Professional Documents
Culture Documents
METHOD STATEMENT FOR INSTALLATION OF CURTAIN WALL, LOUVER AND ACP - Compressed PDF
METHOD STATEMENT FOR INSTALLATION OF CURTAIN WALL, LOUVER AND ACP - Compressed PDF
METHOD STATEMENT FOR INSTALLATION OF CURTAIN WALL, LOUVER AND ACP - Compressed PDF
Notes:
This compliance sheet shall be prepared by the contractor to match with the issued comment /
comments from the project consultant. The provide comments or responses shall be clearly
understood and delivered (e.g. specific, refer to sheet number, detail number, date submittal).
Delivery and storage to be as per specification, Delivery and storage is as per the
3 manufacturer’s recommendation and to be manufacturers’ recommendation
attached in the method statement. and same is attached.
In case of failure for test to be mentioned. Please refer to section 7.4 of the
12
Cause 3.5 (G and H). method statement
13 ITP to be attached.
CONSULTANT COMMENTS:
The remedial action has been taken and the specific Site Inspection are approved
Project:
CONTRACT No:
DOCUMENT TITLE:
Method Statement for Installation of Glazed Aluminum curtain wall, Aluminum Louver and Aluminum Composite Panel
Client Consultant: Contractor:
Project:
Table of Contents
1. SCOPE & OBJECTIVES .....................................................................................................................3
2. REFERENCES .....................................................................................................................................3
3. DEFINITIONS .......................................................................................................................................3
13. ATTACHMENTS.............................................................................................................................15
Method Statement for Installation of Glazed Aluminum curtain wall, Aluminum Louver and Aluminum Composite Panel
Client Consultant: Contractor:
Project:
2. REFERENCES
This method statement shall read and refer in conjunction with below
references.
Project Specifications Section 08 44 13 – Aluminum Curtain Wall
QCS 2014 Section 25 Part 5 & 6 - Glass and Glazing
IFC Drawings & Approved Shop Drawing
Material submittal for glazed aluminum curtain wall, Aluminum Louver &
ACP
3. DEFINITIONS
Method Statement for Installation of Glazed Aluminum curtain wall, Aluminum Louver and Aluminum Composite Panel
Client Consultant: Contractor:
Project:
RA Risk Assessment
IFC Issued for Construction
4. RESPONSIBILITIES/ SUPERVISION
POSITION RESPONSIBILITY
Project Manager Ensure the work is progressing as per the approved schedule
and contractual requirements
Construction Responsible for planning, organizing and carrying out the
Manager work in accordance with project requirements and monitor
the progress of works.
Project Engineer Responsible for carrying out the work in accordance with
project requirements.
QA/QC Engineer Ensure that the works are carried out as per approved
Method Statement.
HSE Manager Responsible for planning, coordinate and implement issues
and directives within the organization and ensures safe
environmental working conditions for all employees and also
enforces safety procedures in accordance with the approved
HSE Plan.
HSE Officer Ensure the works are carried in a safe manner. Provides
Safety toolbox tasks and monitors are the work force for
working safely.
Supervisor/ To carry out the works as instructed by the Project Engineer
Foreman and monitor the work force.
Workers Carryout the work as advised by the Supervisor/Foreman.
5. MANPOWER REQUIREMENT
Sl. No Manpower
1 Project Manager
3 Project Engineer
4 Land Surveyor
Method Statement for Installation of Glazed Aluminum curtain wall, Aluminum Louver and Aluminum Composite Panel
Client Consultant: Contractor:
Project:
5 Safety Officer
6 QA/QC Engineer
7 Foreman
8 Fabricators
9 Installers
10 Skilled helpers
11 Helpers
Method Statement for Installation of Glazed Aluminum curtain wall, Aluminum Louver and Aluminum Composite Panel
Client Consultant: Contractor:
Project:
7. PROCEDURE
7.1 CURTAINWALL
7.11 General Requirements
Method Statement for Installation of Glazed Aluminum curtain wall, Aluminum Louver and Aluminum Composite Panel
Client Consultant: Contractor:
Project:
Project:
Mullions with brackets are fixed as per the approved shop drawings.
Erection Tolerances: Erection Tolerances of 10 – 20mm will be provided
between the structure and frames, which will be covered with sealant.
Transoms are fixed to the connection brackets of mullion and secures with
screw
Method Statement for Installation of Glazed Aluminum curtain wall, Aluminum Louver and Aluminum Composite Panel
Client Consultant: Contractor:
Project:
Glazing support bracket, insulator and inner gaskets are installed as per
manufacturer’s recommendation.
Ensure the frame is squared prior to start glass installation.
Install glass using crane and held temporarily with small pieces of pressure
plate.
The temporary pressure plate is to allow all glass to be installed and aligned
properly.
Mineral fiber insulation, along with the back pans, shall be installed at all
spandrel areas.
The glass will be held and controlled using suction pads. At the ground
floor, glass will be installed manually.
Install the rest of the glass and ensure all are in alignment.
Fill the gap in-between the installed glasses with backer rod before
applying the sealant.
Installations are carried out in conformity with installation and approved
shop drawings as per system supplier’s recommendation.
7. 2 Installation of Louver
Method Statement for Installation of Glazed Aluminum curtain wall, Aluminum Louver and Aluminum Composite Panel
Client Consultant: Contractor:
Project:
The louver units will be assembled on the ground with the brackets before
installing to the respective openings.
The assembled units will be fix to the opening and screwed to the structure
Before fastening to the wall, ensure the verticality of the louver.
The units will be fix at bottom of the units by using screws. Cover cap will
be fixed in to free hole.
7.3 Aluminum Cladding Installation
Project:
Edge of sealing material will not be trimmed after the joints are tooled.
Application of approved silicone sealant will be done with the help of gun.
Ensure the surface is smooth.
Remove masking tape immediately after filling joint. Scrape off fresh
compound from adjacent surfaces immediately and rub clean with
approved solvent.
Upon completion of caulking and sealing, remove remaining smears,
stains, and other soiling, and leave work in clean neat condition.
Sealant Adhesive test will be performed by main contractor.
After the completion of the job, tests as mention in the specification
1
(water Penetration, Air Infiltration, thermal conductance and deflection
test) will be conducted by main contractor.
In case there is failure of test, retesting will be done.
Should system fail field test, system will be modified or repaired, and
retested.
Should system fail second field test, system may be additionally modified
or repaired, and retested.
All modifications and repairs made to tested areas shall be recorded, and
same modifications and repairs made to all system and adjacent
1
construction on project.
Should second test fail, Contracting Officer may require testing of
additional areas of the curtain wall.
Failure of any of specimens to meet test requirements of third test shall
be cause for rejection of wall system and adjacent construction on project.
7.5 Protection
After installation, the aluminum frames will be protect with stickers to
avoid scratches that may result from other parties.
1 The glass area will be protected with hard boards.
7.6 Inspection
Inspections for the works above will be carried at as stipulated in the ITP.
Request for Inspection shall be raised for each stage of work as stipulated
in ITP.
7.7 Cleaning
Method Statement for Installation of Glazed Aluminum curtain wall, Aluminum Louver and Aluminum Composite Panel
Client Consultant: Contractor:
Project:
All the Inspection Request shall be raised as per approved Inspection &
Test Plan (ITP) for the activity.
Material will be inspected on site before being used.
8.1 QUALITY ASSURANCE
Project:
Appropriate & correct Personnel Protective Equipment (PPE) shall be provided and
always worn. The basic PPE requirement includes Helmets, safety shoes, safety
glass and reflective jackets.
Method Statement for Installation of Glazed Aluminum curtain wall, Aluminum Louver and Aluminum Composite Panel
Client Consultant: Contractor:
Project:
Safety induction training shall be provided to all staff, work force, operators
prior to entry to site premises. An induction sticker shall be provided to all
attendees identifying the satisfactory completion of training.
Toolbox talks shall be carried-out prior to commencing the task to clearly
emphasize the hazards and environmental aspects that might be
encountered, and the mitigating control measures to be undertaken. A
prestart meeting shall be conducted every day prior to start of the activity.
The Method Statement and risk assessment shall be clearly communicated
to the work personnel prior to start of work. PTW and its recommendations
if any will also be conveyed to the work force.
To ensure planned activities, and planned start date are coordinated to the
Consultant/Engineer prior to any site mobilization and commencement of
the work.
Regular coordination with the Client construction and HSE team members
should be maintained.
Appropriate signage shall be provided within the site premises. Proper
access and egress to working sites shall be established.
Work/Access areas shall be free from debris and materials to avoid tripping
hazard.
Scaffolding platform shall be erected as required to execute the works in
safest possible manner. Scaffolding shall be carried out by
qualified/certified scaffolders under the supervision of certified scaffold
supervisor. During erection of scaffolding, the area is barricaded with
provision of safety signs to prevent unauthorized personnel entry.
In General, all working areas shall be adequately barricaded to prevent
unauthorized personnel/public entry.
Appropriate permits as required shall be raised and maintained. Lifting
Permits Template is attached for reference.
Lifting permits along with the valid documents of the lifting crew shall be
maintained at the site during the lifting operations.
Method Statement for Installation of Glazed Aluminum curtain wall, Aluminum Louver and Aluminum Composite Panel
Client Consultant: Contractor:
Project:
Method Statement for Installation of Glazed Aluminum curtain wall, Aluminum Louver and Aluminum Composite Panel
RISK ASSESSMENT
Construction Of Residential Tower for
Qatar Charity (Marina 47) At Lusail District
Probability/
Probability Score Min Max Description 1 / VL 2/L 3/M 4/H 5 / VH Probability x Impact
Impact
Personal injury / fatality All site employees including visitors need to attend
Collision with plant safety induction before entering to the project
Site Engineer
equipment and Always follow the site safety signage within site
Foreman
2.Access & Egress machinery leading to 3 4 12 Medium premises 1 4 4 Low
Supervisor
major injuries, fatalities Everyone on site should wear high visibility vest
HSE Officer
and or property damage with respect to their trade along with appropriate
Lack of site awareness PPE all the time.
Construction Of Residential Tower for
Qatar Charity (Marina 47) At Lusail District
Slips, trips and falls Follow site safety rules and regulations
Uneven floor areas Follow the project traffic management system and
Slippery surfaces speed limit must be observed.
Parking for contractors’ vehicles and plant is
limited at project site.
Materials must be placed in designated areas.
Barricade with appropriate safety
Check the weather forecast in advance while
planning the operation.
Appropriate signage and illumination / lighting
where necessary to highlight and warn of hazard
has to be provided.
Pinch points, Trap hand, All TPI certificates attested and personals
fingers, feet. Sharp / including Riggers and Lifting Tools, tackles as per
Protruding objects lifting plan shall be used.
Unauthorized entry due Crane should be placed on level and stable ground
to lack of barricading Proper Maintenance and Checklist
Lack of Information, Crane should not be placed at near the excavation
instruction and training trench
and supervision Extend outriggers fully and rest on steel or wooden
Noise mats
Fire Use only approved Crane Operator
Crane boom angle should not exceed safe angle
Do not carry out lifting activity during high wind
conditions
Prohibit anyone walking under suspended loads
Confirm balance of load prior to lifting off ground
Do not attempt to lift / shift a load greater than SWL
Only approved anchor points to be used.
Competent and approved riggers to rig-up
equipment.
Secure / remove all loose parts / tools - machine
parts, valve, removed joints, tools, other objects
etc.
The safety clip on the hook must be correctly
closed
Use tag lines to control the lifting load
Correct slinging techniques
Ground must be inspected prior to the setting and
it shall be firm and stable.
The stability and load bearing capacity of the
ground must be sufficient to carry the most severe
static and dynamic loads.
Automatic safe load indicator, load radius indicator
and motion limit switches together with audio-
video warning systems should be in working order
All the out rigs must be extended fully and equally
on both sides.
Weight of the load must be known and check with
crane load chart for safe lifting
Ensure good signalling from rigger to the operator.
Use standard hand signals, if required.
