To be ensured leakage test for floor bottom surface and side area.
Light weight filling top Level Button Mark to be fixed all corner & Center
area, slope level also to be verify as per drawing specification.
Identify as per the drawing thickness of light weigh filling 50mm to 200mm.
Mix proportion to be followed as light weight filling 1:3 (one cement and
Threes parts of vermiculate (CIDOMLITE)) on Mixture machine with
weight base.
To be ensured availability of the material and manpower in working area.
Moist the surfaces before light weight filling to Reduce the water loss due to
absorption.
Top of the surface should be level on the button mark to control undulations.
Levelling top surface by tamping with aluminum straight edge.
2.SCREED CONCRETE:
Cleaning Light weight Filling top surface area thoroughly with water.
Screed top level button fixing at four corner area, slope level also to be
verify as per drawing specification.
Sequence of concreting has been planned and sufficient labour & Materials
to be deployed.
1
Moist the surfaces before concreting to Reduce the water loss due to
absorption.
Mix proportion to be followed as sunken filling screed concrete area 1:2:4
(one cement and two parts of M.sand and four parts of coarge aggregate)
with LW+ Integral liquid waterproofing compound at 200ml/bag on Mixture
machine or using Forma box for manual mixing with MS sheet.
Levelling top surface by tamping with aluminum straight edge.
Brooming after drying of screed concrete top surface area.
Curing should be ensure 7days for OPC cement.