ACCESS

DESCRIPTION UNIT QTY CHEC RATE ACCESS RATE AMOUNT CHEC AMOUNT REMARKS
Access Road to be Completed

Embankment Construction Type


1 m3 91.5 5000 2,060.00 188,490.00 457,500.00
Sub base as compacted in
position m3 274.5 5100 3,330.00 914,085.00 1,399,950.00

Dense graded aggregate base m3 38.5 10700 6,156.00 237,006.00 411,950.00


Asphalt concrete m2 220 2400 1,920.00 422,400.00 528,000.00
Grade C 15 Concrete m3 2.5 25000 14,909.00 37,272.50 62,500.00
Grade C 30 Concrete m 3
25.2 31000 19,800.00 498,960.00 781,200.00
Toe steel kg 2556.2 210 169.00 431,997.80 536,802.00
Formwork rough finish m2 45.8 2950 1,170.00 53,586.00 135,110.00
2,783,797.30 4,313,012.00

RRM steps to be provided for access to the shops

Random rubble masonry m3 24.3 23000 9,653.00 234,567.90 558,900.00

Paranthan-poonaryn road drain cover and foot path slab installation work to be completed

Modification to line drain at


Poonervn Junction - Paranthan
Road 185,000.00 185,000.00 185,000.00
Precast concrete slab
(450x450x50mm)Paving m2 22.275 3398 2,888.00 64,330.20 75,690.45
249,330.20 260,690.45

Three numbers of name boards at poonaryn junction to be installed

Double Pole Sign area up to


2.0m2 nos 3 286,207.40 143,750.00 431,250.00 858,622.20

CH 20+400-20+460 LHS retain wall extension and guard stone installation to be completed

Grade C 20 Concrete m3 4.5 31000 19,800.00 89,100.00 139,500.00


Formwork rough finish m 2
36 2950 1,170.00 42,120.00 106,200.00
131,220.00 245,700.00

TOTAL AMOUNT 3,830,165.40 6,236,924.65


DESCRIPTION UNIT QTY CHEC RATE ACCESS RATE
Water leading path of the culverts to be merged with the existing ground levals beside the culvert

Channel Excavation, unsuitable soil m3 758.00

Painting of guard stones and numbering of culverts to be completed


Painting nos 46

Painting of hand rails of culvert no.133 to be completed


Painting m 20.4

Asphalt paving at the culvert widening area to be completed


Asphalt concrete m2 1075 1,920.00

Earth shoulder at aproved locations to be completed


Earthen Shoulder m3 2230 2,750.00

Road Marking works at the roundabout and the islands to be completed


m3

Soil sloping and grass sodding at the edge of concrete draings to be completed
m3
ACCESS
AMOUNT CHEC AMOUNT REMARKS
g ground levals beside the culvert

- -
-
ts to be completed
-
-
e completed
-
-
o be completed
-

completed
-

ands to be completed
-

draings to be completed
-