Ensure good communication
Rigger should be worn safety vest for the
identification
Construction Of Residential Tower for
Qatar Charity (Marina 47) At Lusail District
Severity of Risk
Severity Description Rating
Minor injury First-aid on site 1
Minor injury Treatment off site 2
Up-to-3 days injury 3
Major injury Reportable 4
Death 5
Al Balagh shall utilize a matrix of severity and likelihood to assist in the evaluation process
MINOR 2 UNLIKELY 2 Action required to control the risk, interim measures may be necessary in
6 – 15 Med
MODERATE 3 OFTEN 3 the short term, able to proceed with work under supervision
MAJOR 4 LIKELY 4
This represents a low risk, although control measures must be
FATALITY 5 EXPECTED 5 1–5 Low
maintained
Construction Of Residential Tower for
Qatar Charity (Marina 47) At Lusail District
Prepared by: Rizwan Ahmad Reviewed by: Suraj Desai Approved by: Vinish Vasudevan
10
Construction Of Residential Tower for
Qatar Charity (Marina 47) At Lusail District
11
12
13
14
15
16
17
18
19
20
ITP
CONSTRUCTION OF RESIDENTIAL TOWER FOR QATAR CHARITY (MARINA 47) AT LUSAIL
INSPECTION TEST PLAN - INSTALLATION OF CURTAIN WALL, ALUMINUM DOORS, ALUMINUM COMPOSITE PANEL AND LOUVER
Action
Document Test or Inspection Verification
No. Activity Description Acceptance Criteria Frequency Record
References Method Responsibility
GALFAR ALB JCP Engr
1 Permits to work Relevant permits and licenses shall Project Submittal Approved Permits Prior to start of works Construction
Approved
be acquired Specification / Manager, H H W
Permits/Licenses
Lusail HSS
2 Method Statements & Layout Drawings Method Project Submittal Approved MS and Prior to start of works Construction
statement and layout drawings submitted and Specification Drawings Manager,
approved and Site Layout QA/QC H H H Approved Submittals
Drawings Engineer
3 HSE & QA/QC Equipment certificates valid and Project Valid HSE records Prior to start of works Construction
updated. Confirmed HSE control Specification,PQ certificates and Manager, HSE
implemented. P safety HSS and Records,Equipment
H H H
and HSE Plan induction, tool QA/QC calibration
box Engineer records
talks records
Material
5 Materials Approved Inspection Delivered Material is matching the Construction
1.Handling and Storage of materials-No damage and Material approved Material Submittal, Manager,
compliance with the specification,Rebars tagged by Submittal, Sample profiles, glass type and QA/QC
the manufaturer with certification,Storage properlyApproved color, type of finish & color of Engineer
and protected from wind blow dust,condensation Sample of frames, door and window schedule Delivery Note,
and other harmful materials 2.Material recieving profiles, of the shop drawings. Material Manufacturer's Test
Each section/Delivery H H H
inspection Finishing type & certificate shall be available. Report, Inspection
colors, Request
Approved Shop
Drawings of
Window & Door
Schedule
Curtain Wall, Aluminum door, Aluminum Composite Panel & Louver Installation Process
8 Mockup Method Inspection Material comply as per approved Construction
Statement, samples and colors and schedule. Manager,
Approved Shop Installation complies the fixing Site Engineer,
Drawings, QCS details as shown in the approved Prior to start the work QA/QC H H H Inspection Request
Sec 17 Part 1 drawing. Mock Up approval from Engineer
Client.
9 Site Readiness of openings / Check opening sizes Method Statement Inspection Compliance to Approved Construction
and Approved Drawings.Paint works shall be Manager,
Drawings, QCS completed. Openings shall be Site Engineer,
Sec 17 Part 3 square,level and plumb.Tolerance of QA/QC
5mm is Acceptable and any non- Engineer H H W/S Inspection Request
Prior to start the work
ready opening or site conditions
should be corrected.
ALB-JCP-QCT-MS-ST-016 Rev 01
1 of 3
CONSTRUCTION OF RESIDENTIAL TOWER FOR QATAR CHARITY (MARINA 47) AT LUSAIL
INSPECTION TEST PLAN - INSTALLATION OF CURTAIN WALL, ALUMINUM DOORS, ALUMINUM COMPOSITE PANEL AND LOUVER
Action
Document Test or Inspection Verification
No. Activity Description Acceptance Criteria Frequency Record
References Method Responsibility
GALFAR ALB JCP Engr
10 Installation of Aluminum, Window & Curtain Wall Method Inspection 1. Material are assigned to each Construction
Frames Statement and Opening as per Approved Door & Manager,
Approved Window Schedule. 2. Frames and Site Engineer,
Drawings, QCS brackets are to be fixed with QA/QC
Sec 17 Part 3 sufficient fastenings as shown in the Engineer
details of the approved drawings.
Use vendor supplied fasteners only.
3. All units are to be fixed square, During the work H S S Approved drawing
level and plumb without distortion. 4.
Frames shall be protected from
damage/ scratches with protection
tapes. 5. Joints between the frames
and the openings are to be sealed
by approved sealant.
11 Installation of Glass, Hardware & Accessories Method Inspection Type and color of Glass, Doors, Site Engineer,
Statement and hardware and accessories shall QA/QC
Approved comply with approved sample Engineer
Drawings, QCS provided in the material submittal.
Sec 17 Part 3 All installations, sealant and
gasketing shall be as per the detail
shown in the approved drawing. During the work H S S Approved drawing
Installed doors & hardwares should
operate freely and smoothly.
Comply with hardware schedule. No
any damage and sign of
deterioration.
12 Completed Installation of Aluminum Glass & Method Inspection Type and color of Glass, Doors, Site Engineer,
Frames for Windows,and Curtain Wall Statement and hardware and accessories shall QA/QC
Approved comply with approved sample Engineer
Drawings, QCS provided in the material submittal.
Sec 17 Part 3 Glass and frames installation shall
be plumbed and aligned. All
installations, sealant and gasketing
During the work H S S Approved drawing
shall be as per the detail shown in
the approved drawing. Installed
doors & hardwares should be fully
functional & operate freely and
smoothly. Comply with hardware
schedule. No any damage and sign
of deterioration.
ALB-JCP-QCT-MS-ST-016 Rev 01
2 of 3
CONSTRUCTION OF RESIDENTIAL TOWER FOR QATAR CHARITY (MARINA 47) AT LUSAIL
INSPECTION TEST PLAN - INSTALLATION OF CURTAIN WALL, ALUMINUM DOORS, ALUMINUM COMPOSITE PANEL AND LOUVER
Action
Document Test or Inspection Verification
No. Activity Description Acceptance Criteria Frequency Record
References Method Responsibility
GALFAR ALB JCP Engr
13 Protection from damages or deterioration until Method Statement Inspection Suitable protection to be provided to Completion of work Site Engineer,
Final Acceptance of the work and Approved avoid damages and deterioration QA/QC
Drawings, QCS until final works are completed and Engineer S
H S Approved drawing
Sec 17 Part 3 handed over to Client.
Final Inspection Method Statement Inspection Final work is to be equal to any Completion of work Site Engineer,
and Approved sample panel submitted to, and QA/QC
Drawings, QCS approved by, the Engineer Engineer H H H Inspection Request
Sec 17 Part 3
ALB-JCP-QCT-MS-ST-016 Rev 01
3 of 3
DELIVERY & STORAGE MANUAL
COOL-LITE® SKN(II) / COOL-
LITE® XTREME (II)
Processing Guidelines
Document code Date
SGG-QD-C-GUI-0018-A April/2021
2
Table of Contents
1. General .............................................................................................................................. 5
1.1. Product description ............................................................................................................. 5
1.2. Thickness, dimensions and tolerances ................................................................................ 5
1.2.1. Thickness and dimensions .......................................................................................... 5
1.2.2. Thickness recommendations ....................................................................................... 5
1.3. CE-Marking ........................................................................................................................ 5
1.4. Quality criteria .................................................................................................................... 6
1.4.1. Defect types: definitions ............................................................................................. 6
1.4.2. General observation conditions and acceptance criteria ............................................. 6
1.5. Position of the coating and identification of the coated face .............................................. 7
1.5.1. Position of the coating................................................................................................. 7
1.5.2. Identification of the coated face .................................................................................. 8
2. Transport, acceptance, storage and Handling ............................................................... 9
2.1. Transport ............................................................................................................................. 9
2.2. Receipt of the delivery ........................................................................................................ 9
2.3. Storage .............................................................................................................................. 10
2.3.1. General ...................................................................................................................... 10
2.3.2. Shelf life .................................................................................................................... 11
2.4. Handling ............................................................................................................................ 11
3. Processing of COOL-LITE® SKN (II) / COOL-LITE® Xtreme (II).......................... 12
3.1. Handling on the production lines ...................................................................................... 12
3.2. Glass cutting...................................................................................................................... 12
3.3. Edge deletion .................................................................................................................... 13
3.4. Edge working .................................................................................................................... 13
3.4.1. Manual Edge Working .............................................................................................. 14
3.4.2. Automatic Edge Working ......................................................................................... 14
3.5. Drilling .............................................................................................................................. 14
3.6. Washing ............................................................................................................................ 14
3.7. Tempering / Heat-Strengthening ....................................................................................... 16
3.7.1. General ...................................................................................................................... 16
3.7.2. Prerequisites for tempering / heat-strengthening ...................................................... 16
3.7.3. Toughening instructions............................................................................................ 16
3.8. Heat-Soak testing .............................................................................................................. 16
3
3.9. Bending ............................................................................................................................. 17
3.10. Enamelling ........................................................................................................................ 17
3.11. Handling of heat-treated glass........................................................................................... 17
3.12. Lamination ........................................................................................................................ 17
3.13. Manufacture of Insulating Glass Units ............................................................................. 18
3.14. Processing quality checks ................................................................................................. 18
4. Environment / Waste glass / Health issues ................................................................... 19
5. Glazing instructions ........................................................................................................ 19
6. Protection, cleaning and maintenance of the end products ........................................ 19
6.1. Protection of the glazing during building works ............................................................... 19
6.2. Removal of labels and markings ....................................................................................... 20
6.3. Cleaning and maintenance ................................................................................................ 20
7. Disclaimer ........................................................................................................................ 21
4
1. GENERAL
COOL-LITE® SKN and XTREME are annealed products. This means that the coated
glasses must not be tempered.
COOL-LITE® SKN II and XTREME II are “to be tempered” products. This means that the
coated glasses must be tempered to reach their nominal properties (performances and
colour). This range of product is available with the temporary protection EASYPRO®.
Please refer to dedicated processing guideline (SGG-QD-C-GUI-006) in that case.
To improve customer satisfaction, we constantly improve the quality of our coatings. This could
lead to improvement in the processability of our coating, so please make sure you have an up-to-
date version of these guidelines.
Calculations and recommendations are the same as those for conventional glass sheets
(annealed, tempered, laminated …) assembled in IGU.
Relevant national and local regulations should be complied with.
1.3. CE-Marking
5
products are available on the CE-marking section of Saint-Gobain Glass web sites and at
www.saint-gobain-glass.com/ce.
Reflection Transmission
Key:
1. Illumination source
2. Observer position
3. Coated glass sample
Figure 1: Schematics of examination procedures for coated glass (as per EN 1096-1)
“Coated glass may be examined in stock size plates or in cut sizes ready for installation. The
examination may be undertaken in the factory or on site when glazed.
The pane of coated glass being examined is viewed from a minimum distance of 3 m. The actual
distance will be dependent on the defect being considered and on which illumination source is being
6
used. The examination of the coated glass in reflection is performed by the observer looking at the
side which will be the outside of the glazing. The examination of the coated glass in transmission is
performed by the observer looking at the side which will be the inside of the glazing. During the
examination the angle between the normal to the surface of the coated glass and the light beam
proceeding to the eyes of the observer after reflection or transmission by the coated glass shall not
exceed 30°.”
7
Figure 2: Possible configurations of use of COOL-LITE® SKN (II) / COOL-LITE® XTREME
(II) In all cases, the coating must be edge deleted.
A real size mock-up, representative of the final configuration (hence mixing annealed and
tempered pieces) must be proposed to the final customer.
This mock-up should be observed and accepted by the final customer.
A report of this observation and a signed agreement should be evidenced.
Saint-Gobain Glass cannot be held responsible of colour mismatch due to the mixing of
annealed and tempered glazing on a same façade when such a mock-up validation has not
been properly performed.
8
2. TRANSPORT, ACCEPTANCE, STORAGE AND
HANDLING
2.1. Transport
Coated glass sheets are usually transported in 2.8 tonnes packs (jumbo or split sizes).
Glass sheets must be transported vertically;
The individual sheets are packed with the coated side towards the inside of the frame unless
otherwise requested by the customer;
The glass panes never come into direct contact with each other: the glass sheets are always
separated by neutral polymeric powder;
In each pack, a clear 4 mm float glass pane is placed as the first sheet during loading to
protect the coating of the first coated glass sheet;
The pack and its contents must be protected from water.
If the glass is wrapped and sealed, the seal should remain closed until the product is used
in the factory. Wrapping of the pack could depend of pile destination and condition of
transport;
During transport, violent and repeated shocks should be avoided;
When handling with a hoisting apparatus, measures must be taken not to damage the pack.
Care must be taken concerning the orientation of the coating that has been ordered. Please check
it before starting processing.
Every pack must be opened with care in order not to damage the glass sheets or the
coating(s) (contacts, scratches, etc.). Handling instructions on the packing must be
respected, particularly the instructions for opening.
Before processing, glass sheets should be checked in accordance with the specifications
defined above. Any possible defect in the coating must immediately be reported to the
supplier, accompanied by:
The date of delivery;
The data mentioned on the identification label;
9
All deliveries are identified with a label providing the following data:
Product Name
Glass Thickness
Dimensions
Number of sheets
Net weight
Date and time of production
(coating)
Bar code
Batch number
No claim can be accepted for damages caused during and/or after processing due to a lack of
adherence to these guidelines. Therefore, glass processor should ensure that the process is adapted
for coated glass and that the quality control is relevant to detect any quality problem as soon as
possible. In case of claim, samples will be required and a visit from a SGG representative may be
requested.
2.3. Storage
2.3.1. General
All glass products may degrade (become stained or corroded) when stored in humid conditions.
The iridescence may take the appearance of a "rainbow" or milky white haze on the surface of the
glass, or corrosion pitting on the coated side.
COOL-LITE® SKN(II) / COOL-LITE® XTREME (II) glass sheets must be stored, as float
glass, vertically (at 3 to 7 degrees) under the following conditions:
In a dry, well ventilated warehouse, to prevent any condensation on the surface;
Away from glass dust;
Protected from rain and running water (e.g. any roof leakage must be rectified);
Never outside or in the open air (even when packed);
Protected from wide changes in temperature and humidity levels (coated glass products
should be stored far from opening doors).
In case the coated glass is delivered packed (aluminium, PE):
Before breaking the seal, to avoid condensation, one should ensure that the temperature
of the pack has reached the temperature of the environment of the warehouse.
