Engineering 30.00 21-Feb-23 12:00 AM 23-Mar-23 12:00 AM 0.00 23-Mar-23 12:00 AM, Engineering
Cluster 3 30.00 21-Feb-23 12:00 AM 23-Mar-23 12:00 AM 0.00 23-Mar-23 12:00 AM, Cluster 3
Connection Modeling 20.00 21-Feb-23 12:00 AM 13-Mar-23 12:00 AM 10.00 13-Mar-23 12:00 AM, Connection Modeling
Zone 2 20.00 21-Feb-23 12:00 AM 13-Mar-23 12:00 AM 10.00 13-Mar-23 12:00 AM, Zone 2
09-C3-EN-CM-Z2-000 Prepare and Submit Calculation Sheets for Connection Modeling 10.00 21-Feb-23 12:00 AM 03-Mar-23 12:00 AM 0.00 Prepare and Submit Calculation Sheets for Connection Modeling
09-C3-EN-CM-Z2-002 Review and Approve Calculation Sheets for Connection Modeling 10.00 03-Mar-23 12:00 AM 13-Mar-23 12:00 AM 10.00 Review and Approve Calculation Sheets for Connection Modeling
Shop Drawings 20.00 03-Mar-23 12:00 AM 23-Mar-23 12:00 AM 0.00 23-Mar-23 12:00 AM, Shop Drawings
Zone 2 20.00 03-Mar-23 12:00 AM 23-Mar-23 12:00 AM 0.00 23-Mar-23 12:00 AM, Zone 2
09-C3-EN-SD-Z2-000 Prepare and Submit DWGs for Steel Structure Works 10.00 03-Mar-23 12:00 AM 13-Mar-23 12:00 AM 0.00 Prepare and Submit DWGs for Steel Structure Works
09-C3-EN-SD-Z2-002 Review and Approve DWGs for Steel Structure Works 10.00 13-Mar-23 12:00 AM 23-Mar-23 12:00 AM 0.00 Review and Approve DWGs for Steel Structure Works
Procurement 42.00 01-Mar-23 12:00 AM 12-Apr-23 12:00 AM 0.00 12-Apr-23 12:00 AM, Procurement
Structure 42.00 01-Mar-23 12:00 AM 12-Apr-23 12:00 AM 0.00 12-Apr-23 12:00 AM, Structure
Short Lead Items 42.00 01-Mar-23 12:00 AM 12-Apr-23 12:00 AM 0.00 12-Apr-23 12:00 AM, Short Lead Items
Zone 2 42.00 01-Mar-23 12:00 AM 12-Apr-23 12:00 AM 0.00 12-Apr-23 12:00 AM, Zone 2
09-C3-PR-Z2-2 Issue Purchase Order [PO] and Procure Raw Material [Z1] [C3] 30.00 01-Mar-23 12:00 AM 31-Mar-23 12:00 AM 2.00 Issue Purchase Order [PO] and Procure Raw Material [Z1] [C3]
09-C3-PR-Z2-4 Prepare Fabrication Drawings/ Sheets [Z1] [C3] 10.00 23-Mar-23 12:00 AM 02-Apr-23 12:00 AM 0.00 Prepare Fabrication Drawings/ Sheets [Z1] [C3]
09-C3-PR-Z2-000 Fabricate and 1st Patch Delivery [Z2] [C3] 10.00 02-Apr-23 12:00 AM 12-Apr-23 12:00 AM 0.00 Fabricate and Delivery [Z2] [C3]
Construction 15.00 08-Apr-23 12:00 AM 23-Apr-23 12:00 AM 0.00 23-Apr-23 12:00 AM, Construction
Cluster 3 15.00 08-Apr-23 12:00 AM 23-Apr-23 12:00 AM 0.00 23-Apr-23 12:00 AM, Cluster 3
Steel Structure Works 15.00 08-Apr-23 12:00 AM 23-Apr-23 12:00 AM 0.00 23-Apr-23 12:00 AM, Steel Structure Works
Zone 2 15.00 08-Apr-23 12:00 AM 23-Apr-23 12:00 AM 0.00 23-Apr-23 12:00 AM, Zone 2
09-C3-CO-Z2-000 Erect Steel Structure Columns [Z2] [C3] 10.00 08-Apr-23 12:00 AM 18-Apr-23 12:00 AM 0.00 Erect Steel Structure Columns [Z2] [C3]
09-C3-CO-Z2-002 Erect Steel Structure Frame [Z2] [C3] 10.00 10-Apr-23 12:00 AM 20-Apr-23 12:00 AM 0.00 Erect Steel Structure Frame [Z2] [C3]
09-C3-CO-Z2-004 Erect Steel Structure Bracing [Z2] [C3] 10.00 13-Apr-23 12:00 AM 23-Apr-23 12:00 AM* 0.00 Erect Steel Structure Bracing [Z2] [C3]