VEDANTA LIMITED, LANJIGARH

Integrated Management System


SOP description: OPERATION OF AIR HANDLING UNIT
Department: Power Revision
Version No: 03 SOP No: VL/2201/OPER/WI- 142 Revision No: 01
Plant Date:15.02.2021

1. PURPOSE: Operation of Air handling unit


2. SCOPE: All three units
3. RESPONSIBILITY: Desk Engineers
4. DURATION: 5 min

5. OUTPUT: Proper air distribution in Turbine floor

6. PROCEDURE:

6.1. Prechecks

6.1.1 All filters should be cleaned.


6.1.2 All dampers should be healthy.
6.1.3 Start up current should be within limit.
6.1.4 Dampers to be easily operate able.
6.1.5 Blower’s belts should be healthy.
6.1.6 Water line drains should be opened and line should be clear.
6.2 Start Procedure:-

6.2.1. Electrical power supply should be normalized.


6.2.2 Cooling water line should be in charged condition.
6.2.3 Spray pump should be running.
6.2.4 Sump level should be 90%.
6.2.5 Discharge and suction dampers should be in open condition.
6.2.6 Belt of blower and its motor should be position.
6.2.7 Blower can be started now.

7. QUALITY:

7.1. All the parameters, activities are maintained as per the manual.
7.2. Any deviation is recorded and corrective action is taken accordingly.

8. ENVIRONMENT: Not applicable

9. OHSAS:

9.1 Persons deployed on the work must use safety helmets, shoes, goggles, dust masks & hand gloves.
9.2 Before starting of any operation, ensure all standard clearance from main control room and
shift in charge.
9.3 Ensure deployment of a group of people (2 or more) while carrying out job in an isolated or deserted place in
night shift.

10. ENERGY:
11. RECORDS: VL/CPP/OPER/FILE/05

Prepared by : Avishek Moitra Revised By : Chaitanya Anand Date of Issue : 10.05.2015


Date of preparation : 30.04.2015 Approved By: Susheem Behera Date of review : 15.02.2021
VEDANTA LIMITED, LANJIGARH
Integrated Management System
SOP description: OPERATION OF AIR HANDLING UNIT
Department: Power Revision
Version No: 03 SOP No: VL/2201/OPER/WI- 142 Revision No: 01
Plant Date:15.02.2021

12. Amendment Table:

Sl No. Description Amendment done Revision date

Document Revision History


VERSION REVISION
DATE CHANGE SUMMARY
NUMBER NUMBER
Version changed:
1. Company name changed(VAL- SSL)
11.09.2013 01 00
2. Indication of Abbreviations, Details of document at the
footer
Version changed:
00
Document format changed.
07.06.2014 02
Content Addition: Equipment safety, Bibliography, Man power
01
required.

Version Changed:
10.05.2015 03 00 1. Company name changed from SSL to Vedanta Limited
2. Company logo changed.

1. Content Addition: Amendment table added.


15.02.2021 03 01
2. Company Logo changed.

Prepared by : Avishek Moitra Revised By : Chaitanya Anand Date of Issue : 10.05.2015


Date of preparation : 30.04.2015 Approved By: Susheem Behera Date of review : 15.02.2021