Was Alb Aeb MST Ar 0009 2 PDF

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 66

- Please refer to the attached CDF

Florian De Joya Engr. Mohammad Ezzat

11/10/2022 11/10/2022
COMMENT DISPOSITION FORM (CDF)
METHOD STATEMENT FOR IFOR INSTALLATION OF GLAZED ALUMINUM
Title: Reviewing Dept.: Arab Engineering Bureau
CURTAIN WALL BY GALFAR
Doc. No.: WAS-ALB-AEB-MST-AR-0009 Rev.: 2 Disposition Dept.: AL BALAGH
Review Date: 03/10/2022 Disposition Date: 02/10/2022

S. No. Comments Dispositions (Contractor) Status/Remarks


Revision 0
Arch:
Section 2 References.
Noted,
Project specification, logistic plan, Structural
a. Include other Project Specification Sections references
1. Calculation, IFC and Approved Shop drawing Closed
b. Logistic Plan
reference have been added to the
c. Structural Calculation
sections#2 Reference
d. (Others)

Noted,
Arch: Contact detail of relevant responsible
2. Closed
Provide Contact details of relevant responsible personnel. personnel is included in the section#7 Project
Organization Chart
Arch:
Section 5 Manpower Requirement. Noted,
a. Contractor to provide the number of persons required. Number of persons required in provided in
Section#5 Manpower requirements
Rev.01
3. Closed
REV.01
Include in the manpower requirement, how many Teams and composition per Noted and complied. Manpower required for
Team per panel installation. Glass and profile installation provided in
section manpower requirement.

Document Reference: WAS-ALB-AEB-MST-AR-0009 Rev. 2 Page 1 of 5


S. No. Comments Dispositions (Contractor) Status/Remarks

Noted,
Arch:
Kindly refer Section #6 Plant and equipment
Provide Section for Plants & Equipment Requirement.
have been categorized.
Categorize the tools and Equipment. e.g., Equipment, Power tools, Hand
Tools, General Items, Required PPE.
REV.01
4. Mobile crane capacity is 25 tons, Tele handler Closed
Rev.01
is 3 tons.
A. Provide specific Mobile crane and Tele Handler boom loader
Hydraulic pallet trolley is required for short
information.
distance material shifting.
Any Trolley for moving short distance?
Kindly refer section 6 Material, Plant and
B. Glass suction Cups?
Equipment requirement
Noted,
Kindly refer Section #8, Detailed method
Arch: system per façade schedule system and per
Provide detailed method statement per façade schedule system and per location is provided.
locations to ensure coordination with other work interfacing.
Rev.01
Rev.01 a. Method statement for replacement or
5. Closed
a. Provide method statement for replacement or in case or breakage in case or breakage during or after
during or after the installation. the installation is provided.
b. Contractor to provide information for installation particular order of b. Same size of glass can be used in
fixation required or whether and/or whenever the same size of glass any place provided the spaces are
can be installed without sequence? same
Kindly refer Section #8,

Arch: Noted,
Provide Detailed Quality Control requirements. Detailed Quality control plan is provided in
6. Closed
Section#9

Document Reference: WAS-ALB-AEB-MST-AR-0009 Rev. 2 Page 2 of 5


S. No. Comments Dispositions (Contractor) Status/Remarks
Rev.01 Rev. 01
Provide the Quality Management Plan as mentioned in section 9, Quality Please refer to Document number WAS-ALB-
Control. AEB-GEN-PQP-0001-Rev 01

Arch: Noted,
Provide detailed delivery storage and handling. Detailed delivery storage and handling is
provided in Section #10
7. Rev.01 Closed
Provide a drawing layout of material storage at site whenever the material is Rev.01
not readily available for direct fixing. Please find the attached drawing layout of
material storage.in Section 13
Arch: Please refer Section#14- Attachments, 5.
Provide Certification and trainings. Certification and trainings.
A. Valid Certification Issued by approving Authority for qualified person.
8. B. Valid Calibration certificate for testing equipment. Rev.01 Closed
C. Qualification Record of Trained Personnel Performing the task. Please find the attached calibration certificate
Rev.01 for Digital coating thickness gauge in
Valid Calibration certificate for testing equipment not found. Section 13
Arch:
Logistic
WAS-ALB-AEB-GEN-DOC-0010 REV 02
Provide the Site Logistic Plan document reference that includes Material
Delivery Temporary, Facilities, Storage, Mobile Crane particular optimum
Rev 01
location etc.
9. Approved Site Logistic plan document Closed
reference number is
Rev.01
WAS-ALB-AEB-GEN-DOC-0010 REV 01
WAS-ALB-AEB-GEN-DOC-0010 REV 02 not yet submitted to AEB. Contractor
to submit.

Arch: Noted,
Contractor to review the ITP prior to submittal. Revised ITP attached.
10. Open

Document Reference: WAS-ALB-AEB-MST-AR-0009 Rev. 2 Page 3 of 5


S. No. Comments Dispositions (Contractor) Status/Remarks
Rev.01 Rev. 01

2.0 Material 2.2 MIR under verifying party CT=H Noted,


3.1 Mock up under verifying party CT=H ITP is revised by complying
2.0 Material 2.2 MIR under verifying party
Rev.02 CT=H
A. 3.1 Mock up under verifying party CT=H

Note: Please find the attached preconstruction


Commented ITP Item No. 2.0 Material 2.2 MIR under verifying party CT=H testing and post construction testing
However, due to the required work required sequence the verifying party CT=H compliance sheet. In Section 13
will be superseded, and works can proceeded according to required work
progress. Materials is expected to be in proper and good condition under
Contractor responsibilities.

Testing
Provide preconstruction testing and post construction testing per required.

B.

Pre-construction Testing
Test requirements as per Project Specification Section 17 Part 8 > 8.1.3.

and

ITP 4.1 The provided information Acceptance Criteria / Standard


Requirements as shown snap shot below,

To be deleted and replaced by Acceptance criteria as per Project


Specification, QCS 2014 requirements and provisions.

Document Reference: WAS-ALB-AEB-MST-AR-0009 Rev. 2 Page 4 of 5


S. No. Comments Dispositions (Contractor) Status/Remarks

Activity Description under > Post Constructions.


Test requirements as per Project Specification Section 17 Part 8 > 8.1.2.
Performance requirements.

ITP 4.1 Verifying Documents


Third Party certification

Florian de Joya – Sr. Architect


Reviewer Name: Signature: Date: 11/10/2022
Rameez Meersha – Structural Engineer

Mohammed Ezzat Ahmed Haggag - PM


Approver Name: Signature: Date: 11/10/2022

Dispositioner Name: Contractor Representative Signature: Date: Select date.

Document Status: Approved Approved as Noted Revise and Resubmit


Rejected For Information Only

Document Reference: WAS-ALB-AEB-MST-AR-0009 Rev. 2 Page 5 of 5


COMMENT DISPOSITION FORM (CDF)
METHOD STATEMENT FOR IFOR INSTALLATION OF GLAZED ALUMINUM
Title: Reviewing Dept.: Arab Engineering Bureau
CURTAIN WALL BY GALFAR
Doc. No.: WAS-ALB-AEB-MST-AR-0009 Rev.: 2 Disposition Dept.: AL BALAGH
Review Date: Select date. Disposition Date: 02/10/2022

S. No. Comments Dispositions (Contractor) Status/Remarks


Revision 0
Arch:
Section 2 References.
Noted,
Project specification, logistic plan, Structural
a. Include other Project Specification Sections references
1. Calculation, IFC and Approved Shop drawing Closed
b. Logistic Plan
reference have been added to the
c. Structural Calculation
sections#2 Reference
d. (Others)

Noted,
Arch: Contact detail of relevant responsible
2. Closed
Provide Contact details of relevant responsible personnel. personnel is included in the section#7 Project
Organization Chart
Arch:
Section 5 Manpower Requirement. Noted,
a. Contractor to provide the number of persons required. Number of persons required in provided in
Section#5 Manpower requirements
Rev.01
3.
REV.01
Include in the manpower requirement, how many Teams and composition per Noted and complied. Manpower required for
Team per panel installation. Glass and profile installation provided in
section manpower requirement.

Document Reference: WAS-ALB-AEB-MST-AR-0009 Rev. 2 Page 1 of 4


S. No. Comments Dispositions (Contractor) Status/Remarks

Noted,
Arch:
Kindly refer Section #6 Plant and equipment
Provide Section for Plants & Equipment Requirement.
have been categorized.
Categorize the tools and Equipment. e.g., Equipment, Power tools, Hand
Tools, General Items, Required PPE.
REV.01
4. Mobile crane capacity is 25 tons, Tele handler
Rev.01
is 3 tons.
A. Provide specific Mobile crane and Tele Handler boom loader
Hydraulic pallet trolley is required for short
information.
distance material shifting.
Any Trolley for moving short distance?
Kindly refer section 6 Material, Plant and
B. Glass suction Cups?
Equipment requirement
Noted,
Kindly refer Section #8, Detailed method
Arch: system per façade schedule system and per
Provide detailed method statement per façade schedule system and per location is provided.
locations to ensure coordination with other work interfacing.
Rev.01
Rev.01 a. Method statement for replacement or
5.
a. Provide method statement for replacement or in case or breakage in case or breakage during or after
during or after the installation. the installation is provided.
b. Contractor to provide information for installation particular order of b. Same size of glass can be used in
fixation required or whether and/or whenever the same size of glass any place provided the spaces are
can be installed without sequence? same
Kindly refer Section #8,

Arch: Noted,
Provide Detailed Quality Control requirements. Detailed Quality control plan is provided in
6.
Section#9

Document Reference: WAS-ALB-AEB-MST-AR-0009 Rev. 2 Page 2 of 4


S. No. Comments Dispositions (Contractor) Status/Remarks
Rev.01 Rev. 01
Provide the Quality Management Plan as mentioned in section 9, Quality Please refer to Document number WAS-ALB-
Control. AEB-GEN-PQP-0001-Rev 01

Arch: Noted,
Provide detailed delivery storage and handling. Detailed delivery storage and handling is
provided in Section #10
7. Rev.01
Provide a drawing layout of material storage at site whenever the material is Rev.01
not readily available for direct fixing. Please find the attached drawing layout of
material storage.in Section 13
Arch: Please refer Section#14- Attachments, 5.
Provide Certification and trainings. Certification and trainings.
A. Valid Certification Issued by approving Authority for qualified person.
8. B. Valid Calibration certificate for testing equipment. Rev.01
C. Qualification Record of Trained Personnel Performing the task. Please find the attached calibration certificate
Rev.01 for Digital coating thickness gauge in
Valid Calibration certificate for testing equipment not found. Section 13
Arch:
Logistic
WAS-ALB-AEB-GEN-DOC-0010 REV 02
Provide the Site Logistic Plan document reference that includes Material
Delivery Temporary, Facilities, Storage, Mobile Crane particular optimum
Rev 01
location etc.
9. Approved Site Logistic plan document
reference number is
Rev.01
WAS-ALB-AEB-GEN-DOC-0010 REV 01
WAS-ALB-AEB-GEN-DOC-0010 REV 02 not yet submitted to AEB. Contractor
to submit.

Arch: Noted,
Contractor to review the ITP prior to submittal. Revised ITP attached.
10.

