Last Update HOOK UP & GATHERING PLAN FOR NEW WATER INJECTION WELLS 2016 - 2017

3/July/2016
Hook-Up PLAN New WI 2016 Hook-Up PLAN New WI 2017 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan-18 Feb-18
ZB-099 ZB-094 ZB-234 ZB-280 ZB-082 AH-21V AH-19_3 AM-36_M AO-30_3 AI-18 5-Feb-18
H M NCS H M NCS H M UMCS Z M LMCS Z SCS HM NCS HM NCS ZM LMCS ZM LMCS HM UMCS
Starting Mob FL from ZB-247 from Zb-105 from Zb-207 FL existing
0----------> 0.1 km FL 2,9 km FL 3.3km New FL 1,0km FL 7.5km FL 4,7 km FL 5.4 km FL 2,3 km FL 3,0 km
ZB-075 ZB-219 ZB-207 ZB-272 ZB-297 AM-20_3 AQ-32_M AR-39_3 INJ-5 5-Feb-18
HU PLAN SCHEDULE H M NCS H M UMCS Z M LMCS H M NCS ZM LMCS HM NCS ZM LMCS ZM SCS HM UMCS
2016-2017 FL from ZB-278 FL existing FL existing
with Zb-099 FL 0,2 km FL 4.3 km FL 4,0 km FL 2.8 km FL 2,5 km FL 3,3 km
INJ-7 21-Feb-18
HM UMCS
Starting Construction Gas Lines(PPG-H IPF)
FL 5,0 km

Zb-99
WI Zb-094 = 65 DD
ZB-219 = 30 DD
WI Zb-234 = 68 DD
New WI lines (Constr+Eng)

ZB-280 =50 DD
CORRIDOR A (Zb-297) Zb-297 AL-35 = 75 DD -------------------->>>> Compl. Zb-297
WI AM-36 = tot. 83 DD ------------------------------------------------------------------------------------------------------------------->>>> Compl. AM-36
WI AH-21 = 100 DD

CORRIDOR B (AH-21)
WI AH-19 = tot. 78 DD ----------------------------------------->>>> Compl. AH-19
AI-18 (FL 3,0 km) = tot. 66 DD ----------------------------------------------------------------------------------------------------------------------->>>> Compl. AI-18 5-Feb-18
WI AM-20 = 74 DD
WI AQ-32 = 66 DD
WI AO-30 = 60 DD
WI AR-39 = 62 DD
WI-UMCS INJ-7 (FL 5,5 km) = 81
DD 5-Feb-18
WI-UMCS INJ-5 (FL 3,2 km) = 68 DD 21-Feb-18
2x12"Gas pipelines PPG-H = 165 DD

(*) Notes:
Zb-099: Current status=Zb-099 is connected to Zb-075 (WSW) by existing FL 6" #1500. Future Config= Zb-075 will be converted to WI well. New 100m connection from NCS to both Zb-099 & Zb-075. Hook-ups & Tie-In to be done.
Zb-094 conversion from Oil Prod. To WI.Well fed by NCS. Well HU, new line and tie-in from Zb-247 well head, to be done
Zb-219: Current configuration=WSW. Future Configuration=WI well - Well HU and tie-in from Zb-278 well head, to be done
Zb-234: Current configuration=WSW. Future Configuration=WI well - Well HU, new line and tie-in from Zb-105 well head, to be done
Zb-280: to be fed by Zb-207. Well HU and line from Zb-207 to Zb-280, to be done
Zb-082: Current configuration=WSW. Future Configuration=WI well - Well HU, Tie-in manifold and flowlines #1500 to be done
Rev 1 A) B) = A+10dd C = B+42dd D) E +D-C Reference to e-mail sent by Operation Mgr. on 20/6/2016 :

Hook-up Hook-up FL Flowlines Well HU Manif. Tie-


7/4/2016 Wells Drilling CompletioHO date date Delays FC2 in Remark
(theorical) (Planned) completion km Nos. Nos.
ZFOD Presentation "Water Injection: Status & Way forward updated on 30/5/2016"
MID term actions LINES & Hook-up(planned to be completed before 1st OCT 2016):

