Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

L

L-
Proiect CosI Matagement

Iii

L- Practice Questions

f
l-t
INSTRUCTIONS: Note the most suitable answer for each multiple-choice
question in the appropriate space on the answer sheet.

L-
-- You are using earned value progress reporting for your curreni project in an
effort to teach your software developers the benefits of earned value. You plan

f
l--- to display project results on lhe cafeteria bulletin board so that the leam knows
how the project is progressing. Use the cunent status, listed below/ to answer

f
questions 1 through 4:

$2,200

f
$2,000
---! AC $2,500
BAC : $10,000

f
--L '1. Accordin8 to earned value analysis, the SV and status of the proiect
described above is-

f
--J! a.
b.
c.
-$300; the project is ahead of schedule
+ $8,000; the project is on schedule

L-
-4 d.
+$200; the project is ahead of schedule
$200; the project is behind schedule

E
E-.!

Fr.
2. What is the CPI for this proiect, and what does it tell us aboLrt cost
performance thus tar?

L- a.
b.
0.20; actual
O.Boi actual
costs
costs
are exactly as planned
have exceeded planned costs

f
I--.L c. 0.80; actual costs are less than planned costs
d. 1.25; actual costs have exceeded planned costs

f
-r
I The CV

a.
is-

E
+ $300
b. $300
c. + $500
d. -$s00

L-
---ra
F--r
what is the EAC for this project, and what does it represent?

L- a.
b.
$12,500; the revised eslimate for total project cost (based on
performance thus far)
$10,000; the revised estimate for total project cost (based on

1_
-I
c.
performance thus far)
$12,500; the original project budget

f
---
d. $10,000;the original project budSet

f 91
J
Proiect Cost Management
_l
5. Your first task on your project is to pfepare a cost estimate You decided
to use analogous estimatinS. Which ofthe following is Dor characteristic
of analogous estimatinS?
_l
a.
b.
Suppods top-down estimating
ls a forn-r of expert judgn]eni
_l
j
c.
d.
Has an accuracy rate of 10% of actual costs
Involves using the cost of a previous, similar proiect as the basis for
_l
estimating current project cost

6. You are managing a three-year proje<1 with a $3 million budget. lf project


_l
requirements change, you expect additional funds to become available
toward theend ofeach fiscal year. You may use these funds for your
project. You decide to establish a cost change control system to- -l
a.
b.
Define when to add contingency funds to the proiect
Define the procedures by which the cost baseline may be chanEied
_t
c. Determine why a cost variance has occurred
)
d. Detern]ine whether a budget update is required
*l
7. You rnust consider direct costs, indirect costs, overhead costs, and general
and administrative costs during cost estimating. Which of the following is
J
rot an exanrple of a direct
a.
cost?

Salary of the project manager


_l
b. Subcontractor expenses
c. Materials used by the project
d. Electricity
_t
B, lfthe cost variance is the same as the schedule variance and both numbers I
-l

are grealer than zero, then -l


a. The cost variance is due to ihe schedule variance
b. The variance is favorable to the project
-l
-
c. The schedule variance can be easily corrected
d. Labor rates have escalated since the project began
_l l

9. You are responsible for preparing a cost estimate for a large World Bank
a bottom-up eslimaie because your
_l
project. You decide io prepare
- l
estimate needs to be as accurate as possible. Your first step is to
__l
a. Locate a computerized tooL to assist in the process
b. Use the cost estimate from a previous project to help you prepare this -l
estirnate
c. Idenlify and estimate the cost for each individual work item
d. Consult with subject matter experts and use their suSSestions as the
basis for your estimate

92

You might also like