/2023
Brickwork of 18th 7/23/2023
Brickwork of 19th 8/12/2023
Brickwork of 20th 9/1/2023
1/1/2024 3/15/2024
3/15/2024 6/1/2024
6/1/2024 9/15/2024
6/1/2024 9/15/2024
9/15/2024 3/1/2025
6/23/2023 20
7/13/2023 20 Internal Plaster of 3rd
8/2/2023 20 Internal Plaster of 4th
Internal Plaster of 5th
8/22/2023 20
9/11/2023 20 Internal Plaster of 6th
10/1/2023 20 Internal Plaster of 7th
Internal Plaster of 8th
10/21/2023 20
11/10/2023 20 Internal Plaster of 9th
11/30/2023 20 Internal Plaster of 10th
Internal Plaster of 11th
12/20/2023 20
1/9/2024 20 Internal Plaster of 12th
1/29/2024 20 Internal Plaster of 13th
Internal Plaster of 14th
2/18/2024 20
3/9/2024 20 Internal Plaster of 15th
3/29/2024 20 Internal Plaster of 16th
Internal Plaster of 17th
4/18/2024 20
5/8/2024 20
5/28/2024 20 Internal Plaster of 18th
Internal Plaster of 19th
Internal Plaster of 20th
Tiling of GF FF SF