10
2.3.2. Shelf life
If the above (§ 2.3.1) storage conditions are respected, COOL-LITE® SKN (II) / COOL-
LITE® XTREME (II) are guaranteed, from the date of reception at the customer’s premises:
For two months if the glass is not sealed;
For six months if the glass is sealed
For twelve months in case of EasyPro® protection
Once the seal is broken (removal of the peripheral protection tape), the shelf life is
maximum 2 months (dependent upon the length of time expired since receipt - e.g. if glass
was received 5 months previously, it will only have 1 month shelf life left).
The remaining shelf life after seal breakage may also be reduced in particularly humid
countries. Contact your local TSM for more details.
The date of breaking the seal must also be noted on each pack;
A first in – first out system must be adopted;
In case the date of reception is lost by the customer, the date of the delivery note will serve
as evidence;
Once a SGG COOL-LITE SKN(II) / COOL-LITE XTREME (II) coated glass sheet is
removed from the packing, it must be processed in order to be assembled as soon as possible
into a double-glazed unit.
2.4. Handling
COOL-LITE® SKN (II) / COOL-LITE® XTREME (II) coated glass sheets must be
handled with dry, clean and appropriate safety gloves.
In case handling operations with vacuum cups on the coated side cannot be avoided, make
sure that the vacuum cups are perfectly clean. Not all solutions are suitable for cleaning
vacuum cups, see manufacturer documentation for details. A sheet of interlayer paper (acid-
free, thin, soft and air-permeable) or suitable suction-cups caps can also be placed on the
coated side, between the vacuum cups and the surface, but care must be exercised as this
may reduce the vacuum level (especially in the case of thick and heavy panes).
Each coated glass pane must be released from the next pane before being lifted from the
pack. Any relative movement of the coating with the next glass pane must be avoided.
Automatic unstacking of glass sheets or removal using a glass clamp is possible, but the
gripping area should be kept to a minimum and condemned from the cutting pattern;
In case of doubt, the position of the coating must be checked (see § 1.5.2). Do not place the
coating in contact with a rough surface or hard objects.
Do not place the glass sheet in a horizontal position with the coating in contact with the
cutting table or conveying belts, rollers...
Try to avoid wiping the coating. If necessary, the coating may be gently wiped with a soft
dry cloth and a suitable solution (e.g. isopropyl alcohol (IPA)).
11
3. PROCESSING OF COOL-LITE® SKN (II) / COOL-LITE®
XTREME (II)
3.1. Handling on the production lines
Ensure, as much as possible, that the coating does not come in contact with guide rollers on
the line; the coating must be turned towards the operator when facing the line. If it has to
go through, make sure the conveying belts are perfectly clean and free from any abrasive
material / particle;
Hoisting and handling instruments, tools and vacuum cups must be kept perfectly clean (or
covered with adapted caps) so as not to leave traces on the coating;
Wear dry and clean safety gloves when lifting the glass sheet manually. Limit area of
contact as much as possible;
The coating must be protected from any contact with greasy substances;
COOL-LITE® SKN (II) / COOL-LITE® XTREME (II) is cut in the same way as any other
ordinary coated glass. However, the following recommendations have to be respected:
Any irregularity or damage of the edges must be avoided since it is likely to increase the
risk of breakage during the toughening process;
Use only light vaporising cutting oil (for instance Acecut 5503 or 5250) adapted to coated
glass;
Do not dilute or mix the cutting oil;
Avoid all excess of cutting oil: Max width: 1 cm;
For cutting operation, avoid using natural latex coated gloves as latex tends to dissolve in
cutting oil. This leaves a greasy residue on the coating which may be difficult to wash in
the industrial washing machines. Grade 5 leather or PU palmed gloves as well as NBR
nitrile dipped gloves should be preferred;
Cutting templates can be used but great care must be taken not to scratch the coating. Glass
particle free protection (soft tissue, felt or cork pad) should be placed underneath the
template;
Fine glass splinters on the coated surface should not be wiped off by hand, but blown off
by dry and oil-free air;
When stacking cut sizes prior to further processing, separate the panes by either:
New cork pads (recommended);
Paper interlayer (chlorine free);
Foam pads;
Corrugated cardboard strips.
This is especially important with glass of different dimensions. Do not put additional separating
powder.
12
The use of so-called “harp carts” to store the cut sizes is not recommended as the contact
of the wires on the coating may damage the latter when the cut sizes are pulled from or
pushed in between the wires
In case such carts are however used: it must be ensured that the metallic wires are
well protected with plastic sleeves on their whole length. Those protections must
be totally free of glass shards;
The cut sizes must be inserted in such a way that the coating is never rubbed onto
the wires;
Such carts must not be used in case the coating is to be tempered.
COOL-LITE® SKN (II) / COOL-LITE® XTREME (II) must be edge deleted whatever the
configuration of use. Please refer to EasyPro® processing guideline (SGG-QD-C-GUI-006) to be
guided in case of EasyPro®protection.
The removal of the coating from the edge of the individual panes is absolutely essential for
all COOL-LITE® SKN(II) / COOL-LITE® XTREME (II) panes processed into double-
glazed units, to achieve secondary seal bond strength.
The width of the removed coating edge should be adjusted to the depth of the secondary
seal – the aim is to ensure that the deleted strip reaches at least the centre of the butyl bead.
This bead should not be completely on the coating. In any case the edge deletion width
must be at least 10 mm.
For COOL-LITE® SKN(II) / COOL-LITE® XTREME (II), edge deletion can be done
before or after toughening (or heat strengthening).
The coating may be removed manually or automatically. The edge deletion can be
performed with suitable grinding machines either on the cutting table, stand alone or as part
of the double-glazed unit line, operating horizontally or vertically, using a normal grinding
wheel.
For wide edge deletion, manual grinding or several passes with normal edge deletion
equipment can be done. In this case, be aware of the aesthetics of the edge deleted area.
Take care that grinding dust is sucked away to avoid scratching.
Any coating trace perpendicular to the glass edge must be totally prevented.
Check the quality of the edge deletion with a coating tester or visually by placing a sheet
of white paper behind the glass.
It is good practice to edge work the glass directly after cutting. Provided the glass is stored
under above defined conditions, the glass must be edge worked within 24 hours from cutting.
Wet edge-working: it is essential to keep the glass fully wet during the whole grinding
process and to wash the glass directly afterwards so that the grinding water is not able to
dry on the coated surface.
Dry edge-working: such processing is generally not recommended as small glass dust
particles may be sprayed on the dry coated surface. In case of use, make sure the suction is
powerful enough to avoid a too important dispersion of dust.
13
3.4.1. Manual Edge Working
Generally carried out using manual cross belts to achieve arrissed edges (100 - 120 grit belts
are recommended);
The top belt should run downwards to minimise grit deposited on the coated surface;
Horizontal roller backstops can be fitted to ensure consistent pressure and arriss width;
The glass should be handled (with glass dust free gloves) at the edges to avoid damaging
the coating.
3.5. Drilling
The drilling of coated glass can be performed provided that the handling instructions are
observed and adaptations of the machines are made (if necessary, contact your local Technical
Support Manager - TSM). For special glazing application (e.g. spider glass) the coating may have
to be placed on the conveying rollers. In such a case, it is recommended to protect the coating with
a low tack plastic film.
The coating must be edge deleted on the periphery of the holes.
3.6. Washing
It is recommended to wash the glass immediately after edge working. In case COOL-LITE®
SKN (II) / COOL-LITE® XTREME (II) is submitted to several processing steps (edge working +
drilling +…) each of them followed by washing, it is recommended to pass the cut sizes in the same
direction for each washing phase (to avoid possible generation of multiple crossed scratches).
We recommend the use of the following installation. If the washing installation differs from the
one described here, we recommend that tests be carried out to check the washing quality (traces,
rings, dust, etc.) and to ensure that the installation does not damage the coating. Please contact your
local TSM:
Pre-washing area:
Prewash ramp followed by one pair of cylindrical brushes
Tap water between 30 and 40°C, preferably close to 40°C, without any detergent
The prewash ramp is particularly important for the removal of the glass dust and
splinters created during the edge-working process
Washing area:
2 pairs of cylindrical brushes
demineralised water
pH value comprised between 6 and 8;
Rinsing area:
Demineralised water at room temperature
Maximum conductivity 20 μS/cm
pH value comprised between 6 and 8;
14
Brushes:
Flexible (soft) clean polyamide bristles
Maximum diameter of 0.2 mm, 20 - 40 mm long.
Take care that all the brushes are perfectly clean and regularly maintained. Any
hard brush must be lifted;
Compatible rotation speed with soft coatings.
Drying:
Use an air-blowing installation equipped with filters
Clean and regularly maintained filters;
Water should be sprayed directly onto the glass, not onto the brushes (as per below
drawing);
The glass sheet does not stop inside the washing machine. The washed panes should not
remain in the washing unit for any length of time, especially not while the brushes are
rotating;
No water must remain on the coated surface after the drying process;
It is strongly recommended that the washing machine is regularly cleaned, especially for
the brushes and in areas where demineralised water is used. Clean the filters every day, and
the tanks every week. For the brushes, steam cleaning gives good results, but do not spray
the bristles with high temperature and high pressure water.
In case dirt / stains are still present on the coating after the washer, cleaning may be
performed using a soft cloth and isopropanol (IPA) or ethanol followed by rapid drying,
provided this is done carefully and immediately after contamination has occurred.
For interim stacking of washed panes, use cork pads near the edge of the sheets.
15
3.7. Tempering / Heat-Strengthening
3.7.1. General
COOL-LITE® SKN II / COOL-LITE® XTREME II must always be tempered / heat-
strengthened.
The sheets are always toughened with the coated side upwards, never place the coating
against the furnace rollers
Radiation furnaces:
As COOL-LITE® SKN II / COOL-LITE® XTREME II coatings exhibit
Low-E characteristics, it is not recommended to use radiation only furnace
to temper / heat-strengthen these products;
Convection Furnaces:
Convection furnaces are recommended for the heat treatment of COOL-
LITE® SKN II / COOL-LITE® XTREME II. Contact your local TSM for
the adjustment of the appropriate settings.
Note: the high convection furnaces give much faster cycle times as well as
improved optical quality of the end-product.
Do not use SO2 in the furnace when tempering COOL-LITE® SKN II / COOL-LITE®
XTREME II. Do stop SO2 right in time. SO2 may remain in the furnace for up to 48h.
16
coating should be limited to a minimum and located at the edge deleted area so that there will be
no contact of the PTFE with the coating. Gas fired heat-Soak-Test furnaces with direct combustion
in the oven must not be used as hot fumes may damage the coating.
3.9. Bending
3.10. Enamelling
Saint-Gobain Glass cannot commit on the enamelling of any COOL-LITE® SKN II / COOL-
LITE® XTREME II product.
The capability to supply enamelled COOL-LITE® SKN II / COOL-LITE® XTREME II
glazing would be on the processor’s sole responsibility.
Exceptions:
Normative stamp is possible on the coating
Enamel on removed coating areas (edge deletion, laser…)
3.12. Lamination
17
When laminating heat treated COOL-LITE® SKN II / COOL-LITE® XTREME II take
care that the PVB thickness is adapted as to compensate the possible glass deformation
(roller wave, bow, edge lift) created during the heat-treatment process. Optimised heat
treatment recipes are recommended to limit glass deformation and avoid any defect after
the lamination process. Contact your local TSM if necessary.
In any case, the coating must be edge deleted with a minimum width of 10 mm.
It is recommended to assemble the panes in insulating glass units as quickly as possible and
within 24 hours in storage conditions as described in section 2.3.1. When manufacturing double-
glazed units using COOL-LITE® SKN (II) / COOL-LITE® XTREME (II) please follow the
handling, cutting, and washing instructions detailed above.
The coated glass must be washed before making it into insulating glass units. Recommended
washing conditions are described in § 3.6.
In case the coating has to be placed against the rollers / conveyors, make sure they are all
free of glass particles and free to rotate;
All types of secondary seal can be used (polyurethane, polysulfide, silicone and hot melt).
It is the responsibility of the processing plant to define and adjust the quality process control to
match the quality standards acceptable for its own market and in respect of relevant national
requirements.
Reception: Control of delivery document of the coated glass supplier. Visual inspection of
the packs (breakages, condensation…);
After cutting:
Visual aspect control (scratches, oxidation/corrosion, splinters etc.);
Normal control of the cutting quality;
After grinding / drilling / washing:
Visual aspect control (scratches, oxidation/corrosion, splinters etc.);
Visual control (as to whether the pane is completely dry);
Check for suction cups or cork pad marks etc…;
Normal control of the grinding / drilling quality;
Prior to toughening (or heat-strengthening):
Check for glass splinters (if present, remove them by rewashing);
Check for marks, dirt… If any remove them by gently wiping the coating with a
soft cloth and IPA;
After toughening (or heat-strengthening):
Visual aspect control (burns, cracks, scratches, oxidation/corrosion, haze…);
Optical quality (distortion, bow etc.);
Visual detection of roller wave;
Normal control of the toughening quality (break pattern etc.);
After heat-soak testing:
Visual aspect control (scratches, oxidation/corrosion, splinters etc.);
Check that no damage has been caused by separating blocks;
18
On the insulating glazing unit line:
Visual aspect control in conformity with the relevant national quality standard for
double-glazed units.
For plants just starting to use coated glass products, a system of “first off” inspection after each
process can be useful until experience is gained. Operator training and experience in identifying
faults (which are often difficult to see, especially before toughening) is important. In any case, a
visit from your local TSM should be organised.
5. GLAZING INSTRUCTIONS
The selection of a suitable and practical glazing method depends on a variety of factors such as
the size of the glass, the exposure and the type of framing material and system.
