Back filling 5 5 25 A 3 1 3 C
1. Edge collapse 1. Do not allow the formation of cavity on the
or slide edge of excavated area.
2. Falling of 2. Barricade around the said area one meter
personnel or away from the edge and post the warning sign
moving board “Deep excavation”,
equipment into 3. fix signage’s like Vehicle Movement area keep
the excavated away.
area.
3. Personnel
falling into the
excavated area
while crossing.
Unloading of 1. Mechanical 5 5 25 A 1. Prior checks to be done before starting 3 1 3 C
soil failure. the activity.
2. Improper 2. Continuous supervision to be provided.
supervision. 3. Area to be leveled on continuous basis.
3. Uneven 4. Provide designated signal man.
surface. 5. Area to be clear of personnel.
4. No
ELITE ENGINEERING & CONSTRUCTION (HYD) PVT LTD LIMITED
unauthorized
entry.
5 0 5 10 15 20 25 PROBABILITY SEVERITY
* 0 1 2 3 4 5
Rating 5 = Almost certain Rating 5 = Fatality, disabling injury, etc.
A UNACCEPTABLE RISK
B FURTHER REVIEW
C ACCEPTABLE