COMMENT DISPOSITION FORM (CDF)
METHOD STATEMENT FOR IFOR INSTALLATION OF GLAZED ALUMINUM
Title: Reviewing Dept.: Arab Engineering Bureau
CURTAIN WALL BY GALFAR
Doc. No.: WAS-ALB-AEB-MST-AR-0009 Rev.: 2 Disposition Dept.: AL BALAGH
Review Date: 03/10/2022 Disposition Date: 02/10/2022
Noted,
Arch: Contact detail of relevant responsible
2. Closed
Provide Contact details of relevant responsible personnel. personnel is included in the section#7 Project
Organization Chart
Arch:
Section 5 Manpower Requirement. Noted,
a. Contractor to provide the number of persons required. Number of persons required in provided in
Section#5 Manpower requirements
Rev.01
3. Closed
REV.01
Include in the manpower requirement, how many Teams and composition per Noted and complied. Manpower required for
Team per panel installation. Glass and profile installation provided in
section manpower requirement.
Noted,
Arch:
Kindly refer Section #6 Plant and equipment
Provide Section for Plants & Equipment Requirement.
have been categorized.
Categorize the tools and Equipment. e.g., Equipment, Power tools, Hand
Tools, General Items, Required PPE.
REV.01
4. Mobile crane capacity is 25 tons, Tele handler Closed
Rev.01
is 3 tons.
A. Provide specific Mobile crane and Tele Handler boom loader
Hydraulic pallet trolley is required for short
information.
distance material shifting.
Any Trolley for moving short distance?
Kindly refer section 6 Material, Plant and
B. Glass suction Cups?
Equipment requirement
Noted,
Kindly refer Section #8, Detailed method
Arch: system per façade schedule system and per
Provide detailed method statement per façade schedule system and per location is provided.
locations to ensure coordination with other work interfacing.
Rev.01
Rev.01 a. Method statement for replacement or
5. Closed
a. Provide method statement for replacement or in case or breakage in case or breakage during or after
during or after the installation. the installation is provided.
b. Contractor to provide information for installation particular order of b. Same size of glass can be used in
fixation required or whether and/or whenever the same size of glass any place provided the spaces are
can be installed without sequence? same
Kindly refer Section #8,
Arch: Noted,
Provide Detailed Quality Control requirements. Detailed Quality control plan is provided in
6. Closed
Section#9
Arch: Noted,
Provide detailed delivery storage and handling. Detailed delivery storage and handling is
provided in Section #10
7. Rev.01 Closed
Provide a drawing layout of material storage at site whenever the material is Rev.01
not readily available for direct fixing. Please find the attached drawing layout of
material storage.in Section 13
Arch: Please refer Section#14- Attachments, 5.
Provide Certification and trainings. Certification and trainings.
A. Valid Certification Issued by approving Authority for qualified person.
8. B. Valid Calibration certificate for testing equipment. Rev.01 Closed
C. Qualification Record of Trained Personnel Performing the task. Please find the attached calibration certificate
Rev.01 for Digital coating thickness gauge in
Valid Calibration certificate for testing equipment not found. Section 13
Arch:
Logistic
WAS-ALB-AEB-GEN-DOC-0010 REV 02
Provide the Site Logistic Plan document reference that includes Material
Delivery Temporary, Facilities, Storage, Mobile Crane particular optimum
Rev 01
location etc.
9. Approved Site Logistic plan document Closed
reference number is
Rev.01
WAS-ALB-AEB-GEN-DOC-0010 REV 01
WAS-ALB-AEB-GEN-DOC-0010 REV 02 not yet submitted to AEB. Contractor
to submit.
Arch: Noted,
Contractor to review the ITP prior to submittal. Revised ITP attached.
10. Open
Testing
Provide preconstruction testing and post construction testing per required.
B.
Pre-construction Testing
Test requirements as per Project Specification Section 17 Part 8 > 8.1.3.
and
Noted,
Arch: Contact detail of relevant responsible
2. Closed
Provide Contact details of relevant responsible personnel. personnel is included in the section#7 Project
Organization Chart
Arch:
Section 5 Manpower Requirement. Noted,
a. Contractor to provide the number of persons required. Number of persons required in provided in
Section#5 Manpower requirements
Rev.01
3.