Glazing and fixing techniques must comply with the recommendations of the relevant national
standards. Glazing blocks, frame size and maximum frame deflection for double-glazed units are
not specific to COOL-LITE® SKN(II) / COOL-LITE® XTREME (II) glass products.
As for other glass products, it is important with COOL-LITE® SKN (II) / COOL-LITE®
XTREME (II) glass products to respect the following:
In order to avoid damaging the glass with aggressive contaminants from site-works (e.g.
paint, plaster, mortar…), it is recommended that glazings are installed after all other work
19
on site has been completed. In case this cannot be respected, efficient protection of the
glazing, by means of polyethylene film for instance, must be put in place;
Minimise, as far as possible, the amount of time that the glass is stored on site prior to
installation;
Follow the usual recommendations: store in a dry, well ventilated location, protected from
adverse weather conditions and variations in temperature and humidity;
Avoid splashes of concrete, plaster, mortar residues as much as possible. To prevent a
chemical attack on the glass, such substances must be removed from the glass immediately.
It is recommended that the glass is cleaned as soon as it is installed.
Glazing and fixing techniques must comply with the recommendations of the relevant
national standards. Glazing blocks, frame size and maximum frame deflection for double-
glazed units are not specific to COOL-LITE® SKN (II) / COOL-LITE® XTREME (II)
glass products glass products.
Alkaline products may be emitted from concrete, plaster, mortar... Such materials or materials
containing fluorine and acids will lead to a staining or matting of the surface. To prevent such an
occurrence, all such substances must be removed from the glass immediately. It is recommended
that the glazing is cleaned as soon as it is installed.
Cleaning means: washing, rinsing and drying the glass. A mild soap or neutral detergent can be
used, and subsequently and immediately rinsing with clear water. Excess water must be removed
quickly. Washing tools and towels must be free of abrasive particles. Never use abrasive cleaning
products or compounds likely to generate fluorine salts or hydrofluoric acid.
Grease, oil and materials used for facilitating the installation must be removed. The materials
recommended for cleaning the coating are isopropanol (IPA) or ethanol. Cleaning with the help of
solvents must be immediately followed by normal washing with water and rinsing.
The owner of the building must ensure the regular and proper maintenance of the glass. This
entails washing the windows, checking and if necessary repairing joints and frames, checking and,
if necessary, unclogging the drain and ventilation holes and detecting any anomaly.
20
7. DISCLAIMER
SAINT-GOBAIN GLASS has taken every reasonable measure to ensure that the information
contained in the present leaflet was exact at the time of its publication.
However, SAINT-GOBAIN GLASS keeps the right to modify or add any information without
previous notice. SAINT-GOBAIN GLASS is not liable for the possible lack of information on
COOL-LITE® SKN (II) / COOL-LITE® XTREME (II) products that would not be contained in
the present document.
21
SAINT GOBAIN
12 Place de l’Iris
92400 Courbevois - France
SGG Cool-Lite ST / STB / STBS
Processing Guidelines
2 March 2019
Table of Contents
1. General .............................................................................................................................. 5
1.1. Product description ............................................................................................................. 5
1.2. Thickness, dimensions and tolerances ................................................................................ 5
1.2.1. Thickness and dimensions .......................................................................................... 5
1.2.2. Thickness recommendations ....................................................................................... 5
1.3. CE-Marking ........................................................................................................................ 5
1.4. Quality criteria .................................................................................................................... 5
1.4.1. Defect types: definitions ............................................................................................. 5
1.4.2. General observation conditions and acceptance criteria ............................................. 6
1.5. Position of the coating and identification of the coated face .............................................. 7
1.5.1. Position of the coating................................................................................................. 7
1.5.2. Identification of the coated face .................................................................................. 8
2. Transport, acceptance, storage and Handling ............................................................... 9
2.1. Transport ............................................................................................................................. 9
2.2. Receipt of the delivery ........................................................................................................ 9
2.3. Storage .............................................................................................................................. 10
2.3.1. General ...................................................................................................................... 10
2.3.2. Shelf life .................................................................................................................... 11
2.4. Handling ............................................................................................................................ 11
3. Processing of SGG Cool-Lite ST/STB/ST Bright Silver ............................................. 12
3.1. Handling on the production lines ...................................................................................... 12
3.2. Glass cutting...................................................................................................................... 12
3.3. Edge deletion .................................................................................................................... 13
3.4. Edge working .................................................................................................................... 13
3.4.1. Manual Edge Working .............................................................................................. 13
3.4.2. Automatic Edge Working ......................................................................................... 13
3.5. Drilling .............................................................................................................................. 13
3.6. Washing ............................................................................................................................ 14
3.7. Tempering / Heat-Strengthening ....................................................................................... 15
3.7.1. General ...................................................................................................................... 15
3.7.2. Prerequisites for tempering / heat-strengthening ...................................................... 15
3.7.3. Toughening instructions ............................................................................................ 15
3.8. Heat-Soak testing .............................................................................................................. 16
3 March 2019
3.9. Bending ............................................................................................................................. 16
3.10. Enamelling ........................................................................................................................ 16
3.11. Handling of heat-treated glass........................................................................................... 17
3.12. Lamination ........................................................................................................................ 18
3.13. Manufacture of Insulating Glass Units ............................................................................. 18
3.14. Processing quality checks ................................................................................................. 18
4. Environment / Waste glass / Health issues ................................................................... 20
5. Glazing instructions ........................................................................................................ 20
6. Protection, cleaning and maintenance of the end products ........................................ 20
6.1. Protection of the glazing during building works ............................................................... 20
6.2. Removal of labels and markings ....................................................................................... 21
6.3. Cleaning and maintenance ................................................................................................ 21
7. Disclaimer ........................................................................................................................ 21
4 March 2019
1. GENERAL
1.1. Product description
1.3. CE-Marking
5 March 2019
Punctual defects: punctual disturbance of the visual transparency looking through the
glass and of the visual reflectance looking at the glass. Spots, pinholes and scratches are
types of punctual defects;
o Spot: defect that commonly looks dark against the surrounding coating, when
viewed in transmission;
o Pinhole: punctual void in the coating with partial or total absence of the coating.
Normally contrasts clear relative to the coating, when viewed in transmission.
o Scratches: variety of linear score marks, whose visibility depend on their length,
depth, width, position and arrangements;
Cluster: accumulation of very small defects giving the impression of stain.
Reflection Transmission
Key:
1. Illumination source
2. Observer position
3. Coated glass sample
Figure 1: Schematics of examination procedures for coated glass (as per EN 1096-1)
6 March 2019
1.5. Position of the coating and identification of the coated face
» Monolithic glass
SGG Cool-Lite ST / STB / STBS are class B product (as per EN 1096-1 definition). This
means that the coating must always be placed towards the inside of the building.
In the case of monolithic use in non-opacified spandrels, one has to ensure that an efficient
system of draining or ventilation (in case of prefabricated panels) is foreseen to avoid
accumulation of water or condensation to occur on the coated side. Direct contact of corrosive
materials on the coating, or materials likely to emit corrosive vapours with the action of heat
(acids, ammonia, mortar water, acetic-curing silicones, among others) is prohibited.
7 March 2019
» Laminated glass
SGG Cool-Lite ST / STB / STBS can be placed inside (against the PVB) or outside the
laminate. However, the final rendering will not be the same according to the position of the
coating. It should then be ensured that the chosen position of the coating will remain the same
throughout a same project to ensure colour consistency. In any case, the coating must be placed in
face 2 or 4 of the laminate (never in face 3). The list of validated interlayers is given in document
SGG-TI-01 which can be obtained on request from your local sales service.
Important notice for lamination of SGG Cool-Lite ST / STB / STBS against the PVB:
Saint-Gobain Glass, as the coating glass supplier, cannot ensure that the adhesion of the
assembly made by the laminated glass manufacturer will comply with any desired level of safety.
It is thus the laminated glass manufacturer’s sole responsibility to check that the adhesion of the
assembly is compliant with the level required by the final intended use of the product.
A real size mock-up, representative of the final configuration (hence mixing annealed and
tempered pieces) must be proposed to the final customer.
This mock-up should be observed and accepted by the final customer.
A report of this observation and a signed agreement should be evidenced.
Saint-Gobain Glass cannot be held responsible of colour mismatch due to the mixing of
annealed and tempered glazing on a same façade when such a mock-up validation has not been
properly performed.
8 March 2019
2. TRANSPORT, ACCEPTANCE, STORAGE AND
HANDLING
2.1. Transport
Coated glass sheets are usually transported in 2.8 tonnes packs (jumbo or split sizes).
Glass sheets must be transported vertically;
The individual sheets are packed with the coated side towards the inside of the frame
unless otherwise requested by the customer;
The glass panes never come into direct contact with each other: the glass sheets are
always separated by neutral polymeric powder;
In each pack, a clear 4 mm float glass pane is placed as the first sheet during loading to
protect the coating of the first coated glass sheet;
The pack and its contents must be protected from water.
If the glass is wrapped and sealed, the seal should remain closed until the product is used
in the factory;
During transport, violent and repeated shocks should be avoided;
When handling with a hoisting apparatus, measures must be taken not to damage the
pack.
Care must be taken concerning the orientation of the coating that has been ordered. Please
check it before starting processing.
Every pack must be opened with care in order not to damage the glass sheets or the
coating(s) (contacts, scratches, etc.). Handling instructions on the packing must be
respected, particularly the instructions for opening.
Before processing, glass sheets should be checked in accordance with the specifications
defined above. Any possible defect in the coating must immediately be reported to the
supplier, accompanied by:
The date of delivery;
The data mentioned on the identification label;
9 March 2019
All deliveries are identified with a label providing the following data:
Product Name
Glass Thickness
Dimensions
Number of sheets
Net weight
Date and time of production
(coating)
Bar code
Batch number
CE marking (Coating)
Cover sheet
Traceability
No claim can be accepted for damages caused during and after processing due to a lack of
adherence to these guidelines. Therefore glass processor should ensure that the process is adapted
for coated glass and that the quality control is relevant to detect any quality problem as soon as
possible. In case of claim, samples will be required and a visit from a SGG representative may be
requested.
2.3. Storage
2.3.1. General
All glass products may degrade (become stained or corroded) when stored in humid
conditions. The iridescence may take the appearance of a "rainbow" or milky white haze on the
surface of the glass, or corrosion pitting on the coated side.
Cool-Lite ST / STB / STBS glass sheets must be stored, as float glass, vertically (at 3 to 7
SGG
degrees) under the following conditions:
In a dry, well ventilated warehouse, to prevent any condensation on the surface;
Away from glass dust;
Protected from rain and running water (e.g. any roof leakage must be rectified);
Never outside or in the open air (even when packed);
Protected from wide changes in temperature and humidity levels (coated glass products
should be stored far from opening doors).
In case the coated glass is delivered packed (aluminium, PE):
Before breaking the seal, to avoid condensation, one should ensure that the
temperature of the pack has reached the temperature of the environment of the
warehouse.
10 March 2019
2.3.2. Shelf life
If the above (§ 2.3.1) storage conditions are respected, SGG Cool-Lite ST / STB / STBS
is guaranteed for 2 years from the date of reception at the customer’s premises. In case the
date of reception is lost by the customer, the date of the delivery note will serve as evidence.
2.4. Handling
SGG Cool-Lite ST / STB / STBS coated glass sheets must be handled with dry, clean and
appropriate safety gloves.
In case handling operations with vacuum cups on the coated side cannot be avoided, make
sure that the vacuum cups are perfectly clean. Not all solutions are suitable for cleaning
vacuum cups, see manufacturer documentation for details. A sheet of interlayer paper
(acid-free, thin, soft and air-permeable) or suitable suction-cups caps can also be placed
on the coated side, between the vacuum cups and the surface, but care must be exercised
as this may reduce the vacuum level (especially in the case of thick and heavy panes).
Each coated glass pane must be released from the next pane before being lifted from the
pack. Any relative movement of the coating with the next glass pane must be avoided.
Automatic unstacking of glass sheets or removal using a glass clamp is possible, but the
gripping area should be kept to a minimum and condemned from the cutting pattern;
In case of doubt, the position of the coating must be checked (see § 1.5.2). Do not place
the coating in contact with a rough surface or hard objects.
Try to avoid wiping the coating. If necessary, the coating may be gently wiped with a soft
dry cloth and a suitable solution (e.g. isopropyl alcohol (IPA)).
11 March 2019
3. PROCESSING OF SGG COOL-LITE ST/STB/ST BRIGHT
SILVER
3.1. Handling on the production lines
Ensure, as much as possible, that the coating does not come in contact with guide rollers
on the line; the coating must be turned towards the operator when facing the line. If it has
to go through, make sure the conveying belts are perfectly clean and free from any
abrasive material / particle;
Hoisting and handling instruments, tools and vacuum cups must be kept perfectly clean
(or covered with adapted caps) so as not to leave traces on the coating;
Wear dry and clean safety gloves when lifting the glass sheet manually. Limit area of
contact as much as possible;
The coating must be protected from any contact with greasy substances;
SGG Cool-Lite ST / STB / STBS is cut in the same way as any other ordinary coated glass.
However, the following recommendations have to be respected:
Any irregularity or damage of the edges must be avoided since it is likely to increase the
risk of breakage during the toughening process;
Use only light vaporising cutting oil (for instance Acecut 5503 or 5250) adapted to
coated glass;
Do not dilute or mix the cutting oil;
Avoid all excess of cutting oil: Max width : 1 cm;
For cutting operation, avoid using natural latex coated gloves as latex tends to dissolve in
cutting oil. This leaves a greasy residue on the coating which may be difficult to wash in
the industrial washing machines. Grade 5 leather or PU palmed gloves as well as NBR
nitrile dipped gloves should be preferred;
Cutting templates can be used but great care must be taken not to scratch the coating. Soft
protection (soft tissue, felt or cork pad) should be placed underneath the template;
Fine glass splinters on the coated surface should not be wiped off by hand, but blown off
by dry and oil-free air;
When stacking cut sizes prior to further processing, separate the panes by either:
New cork pads (recommended);
Paper interlayer (chlorine free);
Foam pads;
Corrugated cardboard strips.