Document Reference: WAS-ALB-AEB-MST-AR-0009 Rev. 2 Page 3 of 4


S. No. Comments Dispositions (Contractor) Status/Remarks
Rev.01 Rev. 01

2.0 Material 2.2 MIR under verifying party CT=H Noted,


3.1 Mock up under verifying party CT=H ITP is revised by complying
2.0 Material 2.2 MIR under verifying party
CT=H
3.1 Mock up under verifying party CT=H

Please find the attached preconstruction


Testing testing and post construction testing
Provide preconstruction testing and post construction testing per required. compliance sheet. In Section 13

Reviewer Name: Florian de Joya – Sr. Architect Signature: Date: Select date.

Mohammed Ezzat Ahmed Haggag - PM


Approver Name: Signature: Date: Select date.

Dispositioner Name: Contractor Representative Signature: Date: 02/10/2022

Document Status: Approved Approved as Noted Revise and Resubmit


Rejected For Information Only

Document Reference: WAS-ALB-AEB-MST-AR-0009 Rev. 2 Page 4 of 4


Project Logo Project Name: WADI AL SAIL OFFICE BUILDING WITH DATA CENTER (4B+G+2F) 4B+G+7F) at C RING ROAD, DOHA QATAR
Project No.: 1429 Form No.: P07-F06 / Rev. 0 / Nov. 2012
Client Project Manager Consultant Contractor

METHOD STATEMENT FOR INSTALLATION OF GLAZED ALUMINUM CURTAIN WALL


METHOD STATEMENT No: WAS-ALB-AEB-MST-AR-0009 Rev: 2

ORIGINATOR: Al Balagh Trading & Contracting DISCIPLINE: Architectural


Title:

METHOD STATEMENT FOR INSTALLATION OF GLAZED ALUMINUM CURTAIN WALL BY


GALFAR.

REVIEWER / APPROVER
REV DATE STATUS REVISION DETAILS Sub Main
Con Con EXTERNAL

0 11/08/2022 FA For Review and Approval

1 30/08/2022 FA For Review and Approval


2 01/10/2022 FA For Review and Approval

Status Code:
D : Draft FI : For Information FC : For Construction
P : Preliminary FA : For Approval * External Authorization (Client),
where required
Distribution:

Method Statement for Installation of curtain wall and Aluminum windows


Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms
Project Logo Project Name: WADI AL SAIL OFFICE BUILDING WITH DATA CENTER (4B+G+2F) 4B+G+7F) at C RING ROAD, DOHA QATAR
Project No.: 1429 Form No.: P07-F06 / Rev. 0 / Nov. 2012
Client Project Manager Consultant Contractor

Table of Contents
1. SCOPE & OBJECTIVES.....................................................................................................................7

2. REFERENCES .....................................................................................................................................7

3. DEFINITIONS .......................................................................................................................................7

4. RESPONSIBILITIES/ SUPERVISION ..............................................................................................8

5. MANPOWER REQUIREMENT ..........................................................................................................9

6. PLANT & EQUIPMENT REQUIREMENT.........................................................................................9

7. PROCEDURE / METHOD TO BE EMPLOYED: ...........................................................................12

8. QUALITY CONTROL.........................................................................................................................17

9. DELIVERY, STORAGE AND HANDLING......................................................................................17

10. HOUSE KEEPING .........................................................................................................................18

11. LOGISTICS .....................................................................................................................................18

12. HEALTH & SAFETY HAZARDS ..................................................................................................18

13. ATTACHMENTS.............................................................................................................................20

Method Statement for Installation of curtain wall and Aluminum windows


Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms
Project Logo Project Name: WADI AL SAIL OFFICE BUILDING WITH DATA CENTER (4B+G+2F) 4B+G+7F) at C RING ROAD, DOHA QATAR
Project No.: 1429 Form No.: P07-F06 / Rev. 0 / Nov. 2012
Client Project Manager Consultant Contractor

1. SCOPE & OBJECTIVES

The purpose of this Method Statement is to outline the methodology to be implemented for
Installation of Aluminum Curtain wall, Doors, Windows for wadi al sail office building with data
center and any miscellaneous works to ensure that all works are carried out in accordance with
QCS regulations, approved construction drawings and project specification.

2. REFERENCES

This method statement shall read and refer in conjunction with below references.
Project Specifications AEB-1429-20_ACS SPECS_IFT-REV 0 Volume 2, Section 17
Glazed Aluminum Curtain wall, Arch & Structural Specification

QCS 2014 Section 25 Part 4 - Glass and Glazing

Logistic Plan - WAS-ALB-AEB-GEN-DOC-0010 REV 01

Structural Calculation WAS-ALB-AEB-CAL-ST-0016 Rev 1

Material Submittal - WAS-ALB-AEB-AR-MAR-0007-2

WAS-ALB-AEB-GEN-PQP-0001 Rev 1 Project Quality Plan

IFC Drawings & Approved Shop Drawing

WAS-ALB-AEB-AR-MAR-007 - Material submittal for Aluminum & Glazing Scope of


work for the project (Glazed aluminum, Curtain wall, Sliding window and accessories)

3. DEFINITIONS

AEB Arab Engineering Bureau (Consultant/Engineer)


ALB Al Balagh Trading & Contracting (Main Contractor)
Contractor Al-Balagh Trading & Contracting Co W.L.L
Client Wadi Al Sail Holding
BBS Bar Bending Schedule
PBM Permanent Benchmark
PPE Personal Protective Equipment
MS Method Statement
QCP Quality Control Procedures

Method Statement for Installation of curtain wall and Aluminum windows


Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms
Project Logo Project Name: WADI AL SAIL OFFICE BUILDING WITH DATA CENTER (4B+G+2F) 4B+G+7F) at C RING ROAD, DOHA QATAR
Project No.: 1429 Form No.: P07-F06 / Rev. 0 / Nov. 2012
Client Project Manager Consultant Contractor

SD Shop drawing
QA/QC Quality Assurance / Quality Control
ITP Inspection Test Plan
RA Risk Assessment
IFC Issued for Construction

4. RESPONSIBILITIES/ SUPERVISION

POSITION RESPONSIBILITY
Project Ensure the work is progressing as per the approved schedule and
contractual requirements
Manager
Construction Responsible for planning, organizing and carrying out the work in
accordance with project requirements and monitor the progress of
Manager
works.
Project Responsible for carrying out the work in accordance with project
requirements.
Engineer
QA/QC Ensure that the works are carried out as per approved Method
Statement.
Engineer
HSE Manager Responsible for planning, coordinate and resolving the issues and
directives within the organization and develop & reviews
plans/procedures for safe execution of work.
HSE Officer Ensure the works are carried in a safe manner. Provides Safety tool
box tasks and monitors are the work force for working safely. ensures
that construction workers are following established policies
and safety regulations
Supervisor/ Responsible for carrying out the works as per instructions of the
Project Engineer/ Construction Manager and provide proper
Foreman
documentation to his workers so they can proceed with tasks. Examine
the work location for any unsafe or unhealthful workplace conditions
or hazards prior to permit the workers to start task and ensure
adequate control measures are in place.
Workers Carryout the work as advised by the Foreman/ Charge hands and follow all
lawful employer safety and health rules and regulations, and wear or use
required protective equipment while working. Report hazardous conditions to
the employer.

Method Statement for Installation of curtain wall and Aluminum windows


Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms
Project Logo Project Name: WADI AL SAIL OFFICE BUILDING WITH DATA CENTER (4B+G+2F) 4B+G+7F) at C RING ROAD, DOHA QATAR
Project No.: 1429 Form No.: P07-F06 / Rev. 0 / Nov. 2012
Client Project Manager Consultant Contractor

5. MANPOWER REQUIREMENT

Sl. No Manpower Number

1 Project Manager 1

3 Project Engineer 1

5 Surveyor 1

6 Safety Officer 1

7 QA/QC Inspector 1

8 Supervisor 1

9 Charge hand 2

10 Technicians/installers 15

11 Skilled helpers 25

MANPOWER ALLOCATION.

GLASS INSTALLATION 2
Three team for installation will be constituted for glass installation.
Each Team will comprise of 2 installers and 4 skilled helper.
ALUMINUM PROFILE FIXING
Four teams will be constituted for the aluminum profile fixing.
Each Team will comprise of 2 installers and 4 skilled 4 helper
One Installer and skilled helper will be in charge of checking final alignment.

6. MATERIAL, PLANT & EQUIPMENT REQUIREMENT


2

Sl. No Machinery CAPACITY Quantity


A EQUIPMENT
1 Mobile Crane 25 TONS 1
2 Tower Crane 1
3 Tele handler boom loader 3 TONS 1
Method Statement for Installation of curtain wall and Aluminum windows
Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms
Project Logo Project Name: WADI AL SAIL OFFICE BUILDING WITH DATA CENTER (4B+G+2F) 4B+G+7F) at C RING ROAD, DOHA QATAR
Project No.: 1429 Form No.: P07-F06 / Rev. 0 / Nov. 2012
Client Project Manager Consultant Contractor

1
4 Total station

5 Hydraulic Pallet Trolley 1


6 Glass suction Cups 4
B HAND TOOLS
1 Aluminum Straight edge 5
As per
2 Crew drivers
requirement
3 Wooden & Rubber Mallet/ hammer 5
C POWER TOOL
1 Portable drilling machine 1
As per
2 Concrete Drilling machine
requirement
D MATERIALS
As per
1 SMARTIA M7 Aluminum Profile
requirement
As per
2 SMARTIA M9660
requirement
As per
3 Glass
requirement

Method Statement for Installation of curtain wall and Aluminum windows


Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms
Project Logo Project Name: WADI AL SAIL OFFICE BUILDING WITH DATA CENTER (4B+G+2F) 4B+G+7F) at C RING ROAD, DOHA QATAR
Project No.: 1429 Form No.: P07-F06 / Rev. 0 / Nov. 2012
Client Project Manager Consultant Contractor

7. PROJECT ORGANIZATION CHART & CONTACT NUMBERS

Project Manager

Mansoor Ali -70200129


QAQC Inspector HSE Officer
Devananth Thopanam 30482969 Subhramanayan 30482600

Project Engineer

Aromal Shaji 70200227

Supervisor

Bishwa Shamar 31296397

Charge hand

Technicians Skilled helpers

Method Statement for Installation of curtain wall and Aluminum windows


Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms
Project Logo Project Name: WADI AL SAIL OFFICE BUILDING WITH DATA CENTER (4B+G+2F) 4B+G+7F) at C RING ROAD, DOHA QATAR
Project No.: 1429 Form No.: P07-F06 / Rev. 0 / Nov. 2012
Client Project Manager Consultant Contractor

8. PROCEDURE

8.1 CURTAINWALL
General Requirements
 All works shall be carried out as per approved drawings, method statements, material
approval and in accordance with Project specification and QCS 2014
 Permit will be will be obtained before the commencement of work,
Mock up
 Prior to installation of curtain wall and aluminum window, mockup will be prepared and
approved by the consultant
 Site Installation.

 The area shall be finished properly by the main contractor based on the approved finishes
schedule before installation of curtain wall begins
 All fabricated units shall be kept at the respective work location.
 Work shall be coordinated with other disciplines to ensure all interface with other
contractors are well condinated.
 Separators are used in between anchorages & adjacent materials to prevent corrosion.
Dielectric material is used as insulator.
 Site survey and marking/lay-out will be done for first fix/anchoring.
 The wall bracket and shoe bracket will be fixed at the required areas and fastened with
anchor bolt as per the shop drawing.