REV.01
Include in the manpower requirement, how many Teams and composition per Noted and complied. Manpower required for
Team per panel installation. Glass and profile installation provided in
section manpower requirement.
Noted,
Arch:
Kindly refer Section #6 Plant and equipment
Provide Section for Plants & Equipment Requirement.
have been categorized.
Categorize the tools and Equipment. e.g., Equipment, Power tools, Hand
Tools, General Items, Required PPE.
REV.01
4. Mobile crane capacity is 25 tons, Tele handler
Rev.01
is 3 tons.
A. Provide specific Mobile crane and Tele Handler boom loader
Hydraulic pallet trolley is required for short
information.
distance material shifting.
Any Trolley for moving short distance?
Kindly refer section 6 Material, Plant and
B. Glass suction Cups?
Equipment requirement
Noted,
Kindly refer Section #8, Detailed method
Arch: system per façade schedule system and per
Provide detailed method statement per façade schedule system and per location is provided.
locations to ensure coordination with other work interfacing.
Rev.01
Rev.01 a. Method statement for replacement or
5.
a. Provide method statement for replacement or in case or breakage in case or breakage during or after
during or after the installation. the installation is provided.
b. Contractor to provide information for installation particular order of b. Same size of glass can be used in
fixation required or whether and/or whenever the same size of glass any place provided the spaces are
can be installed without sequence? same
Kindly refer Section #8,
Arch: Noted,
Provide Detailed Quality Control requirements. Detailed Quality control plan is provided in
6.
Section#9
Arch: Noted,
Provide detailed delivery storage and handling. Detailed delivery storage and handling is
provided in Section #10
7. Rev.01
Provide a drawing layout of material storage at site whenever the material is Rev.01
not readily available for direct fixing. Please find the attached drawing layout of
material storage.in Section 13
Arch: Please refer Section#14- Attachments, 5.
Provide Certification and trainings. Certification and trainings.
A. Valid Certification Issued by approving Authority for qualified person.
8. B. Valid Calibration certificate for testing equipment. Rev.01
C. Qualification Record of Trained Personnel Performing the task. Please find the attached calibration certificate
Rev.01 for Digital coating thickness gauge in
Valid Calibration certificate for testing equipment not found. Section 13
Arch:
Logistic
WAS-ALB-AEB-GEN-DOC-0010 REV 02
Provide the Site Logistic Plan document reference that includes Material
Delivery Temporary, Facilities, Storage, Mobile Crane particular optimum
Rev 01
location etc.
9. Approved Site Logistic plan document
reference number is
Rev.01
WAS-ALB-AEB-GEN-DOC-0010 REV 01
WAS-ALB-AEB-GEN-DOC-0010 REV 02 not yet submitted to AEB. Contractor
to submit.
Arch: Noted,
Contractor to review the ITP prior to submittal. Revised ITP attached.
10.
Reviewer Name: Florian de Joya – Sr. Architect Signature: Date: Select date.
REVIEWER / APPROVER
REV DATE STATUS REVISION DETAILS Sub Main
Con Con EXTERNAL
Status Code:
D : Draft FI : For Information FC : For Construction
P : Preliminary FA : For Approval * External Authorization (Client),
where required
Distribution:
Table of Contents
1. SCOPE & OBJECTIVES.....................................................................................................................7
2. REFERENCES .....................................................................................................................................7
3. DEFINITIONS .......................................................................................................................................7
8. QUALITY CONTROL.........................................................................................................................17
13. ATTACHMENTS.............................................................................................................................20
The purpose of this Method Statement is to outline the methodology to be implemented for
Installation of Aluminum Curtain wall, Doors, Windows for wadi al sail office building with data
center and any miscellaneous works to ensure that all works are carried out in accordance with
QCS regulations, approved construction drawings and project specification.
2. REFERENCES
This method statement shall read and refer in conjunction with below references.