This is especially important with glass of different dimensions. Do not put additional
separating powder.
12 March 2019
The use of so-called “harp carts” to store the cut sizes is not recommended as the contact
of the wires on the coating may damage the latter when the cut sizes are pulled from or
pushed in between the wires
In case such carts are however used: it must be ensured that the metallic wires are
well protected with plastic sleeves on their whole length. Those protections must
be totally free of glass shards;
The cut sizes must be inserted in such a way that the coating is never rubbed onto
the wires;
Such carts must not be used in case the coating is to be tempered.
SGG Cool-Lite ST / STB / STBS do not need to be edge deleted whatever the configuration of
use.
It is good practice to edge work the glass directly after cutting. Provided the glass is stored
under above defined conditions, the glass must be edge worked within 5 days from cutting.
Wet edge-working: it is essential to keep the glass fully wet during the whole grinding
process and to wash the glass directly afterwards so that the grinding water is not able to
dry on the coated surface.
Dry edge-working: such processing is generally not recommended as small glass dust
particles may be sprayed on the dry coated surface. In case of use, make sure the suction
is powerful enough to avoid a too important dispersion of dust.
3.5. Drilling
The drilling of coated glass can be performed provided that the handling instructions are
observed and adaptations of the machines are made (if necessary, contact your local Technical
Support Manager - TSM). For special glazing application (e.g. spider glass) the coating may have
to be placed on the conveying rollers. In such a case, it is recommended to protect the coating
with a low tack plastic film.
13 March 2019
3.6. Washing
It is recommended to wash the glass immediately after edge working. In case SGG Cool-
Lite ST / STB / STBS is submitted to several processing steps (edge working + drilling +…) each
of them followed by washing, it is recommended to pass the cut sizes in the same direction for
each washing phase (to avoid possible generation of multiple crossed scratches).
We recommend the use of the following installation. If the washing installation differs from
the one described here, we recommend that tests be carried out to check the washing quality
(traces, rings, dust, etc.) and to ensure that the installation does not damage the coating. Please
contact your local TSM:
Pre-washing area:
Prewash ramp followed by one pair of cylindrical brushes
Tap water between 30 and 40°C, preferably close to 40°C, without any detergent
The prewash ramp is particularly important for the removal of the glass dust and
splinters created during the edge-working process
Washing area:
2 pairs of cylindrical brushes
demineralised water
pH value comprised between 6 and 8;
Rinsing area:
Demineralised water at room temperature
Maximum conductivity 20 μS/cm
pH value comprised between 6 and 8;
Brushes:
Flexible (soft) clean polyamide bristles
Maximum diameter of 0.2 mm, 20 - 40 mm long.
Take care that all the brushes are perfectly clean and regularly maintained. Any
hard brushes must be lifted;
Drying:
Use an air-blowing installation equipped with filters
Clean and regularly maintained filters;
Water should be sprayed directly onto the glass, not onto the brushes (as per below
drawing;
The glass sheet does not stop inside the washing machine. The washed panes should not
remain in the washing unit for any length of time, especially not while the brushes are
rotating;
No water must remain on the coated surface after the drying process;
14 March 2019
It is strongly recommended that the washing machine is regularly cleaned, especially for
the brushes and in areas where demineralised water is used. Clean the filters every day,
and the tanks every week. For the brushes, steam cleaning gives good results, but do not
spray the bristles with high temperature and high pressure water.
In case dirt / stains are still present on the coating after the washer, cleaning may be
performed using a soft cloth and isopropanol (IPA) or ethanol followed by rapid drying,
provided this is done carefully and immediately after contamination has occurred.
For interim stacking of washed panes, use cork pads near the edge of the sheets.
In case, in a further step, SGG Cool-Lite ST / STB / STBS will be tempered, it is of the highest
importance that no residues or marks are left on the coating surface after the exit of the pre-
processing washing machine. Pollutions left on the coating may induce hot corrosion (giving the
aspect of pinholes) of the coating in the tempering furnace. Such marks may not be washable.
3.7.1. General
SGG Cool-Lite ST / STB / STBS can be heat-treated to get a tempered / heat-strengthened
coated glass.
The sheets are always toughened with the coated side upwards, never place the coating
against the furnace rollers;
The functional layers giving their properties to SGG ST / STB / ST Bright Silver bring
some low emissive characteristics to the product. Even though not comparable to Low-E
used for energy efficient glazing (e.g. PLT, Cool-Lite), this low-emissivity characteristic
is to be taken into consideration when tempering SGG Cool-Lite ST/STB/STBS. This is
especially true for Cool-Lite ST 108.
15 March 2019
Radiation furnaces:
Cool-Lite ST 150, 167 and St Bright Silver can be tempered in such
furnaces without restriction
ST/STB 120 and 136 showing a low-e characteristics a bit more
pronounced, reaching a good final quality will be obtained to the expense
of cycle time;
It is not possible to temper Cool-Lite ST 108 in a radiative furnace;
In any case, your local TSM should be contacted to set-up the appropriate
settings;
Convection Furnaces:
Convection furnaces are recommended for the heat treatment of Cool-
Lite ST / STB / STBS. Contact your local TSM for the adjustment of the
appropriate settings.
Note: the high convection furnaces give much faster cycle times as well
as improved optical quality of the end-product.
Do not use SO2 in the furnace when tempering SGG Cool-Lite ST / STB / STBS. Do stop
SO2 right in time. SO2 may remain in the furnace for up to 48h.
Heat-soaking toughened SGG Cool-Lite ST / STB / STBS cut sizes must be carried out in
accordance with EN 14179 European standard. Every piece must be individually separated; the
separating blocks may be made out of PTFC (e.g. Teflon) and contact with the coating should be
limited to a minimum and located at the extreme edge of the glass. Gas fired heat-Soak-Test
furnaces with direct combustion in the oven must not be used as hot fumes may damage the
coating.
3.9. Bending
3.10. Enamelling
SGG Cool-Lite ST / STB / STBS may be fully or partially enamelled using different techniques
(roller-coater, spray or screen-printing for instance). Given the variety of enamelling products,
different operations and practical experiences, each processor should carry out tests with its own
equipment. It is recommended that any offer for the possible supply of enameled Cool-Lite
ST/STB/STBS be subject to previous acceptance by the client of samples produced in the
operation concerned.
16 March 2019
General features:
Enamel pastes to be used on Cool-Lite ST are from Ferro supplier and only from
the Ferro 140 serie for face 2 applications1
The viscosity of the paste has to be adjusted according to the printing process
(roller, spray, or screen-printing). For roller-coater, the paste should flow in
between 60 - 120 seconds at working temperature, measured with 6mm cup2;
The coated Cool-Lite ST glass has to be properly cleaned before enamel printing;
Wet thickness of the enamel deposited by roller, spray or screen-printing has to
be ≥ 40µm3;
After firing / tempering the enamel should not be porous, liquid dropped on the
enamel side must not soak through the layer and be visible on glass side4;
After firing / tempering the enamel has to reach a gloss value ≥ 15 GU5;
After firing / tempering the enamel has to reach a scratch resistance of 20N6;
After firing / tempering of different batch of the enamel on the same ST, the
enamelled glass colour has to reach a DeltaE ≤ 1,57.
Specific cases:
Cool-Lite ST 108: Fine tuning of the tempering parameters may be needed to
enamel Cool-Lite ST 108. A slight residual haze may however remain even with
the best settings;
Cool-Lite STB: For full surface opacification (especially with dark enamels), care
must be taken to keep the glass flat during the heating process to avoid cracking
of the coating
Cool-Lite ST Bright Silver: Cool-Lite STBS may be fully enamelled with clear
colours (white, light grey,…). For darker colours only partial patterned
enamelling is possible. For dark colour, a maximum of 2/3 of the surface
(patterned) may be enamelled. It is highly recommended to perform real size
samples before any order validation.
1
Ferro Technical Information Flat Glass System 140 – accessed April 2018
2
Viscometer measurement - ISO 3219 / DIN 53018 or Ford cup measurement - ISO 2431:2011 /
ASTM D1200
Ferro Technical Information Flat Glass System 140 - Methods of use & recommendations 4.
Screen-Printing p22/ 5. Roller-coating p23/ 6. Spraying p24– accessed April 2018
3
Roller gauge measurement - ISO 2808:2007 / ASTM D1212
4
Ferro Technical Information Flat Glass System 140 - Methods of use & recommendations
9. p26 – accessed April 2018
5
Gloss measurement - ISO 2813 :2014
6
Scratch resistance measurement - ISO 1518-2 :2011
7
Color measurement based on CIE-L*ab (SCE) colour space - CIE 15.3:2004
17 March 2019
– stretch – foam film (in that case, particular care should be taken when stacking different glass
dimensions).
Glass panes must be stored vertically (at 3 to 7 degrees) under the following conditions:
In a dry, well ventilated store, to prevent any condensation on the surface;
Protected from rain and running water (any roof leaks must be rectified);
Never outside or in the open air;
Protected from wide changes in temperature and humidity levels (store coated
glass products far from opening doors).
Clean, dry and soft gloves must be worn for all handling.
In case SGG Cool-Lite ST / STB / STBS is assembled into double-glazed units, this should
be performed in 2 days.
3.12. Lamination
SGG Cool-Lite ST / STB / STBS can be laminated with the coating placed inside (against
the PVB) or outside the laminate. However, the final rendering will not be the same
according to the position of the coating. It should then be ensured that the chosen position
of the coating will remain the same throughout a same project to ensure colour
consistency. In any case, the coating must be placed in face 2 or 4 of the laminate (never
in face 3). The list of validated interlayers is given in document SGG-TI-01 which can be
obtained on request from your local sales service or TSM.
To assemble the glass, ensure that the calendaring rollers are in good condition (clean and
no particles of glass). Check that the circumferential speed is regular and corresponds to
that of the conveyor system. Clean off all deposits of PVB in contact with the coating
before placing in the furnaces or autoclaves.
When laminating heat treated SGG Cool-Lite ST / STB / STBS take care that the PVB
thickness is adapted as to compensate the possible glass deformation (roller wave, bow,
edge lift) created during the heat-treatment process. Contact your local TSM if necessary.
It is the responsibility of the processing plant to define and adjust the quality process control
to match the quality standards acceptable for its own market and in respect of relevant national
requirements.
18 March 2019
Reception: Control of delivery document of the coated glass supplier. Visual inspection
of the packs (breakages, condensation…);
After cutting:
Visual aspect control (scratches, oxidation/corrosion, splinters etc.);
Normal control of the cutting quality;
After grinding / drilling / washing:
Visual aspect control (scratches, oxidation/corrosion, splinters etc.);
Visual control (as to whether the pane is completely dry);
Check for suction cups or cork pad marks etc…;
Normal control of the grinding / drilling quality;
Prior to toughening (or heat-strengthening):
Check for glass splinters (if present, remove them by rewashing);
Check for marks, dirt… If any remove them by gently wiping the coating with a
soft cloth and IPA;
After toughening (or heat-strengthening):
Visual aspect control (burns, cracks, scratches, oxidation/corrosion, haze…);
Optical quality (distortion, bow etc.);
Visual detection of roller wave;
Normal control of the toughening quality (break pattern etc.);
After heat-soak testing:
Visual aspect control (scratches, oxidation/corrosion, splinters etc.);
Check that no damage has been caused by separating blocks;
On the insulating glazing unit line:
Visual aspect control in conformity with the relevant national quality standard for
double-glazed units.
For plants just starting to use coated glass products, a system of “first off” inspection after
each process can be useful until experience is gained. Operator training and experience in
identifying faults (which are often difficult to see, especially before toughening) is important. In
any case, a visit from your local TSM should be organised.
19 March 2019
4. ENVIRONMENT / WASTE GLASS / HEALTH ISSUES
SGG Cool-Lite ST / STB / STBS coated glass product can be disposed of as per clear float
glass.
Edge working residues have to be continuously and completely collected during the grinding
process. These residues must be further treated in compliance with national legislation about
industrial wastes. In some legislation, residues from grinding process have to be treated as toxic
wastes.
As for any dust coming from the grinding process, any inhalation or skin contact of these
residues must be avoided.
On request, a Safety Use Instruction Sheet (SUIS) relating to the ECDirective 91/155/EEC
can be supplied.
5. GLAZING INSTRUCTIONS
The selection of a suitable and practical glazing method depends on a variety of factors such
as the size of the glass, the exposure and the type of framing material and system.
Glazing and fixing techniques must comply with the recommendations of the relevant
national standards. Glazing blocks, frame size and maximum frame deflection for double-glazed
units are not specific to SGG Cool-Lite ST / STB / STBS glass products.
As for other glass products, it is important with SGG Cool-Lite ST / STB / STBS glass
products to respect the following:
In order to avoid damaging the glass with aggressive contaminants from site-works (e.g.
paint, plaster, mortar…), it is recommended that glazings are installed after all other work
on site has been completed. In case this cannot be respected, efficient protection of the
glazing, by means of polyethylene film for instance, must be put in place;
Minimise, as far as possible, the amount of time that the glass is stored on site prior to
installation;
Follow the usual recommendations: store in a dry, well ventilated location, protected from
adverse weather conditions and variations in temperature and humidity;
Avoid splashes of concrete, plaster, mortar residues as much as possible. To prevent a
chemical attack on the glass, such substances must be removed from the glass
immediately. It is recommended that the glass is cleaned as soon as it is installed.