Method Statement for Installation of curtain wall and Aluminum windows


Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms
Project Logo Project Name: WADI AL SAIL OFFICE BUILDING WITH DATA CENTER (4B+G+2F) 4B+G+7F) at C RING ROAD, DOHA QATAR
Project No.: 1429 Form No.: P07-F06 / Rev. 0 / Nov. 2012
Client Project Manager Consultant Contractor

 Mullions with brackets are fixed as per the approved shop drawings.
 Erection Tolerances: Erection Tolerances of 10 – 20mm will be provided between the
structure and frames, which will be covered with sealant.
 Transoms are fixed to the connection brackets of mullion and secures with screw

 Glazing support bracket, insulator and inner gaskets are installed as per manufacturer’s
recommendation.
 Install glass using crane and held temporarily with small pieces of pressure plate.
 The temporary pressure plate is to allow all glass to be installed and aligned properly.

Method Statement for Installation of curtain wall and Aluminum windows


Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms
Project Logo Project Name: WADI AL SAIL OFFICE BUILDING WITH DATA CENTER (4B+G+2F) 4B+G+7F) at C RING ROAD, DOHA QATAR
Project No.: 1429 Form No.: P07-F06 / Rev. 0 / Nov. 2012
Client Project Manager Consultant Contractor

 The glass will be held and controlled using suction pads. At the ground floor, glass will be
installed manually.
 Install the rest of the glass and ensure all are in alignment.
 Fix the pressure plate and cover with cap.
 Installations are carried out in conformity with installation and approved shop drawings as
per system supplier’s recommendation

8.2 INSTALLATION OF ALUMINIUM DOOR, WINDOWS

Installation of Frames / Profiles.

 Ensure all opening are as per the approved shop drawings.


 Cleaning of the dust on masonry opening of windows, Doors and Partitions with the brush
or cloth.
 Opening shall be ensured prior to installation to match Aluminum Schedule.
 Verify site dimensions prior to start fabrication.
 Frames shall be aligned plumb and square in the openings by use of plumb, spirit level and
PVC shims.
 All units shall be installed from inside according to relevant approved drawings.
 The frame shall be installed first, by using fixing screws according to the drawings. Screw
type, material and length shall be determined by the structural calculation
 Even margin between frame and wall finishing to be maintained according to approved
drawing.
 Frames shall be rigidly anchored by used of screw and nylon fisher plug.
 Once the frame is check for correct alignment, plumb, and square, all fixing screws will be
tightened properly.
 All fasteners and anchors shall be concealed unless otherwise directed by consultant & client.
 Any construction mark to the finished frames shall be rectified as per the Engineer's approval.
 All work execution will be conducted in accordance to safe system of work, quality and
environment.
Glazing Method

Glazing is done in the following manner:

 Insert the glass setting block, ensuring that it is placed correctly locations.
 Clean the glass unit thoroughly.
 Fix the outer gasket and weather strip (vertical and horizontal) using siliconized woven
polypropylene, wool pile or neoprene as per project specifications.
 Corners of gasket at joints will be sealed with sealant as approved.
 Insert the glass unit into the aperture and set properly onto the setting blocks.
 Fix the glazing beads at the top and bottom of the shutter.
 Fix the side glazing beads (in both the cases ensure that the bead retention clips are
located in the place).
 Insert the internal wedge gasket.
Method Statement for Installation of curtain wall and Aluminum windows
Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms
Project Logo Project Name: WADI AL SAIL OFFICE BUILDING WITH DATA CENTER (4B+G+2F) 4B+G+7F) at C RING ROAD, DOHA QATAR
Project No.: 1429 Form No.: P07-F06 / Rev. 0 / Nov. 2012
Client Project Manager Consultant Contractor

 Clean off all mark on glass and ensure it is clean


 Application of silicone sealant around the window perimeter according to approved
color and location.

Application of Sealant

Application of silicone sealant at the joint between Aluminum frames and wall (external

and internal):
 Clear joints and surfaces free from grease, dust or other contaminates by using brush
and cloth.
 Application of approved silicone sealant will be done with the help of gun.
 Ensure the surface is smooth.
 Masking tape will be used where necessary to prevent contamination of adjacent
surfaces.
 Tape will be removed immediately after completion of the joint.
Broken Glass Replacement.

Work Methodology 2

 Prior to starting glass replacement activities, necessary permissions from


building management to be obtained to access to the curtain wall area.
 Coordinate with the Building management/ Main Contractor for the access and
work area clearance.
 Ensure that all requirements (equipment, material, tools, fasteners and documents like
permit to work) are ready before commencing the work.
 All operatives and visitors to site shall wear the mandatory PPE’s hard-hats,
Safety goggles, Safety footwear and High Visibility Vests and all other task
dependent mandatory PPEs.
 Work access and egress shall be free from unwanted materials.
Coordinate with MEP key personal the all works above ceiling is completed and
approved.
General Sequence of De-glazing
 Small pieces of glass shall be removed by applying masking tape/safety film on the
broken glass and then removed carefully.
 Remove the relevant mullion capping from the sides of the unit by twisting/rotating the
cap to disengage from the pressure plate

Method Statement for Installation of curtain wall and Aluminum windows


Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms
Project Logo Project Name: WADI AL SAIL OFFICE BUILDING WITH DATA CENTER (4B+G+2F) 4B+G+7F) at C RING ROAD, DOHA QATAR
Project No.: 1429 Form No.: P07-F06 / Rev. 0 / Nov. 2012
Client Project Manager Consultant Contractor

 Retain glass in position and remove pressure plate screws and plates.

 Large pieces of broken glass shall be removed carefully using manual glass
catchers/Hand Vacuum Lifters.

Method Statement for Installation of curtain wall and Aluminum windows


Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms
Project Logo Project Name: WADI AL SAIL OFFICE BUILDING WITH DATA CENTER (4B+G+2F) 4B+G+7F) at C RING ROAD, DOHA QATAR
Project No.: 1429 Form No.: P07-F06 / Rev. 0 / Nov. 2012
Client Project Manager Consultant Contractor

General Sequence for Fixing the New Replacement Glass


 The adjacent glass edges shall be properly cleaned prior to installing the glass 2
 The new replacement glass is safely stacked at ground level.
 Considering the location of the glass, the glass to be lifted to installation location by
manually or with the help of a hoist.
 Once the glass reached the target place, the operatives will place the glass in its
appropriate position with the help of manual glass catchers/Hand Vacuum Lifters.
 The glass shall be secured using toggles and pressure plates
 The vertical cover cap will be installed

9. QUALITY CONTROL

All the Inspection Request (IRS) shall be raised as per approved Inspection & Test Plan (ITP) for
the activity.

Material will be inspected on site before being used.

 A quality management plan shall be developed for the project.


 The plan will define the requirements and processes for quality management on the
project and will be the principal mechanism for ensuring compliance and consistency of
completed work on the project.
 The quality management plan is a controlled document and will be reviewed on a regular
basis and updated as required.
 All construction work will be controlled through a site based quality control plan.
 The key elements of the plan will be
Conformance to the scope of work.
Compliance with specifications.
Inspection and testing.
 The Quality control plan will be developed by The QA/QC in charge in collaboration with
the Project
 Manager. The plan is a controlled document and will be reviewed as required.

10. DELIVERY, STORAGE AND HANDLING

 Incoming Material Inspection (MIR) shall be initiated for the material supplied for
permanent works in the project and approval obtained from the Consultant based on
approved Material Approval Request (MAR).
 Material shall be stored at a safe place.
 Material shall place on an elevated platform (placed on top of wood logs).

Method Statement for Installation of curtain wall and Aluminum windows


Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms
Project Logo Project Name: WADI AL SAIL OFFICE BUILDING WITH DATA CENTER (4B+G+2F) 4B+G+7F) at C RING ROAD, DOHA QATAR
Project No.: 1429 Form No.: P07-F06 / Rev. 0 / Nov. 2012
Client Project Manager Consultant Contractor

 Material shall not have direct contact with the soil and shall be properly covered with
plastic.

11. HOUSE KEEPING

 Housekeeping will be conducted daily, and debris will be removed.


 Workers will be instructed to clean up and keep their places of work clean and tidy
after completion of their day to day works.

12. LOGISTICS

A Site logistics plan indicating the temporary facilities and traffic management shall be
submitted and approval obtained.

All material deliveries for the works must be made through the authorized entry to the site.

Vehicular movements shall be managed by trained traffic management operatives.

Necessary permits shall be in place prior to start of works.

13. HEALTH & SAFETY HAZARDS

Appropriate & correct Personnel Protective Equipment (PPE) shall be provided and
always worn. The basic PPE requirement includes Helmets, safety shoes, safety glass
and reflective jackets.

 Safety induction training shall be provided to all staff, work force, operators prior to
entry to site premises. An induction sticker shall be provided to all attendees
identifying the satisfactory completion of training.
 Toolbox talks shall be carried-out prior to commencing the task to clearly emphasize
the hazards and environmental aspects that might be encountered, and the
mitigating control measures to be undertaken. A prestart meeting shall be
conducted every day prior to start of the activity.
 The Method Statement and risk assessment shall be clearly communicated to the
work personnel prior to start of work. PTW and its recommendations if any will also
be conveyed to the work force.

Method Statement for Installation of curtain wall and Aluminum windows


Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms
Project Logo Project Name: WADI AL SAIL OFFICE BUILDING WITH DATA CENTER (4B+G+2F) 4B+G+7F) at C RING ROAD, DOHA QATAR
Project No.: 1429 Form No.: P07-F06 / Rev. 0 / Nov. 2012
Client Project Manager Consultant Contractor

 To ensure planned activities, and planned start date are coordinated to the
Consultant/Engineer prior to any site mobilization and commencement of the work.
 Regular coordination with the Client construction and HSE team members should
be maintained.
 Appropriate signage shall be provided within the site premises. Proper access and
egress to working sites shall be established.
 Work/Access areas shall be free from debris and materials to avoid tripping hazard.
 Scaffolding platform shall be erected as required to execute the works in safest
possible manner. Scaffolding shall be carried out by qualified/certified scaffolders
under the supervision of certified scaffold supervisor. During erection of scaffolding,
the area is barricaded with provision of safety signs to prevent unauthorized
personnel entry.
 In General, all working areas shall be adequately barricaded to prevent
unauthorized personnel/public entry.
 Appropriate permits as required shall be raised and maintained. Lifting Permits
Template is attached for reference.
 Lifting permits along with the valid documents of the lifting crew shall be maintained
at the site during the lifting operations.
 During Lifting Operations care shall be taken that adjoining structures / properties
are not damaged.
 Regular housekeeping shall be always maintained.
 A thorough inspection of tubular steel centering must be carried out before its
installation, and members showing evidence of excessive resting, dents, kinks, or
damaged welds shall be removed.
 The effect of weather conditions shall also be taken into consideration.
 During the pouring of the concrete, the centering shall be continuously inspected
and strengthened.

 Emergency Procedure: - On hearing emergency alarm, all people shall vacate


workplace. Before leaving each person shall ensure that the area is as safe as
possible. All the people shall assemble at the assembly point and head count is
Method Statement for Installation of curtain wall and Aluminum windows
Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms
Project Logo Project Name: WADI AL SAIL OFFICE BUILDING WITH DATA CENTER (4B+G+2F) 4B+G+7F) at C RING ROAD, DOHA QATAR
Project No.: 1429 Form No.: P07-F06 / Rev. 0 / Nov. 2012
Client Project Manager Consultant Contractor

taken to ensure every person is accounted for. No one will be permitted to return to
work site until communication has been received from consultant HSE team / HSE
Manager/ Project Manager.

