ESTIMATED COST OF THE INSTALLATION TESTING AND COMMISSIONING

FOR
S/NO LIST OF MACHINERY DESCRIPTION NO OF EQ NO OF DAYS PER DAY
1 CRANE 1 20 4500
2 FORK LIFT 1 20 3000
3 WELDING MACHINE 2 45 1000
4 PAINTING MACINE 2 35 1200
5 PICK UP SINGLE CABIN 1 40 1500
6 PICK UP DOUBLE CABIN 1 40 2000

G . TOTAL

S/NO NO OF DAY NO OF CREW PER DAY TOTAL REMARK


1 MAN POWER COST 1
2 SKILLED WORKER 15 1 1800 27,000
3 PROJECT MANGER 15 1 2500 37,500
4 E/M EXPERT 10 2 2000 20,000
5 SITE SUPERVISOR 30 1 1500 45,000
6 MECHANIC 30 4 800 96,000
7 ELECTRICIAN 30 4 800 96,000
8 WELDER 30 3 1000 90,000
9 FITTER 30 3 1000 90,000
10 HELPER 30 3 500 45,000
11 LABOUR 30 6 500 90,000,00

TOTAL 456,000,00

S/NO CONSUMABLE MATERIAL KG QTTY UNIT PRICE TOTAL PRICE


1 ELECTROD 20KG
2 DISKHACK SAW BLADE 5PC
3 RAGES 5KG
4 CUTTING DISK 50 PC
5 GRINDING DISK 50PC
6 HACK SAW BLADE 10PC
TOTAL
COMMISSIONING

TOTAL PRICE REMARK


90,000,00
60,000,00
90,000,00
84.000,00
60,000,00
80,000,00

464.000,00