HARMONIC FILTER PANEL

LV HARMONIC FILTER
TESTING & COMMISSIONING PROJECT: SJMB&GDC, JUBAIL Page 1 of 2
REPORT

LV SWGR PANEL NAME PLATE DETAILS:

PANEL TAG VOLTAGE RATING 400/230V

LOCATION

1. MECHANICAL CHECK AND VISUAL INSPECTION:

Item Description Remarks


1 Inspect for physical damage/defects. OK

2 Check nameplate information for correction. OK

Check quality of paintwork, condition of lifting lugs, quality of weld


3 OK
areas and rust spots.

4 Check tightness of all bolted connections OK

5 Check that all grounding is securely connected. OK

6 Check proper operation of all auxiliary devices: OK

7 Performs all of the manufacturer’s specific checks. OK

8 Check proper operation of all Push Buttons, Indication. OK

2. FUNCTIONAL TEST:

Sl.No Description Remarks


Verification of the proper power connection (L1, L2, L3,
1 OK
N) and Earth before energization.
Check that the mains voltage is suitable for the filter’s
2 OK
working range.
Shuwayer Engineer SPML-QC Engineer SABIC
Name
Signature

Date
HARMONIC FILTER PANEL

LV HARMONIC FILTER
TESTING & COMMISSIONING PROJECT: SJMB&GDC, JUBAIL Page 2 of 2
REPORT

Ensure the connection type(open/close loop) before OK


3
energization
Confirm the necessary terminal connection for 3W/4W OK
4
before energization.
Check the External measurement CT wiring and ensure OK
5
the polarity at X1 terminal.
6 Close incoming breaker OK

7 Check the voltage L-L and L-N OK

8 Turn on the power button of harmonic filter OK

9 Select ‘Electrical connection’ on HMI OK

10 Select the nominal system frequency on HMI. OK

11 Select the nominal system Mains voltage. OK

12 Select Compensation mode. OK

13 Put the CT ratio of external measurement CTs OK

14 Put total installed current OK

15 Put the ratio of X3 CT. OK


Use selectable mode, set all harmonics to zero initially OK
16 and ramp up individually starting from the lowest one
and found THD is reduced.

▪ Successful completion of above mentioned steps leads to the successful


commissioning of respective Harmonic filter Panel.

Equipment used:-

Equipment Serial No. Calibration Due Date


Multimeter 11350105 15/10/2023

Shuwayer Engineer SPML-QC Engineer SABIC


Name
Signature

Date