Professional Documents
Culture Documents
RoD Secretary Meeting 28th April 2021
RoD Secretary Meeting 28th April 2021
latasampad;:;:'":::i"#::;'{:,{;:;::2ff "[o',r,,.7ooost,
Record of discussion of the review meeting taken by the Secretarv on 28.04.2021 at the l't
floor conference room of Jalasampad Bhavan with C.E.s/ S.E.s of I&W Dte.
The meeting started at 12.00 noon in the conference room at l't floor of Jalasampad
Bhavan under the chairmanship of the Secretary, I&WD. The Joint Secretary (Works), Joint
Secretary (Technical), Deputy Secretaries of Works Branch, the C.E (D&R), C.E.(S),
C.E.(IJorth), along with their S.E.s attended the meeting physically at Jalasampad Bhavan. Other
C.E.s and the Concerned S.E.s (E.E.s in some cases) attended online.
The issues relating to compliance of the decisions taken in the previous review meeting on
02.03.2021, progress of preparation and submission of new plan schemes emerging from Safety
Audits carried out recently by WAPCOS (I) Ltd, RITES Ltd and Departmental Bridge Inspection
Units, Pre-monsoon maintenance works, auction through MSTC, etc. were discussed. After
a) Henceforth, Secretary, I&WD will conduct review meeting on 15th day of each month.
The Chief Engineers will take monthly review meeting will their subordinates, prior to
the review meeting of the Secretary and send RoDs of the said meetings to the
department by 10th day of each month at the e-mail of the Secretary, (secretar),-
highlighted and mentioned separately in these RoDs of the Directorate Level Review
Meetings.
b) The Chief Engineer (North) will send a concept note on Bituminous Canal Lining, as
comparison of financial involvement and its advantage over the conventional canal
examination of the same at his end, will send a Report to the Department by
3t.05.2021.
c) No further fund requisition under RIDF- 23 wlll be accepted at the Department, since
d) It was reported by the Chief Engineer (North) that a scheme, received from PWD
Electrical Division relating to electrical installation at the under construction new
inspection bungalow at Malda, amounting to Rs. l6 Lakhs , had been submitted to the
I&W Department seeking Administrative Approval. It was decided that the process of
e) The C.E/ TBP informed that renovation of MMC in the left out portion will be
completed by 21.05.2021 and canal water would be released for power generation
from 26.05 .2021. Secretary instructed to ensure completion of all the left out
The C.E(S) will inform the Department about the latest position of landscape &
beautification work along the banks of lower Bagjola Khal, adjacent to Convention
Centre, under HIDCO funding by 07.05.2021. A letter from the Department will be
issued thereafter to HIDCO informing the status of completed portion of the scheme
important structures to the department by the Directorate, as per the timeline fixed in
submitted to the Department within 31.05.2021, if not covered under DRIP-II. All
estimated by mechanical wings and the same would be forwarded to the respective
civil wing. The concemed civil wing will in turn send the comprehensive scheme to
Report by WAPCOS (D Ltd, RITES (I) Ltd and in the recommendations of the Bridge
Inspection Unit of the Department are also to the submitted to the Department by
31.05.2021, even those are considered under Special Infrastructure Project Funding.
h) per the decision taken in the last Review Meeting of the Secretary on 02.03.2021,
.As
list of 46 damaged canal regulator gates from C.E./TBP,32 damaged canal regulator
gates from C.E.(S-W) and 102 damaged canal regulator gates from C.E.(W) have been
cross regulators on main canals or head regulators of canals off-taking from main
canals. It was decided that C.E.(Mechanical & Electrical) will examine these gates
involving concerned sub-ordinate offices and will submit D.P.Rs for tepairl
Engineers will also submit the lists of such damaged canal regulator gates within their
' 15.05.2021.
channels has been received at the Department though the Chief Engineers were asked
in the Review Meeting on 02.03.2021, to identify and submit such rehabilitation
rehabilitation of damaged sluices, after their identification and clubbing into one
their Auction through MSTCL, it was reported that C.E.(N-E) and C.E(North) have
already submitted their lists to the C.E./TBP (the chairman of the Technical
Committee of I&WD for Condemnation in North Bengal). Similarly such lists from
C.E.(West) has been repofted to be submitted to the C.E.(D&R) ( the chairman of the
that base rates of the concerned items will be finalised by the respective Technical
Committees of Condemnation by 15.05.2021. Other C.E.s will send their lists to the
visit of the Deputy Director/CDO in the last week of March-2021, immediate after the
m) The status of pre-monsoon maintenance works out of the allocations made vide memo
No.-O8/SIWl202l dated 02.02.2021 were placed by all the C.Es in prescribed format.
It was observed from these submitted Reports that tenders have yet not been invited in
many cases. Secretary instructed to initiate the balance tender process immediate after
positively by 1Oth June-2021. Work orders for such works, proposed under SDS can
also be issued and the clubbed schemes should be sent to the Department positively by
n) The Chief Engineer (S-W) and the Chief Engineer (W) informed that requisition for
additional maintenance fund allocation for taking up emergent repair works of Chetua
have been submitted by them to the department. Secretary instructed the said two
Chief Engineers to conduct site visits and send fresh proposal for additional allocation
Memorandum is to be followed.
3orqtLt
,^S,fi,
Secretary to the
1. Senior P.A to the Additional Chief Secretary, Irrigation & Waterways Department I't
floor, Jalasampad Bhavan, Salt Lake, Kolkata- 91.
Wrofitut
[Amit Roy]
Secretary to the
Government of West Bengal
Irrigation & Waterways Department
ffidolt'1oL\
\FMukherjeel
Deputy Secretary to the
Government of West Bengal
Irrigation & Waterways Department