C3 - WO9 - Steel Structure Works - Internal Schedule (Energya) PDF
C3 - WO9 - Steel Structure Works - Internal Schedule (Energya) PDF
Engineering 30.00 12-Mar-23 12:00 AM 11-Apr-23 12:00 AM 0.00 11-Apr-23 12:00 AM, Engineering
Cluster 3 30.00 12-Mar-23 12:00 AM 11-Apr-23 12:00 AM 0.00 11-Apr-23 12:00 AM, Cluster 3
Connection Modeling 20.00 12-Mar-23 12:00 AM 01-Apr-23 12:00 AM 0.00 01-Apr-23 12:00 AM, Connection Modeling
Central Part 20.00 12-Mar-23 12:00 AM 01-Apr-23 12:00 AM 0.00 01-Apr-23 12:00 AM, Central Part
09-C3-EN-CM-CP-000 Prepare and Submit Calculation Sheets for Connection Modeling 10.00 12-Mar-23 12:00 AM 22-Mar-23 12:00 AM 0.00 Prepare and Submit Calculation Sheets for Connection Modeling
09-C3-EN-CM-CP-002 Review and Approve Calculation Sheets for Connection Modeling 10.00 22-Mar-23 12:00 AM 01-Apr-23 12:00 AM 0.00 Review and Approve Calculation Sheets for Connection Modeling
Shop Drawings 20.00 22-Mar-23 12:00 AM 11-Apr-23 12:00 AM 0.00 11-Apr-23 12:00 AM, Shop Drawings
Central Part 20.00 22-Mar-23 12:00 AM 11-Apr-23 12:00 AM 0.00 11-Apr-23 12:00 AM, Central Part
09-C3-EN-SD-CP-000 Prepare and Submit DWGs for Steel Structure Works 10.00 22-Mar-23 12:00 AM 01-Apr-23 12:00 AM 0.00 Prepare and Submit DWGs for Steel Structure Works
09-C3-EN-SD-CP-002 Review and Approve DWGs for Steel Structure Works 10.00 01-Apr-23 12:00 AM 11-Apr-23 12:00 AM 0.00 Review and Approve DWGs for Steel Structure Works
Procurement 63.00 13-Mar-23 12:00 AM 15-May-23 12:00 AM 0.00 15-May-23 12:00 AM, Procurement
Structure 63.00 13-Mar-23 12:00 AM 15-May-23 12:00 AM 0.00 15-May-23 12:00 AM, Structure
Short Lead Items 63.00 13-Mar-23 12:00 AM 15-May-23 12:00 AM 0.00 15-May-23 12:00 AM, Short Lead Items
Central Part 63.00 13-Mar-23 12:00 AM 15-May-23 12:00 AM 0.00 15-May-23 12:00 AM, Central Part
08-C4-1004 Issue Purchase Order [PO] and Procure Raw Material [CP] [C3] 30.00 13-Mar-23 12:00 AM 12-Apr-23 12:00 AM 3.00 Issue Purchase Order [PO] and Procure Raw Material [CP] [C3]
08-C4-1006 Prepare Fabrication Drawings/ Sheets [CP] [C3] 10.00 05-Apr-23 12:00 AM 15-Apr-23 12:00 AM 0.00 Prepare Fabrication Drawings/ Sheets [CP] [C3]
09-C3-PR-CP-000 Fabricate and Delivery [CP] [C3] 30.00 15-Apr-23 12:00 AM 15-May-23 12:00 AM 0.00 Fabricate and Delivery [CP] [C3]
Actual Work Critical Remaining Work Summary Page 1 of 1 TASK filter: Subcontractors Code.
Remaining Work Milestone © Oracle Corporation