Project Specifications AEB-1429-20_ACS SPECS_IFT-REV 0 Volume 2, Section 17
Glazed Aluminum Curtain wall, Arch & Structural Specification
3. DEFINITIONS
SD Shop drawing
QA/QC Quality Assurance / Quality Control
ITP Inspection Test Plan
RA Risk Assessment
IFC Issued for Construction
4. RESPONSIBILITIES/ SUPERVISION
POSITION RESPONSIBILITY
Project Ensure the work is progressing as per the approved schedule and
contractual requirements
Manager
Construction Responsible for planning, organizing and carrying out the work in
accordance with project requirements and monitor the progress of
Manager
works.
Project Responsible for carrying out the work in accordance with project
requirements.
Engineer
QA/QC Ensure that the works are carried out as per approved Method
Statement.
Engineer
HSE Manager Responsible for planning, coordinate and resolving the issues and
directives within the organization and develop & reviews
plans/procedures for safe execution of work.
HSE Officer Ensure the works are carried in a safe manner. Provides Safety tool
box tasks and monitors are the work force for working safely. ensures
that construction workers are following established policies
and safety regulations
Supervisor/ Responsible for carrying out the works as per instructions of the
Project Engineer/ Construction Manager and provide proper
Foreman
documentation to his workers so they can proceed with tasks. Examine
the work location for any unsafe or unhealthful workplace conditions
or hazards prior to permit the workers to start task and ensure
adequate control measures are in place.
Workers Carryout the work as advised by the Foreman/ Charge hands and follow all
lawful employer safety and health rules and regulations, and wear or use
required protective equipment while working. Report hazardous conditions to
the employer.
5. MANPOWER REQUIREMENT
1 Project Manager 1
3 Project Engineer 1
5 Surveyor 1
6 Safety Officer 1
7 QA/QC Inspector 1
8 Supervisor 1
9 Charge hand 2
10 Technicians/installers 15
11 Skilled helpers 25
MANPOWER ALLOCATION.
GLASS INSTALLATION 2
Three team for installation will be constituted for glass installation.
Each Team will comprise of 2 installers and 4 skilled helper.
ALUMINUM PROFILE FIXING
Four teams will be constituted for the aluminum profile fixing.
Each Team will comprise of 2 installers and 4 skilled 4 helper
One Installer and skilled helper will be in charge of checking final alignment.
1
4 Total station
Project Manager
Project Engineer
Supervisor
Charge hand
8. PROCEDURE
8.1 CURTAINWALL
General Requirements
All works shall be carried out as per approved drawings, method statements, material
approval and in accordance with Project specification and QCS 2014
Permit will be will be obtained before the commencement of work,
Mock up
Prior to installation of curtain wall and aluminum window, mockup will be prepared and
approved by the consultant
Site Installation.
The area shall be finished properly by the main contractor based on the approved finishes
schedule before installation of curtain wall begins
All fabricated units shall be kept at the respective work location.
Work shall be coordinated with other disciplines to ensure all interface with other
contractors are well condinated.
Separators are used in between anchorages & adjacent materials to prevent corrosion.
Dielectric material is used as insulator.
Site survey and marking/lay-out will be done for first fix/anchoring.
The wall bracket and shoe bracket will be fixed at the required areas and fastened with
anchor bolt as per the shop drawing.
Mullions with brackets are fixed as per the approved shop drawings.
Erection Tolerances: Erection Tolerances of 10 – 20mm will be provided between the
structure and frames, which will be covered with sealant.
Transoms are fixed to the connection brackets of mullion and secures with screw
Glazing support bracket, insulator and inner gaskets are installed as per manufacturer’s
recommendation.
Install glass using crane and held temporarily with small pieces of pressure plate.
The temporary pressure plate is to allow all glass to be installed and aligned properly.
The glass will be held and controlled using suction pads. At the ground floor, glass will be
installed manually.
Install the rest of the glass and ensure all are in alignment.
Fix the pressure plate and cover with cap.
Installations are carried out in conformity with installation and approved shop drawings as
per system supplier’s recommendation
Insert the glass setting block, ensuring that it is placed correctly locations.
Clean the glass unit thoroughly.
