TABLERO DE CONTROL DE SERVICIO DE REPARACIÓN INTEGRAL POR SOLDADURA

CURVA S INTEGRAL
5

% Acumulado Programado Rev 0 100%

94.87%
29-May; 100.00%
% DE AVANCE

84.82% 80%

70.18%
60%

48.23%
40%

28.66%
20%

14.73%
2.96% 0%
14-May 16-May 18-May 20-May 22-May 24-May 26-May 28-May 30-May

1.- BARANDAS, PLATAFORMAS, ESCALERAS, FENDERS Y OTROS 2.- CUARTO DE MOTORES

100% 100% 100.00%


100.0% 92.61%
89.1% 80%
80%

% DE AVANCE
% DE AVANCE

72.0% 65.34%
60% 60%
54.8%
40% 44.9% 40%
38.07%
33.8%
20% % Prog. Rev 0 20% % Prog. Rev 0
19.5% 13.26%
% Real Ejecutado % Real Ejecutado
5.2% 0%
0%
14-May 16-May 18-May 20-May 22-May 24-May 26-May 28-May 14-May 15-May 16-May 17-May 18-May 19-May 20-May

3.- CONTRAPESOS 4.- MAIN FRAME

% Prog. Rev 0
100% 100.00% 100% 100.00%
% Real Ejecutado 96.65%
80% 80%
76.88%
% DE AVANCE
% DE AVANCE

64.51%
60% 60%

46.88%
40% 40%
32.37%
24.58%
20% 20%
% Prog. Rev 0
8.48%
4.58%
0% 0%
14-May 15-May 16-May 17-May 18-May 19-May 20-May 15-May 16-May 17-May 18-May 19-May 20-May 21-May

5.- SIDES FRAME (BASTIDORES) 6.- TRUCK FRAME

100% % Prog. Rev 0


100%
100.00% 100.00%
% Real Ejecutado
89.63%
80% 84.58% 80%
% DE AVANCE
% DE AVANCE

60% 64.58% 60%


60.37%
44.58%
40% 40%
31.10%
20% 24.58% 20% % Prog. Rev 0

7.83% 10.67% % Real Ejecutado


0% 1.83% 0%
17-May 18-May 19-May 20-May 21-May 22-May 23-May 24-May 25-May 19-May 20-May 21-May 22-May 23-May 24-May 25-May

7.- MAQUINADO DE BUJES Y ALINEAMIENTO DE CARAS 8.- RECUPERACIÓN DE MEDIDAS, MAQUINADO Y RECTIFICADO DE ALOJAMIENTOS ROSCADOS

100% % Prog. Rev 0


100%
% Real Ejecutado 100.00% 100.00%
87.29% 99.72%
80% 80% 86.39%
% DE AVANCE
% DE AVANCE

73.06%
60% 67.29%
60%
59.72%

40% 47.29% 46.39%


40%

33.06%
20% 27.29%
20% % Prog. Rev 0
14.58%
7.29% % Real Ejecutado
0% 0%
18-May 20-May 22-May 24-May 26-May 28-May 30-May 20-May 21-May 22-May 23-May 24-May 25-May 26-May 27-May 28-May 29-May