Professional Documents
Culture Documents
04 - Preguntas Costos 1
04 - Preguntas Costos 1
L-
Proiect CosI Matagement
Iii
L- Practice Questions
f
l-t
INSTRUCTIONS: Note the most suitable answer for each multiple-choice
question in the appropriate space on the answer sheet.
L-
-- You are using earned value progress reporting for your curreni project in an
effort to teach your software developers the benefits of earned value. You plan
f
l--- to display project results on lhe cafeteria bulletin board so that the leam knows
how the project is progressing. Use the cunent status, listed below/ to answer
f
questions 1 through 4:
$2,200
f
$2,000
---! AC $2,500
BAC : $10,000
f
--L '1. Accordin8 to earned value analysis, the SV and status of the proiect
described above is-
f
--J! a.
b.
c.
-$300; the project is ahead of schedule
+ $8,000; the project is on schedule
L-
-4 d.
+$200; the project is ahead of schedule
$200; the project is behind schedule
E
E-.!
Fr.
2. What is the CPI for this proiect, and what does it tell us aboLrt cost
performance thus tar?
L- a.
b.
0.20; actual
O.Boi actual
costs
costs
are exactly as planned
have exceeded planned costs
f
I--.L c. 0.80; actual costs are less than planned costs
d. 1.25; actual costs have exceeded planned costs
f
-r
I The CV
a.
is-
E
+ $300
b. $300
c. + $500
d. -$s00
L-
---ra
F--r
what is the EAC for this project, and what does it represent?
L- a.
b.
$12,500; the revised eslimate for total project cost (based on
performance thus far)
$10,000; the revised estimate for total project cost (based on
1_
-I
c.
performance thus far)
$12,500; the original project budget
f
---
d. $10,000;the original project budSet
f 91
J
Proiect Cost Management
_l
5. Your first task on your project is to pfepare a cost estimate You decided
to use analogous estimatinS. Which ofthe following is Dor characteristic
of analogous estimatinS?
_l
a.
b.
Suppods top-down estimating
ls a forn-r of expert judgn]eni
_l
j
c.
d.
Has an accuracy rate of 10% of actual costs
Involves using the cost of a previous, similar proiect as the basis for
_l
estimating current project cost
9. You are responsible for preparing a cost estimate for a large World Bank
a bottom-up eslimaie because your
_l
project. You decide io prepare
- l
estimate needs to be as accurate as possible. Your first step is to
__l
a. Locate a computerized tooL to assist in the process
b. Use the cost estimate from a previous project to help you prepare this -l
estirnate
c. Idenlify and estimate the cost for each individual work item
d. Consult with subject matter experts and use their suSSestions as the
basis for your estimate
92