 Health and safety risk assessments shall be as per attached JHA.


 Personal Protective Equipment (PPE) Requirement
 Hard hat & Coverall
 Safety Shoes
 Safety Eye glasses
 Hand gloves
 High visibility vest
 Red, green flags.

14. ATTACHMENTS

1. Risk Assessment
2. Inspection and Test Plan
3. Quality Control Check List
4. Drawings
5. Certification and Training
6. PRECONSTRUCTION TESTING AND POST CONSTRUCTION TESTING COMPLIANCE SHEET.

Method Statement for Installation of curtain wall and Aluminum windows


Form No. P07-F06 / Rev. 0 / Nov. 2012
AEB-CSD Quality Forms
Date: 19.03.2022 PROJECT: Wadi Al Sail office Building with Data Center DOC. Ref: No. -WAS-ALB-AEB-MST-AR-0009

Rev. 2 RISK ASSESSMENT FOR INSTALLATION OF GLAZED ALUMINUM Page 1 of 14


CURTAIN WALL

Risk Rating Responsible Final Residual Risk Rating


Activities Potential Hazard/Impact Hazards Control
L S R Category Person L S R Category
 Sufficient skills (competency) to complete the
required task. Adequate consultation with relevant
employees. Adequate competent supervision.
Planning for required equipment carried out.
Improvisation using in appropriate equipment.
 Sufficient lighting provided to the work face,
 Task specific injuries due especially in basement and other enclosed areas.
to inexperience, Access ways suitably defined or lighted.
inadequate consultation,  Safe work methods for use, storage and disposal
or failure to provide followed. Hazardous substances & dangerous
appropriate equipment. goods stored and labelled correctly. Provide
 Slips, trips and falls; mechanical or other types of ventilation of
walking into objects or extraction where necessary.
projections.  Penetration/s covered and cover secured Site Engineer
 Illness; breathing  Use low height access steps or other means (Step Foreman
1.General Planning 3 3 9 Medium 1 3 3 Low
difficulties – overcome by ladders). Supervisor
fumes.  Construction of proper working platforms. Planks HSE Officer
 Fall through penetration. lapped correctly and of correct length. Remove
 Partial or complete damaged planks which can give way when loaded.
collapse causing a fall  Follow the project traffic management system and
onto the lower level. speed limit must be observed.
 Fall from wheelbarrow or  Parking for contractors’ vehicles and plant is
unstable stacks of bricks. limited at project site.
 Personal injury / fatality  Materials must be placed in designated areas.
 Barricade with appropriate safety
 Check the weather forecast in advance while
planning the operation.
 Appropriate signage and illumination / lighting
where necessary to highlight and warn of hazard
has to be provided.
Date: 19.03.2022 PROJECT: Wadi Al Sail office Building with Data Center DOC. Ref: No. -WAS-ALB-AEB-MST-AR-0009

Rev. 2 RISK ASSESSMENT FOR INSTALLATION OF GLAZED ALUMINUM Page 2 of 14


CURTAIN WALL

 All site employees including visitors need to attend


safety induction before entering to the project
 Always follow the site safety signage within site
premises
 Everyone on site should wear high visibility vest
 Personal injury / fatality with respect to their trade along with appropriate
 Collision with plant PPE all the time.
equipment and  Follow site safety rules and regulations
machinery leading to  Follow the project traffic management system and Site Engineer
major injuries, fatalities speed limit must be observed. Foreman
2.Access & Egress 3 4 12 Medium 1 4 4 Low
and or property damage  Parking for contractors’ vehicles and plant is Supervisor
 Lack of site awareness limited at project site. HSE Officer
 Slips, trips and falls  Materials must be placed in designated areas.
 Uneven floor areas  Barricade with appropriate safety
 Slippery surfaces  Check the weather forecast in advance while
planning the operation.
 Appropriate signage and illumination / lighting
where necessary to highlight and warn of hazard
has to be provided.

 Watch steps at uneven walkways.


 Pinch points
 Do not take short cut. Use designated
 Slips, trips, and falls.
walkways/access.
 Muscle sprains and
 Correct lifting technique to be follow.
strains.
 Maximum load per person is 25 Kg
 Back injuries, including
 Do not lift any materials without knowing its weight Site Engineer
injuries to muscles and
or too heavy. Foreman
3.Manual handling ligaments. 5 2 10 Medium 2 2 4 Low
 Use trolley for carrying long distance materials. Supervisor
 Soft tissue injuries to
 Designated area to be used on firm and level HSE Officer
nerves, ligaments and
ground. Materials not to be stacked too high.
tendons in the wrists,
 Use mechanical lift if possible
arms, shoulders, neck or
 Safe system of work to be implemented.
legs.
Supervisor to assess the load, where applicable

and avoid manual lifts.
Date: 19.03.2022 PROJECT: Wadi Al Sail office Building with Data Center DOC. Ref: No. -WAS-ALB-AEB-MST-AR-0009

Rev. 2 RISK ASSESSMENT FOR INSTALLATION OF GLAZED ALUMINUM Page 3 of 14


CURTAIN WALL

 Trained, Competent and Authorized operatives


can use power tools
 Qualified, Competent and Authorized electricians
to test all portable electrical equipment at
recommended regular intervals
 Employee conducts daily inspections of power
tools (including electrical cords) before operation
and where faults are identified that require
immediate maintenance the tool is put out of
service until maintenance is conducted by a
Trained, Competent and Authorised person
 Eye injuries from dust
 Ensure that the power tool has the correct guard,
or other fragments
shield, or other attachment that the manufacturer
 Wrist and hand injuries
recommends. Ensure all electrical distribution
due to tool jamming or
boards are fitted with ELCB and this is regularly
binding Site Engineer
tested to evaluate if it is working safely or not with
 Hand/Arm Vibration Foreman
4. Use of Power Tools 4 4 16 Medium immediate rectification of all faults. 1 4 4 Low
Syndrome (HAVS) Supervisor
 STARRT and/or RAMS discussed to all persons
 Electric HSE Officer
involved in the task prior to works commencing
shock/Electrocution
 Select power tools with lowest vibration level. A
 Fire/explosion
tool producing high levels of vibration to have
 Health hazard
anti-vibration handles to reduce the risks
 Noise
 Noise Assessment required where deemed
necessary
 Switch off the tools before connecting them to a
power supply.
 If a power cord feels more than comfortably warm
or if a tool is sparking, have it checked by an
electrician or other qualified person.
 Disconnect the power supply before adjusting or
changing accessories.
 Remove any wrenches and adjusting tools before
turning on a tool.
Date: 19.03.2022 PROJECT: Wadi Al Sail office Building with Data Center DOC. Ref: No. -WAS-ALB-AEB-MST-AR-0009

Rev. 2 RISK ASSESSMENT FOR INSTALLATION OF GLAZED ALUMINUM Page 4 of 14


CURTAIN WALL

 Use only approved extension cords that have the


proper wire size (gauge) for the length of cord and
power requirements of the electric tool that you
are using. This will prevent the cord from
overheating.
 Suspend power cords over aisles or work areas
to eliminate stumbling or tripping hazards.
 Follow good housekeeping procedures - keep the
work area free of clutter and debris that could be
tripping or slipping hazards.
 Store tools in a dry, secure location when they are
not being used.
 Do not leave a running tool unattended. Do not
leave it until it has been turned off, has stopped
running completely, and has been unplugged.
 Do not expose electric power tools to rain or wet
conditions; wet tools increase the likelihood of
electric shock.
 Stop using an electric power tool if you feel a
tingle in your fingers. This is a warning that the
tool is faulty and needs repair.
 Prevent shocks. Ensure that the tools are
properly grounded using an industrial type three-
prong plug, are double-insulated (and are
labelled as such), or are powered by a low-
voltage isolation transformer: this will protect
users from an electrical shock.
 Ensure the power tool has a current
tag otherwise immediately return to store
 Do not surprise or touch anyone who is operating
a tool. Startling a tool operator could end up
causing an accident or injury.
 Improper/Defective  Use proper hand tools Site Engineer
5. Use of Hand Tools 3 3 9 Medium 1 3 3 Low
Damaged Hand Tools  Check the tool before commence to the work Foreman
Date: 19.03.2022 PROJECT: Wadi Al Sail office Building with Data Center DOC. Ref: No. -WAS-ALB-AEB-MST-AR-0009

Rev. 2 RISK ASSESSMENT FOR INSTALLATION OF GLAZED ALUMINUM Page 5 of 14


CURTAIN WALL

 Personnel injury (Pinch  Do not alter or modify any tools Supervisor


points, Trap hand,  Do not use damaged / worn out hand tools. HSE Officer
fingers, feet. Sharp /  Do not use tools not made for the purposes.
Protruding objects)  Use Hand Gloves / Safety Goggles/ helmet/ Use
 Sharp Edges / corners all required PPE’s
 Do not allow unauthorized persons nearby.
 Check for sharp corners, edges etc.
 Deploy experienced persons on the job.

 Deploy only trained people for erecting all


scaffolds.
 Ensure proper supervision
 Use safety harness with double lanyard effectively.
 Do not stand on ledgers – use suitable number of
planks as temporary platform.
 Tie all planks properly
 Ensure proper ladder access in the scaffolding
during erection and after completion
 Regular tool box meeting with all scaffolders.
 Ensure any scaffolds that are more than 9 Meter
 Fall from height Site Engineer
6. Working on in height above the base must be designed by a
 Falling of objects Foreman
scaffolding 3 3 9 Medium competent structural engineer. 1 3 3 Low
 Collapse of the scaffold Supervisor
 Ensure scaffolding inspector carry out weekly
HSE Officer
inspection and revalidation must be applied prior
to usage.
 Lower and raise the materials carefully – throwing
of material is not allowed.
 Provide toe boards all around.
 Remove the loose materials from the platforms.
 Close all openings in the platform
 Ensure Scaffolders must secure the spanner with
Fall arrester connector to avoid drop Object.
 Erect the scaffolding as per the drawing or
standard practice.
Date: 19.03.2022 PROJECT: Wadi Al Sail office Building with Data Center DOC. Ref: No. -WAS-ALB-AEB-MST-AR-0009

Rev. 2 RISK ASSESSMENT FOR INSTALLATION OF GLAZED ALUMINUM Page 6 of 14


CURTAIN WALL

 Deploy only trained persons.


 Ensure proper supervision throughout.
 Ground conditions must be verified, if the
scaffolding is going to be erected on sand.
 Provide the ties and supports, if required, during
the process of erection
 Inspect the scaffolding by the foreman during and
after the erection and ensure the stability.
 Use only standard and good materials – never mix
the components of different suppliers.
 Place scaff-tag after inspection.
 Do not remove any structural member from
inspected scaffolding by anybody for any reasons.
 11) All alterations required shall be done by
scaffolders only with the approval from the
foreman.
 Competent scaffolding inspector shall be assigned
to inspect scaffolds and tag the scaffold safe to
use by putting green scaffold tag.
 Incomplete scaffolding working platform shall be
tagged with red (not safe to use) until it is modified
or completely d
 Ensure the scaffolding Inspector to verify design
and load scaffolds in accordance with that design
prior to use.
 Failure / collapse of  Obtain the valid work permit & approved lifting plan
equipment/crane and prior to start of the job
tackles due to overload  Conduct Tool Box Talk and explain the hazards
Site Engineer
7. Lifting, Shifting and  Fall / Slip of Lifted and precautions needed to the workforce
Foreman
installation of Material due to improper 4 4 16 High  Use Right Equipment / Crane for the job. Do not 1 4 4 Low
Supervisor
curtainwall rigging and slinging use equipment’s not made for the purpose
HSE Officer
 Overturning of crane  All the rigging equipment’s should be inspected by
due to poor ground TPI and approved and colour coded as per Lifting
condition and over load procedures
Date: 19.03.2022 PROJECT: Wadi Al Sail office Building with Data Center DOC. Ref: No. -WAS-ALB-AEB-MST-AR-0009

Rev. 2 RISK ASSESSMENT FOR INSTALLATION OF GLAZED ALUMINUM Page 7 of 14


CURTAIN WALL

 Toppling due to high  Equipment shall be inspected prior to use.


