DAILY ACTIVITY REPORT

PROJECT OWNER : PT SORIK MARAPI GEOTHERMAL POWER DATE : 22 March 2023


CONTRACTOR : BANAWA CIPTA JAYA REPORT NO :
PROJECT NAME : Install Cover Gabion, Inclinometer WORKING HOURS : 10 hours
CONTRACT NO :
1. WEATHER REPORT
Weather 7:00 8:00 9:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00
Clear
Cloudy
Tiny Rain
Heavy Rain
2. DAILY PROGRESS
Previous Progress
No Item Description Unit Total Remarks
Cumm Today
1 Dismantlin form work cover gabion & House keeping m3 108.17 108.17
2 Continue to boring BH-08 (Acces road to ORC 32-33 ) m1 96.5 2 98.5

3. PLAN TOMORROW
No Description/Activity Remarks
1 Waiting information from SMGP to start work pouring cover gabion Trap 4 up to Tra 13
2 Continue boring BH 08 (Acces road to ORC 32-33 )

4. PERSONNEL ON BOARD & TOOLS


A. Personnel B. Equipment C. Tools
Status Personel
No Personnel Qty Hours Total Description Qty Description Qty Unit
Local Non Local
1 Project Manager 1 1 10 10 Mixer ( 0.3 m3) 1
2 Site Manager 1 1 10 10
3 HSE Supervisor 1 1 10 10
4 QC 1 1 10 10
5 Foreman 1 1 10 10
6 Operator Bor 1 1 10 10
7 Operator Compactor - 10 0
8 Mansory Man - 10 0
9 Rebar Man 1 10 10
10 Carpenter - 10 0
11 Helper 4 3 10 40
12 Survey - 10 0
Daily Man Hours 110
Total Person On Board 11 Previous 6760 Total Equipment 1 Total Tools 0 Unit
Cummulative Man Hours 6870
5. Obstacle On Site, Community & HSE Issue
A. Obstacle On Site B. Community & HSE Issue
No Obstacle Issue No Community & HSE Issue

Prepared By Checked By Acknowledge By


BCJ BCJ PT SMGP

Project Control Project Manager SMGP Representative


DOCUMENTATION ACTIVITY

Install Inclinometer BH 07 ( ORC 23 )

Boring BH -08 ( access road to ORC 32,33 ) Boring BH -08 ( access road to ORC 32,33 )