20 March 2019
Glazing and fixing techniques must comply with the recommendations of the relevant
national standards. Glazing blocks, frame size and maximum frame deflection for double-
glazed units are not specific to SGG Cool-Lite ST / STB / STBS glass products glass
products.
Alkaline products may be emitted from concrete, plaster, mortar... Such materials or materials
containing fluorine and acids will lead to a staining or matting of the surface. To prevent such an
occurrence, all such substances must be removed from the glass immediately. It is recommended
that the glazing is cleaned as soon as it is installed.
Cleaning means: washing, rinsing and drying the glass. A mild soap or neutral detergent can
be used, and subsequently and immediately rinsing with clear water. Excess water must be
removed quickly. Washing tools and towels must be free of abrasive particles. Never use abrasive
cleaning products or compounds likely to generate fluorine salts or hydrofluoric acid.
Grease, oil and materials used for facilitating the installation must be removed. The materials
recommended for cleaning the coating are isopropanol (IPA) or ethanol. Cleaning with the help of
solvents must be immediately followed by normal washing with water and rinsing.
The owner of the building must ensure the regular and proper maintenance of the glass. This
entails washing the windows, checking and if necessary repairing joints and frames, checking and,
if necessary, unclogging the drain and ventilation holes and detecting any anomaly.
7. DISCLAIMER
SAINT-GOBAIN GLASS has taken every reasonable measure to ensure that the information
contained in the present leaflet was exact at the time of its publication.
However, SAINT-GOBAIN GLASS keeps the right to modify or add any information
without previous notice. SAINT-GOBAIN GLASS is not liable for the possible lack of
information on SGG Cool-Lite ST / STB / STBS products that would not be contained in the
present document.
21 March 2019
SAINT GOBAIN
Les Miroirs
18, avenue d’Alsace
92096 la Défense Cedex - France
ALUMINUM COMPOSITE PANEL
Delivery, Fabrication,
Handling and Storage
FR
ALUCOPANEL® FR Delivery, Fabrication,
Delivery, HandlingHandling
Fabrication, and Storage
and Storage
Product Description
ALUCOPANEL® FR is composed of two sheets of aluminum alloy 3000 Series with 0.50 mm thickness
Product Description
on Top (Choice of Coating ranging from PVDF 2-coat & 3-coat and HDPE 2-coat & 3-coat which are high
ALUCOPANEL®
quality paint comes inFR is composed
various ofastwo
finishes such sheets
Solid Colorsof aluminum
& Metallic alloy
colors) 3000 Series
& Bottom (primerwith
coated)
that
0.50is mm
sandwiched with on
thickness mineral
Top filled flameof
(Choice retardant
Coatingingredients as core
ranging from material,
PVDF hence
2-coat ALUCOPANEL®
& 3-coat and
FR have achieved “Class A” in accordance to ASTM E84, “Class B-s1, d0” when tested in accordance to
HDPE 2-coat & 3-coat which are high quality paint comes in various finishes such as
EN 13501-1, which are mandatory requirements of relevant internationally acceptable standards and is
Solidsuitable
best Colorsfor&external
Metallicand
colors) & Bottom
internal uses. (primer coated) that is sandwiched with mineral
filled flame retardant ingredients as core material, hence ALUCOPANEL® FR have
Core of the
achieved “ ALUCOPANEL®
Class A” in accFR are mainly
ordance composed
to ASTM E84, “ of mineral which
Class can resist
B-s1, fire, however
d0” when tested in a small
amount of Polyethylene also included. Main ingredient (minerals) does not permit the propagation of flame
accordance to EN 13501-1, which are mandatory requirements of relevant
and restricts development of smoke.
internationally acceptable standards and is best suitable for external and internal uses.
The core material formed in a continuous co-extrusion process with high molecular adhesives. The core
material
Core ofisthe
freeALUCOPANEL®
of voids and air spaces
FR areand does not
mainly contain foamed insulation materials.
composed
of mineral which can resist fire, however a small
THICKNESS WEIGHT:
amount of
4 mm 7.8 to 8.0 Kgs/m²,
6Polyethylene
mm also included.
10.5Main ingredient
to 11.0 Kgs/m²(minerals)
does not permit the propagation of flame and restricts
development of smoke.
Minimum investment
Fabrication
Simple operating technique
ALUCOPANEL® FR can be shaped by means of a simple processing technique. This
Folding need not be done in the workshop, it can be done on site; this means low transport costs
procedure, the routing and folding technique, enables a production of folded elements in
different
Low-costshapes and sizes.
manufacture of shaped parts like façade elements, frames, fascia claddings and roof edgings,
V-shaped
corner piecesor and
rectangular
many moregrooves are routed on the rear of the ALUCOPANEL® FR using disk or
are possible
end milling cutters, whereby the aluminum cover sheet at the front and part of the FR core are
retained. The small -thickness
Versatile formability of the remaining material then allows folding by hand. A brake
Good economy
press is not required. The shape of the groove determines the edge radius. The grooves can be
Shapes are
produced notarestricted
with saw with by machine
routing dimensions.
device, on a CNC machining centre, Routed / folded elements
with a routing machine or a hand routing machine. The routing and folding technique can be
Tension-free
used folding, therefore
for ALUCOPANEL® noall
FR of buckling in the
standard corner area and thus even elements.
surfaces.
Advantages
Upon arrival of your order, inventory and inspect each ALUCOPANEL® FR and note any
damage to ALUCOPANEL® FR packaging. If there are any signs of damage, note the bill of
lading at the time of delivery. Failure to do so can make it difficult to file a freight claim. Send a
list of damaged materials to Alucopanel Middle East LLC representative for further instructions.
It is crucial that damaged ALUCOPANEL® FR be reported to Alucopanel Middle East LLC as
soon as they are discovered.
ALUCOPANEL® FR should be transported using Alucopanel Middle East LLC standard pallets.
Bailing bands are to be removed upon delivery. Lift ALUCOPANEL® FR from each stacks
individually, taking care not to scratch or damage any adjacent ALUCOPANEL® FR when
removing ALUCOPANEL® FR from the stack.
Bad Lifting Manner FR needs to be stored in an area that is well covered from the elements, cool,
ALUCOPANEL®
ventilated, and dry.
Safety Precautions:
1. Wear proper Personal Protective Equipment (PPE) – Gloves, safety shoes, hard hat and etc.
2. Limit weight you lift to no more than 50 pounds (22.6796kg). When lifting loads heavier than 50 pounds
(22.6796kg). Use two or more people to lift the ACP Sheet.
Handling and Storage
Delivery, Fabrication, Handling and Storage
Upon arrival of your order, inventory and inspect each ALUCOPANEL® FR and note any damage to
ALUCOPANEL®
Pallet FR packaging.
Stacking Standard should If there are any
be follow assigns of damage,
per the notebelow
illustration the bill of lading at the time of delivery.
ALUCOPANEL® FR:make
Failure to do so can Maximum 3 Pallets
it difficult to file aper Stack
freight (2.5tons/pallet)
claim. Send a list of damaged materials to Alucopanel
Middle East LLC representative for further instructions. It is crucial that damaged ALUCOPANEL® FR be
ALUCOPANEL® FR should be transported using Alucopanel Middle East LLC standard pallets. Bailing bands
are to be removed upon delivery. Lift ALUCOPANEL® FR from each stacks individually, taking care not to
scratch or damage any adjacent ALUCOPANEL® FR when removing ALUCOPANEL® FR from the stack.
ALUCOPANEL® FR needs to be stored in an area that is well covered from the elements, cool, ventilated,
and dry.
Pallet Stacking Standard shouldDelivery,
be Delivery,
Fabrication,
follow as Fabrication,
per Handling
Handling
the illustration below andand
Storage
Storage
ALUCOPANEL® FR: Maximum 3 Pallets per Stack (2.5tons/pallet = 4 x 1250 x 4000mm(60sheets)
Pallet
Pallet
Stacking
Stacking
Standard
Standard
should
should
be follow
be follow
as per
as per
the the
illustration
illustration
below
below
ALUCOPANEL®
ALUCOPANEL® FR:FR:
Maximum
Maximum
3 Pallets
3 Pallets
per per
Stack
Stack
(2.5tons/pallet)
(2.5tons/pallet)
Alucopanel Middle East LLC recommended to stack the Fabricated ALUCOPANEL® FR in a Vertical manner
specifically during the delivery of the ALUCOPANEL® FR on the construction site in able to reduce the
can be stacked for about 5 to 6 hours for the application of stiffeners, afterwards it must be stored and
transported vertically.
For Adhesive Residue, such as those caused by Protective film, sealant and caulking compounds, a mild
solvent such as IPA (Isopropyl Alcohol), n-Hexane or Ethanol 46.7% can be used. It is recommended to
start the cleaning from the top of the building, as opposed to the bottom of the building, so as to avoid any
rundown and streaking of the water and cleaning agents on the ALUCOPANEL® FR that have already been
cleaned. After the soil and dirt has been removed, ALUCOPANEL® FR must immediately be rinsed with
DoWARNING:
not use any strong organic solvents or cleaning agents under any circumstances, such as MEK (Me-
thylDo
Ethyl
notKetone),
use anyMIBK (Methyl
strong Iso Butyl
organic Ketone),
solvents Triclene, agents
or cleaning Paint Thinner,
under household detergents,such
any circumstances, cleaning
as
MEK strong
agents, (Methylalkali
Ethylor Ketone), MIBK
strong acid (Methyl
based Isoagents
cleaning Butyl Ketone),
containingTriclene, Paint Thinner,
sodium carbonate, household
caustic soda, po-
detergents,
tassium cleaning
hydroxide agents,
or similar, or any strong alkaliabrasive
such strong or strong acid based
and lacquer cleaning
dissolving agents.agents containing
All cleaning agents
sodium
must have acarbonate,
neutral PHcaustic soda,
of 5-10% only.potassium
The use of hydroxide or similar,
abrasive cloths, or damage
pads will any such
thestrong abrasive
surface coating
and lacquer dissolving agents. All cleaning agents must have a neutral PH of 5-10% only. The
of the ALUCOPANEL® FR. While using any cleaning agents, caution should be taken at all times. It should
use of abrasive cloths, pads will damage the surface coating of the ALUCOPANEL® FR. While
be noted that many cleaning agents may be inflammable and dangerous; hence it is important to avoid any
using any cleaning agents, caution should be taken at all times. It should be noted that many
contact with fire or the use of lighters or the permitting of smoking around any cleaning agents. It should
cleaning agents may be inflammable and dangerous; hence it is important to avoid any contact
also be ensured that cleaning site is always adequately ventilated to prevent any
with fire or the use of lighters or the permitting of smoking around any cleaning agents. It should
Explosions and inhalation, as vapors from such cleaning agents can build up in the cleaning site.
also be ensured that cleaning site is always adequately ventilated to prevent any
All cleaning materials must be disposed of properly. The company shall bear no liability whatsoever for non-
Explosions and inhalation, as vapors from such cleaning agents can build up in the cleaning
compliance with the warnings stated above and for the noncompliance with the local work safety laws and
site.
regulations in the respective countries by any parties whatsoever.
All cleaning materials must be disposed of properly. The company shall bear no liability
whatsoever for noncompliance with the warnings stated above and for the noncompliance with
THANK YOU
the local work safety laws and regulations in the respective countries by any parties whatsoever.
THANK YOU
DRAWINGS
MARINA - MIX 046
N:2310213792
E:4036156698
MARINA - COM 045
A
7
5863
N:2309657504
E:4035971290
M L K J I H G F E D 02 C B A 12 11
MARINA - MIX 048
7073
6
MARINA - COM 047
4148 m²
ROA
7073
6
D
B
N:2310437455
C 7 E:4035485632
5863
AD
RO
N:2309881168
E:4035300224
N
W E
+17.25
RF FFL.
SITE LOCATION PLAN
+13.65
3rd FFL. GRE
EN
EN
GRE
KEY PLAN
NOTES :
02
ACTION
ACP CLADDING 01 Elevation
01 SCALE 1:100 ACP CLADDING 01 Section A NO OBJECTION
02 SCALE 1:100 NO OBJECTION SUBJECT TO INCORPORATION OF ALL
B COMMENTS AS NOTED.
C REJECTED, TO BE RESUBMITTED
Eng'r. R.E.
Date: Date:
M L K J I H G F E D C B A
SHOP DRAWING
IFC DRAWING REFERENCE NO.:
DN
SHOPDRAWING REVISIONS:
QATAR CHARITY
Tel: 974 - 44667711
L Fax: 974 - 44667733
QATAR CHARITY
LUSAIL MARINA COM 47
ACP CLADDING 01
ELEVATION, PLAN & SECTION
AS SHOWN @ A1 - ALB-JCP-QCT-GAEC-SD-AR-400
FG GR - 2
12 11 10 9 8 7 6 5 4 3 2 1 A
02
MARINA - MIX 046
N:2310213792
E:4036156698
MARINA - COM 045
A
7
5863
N:2309657504
E:4035971290
D
02
MARINA - MIX 048
7073
6
MARINA - COM 047
4148 m²
RO
7073
AD
6
B
N:2310437455
C 7 E:4035485632
5863
D
ROA
N:2309881168
E:4035300224
+17.25 +17.25
N
RF FFL. RF FFL. W E
+13.65 +13.65 N
3rd FFL. 3rd FFL.
