ADCOP - ABU DHABI CRUDE OIL PIPELINE PROJECT

Habshan - Fujairah

GENERAL ARRANGEMENT DRAWINGS FOR HPU


P195-30-99-50-0811

EPC CONTRACTOR: PROJECT MANAGEMENT CONSULTANT: VENDOR / SUBCONTRACTOR:

China Petroleum Engineering ILF Consulting Engineers


& Construction Corporation P.O.Box 73250
Abu Dhabi Branch
Abu Dhabi, UAE CONSULTING
P.O. Box 127345 EN GI N EERS

PROJECT: ADCOP - ABU DHABI CRUDE OIL PIPELINE PROJECT


Habshan - Fujairah
EPC Contractor Doc. No.: ADCOP/C013/08 PAGE: 1 of 5
DOCUMENT No.: P195-30-99-50-0811 Rev. 0 Project No: E30153 DATE: 18-01-2017
REVISION RECORD

REV DATE ORIGINATOR REVIEWED APPROVED DESCRIPTION

RASHMI ANAND
A 27-7-2015 ANAND KUMAR ISSUED FOR APPROVAL
SHARMA KUMAR

0 18-01-2017 RASHMI S ANAND K ANAND K ISSUED FOR CONSTRUCTION

© Copyright China Petroleum Engineering &Construction (Group) Corporation 2008 All rights reserved.
“This document is issued for the execution of Abu Dhabi Crude Oil Pipeline (ADCOP) project.
Copying this report without the permission of CPECC, ILF and IPIC is not permitted.

DOCUMENT TITLE : GENERAL ARRANGEMENT DRAWING FOR


Project No: E30153
HPU
PROJECT: ABU DHABI CRUDE OIL PIPELINE PROJECT
Page 2 of 5
Habshan - Fujairah
DOCUMENT No.: P195-30-99-50-0811 Rev. 0 Date: 18/01/2017
HABSHAN FUJAIRAH OIL PIPELINE PROJECT
HYDRAULIC DESIGN CALCULATIONS
P.O.: 71407784

General Arrangement Drawing for HPU

PROSERV Document No.: PJ-05-000346-ME-300-GA

PROSERV PROJECT No.: PJ-05-000346

00 04-Dec-2014 Issued for Review/Comments VC SGK VS


Approval
Rev Date Reason For Issue Prep. Chkd. Apprd.