Fix the outer gasket and weather strip (vertical and horizontal) using siliconized woven
polypropylene, wool pile or neoprene as per project specifications.
Corners of gasket at joints will be sealed with sealant as approved.
Insert the glass unit into the aperture and set properly onto the setting blocks.
Fix the glazing beads at the top and bottom of the shutter.
Fix the side glazing beads (in both the cases ensure that the bead retention clips are
located in the place).
Insert the internal wedge gasket.
Method Statement for Installation of curtain wall and Aluminum windows
Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms
Project Logo Project Name: WADI AL SAIL OFFICE BUILDING WITH DATA CENTER (4B+G+2F) 4B+G+7F) at C RING ROAD, DOHA QATAR
Project No.: 1429 Form No.: P07-F06 / Rev. 0 / Nov. 2012
Client Project Manager Consultant Contractor
Application of Sealant
Application of silicone sealant at the joint between Aluminum frames and wall (external
and internal):
Clear joints and surfaces free from grease, dust or other contaminates by using brush
and cloth.
Application of approved silicone sealant will be done with the help of gun.
Ensure the surface is smooth.
Masking tape will be used where necessary to prevent contamination of adjacent
surfaces.
Tape will be removed immediately after completion of the joint.
Broken Glass Replacement.
Work Methodology 2
Retain glass in position and remove pressure plate screws and plates.
Large pieces of broken glass shall be removed carefully using manual glass
catchers/Hand Vacuum Lifters.
9. QUALITY CONTROL
All the Inspection Request (IRS) shall be raised as per approved Inspection & Test Plan (ITP) for
the activity.
Incoming Material Inspection (MIR) shall be initiated for the material supplied for
permanent works in the project and approval obtained from the Consultant based on
approved Material Approval Request (MAR).
Material shall be stored at a safe place.
Material shall place on an elevated platform (placed on top of wood logs).
Material shall not have direct contact with the soil and shall be properly covered with
plastic.
12. LOGISTICS
A Site logistics plan indicating the temporary facilities and traffic management shall be
submitted and approval obtained.
All material deliveries for the works must be made through the authorized entry to the site.
Appropriate & correct Personnel Protective Equipment (PPE) shall be provided and
always worn. The basic PPE requirement includes Helmets, safety shoes, safety glass
and reflective jackets.
Safety induction training shall be provided to all staff, work force, operators prior to
entry to site premises. An induction sticker shall be provided to all attendees
identifying the satisfactory completion of training.
Toolbox talks shall be carried-out prior to commencing the task to clearly emphasize
the hazards and environmental aspects that might be encountered, and the
mitigating control measures to be undertaken. A prestart meeting shall be
conducted every day prior to start of the activity.
The Method Statement and risk assessment shall be clearly communicated to the
work personnel prior to start of work. PTW and its recommendations if any will also
be conveyed to the work force.
To ensure planned activities, and planned start date are coordinated to the
Consultant/Engineer prior to any site mobilization and commencement of the work.
Regular coordination with the Client construction and HSE team members should
be maintained.
Appropriate signage shall be provided within the site premises. Proper access and
egress to working sites shall be established.
Work/Access areas shall be free from debris and materials to avoid tripping hazard.
Scaffolding platform shall be erected as required to execute the works in safest
possible manner. Scaffolding shall be carried out by qualified/certified scaffolders
under the supervision of certified scaffold supervisor. During erection of scaffolding,
the area is barricaded with provision of safety signs to prevent unauthorized
personnel entry.
In General, all working areas shall be adequately barricaded to prevent
unauthorized personnel/public entry.
Appropriate permits as required shall be raised and maintained. Lifting Permits
Template is attached for reference.
Lifting permits along with the valid documents of the lifting crew shall be maintained
at the site during the lifting operations.
During Lifting Operations care shall be taken that adjoining structures / properties
are not damaged.
Regular housekeeping shall be always maintained.
A thorough inspection of tubular steel centering must be carried out before its
installation, and members showing evidence of excessive resting, dents, kinks, or
damaged welds shall be removed.
The effect of weather conditions shall also be taken into consideration.