05 05 GRE
EN
EN
GRE
LV-15 LV-16
AR-310 KEY PLAN
AR-310
NOTES :
+8.25 +8.25
2nd FFL. 2nd FFL.
04 04
LV-12 LV-13 LV-14
AR-308 AR-309 AR-309
+4.65 +4.65
1st FFL. 1st FFL.
LEGENDS :
03 03
LV-09 LV-10 LV-11
AR-307 AR-307 AR-308
DOR
+0.45 +0.45
FFL. FFL.
02 02
12 11 10 9 8 7 6 5 4 3 2 1 SCALE 1:100
B NO OBJECTION SUBJECT TO INCORPORATION OF ALL
COMMENTS AS NOTED.
C REJECTED, TO BE RESUBMITTED
Eng'r. R.E.
DN
Date: Date:
D05
A
SHOP DRAWING
DN
IFC DRAWING REFERENCE NO.:
SHOPDRAWING REVISIONS:
QATAR CHARITY
Tel: 974 - 44667711
Fax: 974 - 44667733
QATAR CHARITY
LUSAIL MARINA COM 47
QCT AUGUST 21
AS SHOWN @ A1 - ALB-JCP-QCT-GAEC-SD-AR-401
FG GR - 2
A B C D E F G H I 02 J K L M MARINA - MIX 046
N:2310213792
E:4036156698
MARINA - COM 045
A
7
5863
N:2309657504
02
E:4035971290
D
7073
6
MARINA - COM 047
4148 m²
RO
7073
AD
6
B
N:2310437455
C
1 2 AD
5863
7 E:4035485632
RO
N:2309881168
E:4035300224
N
W E
+17.25 S
RF FFL.
N
+13.65
3rd FFL.
EN
GRE
EN
GRE
+8.25
2nd FFL.
LV-01 LV-03
AR-303 AR-304 D04
D03 D02
+0.45
FFL.
ACTION
ACP CLADDING 03 Section
02 SCALE 1:100 A NO OBJECTION
C REJECTED, TO BE RESUBMITTED
Eng'r. R.E.
Date: Date:
DN
CW02
5x17
D02
71x5
5x17
5x17
71x5
5x17
D04
CW03
D06
SHOP DRAWING
D03
IFC DRAWING REFERENCE NO.:
5x17
QATAR CHARITY
5x17
QATAR CHARITY
LUSAIL MARINA COM 47
QCT AUGUST 21
ACP CLADDING 03
ELEVATION, PLAN & SECTION
05 ACP CLADDING 03 Second Floor Plan
SCALE 1:100 AS SHOWN @ A1 - ALB-JCP-QCT-GAEC-SD-AR-402
FG GR - 2
MARINA - MIX 046
N:2310213792
1 3 4 5 6 7 8 9 11
E:4036156698
5863
7
A
N:2309657504
E:4035971290
D
7073
6
MARINA - COM 047
4148 m²
ROA
7073
6
D
B
N:2310437455
C 7 E:4035485632
5863
AD
RO
02 04 W
N
E
N:2309881168
E:4035300224
+17.25
RF FFL. 03
SITE LOCATION PLAN
+13.65
3rd FFL.
EN
GRE
EN
GRE
+8.25
2nd FFL.
LV-39
AR-322
+4.65 LEGENDS :
1st FFL.
+0.45
FFL.
04
03 02
ACP CLADDING 04 Elevation
01 SCALE 1:100
ACTION
A NO OBJECTION
C REJECTED, TO BE RESUBMITTED
Eng'r. R.E.
D01 D01
Date: Date:
D01
CW01
UP
SHOP DRAWING
IFC DRAWING REFERENCE NO.:
D01 D01
D01
CW01
9861,15
UP QATAR CHARITY
Tel: 974 - 44667711
Fax: 974 - 44667733
D01 D01
D01
CW01 Galfar Al Misnad Engg. & Contg. WLL
Aluminum Facade Division
P.O.BOX 22170 - DOHA - QATAR
TEL.:+974-44332500 - FAX:+974-44332501
9861,15
QATAR CHARITY
LUSAIL MARINA COM 47
QCT AUGUST 21
ACP CLADDING 04
ELEVATION, PLAN & SECTION
FG GR - 2
MARINA - MIX 046
N:2310213792
E:4036156698
MARINA - COM 045
A
7
5863
N:2309657504
E:4035971290
7073
6
MARINA - COM 047
4148 m²
ROA
7073
6
D
B
N:2310437455
C 7 E:4035485632
5863
AD
RO
N:2309881168
E:4035300224
N
W E
M L L
EN
GRE
EN
GRE
KEY PLAN
NOTES :
LEGENDS :
+13.65
FFL
+12.45
3rd bottom of slab
ACTION
A NO OBJECTION
C REJECTED, TO BE RESUBMITTED
Eng'r. R.E.
Date: Date:
+9.05
ACP TOP
+8.25
2nd FFL.
SHOP DRAWING
IFC DRAWING REFERENCE NO.:
QATAR CHARITY
Tel: 974 - 44667711
Fax: 974 - 44667733
QATAR CHARITY
ACP CLADDING 04 Section ACP CLADDING 05 Section ACP CLADDING 06 Section
02 SCALE 1:60
03 SCALE 1:60
04 SCALE 1:60
LUSAIL MARINA COM 47
QCT AUGUST 21
ACP CLADDING 04
ELEVATION, PLAN & SECTION
AS SHOWN @ A1 - ALB-JCP-QCT-GAEC-SD-AR-404
FG GR - 2
MARINA - MIX 046
N:2310213792
E:4036156698
MARINA - COM 045
A
7
5863
N:2309657504
E:4035971290
D
7073
6
MARINA - COM 047
4148 m²
RO
7073
AD
6
B
N:2310437455
C 7 E:4035485632
5863
D
ROA
N:2309881168
E:4035300224
N
W E
EN
GRE
EN
GRE
KEY PLAN
NOTES :
LEGENDS :
DETAIL - 01 DETAIL - 02
ACTION
A NO OBJECTION
C REJECTED, TO BE RESUBMITTED
Eng'r. R.E.
Date: Date:
SHOP DRAWING
IFC DRAWING REFERENCE NO.:
SHOPDRAWING REVISIONS:
QATAR CHARITY
Tel: 974 - 44667711
Fax: 974 - 44667733
DETAIL - 03
DETAIL - 04
Galfar Al Misnad Engg. & Contg. WLL
Aluminum Facade Division
P.O.BOX 22170 - DOHA - QATAR
TEL.:+974-44332500 - FAX:+974-44332501
QATAR CHARITY
LUSAIL MARINA COM 47
QCT AUGUST 21
AS SHOWN @ A1 - ALB-JCP-QCT-GAEC-SD-AR-700
FG GR - 02
MARINA - MIX 046
N:2310213792
E:4036156698
MARINA - COM 045
A
7
5863
N:2309657504
E:4035971290
D
7073
6
MARINA - COM 047
4148 m²
RO
7073
AD
6
B
N:2310437455
C 7 E:4035485632
5863
D
ROA
N:2309881168
E:4035300224
N
W E
EN
GRE
EN
GRE
KEY PLAN
NOTES :
LEGENDS :
DETAIL - 05
ACTION
A NO OBJECTION
C REJECTED, TO BE RESUBMITTED
Eng'r. R.E.
Date: Date:
SHOP DRAWING
IFC DRAWING REFERENCE NO.:
SHOPDRAWING REVISIONS:
QATAR CHARITY
Tel: 974 - 44667711
Fax: 974 - 44667733
QATAR CHARITY
AS SHOWN @ A1 - ALB-JCP-QCT-GAEC-SD-AR-701
FG GR - 02
MARINA - MIX 046
N:2310213792
E:4036156698
MARINA - COM 045
A
7
5863
N:2309657504
E:4035971290
D
7073
6
MARINA - COM 047
4148 m²
RO
7073
AD
6
B
N:2310437455
C 7 E:4035485632
5863
D
ROA
N:2309881168
E:4035300224
N
W E
EN
GRE
EN
GRE
KEY PLAN
NOTES :
LEGENDS :
DETAIL - 12
DETAIL - 09
ACTION
A NO OBJECTION
C REJECTED, TO BE RESUBMITTED
Eng'r. R.E.
Date: Date:
SHOP DRAWING
IFC DRAWING REFERENCE NO.:
SHOPDRAWING REVISIONS:
QATAR CHARITY
Tel: 974 - 44667711
Fax: 974 - 44667733
AS SHOWN @ A1 - ALB-JCP-QCT-GAEC-SD-AR-702
FG GR - 02
MARINA - MIX 046
N:2310213792
E:4036156698
MARINA - COM 045
A
7
5863
N:2309657504
E:4035971290
D
7073
6
MARINA - COM 047
4148 m²
RO
7073
AD
6
B
N:2310437455
C 7 E:4035485632
5863
D
ROA
N:2309881168
E:4035300224
N
W E
EN
GRE
EN
GRE
KEY PLAN
NOTES :
DETAIL - 13 LEGENDS :
DETAIL - 14
ACTION
A NO OBJECTION
C REJECTED, TO BE RESUBMITTED
Eng'r. R.E.
Date: Date:
SHOP DRAWING
IFC DRAWING REFERENCE NO.:
SHOPDRAWING REVISIONS:
QATAR CHARITY
Tel: 974 - 44667711
Fax: 974 - 44667733
QATAR CHARITY
LUSAIL MARINA COM 47
QCT AUGUST 21
AS SHOWN @ A1 - ALB-JCP-QCT-GAEC-SD-AR-703
FG GR - 02
MARINA - MIX 046
N:2310213792
E:4036156698
MARINA - COM 045
A
7
5863
N:2309657504
E:4035971290
D
7073
6
MARINA - COM 047
4148 m²
RO
7073
AD
6
B
N:2310437455
C 7 E:4035485632
5863
D
ROA
N:2309881168
E:4035300224
N
W E
EN
GRE
EN
GRE
KEY PLAN
DETAIL - 18 NOTES :
LEGENDS :
DETAIL - 17
ACTION
A NO OBJECTION
C REJECTED, TO BE RESUBMITTED
Eng'r. R.E.
Date: Date:
SHOP DRAWING
IFC DRAWING REFERENCE NO.:
SHOPDRAWING REVISIONS:
QATAR CHARITY
Tel: 974 - 44667711
Fax: 974 - 44667733
DETAIL - 19
QATAR CHARITY
LUSAIL MARINA COM 47
QCT AUGUST 21
AS SHOWN @ A1 - ALB-JCP-QCT-GAEC-SD-AR-704
FG GR - 02
MARINA - MIX 046
N:2310213792
E:4036156698
MARINA - COM 045
A
7
5863
N:2309657504
E:4035971290
D
7073
6
MARINA - COM 047
4148 m²
RO
7073
AD
6
B
N:2310437455
C 7 E:4035485632
5863
D
ROA
N:2309881168
E:4035300224
N
W E
EN
GRE
EN
GRE
KEY PLAN
NOTES :
LEGENDS :
DETAIL - 22
DETAIL - 21
ACTION
A NO OBJECTION
C REJECTED, TO BE RESUBMITTED
Eng'r. R.E.
Date: Date:
SHOP DRAWING
IFC DRAWING REFERENCE NO.:
SHOPDRAWING REVISIONS:
QATAR CHARITY
Tel: 974 - 44667711
Fax: 974 - 44667733
DETAIL - 26
LUSAIL RESIDENTIAL BUILDING
(2B + G + 25 ) MARINA COM 47
QATAR CHARITY
LUSAIL MARINA COM 47
QCT AUGUST 21
AS SHOWN @ A1 - ALB-JCP-QCT-GAEC-SD-AR-705
FG GR - 02
MARINA - MIX 046
N:2310213792
E:4036156698
MARINA - COM 045
A
7
5863
N:2309657504
E:4035971290
D
7073
6
MARINA - COM 047
4148 m²
RO
7073
AD
6
B
N:2310437455
C 7 E:4035485632
5863
AD
RO
N:2309881168
E:4035300224
N
W E
EN
GRE
EN
GRE
KEY PLAN
NOTES :
LEGENDS :
ACTION
A NO OBJECTION
C REJECTED, TO BE RESUBMITTED
Eng'r. R.E.
Date: Date:
SHOP DRAWING
IFC DRAWING REFERENCE NO.:
SHOPDRAWING REVISIONS:
QATAR CHARITY
Tel: 974 - 44667711
Fax: 974 - 44667733
QATAR CHARITY
LUSAIL MARINA COM 47
QCT AUGUST 21
AS SHOWN @ A1 - ALB-JCP-QCT-GAEC-SD-AR-706
FG GR - 02
MARINA - MIX 046
N:2310213792
E:4036156698
MARINA - COM 045
A
7
5863
N:2309657504
E:4035971290
D
7073
6
MARINA - COM 047
4148 m²
RO
7073
AD
6
B
N:2310437455
C 7 E:4035485632
5863
AD
RO
N:2309881168
E:4035300224
N
W E
EN
GRE
EN
GRE
KEY PLAN
NOTES :
LEGENDS :
DETAIL - 25
ACTION
A NO OBJECTION
C REJECTED, TO BE RESUBMITTED
Eng'r. R.E.
Date: Date:
SHOPDRAWING REVISIONS:
QATAR CHARITY
Tel: 974 - 44667711
Fax: 974 - 44667733
QATAR CHARITY
LUSAIL MARINA COM 47
QCT AUGUST 21
AS SHOWN @ A1 - ALB-JCP-QCT-GAEC-SD-AR-707
FG GR - 02
MARINA - MIX 046
N:2310213792
E:4036156698
MARINA - COM 045
A
7
5863
N:2309657504
E:4035971290
D
7073
6
MARINA - COM 047
4148 m²
RO
7073
AD
6
B
N:2310437455
C 7 E:4035485632
5863
D
ROA
N:2309881168
E:4035300224
N
W E
EN
GRE
EN
GRE
KEY PLAN
NOTES :
LEGENDS :
ACTION
A NO OBJECTION
C REJECTED, TO BE RESUBMITTED
Eng'r. R.E.
