CP FOR FLOW LINES 1/01/2020

External Wall Total Length current Require Commissioning ZFOD CP


Sno Existing Pipeline name /
Typology From To ND OD
diameter of thickness Length including 5%
Surface d
density current and construction
Complection Receiving Remarks
T/R No well [inch] [MM] [m²] Date committee
pipeline [mm] [M] contingency [mA/m2] status
[A] status

Commissioning Inspection
1 T/R CPS07 Zb-082 FL-water South complex satellite Well ZB82 10" 273 0.273 15.9 189 199 170.58678 0.22 0.03753 1/3/2018
completed. done

2 T/R CPS07 Zb-376 FL-water South complex satellite Well ZB376 8" 219 0.219 12.7 4000 4200 2888.172 0.22 0.6354 Commissioning 5/3/2019 Inspection
completed. done

3 T/R CPS08 Zb-67 FL-water ZB-67 F/L TIE IN ZB-376 Well ZB67 8" 219 0.219 12.7 258 271 186.35586 0.22 0.041 Commissioning 3/7/2019 Inspection ZB-67 F/L TIE IN ZB-
F/L completed. done 376 F/L

4 T/R CPS08 Zb-074 FL-water Lower medial complex Well ZB74 10" 273 0.273 15.9 3056 3208.8 2750.64754 0.22 0.60514 Commissioning 12/3/2018 Inspection
satellite completed. done

5 T/R CPS08 Zb-221 FL-water Lower medial complex Well ZB221 10" 273 0.273 15.9 5913 6208.65 5322.17895 0.22 1.17088 Commissioning 16/5/2018 Inspection
satellite completed. done
Zb043 Flow line tie in Zb043 Flow line tie in
6 T/R CPS08 Zb-043 FL-water to Zb 221Existing flow Well ZB043 8" 219 0.219 12.7 1975 2074 1426.20684 0.22 0.31377 HOLD to Zb 221Existing flow
line line

Lower medial complex Commissioning Inspection Our scope Well head


7 T/R CPS08 Zb-207 FL-water Well ZB207 10" 273 0.273 15.9 0 0 0 0 0 11/4/2017
satellite completed. done tie in only

Zb280 Flow line tie in Flow line dirct


Commissioning Inspection
8 T/R CPS08 Zb-280 FL-water to Zb 207 Existing flow Well ZB280 10" 273 0.273 15.9 775 813.75 697.562775 0.22 0.15346 1/3/2018 connect to existing
line completed. done flow line.

Lower medial complex Commissioning Inspection


9 T/R CPS08 Zb-137 FL-water Well ZB137 8" 219 0.219 12.7 2937 3083.8 2120.60591 0.22 0.46653 5/3/2019
satellite completed. done

Zb093 Flow line tie in Zb093 Flow line tie in


Commissioning Inspection
10 T/R CPS08 Zb-093 FL-water to Zb 221Existing flow Well ZB093 10" 273 0.273 15.9 1970 2068.5 1773.15957 0.22 0.3901
completed.
20/2/2019
done to Zb 221Existing flow
line line

North medial complex Commissioning Inspection ZB-75 Flow line Tie to


11 T/R CPS10 Zb-75/99 FL-water satellite Well ZB75/99 10" 273 0.273 15.9 126 132.3 113.410206 0.39 0.04423 completed. 25/3/2017 done ZB-99 Flow line.

Flow line dirct connect to Commissioning Inspection Flow line dirct connect
12 T/R CPS10 ZB-272 FL-water existingZB-272 F/L flow Well ZB272 10" 273 0.273 15.9 145 152.25 130.511745 0.39 0.0509 3/7/2019 to existingZB-272 F/L
line. completed. done flow line.

Zb378 Flow line direct


Zb378 Flow line direct
13 T/R CPS10 Zb-378 FL-water tie in to Zb 247 Existing Zb-378 8" 219 0.219 12.7 1068 1121 770.86686 0.39 0.30064 Commissioning 16/4/2019 Inspection tie in to
completed. done Zb247 Existing flow
flow line line

Zb219 Flow line tie in Flow line dirct


14 T/R CPS09 Zb-219 FL-water to Zb 278 Existing flow Well ZB280 10" 273 0.273 15.9 129 135.45 116.110449 0.39 0.04528 Commissioning 25/3/2017 Inspection connect to existing
completed. done
line flow line.