During the pouring of the concrete, the centering shall be continuously inspected
and strengthened.
taken to ensure every person is accounted for. No one will be permitted to return to
work site until communication has been received from consultant HSE team / HSE
Manager/ Project Manager.
14. ATTACHMENTS
1. Risk Assessment
2. Inspection and Test Plan
3. Quality Control Check List
4. Drawings
5. Certification and Training
6. PRECONSTRUCTION TESTING AND POST CONSTRUCTION TESTING COMPLIANCE SHEET.
Severity of Risk
Severity Description Rating
Date: 19.03.2022 PROJECT: Wadi Al Sail office Building with Data Center DOC. Ref: No. -WAS-ALB-AEB-MST-AR-0009
Al Balagh shall utilize a matrix of severity and likelihood to assist in the evaluation process
MINOR 2 UNLIKELY 2 Action required to control the risk, interim measures may be necessary in
6 – 15 Med
MODERATE 3 OFTEN 3 the short term, able to proceed with work under supervision
MAJOR 4 LIKELY 4
This represents a low risk, although control measures must be
FATALITY 5 EXPECTED 5 1–5 Low
maintained
Prepared by: Rizwan Ahmad Reviewed by: Suraj Desai Approved by: Vinish Vasudevan
10
11
12
13
14
Date: 19.03.2022 PROJECT: Wadi Al Sail office Building with Data Center DOC. Ref: No. -WAS-ALB-AEB-MST-AR-0009
15
16
17
18
19
20
Project Name : WADI AL SAIL OFFICE BUILDING WITH DATA CENTER (4B+G+2F) 4B+G+7F)
Project No. : Form Ref. No. : P07-F06a / Rev. 0 / Feb. 2012
INSPECTION AND TEST PLAN (ITP)
Installation of Aluminum
Client Project Manager Consultant Contractor
2.0 Material
Inspection Test Plan (ITP) Form No.: P07-F06a / Rev. 0 / Feb. 2012
AEB - Construction Supervision Department Quality Forms Page 1 of 3 gr
Project Name : WADI AL SAIL OFFICE BUILDING WITH DATA CENTER (4B+G+2F) 4B+G+7F)
Project No. : Form Ref. No. : P07-F06a / Rev. 0 / Feb. 2012
INSPECTION AND TEST PLAN (ITP)
Installation of Aluminum
Client Project Manager Consultant Contractor
Inspection Test Plan (ITP) Form No.: P07-F06a / Rev. 0 / Feb. 2012
AEB - Construction Supervision Department Quality Forms Page 2 of 3 gr
Project Name : WADI AL SAIL OFFICE BUILDING WITH DATA CENTER (4B+G+2F) 4B+G+7F)
Project No. : Form Ref. No. : P07-F06a / Rev. 0 / Feb. 2012
INSPECTION AND TEST PLAN (ITP)
Installation of Aluminum
Client Project Manager Consultant Contractor
Prepared by (Contractor) : Reviewed and Approved by (AEB Discipline Engineer) : Noted by (AEB-PM or RE):
Name : Name : Name :
Signature : Date : Signature : Date : Signature : Date :
Inspection Test Plan (ITP) Form No.: P07-F06a / Rev. 0 / Feb. 2012
AEB - Construction Supervision Department Quality Forms Page 3 of 3 gr
Project Name : WADI AL SAIL OFFICE BUILDING WITH DATA CENTER (4B+G+2F) 4B+G+7F) at C RING ROAD, DOHA QATAR
Contract Title / No.: 1429
Consultant Main Contractor:
Name/Signature Name/Signature
Name / Signature
B
B
B
B
B
B
B
B
B
B
B
Refering to the workshop meeting held on 24/08/2022, contractor to comply with the
commented shop drawings as attached for final approval.
Mockup on site for termination details and waterproofing details are required
27/08/2022 27/08/2022
24/08/2022
B
B
B
B
B
B
B
B
B
B
Refering to the workshop meeting held on 24/08/2022, contractor to comply with the
commented shop drawings as attached for final approval.
Mockup on site for termination details and waterproofing details are required
27/08/2022 27/08/2022
LOCATION
t ba St.