Mob 9/1/2016
Survey 9/15/2016
Constr 10/1/2016
Dismantling by Maint. to be
SoW Prex Zb-099 Done 7/15/2016 8/26/2016 11/12/2016 78 Aug-16 ### 0.10 1 1 plannedW.I. coversion (from #900 HM flowlines and hook up in North Manifold
to #1500)

Dismantling by Maint. to be
SoW Prex Zb-075 7/5/2016 7/15/2016 8/26/2016 11/12/2016 78 Sep-16 (see Zb-099) 0.00 1 0 planned HM flowlines and hook up in North Manifold
W.I. coversion (from WSW)

Zb-094 Done 7/15/2016 8/26/2016 12/17/2016 Aug-16 ### 2.91 1 0.50 W.I. conversion from Oil Producer HM flowlines and hook up in North Manifold
FL connection from Zb-247
113
Dismantling by Maint to be
NU Zb-219 9/30/2016 ### 11/21/2016 12/17/2016 26 Sep-16 ### 0.15 1 0.50 planned - Hook-up after WO Sept HM flowlines and tie-in to Zb-278 (network flexibility – Upper Manifold)
2016
FL connection from Zb-278

Dismantling by Maint to be
flowlines and tie-in to Zb-108 (network flexibility – Upper Manifold)
NU Zb-234 Done 1/21/2017 Sep-16 1/21/2017 3.30 1 0.50 planned - Hook-up HM
FL connection from Zb-105

Zb-207 Done 1/21/2017 Aug-16 existing existing 1 1 Hook-up ZM hook up in Lower Manifold
Hook-up hook up in Lower Manifold (tie-in to Zb-207)
Zb-280 Done 2/25/2017 Nov-16 2/25/2017 1.00 1 0.50 FL connection from Zb-207 ZM

Zb-272 10/9/2016 ### 11/30/2016 2/25/2017 87 Oct-16 2/25/2017 0.13 1 1 Hook-up after WO Oct 2016 HM hook up in North Manifold
Zb-082 9/30/2016 ### 11/21/2016 4/8/2017 138 Oct-16 4/8/2017 0.17 1 1 Hook-up after WO Sept 2016 ZM hook up in South Manifold
Zb-289 Drilled as Oil Producer ZM flowlines and hook up in Lower Manifold
Tot. km 7.76 9 6
Zb-297 AL-35V 4/6/2017 4/16/2017 5/28/2017 5/28/2017 5/28/2017 4.27 1 1 ex Zb-297 to be done on Q1 2017 ZM flowlines and hook up in Lower Manifold
AH-21_3V 4/6/2017 4/16/2017 5/28/2017 5/28/2017 5/28/2017 7.48 1 1
AH-19_3 7/15/2017 7/25/2017 9/5/2017 9/5/2017 9/5/2017 4.71 1 1
AM-20_3 7/15/2017 7/25/2017 9/5/2017 9/5/2017 9/5/2017 4.05 1 1
AM-36_M 10/6/2017 ### 11/27/2017 11/27/2017 ### 5.32 1 1
AQ-32_M 10/15/2017 ### 12/6/2017 12/6/2017 12/6/2017 2.80 1 1
AO-30_3 10/21/2017 ### 12/12/2017 12/12/2017 ### 2.29 1 1
AR-39_3 10/21/2017 ### 12/12/2017 12/12/2017 ### 2.54 1 1
AI-18_M 12/15/2017 ### 2/5/2018 2/5/2018 2/5/2018 3.06 1 1
INJ-5_M (WI-AP2 12/15/2017 ### 2/5/2018 2/5/2018 2/5/2018 3.29 1 1
INJ-7_M 12/31/2017 1/10/2018 2/21/2018 2/21/2018 2/21/2018 5.06 1 1

52.63 20.00 17.00


BoQ WI lines Rev.0 4-Jul-2016 Flowline duration

Well Elev New flw Notes Crossing TB Crossing OC Only Constr WELL Tie-in Manifold
n well DGS mt List of wells (geomatic) 4th July 2016 (msl) Comp.date dd Hook-UP

