Professional Documents
Culture Documents
Extracted Pages From LOT 3 - Sadaqa IU - Design Brief Report - SoW
Extracted Pages From LOT 3 - Sadaqa IU - Design Brief Report - SoW
CONSULTANCY SERVICE
FOR HEALTH FACILITIES IN YEMEN
22754
KfW‐SRHSP‐COV2‐02‐ AL‐SADAQA IU
Project Brief and Scope of Interventions
Revision ‐2‐ February 2022
Al Sadaqah Isolation Unit
Al Shiekh Othman District ‐ Aden Governorate
Republic of Yemen
Table of Contents
1. Introduction. .................................................................................................................................. 4
2. Scope of Works .............................................................................................................................. 5
2.1. Architectural Works ................................................................................................................... 5
2.1.1. Planning .................................................................................................................................. 5
2.1.1.1. DEMOLISHING PLAN ........................................................................................................... 7
2.1.1.2. NEW PARTITIONS PLAN ...................................................................................................... 8
2.1.1.3. ISOLATION UNIT ZONING PERSPECTIVE ............................................................................. 9
2.1.1.4. REMODELED ISOLATION UNIT KEY ELEMENTS ................................................................ 10
2.1.1.5. 1.5. PATIENT FLOW, FROM ENTRY TO SAMPLING ........................................................... 11
2.1.1.6. PATIENT FLOW FOR CONFIRMED CASES .......................................................................... 12
2.1.1.7. PROPOSED IU ACCESS (ENTRANCE & EXITS) .................................................................... 13
2.1.1.8. STAFF FLOW ...................................................................................................................... 14
2.1.2. Architectural interventions – Finishes and interior architecture ....................................... 15
2.1.3. Architectural‐ Site Works ..................................................................................................... 16
2.1.3.1. Demolition Plan ................................................................................................................ 16
2.1.3.2. Proposed Site Plan ............................................................................................................ 17
2.2. Structural Works: ..................................................................................................................... 18
2.2.1. Design Codes and Standards ................................................................................................ 18
2.2.2. Design Software programs ................................................................................................... 18
2.2.3. Design Criteria ...................................................................................................................... 19
2.2.3.1. Loading .............................................................................................................................. 19
2.2.3.2. Loading Combinations ...................................................................................................... 20
2.2.3.3. Materials ........................................................................................................................... 20
2.2.3.3.1. Concrete ............................................................................................................................ 20
2.2.3.3.2. Reinforcing Steel Bars ....................................................................................................... 21
2.2.3.3.3. Structural Steel .................................................................................................................. 21
2.2.3.4. Proposed Methodology of work ...................................................................................... 21
2.2.3.5. Agreed Building Modifications: ........................................................................................ 22
2.3. MECHANICAL WORKS............................................................................................................... 22
2.4.1. HVAC SYSTEM WORKS .......................................................................................................... 22
2.4.2. MEDICAL GASES WORKS ...................................................................................................... 24
2.4.3. PLUMBING WORKS ............................................................................................................... 24
2.4.4. FIRE PROTECTION WORKS .................................................................................................... 25
2.4.5. FUEL SYSTEM ASSESSMENT: ................................................................................................. 25
2|Page
2.4. ELECTRICAL WORKS: ................................................................................................................. 25
2.4.1. Electrical Power Source: ....................................................................................................... 25
2.4.2. GENERATOR SETS: ................................................................................................................ 26
2.4.3. UNINTERRUPTIBLE POWER SUPPLY: .................................................................................... 26
2.4.4. ISOLATED POWER SYSTEM (IPS): ......................................................................................... 26
2.4.5. CABLES AND CABLE WAY SYSTEM ....................................................................................... 27
2.4.6. LV DISTRIBUTION BOARDS ................................................................................................... 27
2.4.7. EARTHING AND EQUIPOTENTIAL BONDING SYSTEM .......................................................... 28
2.4.8. LIGHTNING PROTECTION SYSTEM ........................................................................................ 29
2.4.9. LIGHTING SYSTEM ................................................................................................................. 29
2.4.10. PLUGS AND SOCKET OUTLETS SYSTEMS .............................................................................. 30
2.4.11. ISOLATION AND SWITCHING ................................................................................................ 30
2.4.12. Telephone and Data Systems ............................................................................................... 30
2.4.13. Fire Alarm Detection & Voice Evacuation System ............................................................... 30
2.4.14. IP Surveillance System .......................................................................................................... 31
2.4.15. IP NURSE CALL SYSTEM ........................................................................................................ 31
2.5. WASTE MANAGEMENT WORKS ............................................................................................... 32
2.5.1. Municipal Waste Management:........................................................................................... 32
2.5.2. Medical Waste Management ............................................................................................... 32
3|Page