15 T/R CPS09 Zb-094 FL-water Upper medial complex Well ZB094 10" 273 0.273 15.9 4680 4914 4212.37908 0.39 1.64283 Commissioning 16/4/2019 Inspection
satellite completed. done

16 T/R CPS09 Zb-234 FL-water Upper medial complex Well ZB234 10" 273 0.273 15.9 6667 7000 6000.54 0.39 2.34021 Commissioning 6/3/2018 Inspection
satellite completed. done

Zb105Flow line tie in to Zb105 Flow line tie in


17 T/R CPS09 Zb-105 FL-water Zb 234 Existing flow Well ZB105 10" 273 0.273 15.9 52 54.6 46.804212 0.39 0.01825 Commissioning 28/5/2018 Inspection
to Zb 234 Existing
line completed. done flow line

Upper medial complex IPF Water Commissioning Inspection


18 T/R CPS09 IPF-1 -T/L IC –FL-Water 10 273 0.273 19.1 3924 4120.2 3531.91784 0.39 1.37745 7/3/2018
satellite Manifold area completed. done

19 T/R CPS09 IPF-2 -T/L Upper medial complex IPF Water 10 273 0.273 19.1 3962 4160.1 3566.12092 0.39 1.39079 Commissioning 7/3/2018 Inspection
IC –FL-Water satellite Manifold area completed. done

Flow line Inspection


20 T/R CPS09 Zb-270 FL-water Upper medial complex Zb-270 12" 323.9 0.323 19.05 7734 8120.7 8236.17635 0.39 3.21211 Commissioning 4/3/2019 done.
satellite ZB-270 SIDE IJ Swing.To
completed. F/L Only be replace Waiting for
operation shut down.
Zb267Flow line tie in to Zb267Flow line tie in
21 T/R CPS09 Zb-267 FL-water Zb 270Existing well Zb-267 8" 219 0.219 12.7 497 522 358.95852 0.39 0.13999 Commissioning 4/3/2019 Inspection to Zb 270Existing well
head. completed. done head.

Zb108Flow line tie in to ZB-108 Flow line dirct


22 T/R CPS09 Zb-108 FL-water Zb 270Existing well Zb-108 8" 219 0.219 12.7 154 162 111.40092 0.39 0.04345 Commissioning 4/3/2019 Inspection connect to ZB-270
completed. done
head. flow line.

Zb266Flow line tie in to Zb266 Flow line tie in


23 T/R CPS09 ZB-266 FL-water Zb 236 Existing well ZB266 8" 219 0.219 12.7 889 933.45 641.896227 0.39 0.25034 Commissioning 20/2/2019 Inspection to Zb 236 Existing
completed. done
head. well head.

18” WI T/L NE - ZB-094 CL-3 Flow line


24 T/R CPS09 ZB-094 CL-3 LINE FL-water Well ZB094 8" 219 0.219 12.7 1548 1625.4 1117.72256 0.39 0.43591 Commissioning 16/4/2019 Inspection dirct connect to ZB-94
CLUSTER - 3 Header completed. done UMCS flow line.

18” WI T/L NE - Commissioning Inspection ZB-218 Flow line dirct


25 T/R CPS09 ZB-218 FL-water Well ZB218 8" 219 0.219 12.7 511 536.55 368.963973 0.39 0.1439 16/4/2019 connect to 18" CL-3 Line
CLUSTER - 3 Header completed. done flow line.

26 T/R CPS09 ZB-102 FL-water Zb102Flow line tie in to Well ZB102 8" 219 0.219 12.7 921 967.05 665.001603 0.39 0.25935 Commissioning 16/4/2019 Inspection
Zb 370 well head. completed. done

Zb370Flow line tie in to ZB-370 Flow line dirct


27 T/R CPS09 ZB-370 FL-water NE - CLUSTER - 3 Well ZB370 8" 219 0.219 12.7 1300 1365 938.6559 0.39 0.36608 Commissioning 16/4/2019 Inspection connect to 18" CL-3 Line
completed. done flow line.
Header.

18” WI T/L NE 18” WI T/L NE Flow line Inspection


28 T/R CPS09 18” WI T/L NE - New PWT WI manifold 18 457.2 0.457 22.2 2950 3097.5 4444.85055 0.39 1.73349 Commissioning 27/2/2019
CLUSTER - 3 - CLUSTER area - CLUSTER - 3 done. RFI CLOSED
-3 Manifold completed. F/L Only

29 T/R CPS14 18" Water out let Water out let Hammer mishrif New north 18 457.2 0.457 22.2 3429 3600.45 5166.57374 0.39 2.01496 Commissioning 27/5/2018 Inspection
T/L T/L existing DGS DGS completed. done BOND TO 16" UMCS F/L
HM Manifold area

24" Water out let Interface water New PWT WI Commissioning Inspection
30 T/R CPS14 New north DGS HM 24 609.3 0.609 31.75 363 381 728.57106 0.39 0.28414 20/2/2019
T/L out manifold area completed. done

18” WI T/L NW 18” WI T/L


18” WI T/L NW - New PWT WI manifold Commissioning Inspection
31 T/R CPS14 CLUSTER - 1 area NW - CLUSTER 18 457.2 0.457 22.2 5637 5918.85 8493.43137 0.39 3.31244 completed. 27/2/2019 done
CLUSTER - 1 - 1 Manifold

Zb050Flow line tie in to Zb050 Flow line tie in


32 T/R CPS14 ZB-050 -ZB-227 FL-water Zb 227 Existing well Well ZB50 8" 219 0.219 12.7 1270 1333.5 916.99461 0.39 0.35763 Commissioning 3/7/2019 Inspection to Zb 227 Existing
head. completed. done well head.
33 T/R CPS14 ZB-227 FL-water 18” WI T/L NE - Well ZB227 8" 219 0.219 12.7 330 346 237.93036 0.39 0.09279 Commissioning 3/7/2019 Inspection
CLUSTER - 3 Header completed. done