Zb-099 and Zb-075 are connected together (WS+WI). Detach the line and
1 Zb-099 HM NCS 100 750846.913 3384441.591 2.067 m 12-Nov-16 tie-in Zb-099 and Zb-075 to NCS (in one common line). The "T" connection 0 0 14 1 1
would have valves for both direction: 099 and 075

2 Zb-075 HM NCS 0 747821.922 3384351.427 2.292 m existing In common (comingle) with above Zb-099 0 0 0 1 0

3 Zb-094 (from Zb-247) HM NCS 2912 752012.161 3379264.730 2.5 m 12/17/2016 Oil Wells became W.I. (fed by Zb-247). The pipe route is the centerline of 0 1 35 1 0.5
seismic NTS. There is a request to enlarg NTS
4 Zb-219 (WI-013) from Zb-278 HM UMCS 150 745540.018 3378601.437 1.992 m 12/17/2016 there is crossing of high-way (need special Thrust boring) 0 0 14 1 0.5
5 Zb-234 (WI-P15) from Zb-105 HM UMCS 3300 754786.815 3376042.658 2.709 m 1/21/2017 Flowline built by JV - missing hook-ups (Well and UMCS) 1 4 38 1 0.5
6 Zb-207 (WI-120S) ZM LMCS 0 755061.389 3369595.776 14.799 m existing Existing Flowlines, only hook-ups Well and LMCS 0 0 0 1 1
7 Zb-280 (WI-O23 Dir) from Zb-207 ZM LMCS 998 755902.928 3369581.663 12.511 m 2/25/2017 connection from Zb-207 0 0 20 1 0.5
Existing line built by JV. Extension of line (Re-routing) and hook-ups(Well
8 Zb-272 (WI-AF15) HM NCS 132 743880.4549 3386199.5033 2.174 2/25/2017 0 0 14 1 1
and NCS) to be done
It was N.U. Producer. To be surveyed to see dismantling of Hus and
9 Zb-082 HM SCS 170 753463.129 3363609.526 19.215 m 4/8/2017 0 0 14 1 1
Flowlines
10 Zb-297 (AL-35V) LMCS 4269 748999.288 3368209.050 4.597 m 5/28/2017 1 5 45 1 1
11 AH-21_3V NCS 7476 745592.000 3380276.000 5/28/2017 0 4 69 1 1
12 AH-19_3 NCS 4713 745805.845 3382198 9/5/2017 0 2 48 1 1
13 AM-20_3 NCS 4045 749971.608 3381867.36 9/5/2017 0 1 44 1 1
14 AM-36_M LMCS 5319 749818.148 3367090.04 11/27/2017 1 6 53 1 1
15 AQ-32_M LMCS 2798 753787.87 3370923.51 12/6/2017 0 2 33 1 1
16 AO-30_3 LMCS 2294 751979.447 3372443.61 12/12/2017 0 2 30 1 1
17 AR-39_3 SCS 2545 754515.12 3365303.82 12/12/2017 0 7 32 1 1
18 AI-18_M NCS 3058 746621.845 3383570.46 2/5/2018 0 1 36 1 1
19 INJ-5_M (WI-AP24) UMCS 3291 751833.852 3378551.53 2/5/2018 1 1 38 1 1
20 INJ-7_M UMCS 5055 753036.67 3375740.81 2/21/2018 2 3 51 1 1
Corridor A 6 39 20 17
Corridor B

Well pad covered by NTS confirmed coordinates


Tot. New Flws #1500 10" (kms) 52,625 tot. # new flowlines 18
Average 4,078 tot. # exist flowlines 2

Flowline duration
Gas lines Only Constr launching and Tie-
Notes Crossing TB Crossing OC Receiving and Tie-in
n Pipeline DGS mt Comp.date dd in
12" Raw gas Pipeline from Hammar IPF to PPG - 1st IPF H
21 10,937 3 10 95 1 1
Line - Interconnecting pipelines PPG-IPF PPG
12" Raw gas Pipeline from Hammar IPF to PPG - 2nd IPF H
22 10,937 3 10 95 1 1
Line - Interconnecting pipelines PPG-IPF PPG
6 20
BoQ WI lines Rev.0 4-Jul-2016
Latest WELL Tie-in
n well DGS FLW (mt) Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 2017-jan 2017-Feb 2017-March 2017-Apr 2017-May 2017-June 2017-July 2017-Aug 2017-Sept 2017-Oct 2017-Nov 2017-Dec Jan-18 Feb-18 Crossing TB Crossing OC
Comp.date Hook-UP Manifold