18m U
MASTER PLAN
VEHICLE PARKING
LOCATION-01
PROJECT GATE
EXIT
WASTE
ENTRY
SITE ACCESS
SKIF
E231582.165 E231627.963 SMOKING
N390096.986 N390096.498 AREA
A E
REST
CHECK POINT 01
PEDESTRIAN ACCESS AREA
PROJECT BOUNDARY 52 50
49
SECURITY APPROVAL STATUS
GUARD
48
47
MESS HALL
HAND WASH
46
PEDESTRIAN ACCESS
45 44
STORE CONTAINER
42
SHOP DRAWING REFERENCES:
GENERATOR
PEDESTRIAN ACCESS
7
E231580.388
N390071.063
E231523.027 8
10 E231467.203 9
PROJECT BOUNDARY
E231512.998 N390069.582
N390069.245 N390069.104 STEEL REBAR STORAGE
TAKYEEF STORAGE 2 STEEL WORKSHOP MATERIAL STORE
FOR CURTAIN WALL
GATE
5
PROJECT BOUNDARY
6 41
TAKYEEF STORE 1 CONTAINER
2 4
E231522.642 E231579.160 TOWER
E231512.572 N390063.927
1 E231458.952 3
N390063.562
N390064.250 CAIN_02 IFC DRAWING REFERENCES:
E231449.530 N390064.138 E231466.250
N390062.983 N390062.861 F2
LOCATION-02
EQUIPMENT STORE
E231571.795
EQUIPMENT & VEHICLE N390057.835
40
E231504.431
DEBRIS N390053.946 36
37
WADI AL SAIL PROJECT
E231485.619 13 14 17
15 E231511.985
N390054.580
E231502.196
E231506.700
N390053.609
16 N390052.893 SHELTER CONSTRUCTION OF OFFICE BUILDING & DATA CENTER
N390053.790 E231522.769
11 E231452.335 12 E231456.564 N390053.215 E231546.395 35
34
FOR QATAR CENTRAL BANK
N390050.908 N390051.325 N390050.249 TOWER 39
SHUTTER STORAGE SHOP DRAWING REVISIONS:
CHECK POINT 02
SCAFFOLDING PREPARATION 29
AREA
SCAFFOLDING MATERIAL
19.063M
MATERIAL
32
TOWER 33
CRANE E231627.069 37 38
N390041.439
19
E231521.895
24 D
20
E231505.934 18 N390042.033 E231528.381 25
27
TOILET
TOILET
N390042.010 26
N390041.966 E231539.021
N390042.146
E231453.271
N390041.654 E231499.139
21
E231511.076 22
RAMP 31 E231618.936 MESS HALL
30
N390038.514 N390038.304 N390033.478
CONTAINER
TOILET E231581.905
PROJECT BOUNDARY
E231511.257
N390035.438 23
E231525.762
RAMP UP N390033.654
C
E231581.587
E231444.611 F1 N390034.268
GATE GENERATOR WATER GENERATOR B
N390034.995
N390035.066 E231534.851 TANK
N390034.192
SITE ACCESS
EXISTING FENCE
Serv
ice R
oad
AEB HEADQUARTERS:
P.O. Box 1148 Doha, Qatar Tel +974 4406 88 88 Fax +974 4447 78 68
Email aeb@aeb-qatar.com Web www.aeb-qatar.com
OTHER BRANCHES:
ABU DHABI * MANILA * KUALA LUMPUR * MUSCAT
SUPERVISION
CAD/CAM
SOLID-WORKS
C++
PROFESSIONAL E X P E R I E N C E S
• Six years of experience as FACADE SITE ENGINEER in JAFCO ALUMINIUM &
STEEL CO.W.L.L, Qatar.
CORE COMPETENCIES
• Develops project objective by reviewing project proposals and plans, conferring with
management.
• Determine project specifications by studying product design, customer
requirements and performance standards.
• Schedule preparation, pre-planning and resource forecasting for engineering and
other technical activities relating to the project.