Wind and poor visibility  Valid inspection certificate for all rigging/lifting
 Failure due to Improper equipment’s. Also marked with SWL (Safe
communication between Working Load)
operator and riggers  Barricade the area and place warning boards
 Damage to Nearby  All TPI certificates attested and personals
Services and live utilities including Riggers and Lifting Tools, tackles as per
 Pinch points, Trap hand, lifting plan shall be used.
fingers, feet. Sharp /  Crane should be placed on level and stable ground
Protruding objects  Proper Maintenance and Checklist
 Unauthorized entry due  Crane should not be placed at near the excavation
to lack of barricading trench
 Lack of Information,  Extend outriggers fully and rest on steel or wooden
instruction and training mats
and supervision  Use only approved Crane Operator
 Noise  Crane boom angle should not exceed safe angle
 Fire  Do not carry out lifting activity during high wind
conditions
 Prohibit anyone walking under suspended loads
 Confirm balance of load prior to lifting off ground
 Do not attempt to lift / shift a load greater than SWL
 Only approved anchor points to be used.
 Competent and approved riggers to rig-up
equipment.
 Secure / remove all loose parts / tools - machine
parts, valve, removed joints, tools, other objects
etc.
 The safety clip on the hook must be correctly
closed
 Use tag lines to control the lifting load
 Correct slinging techniques
 Ground must be inspected prior to the setting and
it shall be firm and stable.
Date: 19.03.2022 PROJECT: Wadi Al Sail office Building with Data Center DOC. Ref: No. -WAS-ALB-AEB-MST-AR-0009

Rev. 2 RISK ASSESSMENT FOR INSTALLATION OF GLAZED ALUMINUM Page 8 of 14


CURTAIN WALL

 The stability and load bearing capacity of the


ground must be sufficient to carry the most severe
static and dynamic loads.
 Automatic safe load indicator, load radius indicator
and motion limit switches together with audio-
video warning systems should be in working order
 All the out rigs must be extended fully and equally
on both sides.
 Weight of the load must be known and check with
crane load chart for safe lifting
 Ensure good signalling from rigger to the operator.
 Use standard hand signals, if required.
 Ensure good communication
 Rigger should be worn safety vest for the
identification
 Be cautious about the trap points.
 Proper PPE (Use rigger leather gloves for rigging
operations)
 Avoid unnecessary persons and materials at site.
 Close supervision of rigging activity by competent
rigger.
 Maintain good housekeeping
 Provide First aid Box at the site

 Material to be stacked in a separate area in an


appropriate manner at same height
 Fire extinguishers has to be provided at the
Site Engineer
 Collapse cement bags storage area
Foreman
8. Housekeeping  Slips & trips 5 2 10 Medium  Access & walkway should be clear 1 2 2 Low
Supervisor
 Personal Injury  Housekeeping should be done at end of work
HSE Officer
everyday
 Regular disposal of waste has to be maintained in
proper designated skips
Date: 19.03.2022 PROJECT: Wadi Al Sail office Building with Data Center DOC. Ref: No. -WAS-ALB-AEB-MST-AR-0009

Rev. 2 RISK ASSESSMENT FOR INSTALLATION OF GLAZED ALUMINUM Page 9 of 14


CURTAIN WALL

 Thermal scanning should be done for all the


employees coming to site at the entrance by a
competent person (Site nurse/ security) with
adequate PPEs.
 Internal training provided to all workforce
regarding “COVID 19 – Preventive measures”
 Awareness posters should be provided on site
regarding “COVID 19 Preventive measures”
 Spread of COVID 19  Social distancing needs to be practiced on site.
virus.  Provision of adequate PPE (mask and hand glove)
 Ill health. to work force.
 Security should check the availability of PPEs
9. COVID 19 –
 Poor health conditions 4 3 12 Medium (mask and gloves) with workforce from the
Preventive measures.
entrance itself.
 Increased absenteeism  Security patrolling on site to implement social
of workforce. distancing on site.
 Floor by Floor TBT conducted by HSEOs
regarding “COVID 19” by maintaining proper social
distancing.
 Medical screening shall be conducted on site -
daily basis.
 Isolation room needs to be provided on site.
 Identified person with symptoms need to be
isolated immediately.

 Adequate provision for rest shelter and cool water


 Heat Stress in work area.
 Dehydration  Provision of personal water carrier for all workers.
Site Engineer
 Heat Stroke  Humidex to be monitored at the work activity and
Foreman
10.Work Environment  Heat exhaustion 4 2 8 Medium communicated to workers about the work to rest 1 2 2 Low
Supervisor
 Heat Cramps ratio rules.
HSE Officer
 Personal Injury /fatality  Provide Job rotation where necessary
 Illness & health issues  Compliance with Qatar summer work regulations.
 Provision of air-conditioned rest and eating area.
Date: 19.03.2022 PROJECT: Wadi Al Sail office Building with Data Center DOC. Ref: No. -WAS-ALB-AEB-MST-AR-0009

Rev. 2 RISK ASSESSMENT FOR INSTALLATION OF GLAZED ALUMINUM Page 10 of 14


CURTAIN WALL

 Trained first aider on site with adequate first aid


kits

 Educate the work force about the emergency


procedure
 In case of emergency all work will be stopped and
all plant and machineries must be shut down
Site Engineer
 Poor Communication  All to report at the nearest muster point.
11. Emergency Foreman
 Improper access Egress 3 3 9 Medium  All workers shall be aware of muster points and 1 3 3 Low
Procedure/ Response Supervisor
 Personal Injury /fatality emergency procedures.
HSE Officer
 Project emergency procedure to be followed
 Emergency Contact number displayed at site.
 All muster point and emergency access will be
highlighted with sufficient signage.

 Provide enough lightings to roads, pedestrians


and working areas.
 Insufficient lightings
 Traffic route and pedestrians must be separated
and visible road
with hard barricades. Safe crossing points should
signs.
be established and clearly define. Site Engineer
 Incomplete PPE such as
 Deploy banks man at highly trafficable location at Foreman
12.Night works highly visible safety vest 3 4 12 Medium 1 4 4 Low
site. Supervisor
 Physical Injury
 Barricades must equip with flasher/warning lights HSE Officer
associated with
particularly to vehicular roads/routes.
vehicular accident and
 Ensure no obstructions on operators view
poor lighting
 Implement speed limit for vehicles.
 Wear complete PPE such as high visibility vest.

Severity of Risk
Severity Description Rating
Date: 19.03.2022 PROJECT: Wadi Al Sail office Building with Data Center DOC. Ref: No. -WAS-ALB-AEB-MST-AR-0009

Rev. 2 RISK ASSESSMENT FOR INSTALLATION OF GLAZED ALUMINUM Page 11 of 14


CURTAIN WALL

Minor injury First-aid on site 1


Minor injury Treatment off site 2
Up-to-3 days injury 3
Major injury Reportable 4
Death 5

Al Balagh shall utilize a matrix of severity and likelihood to assist in the evaluation process

S = Severity; L = Likelihood; Rating = S x L

Risk Assessment Matrix 1 2 3 4 5


2 4 6 8 10
3 6 9 12 15
Likelihood of Harm 4 8 12 16 20
5 10 15 20 25
Date: 19.03.2022 PROJECT: Wadi Al Sail office Building with Data Center DOC. Ref: No. -WAS-ALB-AEB-MST-AR-0009

Rev. 2 RISK ASSESSMENT FOR INSTALLATION OF GLAZED ALUMINUM Page 12 of 14


CURTAIN WALL

Severity Likelihood Evaluation of risk

Action required urgently to control the risk, further resources may be


16 - 25 High
NO INJURY 1 RARE 1 required, work must stop immediately

MINOR 2 UNLIKELY 2 Action required to control the risk, interim measures may be necessary in
6 – 15 Med
MODERATE 3 OFTEN 3 the short term, able to proceed with work under supervision
MAJOR 4 LIKELY 4
This represents a low risk, although control measures must be
FATALITY 5 EXPECTED 5 1–5 Low
maintained

Prepared by: Rizwan Ahmad Reviewed by: Suraj Desai Approved by: Vinish Vasudevan

HSE Construction Project


Manager Manager Manager

Health & Safety Assessment Briefing Register

Risk Assessment on Activity


Risk Assessment No.: Revision No.
Risk Assessment Validation Period:
Date: 19.03.2022 PROJECT: Wadi Al Sail office Building with Data Center DOC. Ref: No. -WAS-ALB-AEB-MST-AR-0009

Rev. 2 RISK ASSESSMENT FOR INSTALLATION OF GLAZED ALUMINUM Page 13 of 14


CURTAIN WALL

No. Name (Print) Organisation Position Date Time Signature

10

11

12

13

14
Date: 19.03.2022 PROJECT: Wadi Al Sail office Building with Data Center DOC. Ref: No. -WAS-ALB-AEB-MST-AR-0009

Rev. 2 RISK ASSESSMENT FOR INSTALLATION OF GLAZED ALUMINUM Page 14 of 14


CURTAIN WALL

No. Name (Print) Organisation Position Date Time Signature

15

16

17

18

19

20
Project Name : WADI AL SAIL OFFICE BUILDING WITH DATA CENTER (4B+G+2F) 4B+G+7F)
Project No. : Form Ref. No. : P07-F06a / Rev. 0 / Feb. 2012
INSPECTION AND TEST PLAN (ITP)

Installation of Aluminum
Client Project Manager Consultant Contractor

Windows and Curtain Wall


eau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau

Verifying Party (Legend): Verification Codes :


SC = Subcontractor H = Hold Point - Mandatory - work cannot proceed until inspection activity has been signed-off by relevant party. ITP Ref. No : WAS-ALB-AEB-MST-AR-0004 Rev. 2
MC = Main Contractor W = Witness Point - Veryfying Party to witness. Evidence of witness shall be by signature of relevant Inspection Report.
CT = Consultant R = Review - Inspection and Test documentation to be presented to Consultant or PM for review. Date Prepared : 02-Oct-22
PM = Client or PM S = Surveillance - Monitoring of work activities, NO report required.

Frequency / Verifying Party


Item Reference Documents
Activity Description Characteristics Acceptance Criteria / Standard Requirements Verifying Documents
No. (Specs/Procedures/Dwgs) SC MC CT PM
to be Verified
1.0 Document Submission

Prequalification Document Submittal, QCS 2014 Sec


1.1 Subcontractor Pre-qualification Prior to start the work Approval of Pre-qualification Approval R R R -
17

Approved Material Submittal, Project Specifications,


1.2 Material Submittal & Samples Prior to start the work Approval of Material Submittal & Sample Approval R R R -
QCS 2014 Sec 17

Drawings to be used shall be as per latest approved


1.3 Shop Drawings drawings. Adequate details and information to Prior to start the work Approved drawings Approval R R R
execute the job as per project requirements.