18” WI T/L NE - Commissioning Inspection


34 T/R CPS14 ZB-223 FL-water Well ZB223 8" 219 0.219 12.7 993 1043 717.22938 0.39 0.27972 3/7/2019
CLUSTER - 3 Header completed. done

35 T/R CPS14 ZB-278 FL-water 18” WI T/L NE - Well ZB278 8" 219 0.219 12.7 2209 2319.45 1594.99299 0.39 0.62205 Commissioning 3/7/2019 Inspection
CLUSTER - 3 Header completed. done

18” WI T/L From


South west Commissioning 18" Line bond to ZB-
36 T/R CPS13 Rafidiya IPF TO S 18" WI Trunkline Rafidiya IPF Header 01 18" 457.2 0.457 22.2 11000 11550 16574.02 0.22 3.64628 completed. 11/1/2020 240 F/L
W Header 01

Zb165Flow line Cable Commissioning Inspection Zb165Flow line Cable


37 T/R CPS 15 ZB-165 FL-water bounding to Zb 231 Well ZB165 8" 219 0.219 12.7 1199 1259 865.76394 0.22 0.19047 3/7/2019 bounding to Zb 231
Existing flow line completed. done Existing flow line

Zb171 Flow line Cable Zb171Flow line Cable


38 T/R CPS15 ZB-171 FL-water bounding to Zb 231 Well ZB171 8" 219 0.219 12.7 2171 2280 1567.8648 0.22 0.34493 Commissioning 3/7/2019 Inspection bounding to Zb 231
completed. done
Existing flow line Existing flow line

12" RAW GAS ZM existing Commissioning


39 T/R CPS PPG RAW GAS FL New ZM trap area 12" 324 0.324 10.3 1013 1064 1082.47104 0.22 0.23814 24/12/2019
NZM TO EZM DGS completed.

40 T/R CPS PPG


12" RAW GAS RAW GAS FL New ZM trap area ZM existing 12" 324 0.324 10.3 2988 3138 3192.47568 0.22 0.70234 Commissioning 24/12/2019
NZM TO PPG DGS completed.

41 T/R CPS PPG


12" RAW GAS PPG RAW GAS FL New PPG trap area Hammer IPF 12" 324 0.324 10.3 10071 10575 10758.582 0.22 2.36689 Commissioning 24/12/2019
TO IPF Line-1 new Trap completed.

42 T/R CPS PPG


12" RAW GAS PPG RAW GAS FL New PPG trap area Hammer IPF 12" 324 0.324 10.3 10100 10605 10789.1028 0.22 2.3736 Commissioning 24/12/2019
TO IPF Line-2 new Trap completed.

8" River ZM
43 FL-water New ZM trap area ZM existing 8" 219 0.219 12.7 2967 3115 2142.0609 0.22 0.47125 Commissioning 24/12/2019
T/R CPS PPG Existing DGS to DGS completed.
new trap area.

8" Reject ZM ZM existing Commissioning


44 T/R CPS PPG Existing DGS to FL-water New ZM trap area 8" 219 0.219 12.7 2980 3129 2151.68814 0.22 0.47337 24/12/2019
new trap area. DGS completed.

8" River ZM New


45 T/R CPS PPG Trap DGS to new FL-water New PPG trap area New ZM trap 8" 219 0.219 12.7 1400 1470 1010.8602 0.22 0.22239 Commissioning 24/12/2019
area completed.
trap area.

8" Reject ZM New New ZM trap Commissioning


46 T/R CPS PPG Trap DGS to PPG FL-water New PPG trap area 8" 219 0.219 12.7 1418 1489 1023.92574 0.22 0.22526 24/12/2019
new trap area. area completed.

8" Condensate
47 T/R CPS PPG PPG Trap to ZM FL-water New PPG trap area New ZM trap 8" 219 0.219 12.7 2490 2614 1797.54324 0.22 0.39546 Construction
area work in progress.
Existing DGS .

Hammer IPF Water Commissioning


48 T/R CPS PPG ZB-383 FL-water Maniold Well ZB 383 8" 219 0.219 12.7 3047 3200 2200.512 0.22 0.48411 completed. 24/12/2019

Actual T/R Measure Balance capacity DSI Project already DSI Project More required Spare capacity in
Existing T/R NO Total Capacity Amp load Amp on 19/06/2019 Amp connected T/R Load Amp T/R Load Amp %

T/R CPS07 SCS 25 1.1 23.9 0.68 0


T/R CPS08 LMCS 25 11 14 3.14 0
T/R CPS10 NCS 25 6.6 18.4 0.09 0
T/R CPS09 UMCS 25 12.2 12.8 13.39 0
T/R CPS14 UMCS 25 9.2 15.8 5.63 0
T/R CPS13 RAFIDIYA DGS 25 2.52 22.48 0 3.646
T/R CPS15 ZMEXISTING DGS 25 0 0 0.53 0
T/R NEW PPG T/R 01 25 0 0 0 7.96