Date: Date:
SHOP DRAWING
IFC DRAWING REFERENCE NO.:
DETAIL - 28
QATAR CHARITY
Tel: 974 - 44667711
Fax: 974 - 44667733
QATAR CHARITY
LUSAIL MARINA COM 47
QCT AUGUST 21
AS SHOWN @ A1 - ALB-JCP-QCT-GAEC-SD-AR-708
FG GR - 02
MARINA - MIX 046
N:2310213792
E:4036156698
MARINA - COM 045
A
7
5863
N:2309657504
E:4035971290
D
7073
6
MARINA - COM 047
4148 m²
RO
7073
AD
6
B
N:2310437455
C 7 E:4035485632
5863
D
ROA
N:2309881168
E:4035300224
N
W E
EN
GRE
EN
GRE
KEY PLAN
NOTES :
LEGENDS :
ACTION
A NO OBJECTION
C REJECTED, TO BE RESUBMITTED
Date: Date:
SHOP DRAWING
IFC DRAWING REFERENCE NO.:
SHOPDRAWING REVISIONS:
QATAR CHARITY
Tel: 974 - 44667711
Fax: 974 - 44667733
DETAIL - 16
Galfar Al Misnad Engg. & Contg. WLL
Aluminum Facade Division
P.O.BOX 22170 - DOHA - QATAR
TEL.:+974-44332500 - FAX:+974-44332501
QATAR CHARITY
LUSAIL MARINA COM 47
QCT AUGUST 21
AS SHOWN @ A1 - ALB-JCP-QCT-GAEC-SD-AR-709
FG GR - 02
MARINA - MIX 046
N:2310213792
E:4036156698
MARINA - COM 045
A
7
5863
N:2309657504
E:4035971290
D
7073
6
MARINA - COM 047
4148 m²
RO
7073
AD
6
B
N:2310437455
C 7 E:4035485632
5863
D
ROA
N:2309881168
E:4035300224
N
W E
EN
GRE
EN
GRE
KEY PLAN
NOTES :
LEGENDS :
ACTION
A NO OBJECTION
C REJECTED, TO BE RESUBMITTED
Eng'r. R.E.
Date: Date:
SHOP DRAWING
IFC DRAWING REFERENCE NO.:
SHOPDRAWING REVISIONS:
QATAR CHARITY
DETAIL - 30 Tel: 974 - 44667711
Fax: 974 - 44667733
QATAR CHARITY
LUSAIL MARINA COM 47
QCT AUGUST 21
AS SHOWN @ A1 - ALB-JCP-QCT-GAEC-SD-AR-710
FG GR - 02
MARINA - MIX 046
N:2310213792
E:4036156698
MARINA - COM 045
A
7
5863
N:2309657504
E:4035971290
D
7073
6
MARINA - COM 047
4148 m²
RO
7073
AD
6
B
N:2310437455
C 7 E:4035485632
5863
D
ROA
N:2309881168
E:4035300224
N
W E
EN
GRE
EN
GRE
KEY PLAN
NOTES :
LEGENDS :
ACTION
A NO OBJECTION
C REJECTED, TO BE RESUBMITTED
Eng'r. R.E.
Date: Date:
SHOP DRAWING
IFC DRAWING REFERENCE NO.:
SHOPDRAWING REVISIONS:
QATAR CHARITY
Tel: 974 - 44667711
Fax: 974 - 44667733
QATAR CHARITY
LUSAIL MARINA COM 47
QCT AUGUST 21
AS SHOWN @ A1 - ALB-JCP-QCT-GAEC-SD-AR-711
FG GR - 02
MARINA - MIX 046
N:2310213792
E:4036156698
MARINA - COM 045
A
7
5863
N:2309657504
E:4035971290
D
7073
6
MARINA - COM 047
4148 m²
RO
7073
AD
6
B
N:2310437455
C 7 E:4035485632
5863
AD
RO
N:2309881168
E:4035300224
N
W E
EN
GRE
EN
GRE
KEY PLAN
NOTES :
LEGENDS :
ACTION
A NO OBJECTION
C REJECTED, TO BE RESUBMITTED
Eng'r. R.E.
Date: Date:
SHOP DRAWING
DETAIL - 32 IFC DRAWING REFERENCE NO.:
DETAIL - 33
SHOPDRAWING REVISIONS:
QATAR CHARITY
Tel: 974 - 44667711
Fax: 974 - 44667733
QATAR CHARITY
LUSAIL MARINA COM 47
QCT AUGUST 21
AS SHOWN @ A1 - ALB-JCP-QCT-GAEC-SD-AR-712
FG GR - 02
MARINA - MIX 046
N:2310213792
E:4036156698
MARINA - COM 045
A
7
5863
N:2309657504
E:4035971290
D
7073
6
MARINA - COM 047
4148 m²
RO
7073
AD
6
B
N:2310437455
C 7 E:4035485632
5863
AD
RO
N:2309881168
E:4035300224
N
W E
EN
GRE
EN
GRE
KEY PLAN
NOTES :
LEGENDS :
ACTION
DETAIL - 35
A NO OBJECTION
C REJECTED, TO BE RESUBMITTED
Eng'r. R.E.
Date: Date:
SHOP DRAWING
IFC DRAWING REFERENCE NO.:
SHOPDRAWING REVISIONS:
DETAIL - 34
QATAR CHARITY
Tel: 974 - 44667711
Fax: 974 - 44667733
AS SHOWN @ A1 - ALB-JCP-QCT-GAEC-SD-AR-713
FG GR - 02
3 4 5 6 7 8
02 MARINA - MIX 046
N:2310213792
E:4036156698
MARINA - COM 045
A
7
5863
N:2309657504
E:4035971290
L L
03
D
7073
6
MARINA - COM 047
4148 m²
RO
7073
AD
+12.45
6
B
N:2309881168
E:4035300224
N
W E
06 06
EEN
GR
+8.25 GR
EEN
2nd FFL.
05 KEY PLAN
05 NOTES :
+4.65
1st FFL.
LEGENDS :
GLASS LEGENDS :
04 04
+0.45
FFL.
02 ACTION
C REJECTED, TO BE RESUBMITTED
Eng'r. R.E.
Date: Date:
3 4 5 6 7 8 9
SHOP DRAWING
IFC DRAWING REFERENCE NO.:
3 4 5 6 7 8 9
QATAR CHARITY
Tel: 974 - 44667711
Fax: 974 - 44667733
5x17
71x5
5x17
71x5
5x17
71x5
5x17
71x5
5x17
71x5
5x17
71x5
5x17
71x5
5x17
71x5
5x17
71x5
5x17
71x5
5x17
71x5
5x17
71x5
5x17
71x5
5x17
71x5
5x17
71x5
5x17
71x5
5x17
71x5
5x17
71x5
5x17
71x5
5x17
71x5
5x17
71x5
5x17
71x5
James Cubitt & Partners
Engineering Consultancy
TEL: 4665216 - FAX: 44665250 - P.O.BOX 24436 - DOHA - QATAR
05 SCALE 1:50
Tel.: +974 - 44667714 / 15 / 16 Fax: +974 - 44660040
Web: www.albalagh.com Email: albalagh@albalagh.com
L
LUSAIL RESIDENTIAL BUILDING
(2B + G + 25 ) MARINA COM 47
QATAR CHARITY
LUSAIL MARINA COM 47
QCT AUGUST 21
CURTAIN WALL 01
ELEVATION, PLAN & SECTION
Curtain wall 01 second plan
06 SCALE 1:50
AS SHOWN @ A1 - ALB-JCP-QCT-GAEC-SD-AR-200
FG GR - 4
MARINA - MIX 046
N:2310213792
E:4036156698
2 2
MARINA - COM 045
A
7
5863
N:2309657504
E:4035971290
D
7073
6
MARINA - COM 047
4148 m²
RO
7073
AD
6
B
+13.65 C
D
5863
7
N:2310437455
E:4035485632
ROA
3rd FFL N:2309881168
E:4035300224
02 03
N
W E
EEN
GR
EEN
GR
KEY PLAN
NOTES :
03 03 +8.25
2nd FFL
LEGENDS :
04 04 GLASS LEGENDS :
+4.65
1st FFL
ACTION
A NO OBJECTION
C REJECTED, TO BE RESUBMITTED
Eng'r. R.E.
Date: Date:
05 05
+0.45
FFL.
02 03 SHOP DRAWING
IFC DRAWING REFERENCE NO.:
SHOPDRAWING REVISIONS:
5x17
2 5x17
5x17
2 5x17
QATAR CHARITY
LUSAIL MARINA COM 47
QCT AUGUST 21
Curtain Wall 02 Ground floor Plan
05 SCALE 1:50 CURTAIN WALL 02
ELEVATION, PLAN & SECTION
AS SHOWN @ A1 - ALB-JCP-QCT-GAEC-SD-AR-201
ANG GR - 4
2 MARINA - MIX 046
N:2310213792
E:4036156698
MARINA - COM 045
A
7
5863
N:2309657504
E:4035971290
D
7073
6
02
MARINA - COM 047
+13.65 4148 m²
RO
7073
3rd FFL
AD
6
B
N:2310437455
C 7 E:4035485632
5863
D
ROA
N:2309881168
E:4035300224
N
W E
EEN
GR
EEN
GR
KEY PLAN
NOTES :
03 03 +8.25
2nd FFL
LEGENDS :
04 04
GLASS LEGENDS :
+4.65
1st FFL
ACTION
A NO OBJECTION
C REJECTED, TO BE RESUBMITTED
Eng'r. R.E.
Date: Date:
+0.45
FFL.
02
SHOP DRAWING
Curtain Wall 03 Elevation
01 SCALE 1:50 IFC DRAWING REFERENCE NO.:
Curtain Wall 03 Section
2 03 SCALE 1:50
SHOPDRAWING REVISIONS:
QATAR CHARITY
2 Tel: 974 - 44667711
Fax: 974 - 44667733
71x5
5x17
71x5
QATAR CHARITY
LUSAIL MARINA COM 47
1 QCT AUGUST 21
CURTAIN WALL 03
ELEVATION, PLAN & SECTION
H
I 05 Curtain Wall 03 Ground Floor Plan
SCALE 1:50 AS SHOWN @ A1 - ALB-JCP-QCT-GAEC-SD-AR-202
ANG GR - 3
MARINA - MIX 046
N:2310213792
E:4036156698
MARINA - COM 045
A
7
5863
N:2309657504
E:4035971290
D
7073
3rd FFL
6
MARINA - COM 047
4148 m²
RO
7073
AD
6
B
N:2310437455
C 7 E:4035485632
5863
D
ROA
N:2309881168
E:4035300224
N
W E
+13.65 N
3rd FFL
EEN
GR
EEN
GR
KEY PLAN
NOTES :
04
K
LEGENDS :
+8.25
2nd FFL
GLASS LEGENDS :
ACTION
+4.65 A NO OBJECTION
1st FFL NO OBJECTION SUBJECT TO INCORPORATION OF ALL
B COMMENTS AS NOTED.
C REJECTED, TO BE RESUBMITTED
Eng'r. R.E.
Date: Date:
SHOP DRAWING
IFC DRAWING REFERENCE NO.:
+0.45
FFL.
04 SHOPDRAWING REVISIONS:
Curtain Wall 04
01 SCALE 1:50
Curtain Wall 04 Section
02 SCALE 1:50
QATAR CHARITY
Tel: 974 - 44667711
Fax: 974 - 44667733
03 SCALE 1:50
Web: www.albalagh.com Email: albalagh@albalagh.com
QATAR CHARITY
LUSAIL MARINA COM 47
K QCT AUGUST 21
2 CURTAIN WALL 04
ELEVATION, PLAN & SECTION
Curtain wall 04 third floor plan
04 SCALE 1:50 AS SHOWN @ A1 - ALB-JCP-QCT-GAEC-SD-AR-203
ANG GR - 3
MARINA - MIX 046
N:2310213792
+17.94
E:4036156698
MARINA - COM 045
A
7073
6
MARINA - COM 047
4148 m²
RO
7073
AD
6
B
N:2310437455
C 7 E:4035485632
5863
D
ROA
N:2309881168
E:4035300224
N
W E
N
H
+13.65
3rd FFL
EEN
GR
EEN
GR
05 KEY PLAN
NOTES :
LEGENDS :
+8.25
2nd FFL GLASS LEGENDS :
ACTION
A NO OBJECTION
C REJECTED, TO BE RESUBMITTED
+4.65
1st FFL Eng'r. R.E.
Date: Date:
SHOP DRAWING
IFC DRAWING REFERENCE NO.:
+0.45
FFL.
SHOPDRAWING REVISIONS:
05
Curtain Wall 05
01 SCALE 1:50
Curtain Wall 05 Section
02 SCALE 1:50
QATAR CHARITY
Tel: 974 - 44667711
1 1 Fax: 974 - 44667733
QATAR CHARITY
LUSAIL MARINA COM 47
H
QCT AUGUST 21
CURTAIN WALL 05
Curtain Wall 05 2nd Floor Plan ELEVATION, PLAN & SECTION
03 SCALE 1:50
AS SHOWN @ A1 - ALB-JCP-QCT-GAEC-SD-AR-204
ANG GR - 2