Suitability and adequacy of information to execute


Method of Statement, Inspection and Test the job. Inspection stages and Hold points are
1.4 Prior to start the work Approved Method statement. Inspection and Test Plan Approval R R R
Plan properly identified and satisfy the project
requirements.

2.0 Material

Delivered Material is matching the approved Material Submittal,


Approved Material Submittal, Approved Sample of Delivery Note, Manufacturer's
Sample profiles, glass type and color, type of finish & color of
2.1 Material Receiving Inspection profiles, Finishing type & colors, Approved Shop Prior to start the work Test Report, Inspection H H H -
frames, door and window schedule of the shop drawings. Material
Drawings of Window & Door Schedule Request
certificate shall be available.

Inspection Test Plan (ITP) Form No.: P07-F06a / Rev. 0 / Feb. 2012
AEB - Construction Supervision Department Quality Forms Page 1 of 3 gr
Project Name : WADI AL SAIL OFFICE BUILDING WITH DATA CENTER (4B+G+2F) 4B+G+7F)
Project No. : Form Ref. No. : P07-F06a / Rev. 0 / Feb. 2012
INSPECTION AND TEST PLAN (ITP)

Installation of Aluminum
Client Project Manager Consultant Contractor

Windows and Curtain Wall


eau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau

Verifying Party (Legend): Verification Codes :


SC = Subcontractor H = Hold Point - Mandatory - work cannot proceed until inspection activity has been signed-off by relevant party. ITP Ref. No : WAS-ALB-AEB-MST-AR-0004 Rev. 2
MC = Main Contractor W = Witness Point - Veryfying Party to witness. Evidence of witness shall be by signature of relevant Inspection Report.
CT = Consultant R = Review - Inspection and Test documentation to be presented to Consultant or PM for review. Date Prepared : 02-Oct-22
PM = Client or PM S = Surveillance - Monitoring of work activities, NO report required.

Frequency / Verifying Party


Item Reference Documents
Activity Description Characteristics Acceptance Criteria / Standard Requirements Verifying Documents
No. (Specs/Procedures/Dwgs) SC MC CT PM
to be Verified
3.0 Aluminum Window & Curtain wall installation Installation Process

Material comply as per approved samples and colors and schedule.


Method Statement, Approved Shop Drawings, QCS
3.1 Mock-Up Prior to start the work Installation complies the fixing details as shown in the approved Inspection Request H H H -
Sec 17 Part 1
drawing. Mock Up approval from Client.
Compliance to Approved Drawings.Paint works shall be completed.
Aprroved Drawing. Aluminu
Site Readiness of openings / Check Method Statement and Approved Drawings, QCS Openings shall be square,level and plumb.Tolerance of 5mm is
3.2 Prior to start the work window and curtain wall H W W -
opening sizes Sec 17 Part 3 Acceptable and any non-ready opening or site conditions should be
checklist
corrected.
1. Material are assigned to each Opening as per Approved Door &
Window Schedule. 2. Frames and brackets are to be fixed with
sufficient fastenings as shown in the details of the approved
Installation of Aluminum, Window & Method Statement and Approved Drawings, QCS drawings. Use vendor supplied fasteners only.
3.3 During the work 3. All units are to be fixed square, level and plumb without distortion. Approved Drawing H W S -
Curtain Wall Frames Sec 17 Part 3
4. Frames shall be protected from damage/ scratches with protection
tapes. 5. Joints between the frames and the openings are to be
sealed by approved sealant.

Type and color of Glass, Doors, hardware and accessories shall


comply with approved sample provided in the material submittal. All
Installation of Glass, Hardware & Method Statement and Approved Drawings, QCS installations, sealant and gasketing shall be as per the detail shown
3.4 During the work Approved Drawing H W S -
Accessories Sec 17 Part 3 in the approved drawing. Installed doors & hardwares should operate
freely and smoothly. Comply with hardware schedule. No any
damage and sign of deterioration.

Inspection Test Plan (ITP) Form No.: P07-F06a / Rev. 0 / Feb. 2012
AEB - Construction Supervision Department Quality Forms Page 2 of 3 gr
Project Name : WADI AL SAIL OFFICE BUILDING WITH DATA CENTER (4B+G+2F) 4B+G+7F)
Project No. : Form Ref. No. : P07-F06a / Rev. 0 / Feb. 2012
INSPECTION AND TEST PLAN (ITP)

Installation of Aluminum
Client Project Manager Consultant Contractor

Windows and Curtain Wall


eau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau

Verifying Party (Legend): Verification Codes :


SC = Subcontractor H = Hold Point - Mandatory - work cannot proceed until inspection activity has been signed-off by relevant party. ITP Ref. No : WAS-ALB-AEB-MST-AR-0004 Rev. 2
MC = Main Contractor W = Witness Point - Veryfying Party to witness. Evidence of witness shall be by signature of relevant Inspection Report.
CT = Consultant R = Review - Inspection and Test documentation to be presented to Consultant or PM for review. Date Prepared : 02-Oct-22
PM = Client or PM S = Surveillance - Monitoring of work activities, NO report required.

Frequency / Verifying Party


Item Reference Documents
Activity Description Characteristics Acceptance Criteria / Standard Requirements Verifying Documents
No. (Specs/Procedures/Dwgs) SC MC CT PM
to be Verified
Type and color of Glass, Doors, hardware and accessories shall
comply with approved sample provided in the material submittal.
Glass and frames installation shall be plumbed and aligned. All
Completed Installation of Aluminum Glass Method Statement and Approved Drawings, QCS installations, sealant and gasketing shall be as per the detail shown
3.5 During the work Approved Drawing H W S
& Frames for Windows,and Curtain Wall Sec 17 Part 4 in the approved drawing. Installed doors & hardwares should be fully
functional & operate freely and smoothly. Comply with hardware
schedule. No any damage and sign of deterioration.

4.0 Post Construction

Final work is to be equal to any sample panel submitted to, and


4.1 Final Inspection Project Specification, QCS 2014, IFC Drawings Completion the work H W W -
approved by, the Engineer

Prepared by (Contractor) : Reviewed and Approved by (AEB Discipline Engineer) : Noted by (AEB-PM or RE):
Name : Name : Name :
Signature : Date : Signature : Date : Signature : Date :

Inspection Test Plan (ITP) Form No.: P07-F06a / Rev. 0 / Feb. 2012
AEB - Construction Supervision Department Quality Forms Page 3 of 3 gr
Project Name : WADI AL SAIL OFFICE BUILDING WITH DATA CENTER (4B+G+2F) 4B+G+7F) at C RING ROAD, DOHA QATAR
Contract Title / No.: 1429
Consultant Main Contractor:

AL-BALAGH TRADING & CONTRACTING


CO. W.L.L.

CHECKLIST FOR INSTALLATION OF ALUMINUM WINDOW & CURTAIN WALL


S/N Checklist Items YES NO N/A Remarks / Comments
A. Material Approvals & Work Preparation
a.1 All materials & accessories are approved?
a.2 Shop drawings are approved?
a.3 Method statement & Risk Assesment approved ?
B. Mock-up Inspection
b.1 Mock-up is as per approved shop drawing?
C. Material Installation
c.1 Delivered Material is Inspected & Approved
c.2 Color and finishes of glass and frames as per approved sample
c.3 Materials are in good condition and free from any physical defects
c.4 Openings are ready to Aluminum Doors & Windows
c.5 Frame Installation is properly done, Correct level and alignment / verticality. Fixing comply as per fixing detail in the approved drawing.
c.6 Glass installation carried out as per approved drawing
c.7 Sealant / gasket application as per approved drawing.
c.8 Survey marking available for alignment of Kerbstones?
c.9 Doors & Accessories installed as per approved drawing.
c.10 Windows/Doors operates smoothly and quietly.
c.11 Final finishing / paint touch up completed
The above activities are found to be as per contract requirements and are ready The above activities are correct and released for the next activity.
for release.

Checked by: Verified by (AEB Architect/Engineer):


a. Subcon Site or QA/QC Engineer b. MainCon Site or QA/QC Engineer

Name/Signature Name/Signature
Name / Signature

Date Date Date


Note: Checking and approval by AEB shall not relieve the Contractor from his obligation to perform the work in accordance with other contract documents and HSE requirements. This inspection
Checklist is a guide and shall be considered in the routine inspections BUT not limited to it.

Checklist for Block Laying (Blockworks) Form No.: CSD-CL-A001


AEB - CSD Quality Forms gr
24/08/2022

B
B
B
B
B
B
B
B
B
B
B

Refering to the workshop meeting held on 24/08/2022, contractor to comply with the
commented shop drawings as attached for final approval.

Mockup on site for termination details and waterproofing details are required

Srinivasn J Engr. Mohammad Ezzat

27/08/2022 27/08/2022
24/08/2022

B
B
B
B
B
B
B
B
B
B

Refering to the workshop meeting held on 24/08/2022, contractor to comply with the
commented shop drawings as attached for final approval.

Mockup on site for termination details and waterproofing details are required

Srinivasn J Engr. Mohammad Ezzat

27/08/2022 27/08/2022
LOCATION

t ba St.
18m U

Ibn Ammar street


50m C Ring Road

MASTER PLAN

VEHICLE PARKING
LOCATION-01
PROJECT GATE

EXIT
WASTE

ENTRY
SITE ACCESS
SKIF
E231582.165 E231627.963 SMOKING
N390096.986 N390096.498 AREA
A E
REST

CHECK POINT 01
PEDESTRIAN ACCESS AREA
PROJECT BOUNDARY 52 50
49
SECURITY APPROVAL STATUS
GUARD
48

47

MESS HALL
HAND WASH
46

PEDESTRIAN ACCESS
45 44

PLOT BOUNDARY PLOT BOUNDARY


43

STORE CONTAINER
42
SHOP DRAWING REFERENCES:

GENERATOR

PEDESTRIAN ACCESS
7
E231580.388
N390071.063
E231523.027 8
10 E231467.203 9

PROJECT BOUNDARY
E231512.998 N390069.582
N390069.245 N390069.104 STEEL REBAR STORAGE
TAKYEEF STORAGE 2 STEEL WORKSHOP MATERIAL STORE
FOR CURTAIN WALL

GATE
5

PROJECT BOUNDARY
6 41
TAKYEEF STORE 1 CONTAINER
2 4
E231522.642 E231579.160 TOWER
E231512.572 N390063.927
1 E231458.952 3
N390063.562
N390064.250 CAIN_02 IFC DRAWING REFERENCES:
E231449.530 N390064.138 E231466.250
N390062.983 N390062.861 F2
LOCATION-02

EQUIPMENT STORE
E231571.795
EQUIPMENT & VEHICLE N390057.835
40

LAYDOWN AREA MOVEMENT


~37.962M

E231504.431
DEBRIS N390053.946 36
37
WADI AL SAIL PROJECT
E231485.619 13 14 17
15 E231511.985
N390054.580
E231502.196
E231506.700
N390053.609
16 N390052.893 SHELTER CONSTRUCTION OF OFFICE BUILDING & DATA CENTER
N390053.790 E231522.769
11 E231452.335 12 E231456.564 N390053.215 E231546.395 35
34
FOR QATAR CENTRAL BANK
N390050.908 N390051.325 N390050.249 TOWER 39
SHUTTER STORAGE SHOP DRAWING REVISIONS:
CHECK POINT 02