• Supervise and manage the caseload of the external architectural services providing
the design element for the adaptation works, ensuring that appropriate permissions are
gained, Planning, Building Control and relevant statutory notices, and timescales are
achieved.
• Assure the accuracy of financial forecasting which should fit into the project
schedules.
• Ensure that the project is completed as per plans.
• Manage project team resources and develop extensive project management
experience and expertise.
• Maintain inter-discipline coordination and overall quality control of the work.
• Manage payment of interim and final invoices, including collecting and checking all
certificates and invoices on completion of works, carrying out final inspections, check
final accounts and defects liability.
• Prepare project status reports by collecting, analyzing and summarizing.Information
and trends.
• Maintain project data base by writing computer programs, entering and backing up
data.
• .Supervise and monitor the work of the contractors throughout its completion,
ensuring risk assessments of COM 2015 regulations are adhered and appropriate
health and safety measures in place.
• Work with the Business Development Manager to identify opportunities to increase
the Technical Service offer to private clients, generating fee income for the
organization.
ACADEMIA
DEGREE COLLEGE/UNIVERSITY YEAR OF PASS %MARKS
COLLEGE P R O J E C T UNDERTAKEN AN D
SEMINAR PRESENTED
Title: Modification and Fabrication of Theo-Jansen Mechanism
Description: Modification and Fabrication of Theo-Jansen
Strandbeest and correcting its limitations thus widening the field of
application in military, transportation and agriculture
Title: Seminar on Crank Based Leg Mechanism.
Description: The paper describes the design and working of a 2-n
legged passive crank-based walking mechanism based on the work
of Theo-Jansen.
PERSONALITY TRAITS
•Quick learning ability
•Optimist
•Adaptability
•Problem solving
HOBBIES
•Origami
•Listening mus1c
•Photography
•Travelling
PERSONAL DETAILS
Name : AROMALS
Father name : SHAJI S
Date of Birth : 18/04/1993
Sex : MALE
Marital Status : SINGLE
Religion : HINDU
Nationality : INDIAN
DECLARATION
I hereby declare that the above mentioned statements are true
and correct to the best of my knowledge and belief.
Signature:
Date:
Place: Qatar
GALFAR FAÇADE SOLUTIONS CORE TEAM
Block / Building Name : WADI AL SAIL OFFICE BUILDING WITH DATA CENTER Material Submittal Ref. No. : WAS-ALB-AEB-AR-MAR-0007
Material submittal for Glazed Aluminum Curtain wall,sliding window
Location of Use : Glazed Curtain Wall Name of Material :
Date Submitted : 02-Oct-2022 Submitted by : Chris.
Item
PROJECT SPECIFICATION EXOVA LABORATORY PERFORMANCE TESTING OF CURTAIN WALL TEST PASS/FAIL CRITERIA RESULT
No.
Air Infiltration
Total permissible
Maximum air leakage through fixed glazing and framing areas airflow is 28.2m3/hour
The avaerage air flow through the sample shall
of 0.3 L/s per sq. m of fixed wall area as determined according Measurement of air flow taken at a positive presure @ +600 Pa
1 not exeed 1.08m3/hour/m2 at a test pressure of
to ASTM E 283 at a minimum static-air-pressure differential of differential of +600 Pa. Area of sample tested
+600 Pa
75 Pa. 26.1m2
PASSED
No evidence of water penetration through fixed glazing and Water was sprayed onto the sample at the rate of at No water penetration allowed.Water penetration
framing areas when tested according to ASTM E 331 at least 3.4 litres/m2. With the water spray continuing, a is defined as the presence of water on any No water penetration.
2
a minimum static-air-pressure differential of 20 percent of pressure defferential equal to +600 Pa was applied normal exposed internal surface other than PASSED
positive wind-load design pressure, but not less than 300 Pa. across the sample and maintained for 15 mins. condensation.
Structural Loads:
Wind Loads: Design to a basic wind speed of not less than 162
4
km/hr (45 meters per second)
Structural-Test Performance:
Provide glazed curtain wall system tested according
Item
PROJECT SPECIFICATION EXOVA LABORATORY PERFORMANCE TESTING OF CURTAIN WALL TEST PASS/FAIL CRITERIA RESULT
No.