E231451.292 SHUTTERING CRANE_01


N390049.868 AREA 28
STEEL SCRAP

SCAFFOLDING PREPARATION 29
AREA
SCAFFOLDING MATERIAL
19.063M
MATERIAL
32
TOWER 33
CRANE E231627.069 37 38
N390041.439
19
E231521.895
24 D
20
E231505.934 18 N390042.033 E231528.381 25
27
TOILET
TOILET
N390042.010 26
N390041.966 E231539.021
N390042.146
E231453.271
N390041.654 E231499.139
21
E231511.076 22
RAMP 31 E231618.936 MESS HALL
30
N390038.514 N390038.304 N390033.478
CONTAINER
TOILET E231581.905
PROJECT BOUNDARY
E231511.257
N390035.438 23
E231525.762
RAMP UP N390033.654
C
E231581.587
E231444.611 F1 N390034.268
GATE GENERATOR WATER GENERATOR B
N390034.995
N390035.066 E231534.851 TANK
N390034.192
SITE ACCESS
EXISTING FENCE
Serv
ice R
oad
AEB HEADQUARTERS:
P.O. Box 1148 Doha, Qatar Tel +974 4406 88 88 Fax +974 4447 78 68
Email aeb@aeb-qatar.com Web www.aeb-qatar.com
OTHER BRANCHES:
ABU DHABI * MANILA * KUALA LUMPUR * MUSCAT

AL-BALAGH TRADING &


CONTRACTING CO. W.L.L.
P.O.Box # 5777, Doha, State of Qatar
Tel.: +974 - 44667714 / 15 / 16 Fax: +974 - 44660040
Web: www.albalagh.com Email: albalagh@albalagh.com

50m C Ring Road


WADI AL-SAIL OFFICE BUILDING WITH
DATA CENTER
WADI AL SAIL HOLDING COMPANY
C - RING ROAD, DOHA, QATAR

1429-20 Feb 15, 2022

SITE LOGISTIC PLAN

AS SHOWN @ A1 SHEET 1 OF 1 WAS-ALB-AEB-PR-GN-0200.00

Mufasil Jigish Girish 01


 
 
 
 
 
 
 
 
 
 
 
 
 
CAREER OBJECTIVE
  Seeking a position as an ARCHITECTURAL ENGINEER
 
  - FACADE SOLUTION which offers key
  participation, team oriented tasks, immediate
 
  challenges, and career opportunity. To be a part of
  an organization where I can fully utilize my technical
skills to com- plete engineering projects by
TIME MANAGEMENT organizing and con- trolling various projects
elements and to make a sig- nificant contribution to
MANAGEMENT OF MATERIAL the success of the employer and at the same time
RESOURCES my individual growth.
 
SERVICE ORIENTATION
 

OPERATIONS ANALYSIS CAREER SYNOPSIS


 
 

MANAGEMENT OF • Goal oriented professional with experience as FACADE ENGINEER -


FINANCIAL RESOURCES under direction, performs Engineering Execution, Planning and Design
  in the areas of Architectural Facade systems- fabrication and installa-
DESIGN SKILLS tion of Aluminium systems and Glazing works.
 
• Technical knowledge in various Aluminium Profiles and Glazing
System- curtain wall units, windows and doors; Aluminium Composite
Panels; Louvers; Canopy and Skylight.
 
SAFETY MANAGEMENT • Experience in Project execution of Aluminium Profiles and systems
based on project specification.
PROCESS IMPROVEMENT

SUPERVISION

CAD (AUTODESK 2016)

CAD/CAM

SOLID-WORKS
 
C++
PROFESSIONAL E X P E R I E N C E S
• Six years of experience as FACADE SITE ENGINEER in JAFCO ALUMINIUM &
STEEL CO.W.L.L, Qatar.

• Currently working as a PROJECT ENGINEER - FACADE SOLUTION at GALFAR


AL MISNAD ENGG. & CONTG. W.L.L, Doha, Qatar
PROJECTS EXECUTED IN QATAR
As FACADE ENGINEER with M/s Jafco Aluminium & Steel Co.W.L.L
1. Al Khayrien Tower B+G+P+18 @ Lusail
Designation: Site Engineer
Consultant: Dimensions
Main Contractor: Pat Engineering
Aluminium Sub Contractor: Jafco Aluminium & Steel Co
2. 3B+G+7 Commercial & Residential @ Muntazah
Designation: Site Engineer
Consultant: MZ & P
Contractor: Zublin International Qatar.
Aluminium Sub Contractor: Jafco Aluminium & Steel Co
3. New Port Project_ Admin & Ancillary Buildings
Designation: Site Engineer
Consultant: AECOM
Contractor: Shapoorji Palloonji/Sinohydro & UCE
Aluminium Sub Contractor: Jafco Aluminium & Steel Co
4. Office Building 2B+G+10 @ New Salata
Designation: Site Engineer
Consultant: Diwan Al Emara
Contractor: Derwind Trading & Contracting
Aluminium Sub Contractor: Jafco Aluminium & Steel Co
 

 
CORE COMPETENCIES
• Develops project objective by reviewing project proposals and plans, conferring with
management.
• Determine project specifications by studying product design, customer
requirements and performance standards.
 
• Schedule preparation, pre-planning and resource forecasting for engineering and
other technical activities relating to the project.
 
• Supervise and manage the caseload of the external architectural services providing
the design element for the adaptation works, ensuring that appropriate permissions are
gained, Planning, Building Control and relevant statutory notices, and timescales are
achieved.
 
• Assure the accuracy of financial forecasting which should fit into the project
schedules.
 
• Ensure that the project is completed as per plans.
 
• Manage project team resources and develop extensive project management
experience and expertise.
 
• Maintain inter-discipline coordination and overall quality control of the work.
 
• Manage payment of interim and final invoices, including collecting and checking all
certificates and invoices on completion of works, carrying out final inspections, check
final accounts and defects liability.
 
• Prepare project status reports by collecting, analyzing and summarizing.Information
and trends.
 
• Maintain project data base by writing computer programs, entering and backing up
data.
 
• .Supervise and monitor the work of the contractors throughout its completion,
ensuring risk assessments of COM 2015 regulations are adhered and appropriate
health and safety measures in place.
 
• Work with the Business Development Manager to identify opportunities to increase
the Technical Service offer to private clients, generating fee income for the
organization.
 

ACADEMIA
     
DEGREE COLLEGE/UNIVERSITY YEAR OF PASS %MARKS

  Bishop Jerome Institute,  


B-TECH Kollam    
(Mechanical ( affiliated to University 2014 66
Engineering) of Kerala)
     
121h Sree Narayana Public 2010 70
School, Kollam ( CBSE)
     
101h Sree Narayana Public 2008 85
School, Kollam ( CBSE)
Note: Acquired B-Tech with no backlogs.
 
 

COLLEGE P R O J E C T UNDERTAKEN AN D
SEMINAR PRESENTED
 
Title: Modification and Fabrication of Theo-Jansen Mechanism
 
 
Description: Modification and Fabrication of Theo-Jansen
Strandbeest and correcting its limitations thus widening the field of
application in military, transportation and agriculture
 
 
Title: Seminar on Crank Based Leg Mechanism.
 
 
Description: The paper describes the design and working of a 2-n
legged passive crank-based walking mechanism based on the work
of Theo-Jansen.
 
 
 
PERSONALITY TRAITS
 
•Quick learning ability
 
 
•Optimist
 
 
•Adaptability
 
 
•Problem solving
 
 
 
 

 
HOBBIES
 
•Origami
 
 
•Listening mus1c
 
 
•Photography
 
 
•Travelling
 
 

PERSONAL DETAILS
 
Name : AROMALS
 
Father name : SHAJI S
 
 
Date of Birth : 18/04/1993
 
 
Sex : MALE
 
 
Marital Status : SINGLE
 
 
Religion : HINDU
 
 
Nationality : INDIAN

Languages Known : MALAYALAM, ENGLISH, TAMIL, HINDI


 
Passport No : K7830284
 
 
Date of issue : 07/01/2013
 
 
Place of issue : TRIVANDRUM
 
 
Date of Expiry : 06/01/2023
 
 
Driving License : INDIA, 2/10619/2011
 
 
Blood Group : B +VE
 
 
Qatar ID.No : 29335617471
 

DECLARATION
 
I hereby declare that the above mentioned statements are true
and correct to the best of my knowledge and belief.
 

Signature:
Date:
 
Place: Qatar
GALFAR FAÇADE SOLUTIONS CORE TEAM

Mr. Aromal Shaji


Project Engineer
Qualification : Mechanical Engineering
Years of Experience: 6 Years in the Façade Industry.

Major Associated Projects


1. Al Madean Complex
Designation : Senior Project Engineer
Consultant : James Cubbit & Partners
Contractor : Hamton International
Façade Contractor : Jafco Aluminium & Steel Co
System Used : Gulf Extrusion

2. Al Khayrien Tower B+G+P+18 @ Lusail


Designation : Site Engineer
Consultant : Dimensions
Contractor : Pat Engineering
Façade Contractor : Jafco Aluminium & Steel Co
System Used : Gutmann Germany.
3. 3B+G+7 Commercial & Residential @ Muntazah
Designation : Site Engineer
Consultant : MZ & P
Contractor : Zublin International Qatar.
Façade Contractor : Jafco Aluminium & Steel Co
System Used : Gutmann Germany.
4. New Port Project_ Admin & Ancillary Buildings
Designation : Site Engineer
Consultant : AECOM
Contractor : Shapoorji Palloonji/Sinohydro & UCE
Façade Contractor : Jafco Aluminium & Steel Co
System Used : Gutmann Germany
5. Office Building 2B+G+10 @ New Salata
Designation : Site Engineer
Consultant : Diwan Al Emara
Contractor : Derwind Trading & Contracting
Façade Contractor : Jafco Aluminium & Steel Co
System Used : Gutmann Germany
Project Logo
Project Name : WADI AL SAIL OFFICE BUILDING WITH DATA CENTER (4B+G+2F) 4B+G+7F) at C RING ROAD, DOHA QATAR
Project No. : 1429 Form Ref. No. : P07-F21 / Rev. 0 / Feb. 2012 COMPLIANCE SHEET OF TEST
Client Project Manager: Consultant: Contractor
REPORT AND PROJECT
SPECIFICATION
ureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engineering bureau arab engine

Block / Building Name : WADI AL SAIL OFFICE BUILDING WITH DATA CENTER Material Submittal Ref. No. : WAS-ALB-AEB-AR-MAR-0007
Material submittal for Glazed Aluminum Curtain wall,sliding window
Location of Use : Glazed Curtain Wall Name of Material :
Date Submitted : 02-Oct-2022 Submitted by : Chris.

Item
PROJECT SPECIFICATION EXOVA LABORATORY PERFORMANCE TESTING OF CURTAIN WALL TEST PASS/FAIL CRITERIA RESULT
No.

Air Infiltration

Total permissible
Maximum air leakage through fixed glazing and framing areas airflow is 28.2m3/hour
The avaerage air flow through the sample shall
of 0.3 L/s per sq. m of fixed wall area as determined according Measurement of air flow taken at a positive presure @ +600 Pa
1 not exeed 1.08m3/hour/m2 at a test pressure of
to ASTM E 283 at a minimum static-air-pressure differential of differential of +600 Pa. Area of sample tested
+600 Pa
75 Pa. 26.1m2
PASSED

Water Penetration under Static Pressure

No evidence of water penetration through fixed glazing and Water was sprayed onto the sample at the rate of at No water penetration allowed.Water penetration
framing areas when tested according to ASTM E 331 at least 3.4 litres/m2. With the water spray continuing, a is defined as the presence of water on any No water penetration.
2
a minimum static-air-pressure differential of 20 percent of pressure defferential equal to +600 Pa was applied normal exposed internal surface other than PASSED
positive wind-load design pressure, but not less than 300 Pa. across the sample and maintained for 15 mins. condensation.

Water penetration under dynamic pressure

Wind generator was mounted to the external face of the


sample. The generator output was adjusted to create a +
No water penetration allowed.Water penetration
600 Pa pressure differential onto the sample.
Water penetration under dynamic pressure when tested is defined as the presence of water on any No water penetration.
3 Water was sprayed onto the whole sample at the rate of
according to AAMA 501.1. normal exposed internal surface other than PASSED
at least 3.4 litres/m2/minute for 15 minute's period.
condensation.
Throught out the test the interior face of the samplewas
examined for water penetration

Structural Loads:
Wind Loads: Design to a basic wind speed of not less than 162
4
km/hr (45 meters per second)

Blast Loads: As recommended in writing per comprehensive


5
engineering analysis by Aluminum System Specialist. Please refer to structural Calculation REF. WAS-ALB-AEB-CAL-ST-0016 REV 1 PASSED

Periodic Maintenance-Equipment Loads: As recommended in


6 writing per comprehensive engineering analysis by Aluminum
System Specialist

Structural-Test Performance:
Provide glazed curtain wall system tested according

1. When tested at positive and negative wind-load design


pressures, assemblies do not evidence deflection exceeding
specified limits.
2. When tested at 150 percent of positive and negative wind-
load design pressures, assemblies, including anchorage, do not
7 Please refer to structural Calculation REF. WAS-ALB-AEB-CAL-ST-0016 REV 1 PASSED
evidence material failures, structural distress, and permanent
deformation of main framing members exceeding 0.2 percent of
span.
3. Test Durations: As required by design wind velocity, but not
less than 10 seconds.

Deflection of Framing Members:

1. Deflection Normal to Wall Plane: Unless otherwise more


stringent deflection criteria is required, shall be limited to edge
of glass in a direction perpendicular to glass plane not
8 Please refer to structural Calculation REF. WAS-ALB-AEB-CAL-ST-0016 REV 1 PASSED
exceeding L/175 of the glass edge length for each individual
glazing lite or an amount that restricts edge deflection of
individual glazing lites to 19 mm, whichever is less.

2. Deflection Parallel to Glazing Plane: Unless otherwise more


stringent deflection criteria is required, shall be limited to L/360
of clear span or 3.2mm, whichever is less; or that which
reduces edge clearance between framing
9 N/A N/A N/A
members and glazing or other fixed components to less than
3.2 meter.
a. Operable Units: Provide a minimum 1.6mm clearance
between framing members and operable units.
3. Dead Load: Provide members that do not deflect an amount,
10 which will reduce glazing bite below 75 percent of design Please refer to structural Calculation REF. WAS-ALB-AEB-CAL-ST-0016 REV 1 PASSED
dimension when carrying full dead load.

Compliance Statement P07-F21 / Rev. 0 / Feb. 2012


AEB - CSD Quality Forms Page 1 of 2 gr
Block / Building Name : WADI AL SAIL OFFICE BUILDING WITH DATA CENTER Material Submittal Ref. No. : WAS-ALB-AEB-AR-MAR-0007
Material submittal for Glazed Aluminum Curtain wall,sliding window
Location of Use : Glazed Curtain Wall Name of Material :
Date Submitted : 02-Oct-2022 Submitted by : Chris.

Item
PROJECT SPECIFICATION EXOVA LABORATORY PERFORMANCE TESTING OF CURTAIN WALL TEST PASS/FAIL CRITERIA RESULT
No.

Air Infiltration

Total permissible
Maximum air leakage through fixed glazing and framing areas airflow is 28.2m3/hour
The avaerage air flow through the sample shall
of 0.3 L/s per sq. m of fixed wall area as determined according Measurement of air flow taken at a positive presure @ +600 Pa
1 not exeed 1.08m3/hour/m2 at a test pressure of
to ASTM E 283 at a minimum static-air-pressure differential of differential of +600 Pa. Area of sample tested
+600 Pa
75 Pa. 26.1m2
PASSED

Water Penetration under Static Pressure

No evidence of water penetration through fixed glazing and Water was sprayed onto the sample at the rate of at No water penetration allowed.Water penetration
framing areas when tested according to ASTM E 331 at least 3.4 litres/m2. With the water spray continuing, a is defined as the presence of water on any No water penetration.
2
a minimum static-air-pressure differential of 20 percent of pressure defferential equal to +600 Pa was applied normal exposed internal surface other than PASSED
positive wind-load design pressure, but not less than 300 Pa. across the sample and maintained for 15 mins. condensation.

Water penetration under dynamic pressure

Wind generator was mounted to the external face of the


sample. The generator output was adjusted to create a +
No water penetration allowed.Water penetration
600 Pa pressure differential onto the sample.
Water penetration under dynamic pressure when tested is defined as the presence of water on any No water penetration.
3 Water was sprayed onto the whole sample at the rate of
according to AAMA 501.1. normal exposed internal surface other than PASSED
at least 3.4 litres/m2/minute for 15 minute's period.
condensation.
Throught out the test the interior face of the samplewas
examined for water penetration

4. Cantilever Deflection: Where framing members overhang an


11 anchor point, limit deflection to 2 times the length of Please refer to structural Calculation REF. WAS-ALB-AEB-CAL-ST-0016 REV 1 PASSED
cantilevered member divided by 175.
Story Drift
1. As recommended in writing per comprehensive engineering
12
analysis by Installer.

The mid-height support beam was dispalced 10mm


vertically up and thenbackto centre. The mid-height
beam was then displaced 10mm down, and then back to
centre. At each stage,visual observation were made. The
The shall be no failure or gross permanent
2. Test Performance: Meets criteria for passing based on above procedure was completed three cycle. No vision damage to
distoryion of anchors,frame, glass, or panels, no
13 building occupancy type when tested according to AAMA 501.4 The mid-height support beam was dispalced 10mm the sample
gasket diengagement and no weather or
at design displacement and 1.5 times the design displacement. horizontally left and then back to centre. The mid-height PASSED
structural sealant failure
beam was then displaced 10mm horizontally to the right,
and then back to centre. At each stage,visual
observation were made. The above procedure was
completed three cycle.

Compliance Statement P07-F21 / Rev. 0 / Feb. 2012


AEB - CSD Quality Forms Page 2 of 2 gr
- Please refer to the attached CDF

Florian De Joya Engr. Mohammad Ezzat

18/09/2022 18/09/2022
COMMENT DISPOSITION FORM (CDF)
METHOD STATEMENT FOR IFOR INSTALLATION OF GLAZED ALUMINUM
Title: Reviewing Dept.: Arab Engineering Bureau
CURTAIN WALL BY GALFAR
Doc. No.: WAS-ALB-AEB-MST-AR-0009 Rev.: 1 Disposition Dept.: AL BALAGH
Review Date: 31/08/2022 Disposition Date: 31/08/2022

S. No. Comments Dispositions (Contractor) Status/Remarks


Revision 0
Arch:
Section 2 References.
Noted,
Project specification, logistic plan, Structural
a. Include other Project Specification Sections references
1. Calculation, IFC and Approved Shop drawing Closed
b. Logistic Plan
reference have been added to the
c. Structural Calculation
sections#2 Reference
d. (Others)

Noted,
Arch: Contact detail of relevant responsible
2. Closed
Provide Contact details of relevant responsible personnel. personnel is included in the section#7 Project
Organization Chart
Arch:
Section 5 Manpower Requirement.
a. Contractor to provide the number of persons required.
Noted,
Rev.01
3. Number of persons required in provided in Open
Section#5 Manpower requirements
Include in the manpower requirement, how many Teams and composition per
Team per panel installation.

Document Reference: WAS-ALB-AEB-MST-AR-0009 Rev. 1 Page 1 of 4


S. No. Comments Dispositions (Contractor) Status/Remarks

Arch:
Provide Section for Plants & Equipment Requirement.
Categorize the tools and Equipment. e.g., Equipment, Power tools, Hand
Tools, General Items, Required PPE.
Noted,
4. Kindly refer Section #6 Plant and equipment Open
Rev.01
have been categorized.
A. Provide specific Mobile crane and Tele Handler boom loader
information.
Any Trolley for moving short distance?
B. Glass suction Cups?
Arch:
Provide detailed method statement per façade schedule system and per
locations to ensure coordination with other work interfacing.
Noted,
Rev.01 Kindly refer Section #8, Detailed method
5. Open
a. Provide method statement for replacement or in case or breakage system per façade schedule system and per
during or after the installation. location is provided.
b. Contractor to provide information for installation particular order of
fixation required or whether and/or whenever the same size of glass
can be installed without sequence?
Arch:
Provide Detailed Quality Control requirements.
Noted,
6. Detailed Quality control plan is provided in Open
Rev.01
Section#9
Provide the Quality Management Plan as mentioned in section 9, Quality
Control.

Document Reference: WAS-ALB-AEB-MST-AR-0009 Rev. 1 Page 2 of 4


S. No. Comments Dispositions (Contractor) Status/Remarks
Arch:
Provide detailed delivery storage and handling.
Noted,
7. Rev.01 Detailed delivery storage and handling is Open
Provide a drawing layout of material storage at site whenever the material is provided in Section #10
not readily available for direct fixing.

Arch:
Provide Certification and trainings.
A. Valid Certification Issued by approving Authority for qualified person.
B. Valid Calibration certificate for testing equipment. Please refer Section#14- Attachments,
8. Open
C. Qualification Record of Trained Personnel Performing the task. 5. Certification and trainings.

Rev.01
Valid Calibration certificate for testing equipment not found.
Arch:
Logistic
Provide the Site Logistic Plan document reference that includes Material
Delivery Temporary, Facilities, Storage, Mobile Crane particular optimum
location etc.
9. WAS-ALB-AEB-GEN-DOC-0010 REV 02 Open
Rev.01
WAS-ALB-AEB-GEN-DOC-0010 REV 02 not yet submitted to AEB. Contractor
to submit.

Arch:
Contractor to review the ITP prior to submittal.
Noted,
10. Rev.01 Open
Revised ITP attached.
2.0 Material 2.2 MIR under verifying party CT=H
3.1 Mock up under verifying party CT=H

Document Reference: WAS-ALB-AEB-MST-AR-0009 Rev. 1 Page 3 of 4


S. No. Comments Dispositions (Contractor) Status/Remarks

Testing
Provide preconstruction testing and post construction testing per required.

Reviewer Name: Florian de Joya – Sr. Architect Signature: Date: 18/09/2022

Mohammed Ezzat Ahmed Haggag - PM


Approver Name: Signature: Date: 18/09/2022

Dispositioner Name: Contractor Representative Signature: Date: Select date.

Document Status: Approved Approved as Noted Revise and Resubmit


Rejected For Information Only

Document Reference: WAS-ALB-AEB-MST-AR-0009 Rev. 1 Page 4 of 4