Air Infiltration
Total permissible
Maximum air leakage through fixed glazing and framing areas airflow is 28.2m3/hour
The avaerage air flow through the sample shall
of 0.3 L/s per sq. m of fixed wall area as determined according Measurement of air flow taken at a positive presure @ +600 Pa
1 not exeed 1.08m3/hour/m2 at a test pressure of
to ASTM E 283 at a minimum static-air-pressure differential of differential of +600 Pa. Area of sample tested
+600 Pa
75 Pa. 26.1m2
PASSED
No evidence of water penetration through fixed glazing and Water was sprayed onto the sample at the rate of at No water penetration allowed.Water penetration
framing areas when tested according to ASTM E 331 at least 3.4 litres/m2. With the water spray continuing, a is defined as the presence of water on any No water penetration.
2
a minimum static-air-pressure differential of 20 percent of pressure defferential equal to +600 Pa was applied normal exposed internal surface other than PASSED
positive wind-load design pressure, but not less than 300 Pa. across the sample and maintained for 15 mins. condensation.
18/09/2022 18/09/2022
COMMENT DISPOSITION FORM (CDF)
METHOD STATEMENT FOR IFOR INSTALLATION OF GLAZED ALUMINUM
Title: Reviewing Dept.: Arab Engineering Bureau
CURTAIN WALL BY GALFAR
Doc. No.: WAS-ALB-AEB-MST-AR-0009 Rev.: 1 Disposition Dept.: AL BALAGH
Review Date: 31/08/2022 Disposition Date: 31/08/2022
Noted,
Arch: Contact detail of relevant responsible
2. Closed
Provide Contact details of relevant responsible personnel. personnel is included in the section#7 Project
Organization Chart
Arch:
Section 5 Manpower Requirement.
a. Contractor to provide the number of persons required.
Noted,
Rev.01
3. Number of persons required in provided in Open
Section#5 Manpower requirements
Include in the manpower requirement, how many Teams and composition per
Team per panel installation.
Arch:
Provide Section for Plants & Equipment Requirement.
Categorize the tools and Equipment. e.g., Equipment, Power tools, Hand
Tools, General Items, Required PPE.
Noted,
4. Kindly refer Section #6 Plant and equipment Open
Rev.01
have been categorized.
A. Provide specific Mobile crane and Tele Handler boom loader
information.
Any Trolley for moving short distance?
B. Glass suction Cups?
Arch:
Provide detailed method statement per façade schedule system and per
locations to ensure coordination with other work interfacing.
Noted,
Rev.01 Kindly refer Section #8, Detailed method
5. Open
a. Provide method statement for replacement or in case or breakage system per façade schedule system and per
during or after the installation. location is provided.
b. Contractor to provide information for installation particular order of
fixation required or whether and/or whenever the same size of glass
can be installed without sequence?
Arch:
Provide Detailed Quality Control requirements.
Noted,
6. Detailed Quality control plan is provided in Open
Rev.01
Section#9
Provide the Quality Management Plan as mentioned in section 9, Quality
Control.
Arch:
Provide Certification and trainings.
A. Valid Certification Issued by approving Authority for qualified person.
B. Valid Calibration certificate for testing equipment. Please refer Section#14- Attachments,
8. Open
C. Qualification Record of Trained Personnel Performing the task. 5. Certification and trainings.
Rev.01
Valid Calibration certificate for testing equipment not found.
Arch:
Logistic
Provide the Site Logistic Plan document reference that includes Material
Delivery Temporary, Facilities, Storage, Mobile Crane particular optimum
location etc.
9. WAS-ALB-AEB-GEN-DOC-0010 REV 02 Open
Rev.01
WAS-ALB-AEB-GEN-DOC-0010 REV 02 not yet submitted to AEB. Contractor
to submit.
Arch:
Contractor to review the ITP prior to submittal.
Noted,
10. Rev.01 Open
Revised ITP attached.
2.0 Material 2.2 MIR under verifying party CT=H
3.1 Mock up under verifying party CT=H
Testing
Provide preconstruction testing and post construction testing per required.