80 HU - 12-Nov-16 11/12/2016
12-11-2016 11/12/2016
1 Zb-099 HM NCS 100 0 0 1 1

Tie-in NCS 11/12/2016


12-Nov-16 11/12/2016
HU - 12-Nov-16
existing
2 Zb-075 HM NCS 0 0 0 1 0
(Existing flw)
11/12/2016
1165 1165 12/17/2016
HU - 17-Dec-16
12/17/2016
3 Zb-094 (from Zb-247) HM NCS 2912 Tie-in 17-12-2016 0 1 1 0.5
Zb-247
#VALUE! 12/17/2016
HU - 17-Dec-16
12/17/2016
4 Zb-219 (WI-013) from Zb-278 HM UMCS 150 Tie-in 17-12-2016 0 0 1 0.5
Zb- 278
#VALUE! 1456 1/21/2017
HU - 21-Jan-17
1/21/2017
5 Zb-234 (WI-P15) from Zb-105 HM UMCS 3300 Tie-in 21-1-2017 1 4 1 0.5
Zb- 105
1/21/2017
HU - 21-Jan-17
Zb-207 (WI-120S) existing
6 ZM LMCS 0 0 0 1 1
(existing Flw) Tie-in LMCS
21-Jan-17 1/21/2017
499 HU - 25-Feb-17 2/25/2017
25-2-2017 2/25/2017
7 Zb-280 (WI-O23 Dir) from Zb-207 ZM LMCS 998 Tie-in 0 0 1 0.5
Zb- 207
HU - 25-Feb-17 2/25/2017
25-2-2017 2/25/2017
8 Zb-272 (WI-AF15) HM NCS 132 0 0 1 1
Tie-in NCS
25-Feb-2017 2/25/2017
23 116 31 HU - 8-Apr-17 4/8/2017
8-4-2017 4/8/2017
9 Zb-082 HM SCS 170 0 0 1 1
Tie-in SCS
8-Apr-2017 4/8/2017
1708 1594 HU - 28-May-17 5/28/2017
Zb-297 (AL-35V)
Corridor 3300m --------------->>>> Compl. 28-5-2017 5/28/2017
10 LMCS 4269 1 5 1 1
(Pipeline in Corridor A) Tie-in LMCS
PIPELINEs LAID IN THE SAME TRENCH 28-May-2017 5/28/2017
1708 1594 HU - 27-Nov-17 11/27/2017
AM-36_M
Corridor 3300m ------------------------------------------------------------------------------------------------------------------------------------------------------->>>> Compl. 27-11-2017 11/27/2017
11 LMCS 5319 1 6 1 1
(Pipeline in Corridor A) Tie-in LMCS
27-Nov-2017 11/27/2017
#VALUE! 2265 HU - 28-May-17 5/28/2017
AH-21_3V
28-5-2017 5/28/2017
12 NCS 7476 0 4 1 1
(Pipeline in Corridor B) Tie-in NCS
28-May-2017 5/28/2017
1400 1400 HU - 5-Sep-17 9/5/2017
AH-19_3
Corridor 2800m ------------------------------------>>>> Compl. 5-9-17 9/5/2017
13 NCS 4713 0 2 1 1
(Pipeline in Corridor B) PIPELINEs LAID IN THE SAME TRENCH Tie-in NCS
5-Sep-17 9/5/2017
1000 1000 HU - 5-Feb-18 2/5/2018
AI-18_M
Corridor 2000m ------------------------------------------------------------------------------------------------------------------------------------------------------------------------>>>> Compl. 5-2-18 2/5/2018
14 NCS 3058 0 1 1 1
(Pipeline in Corridor B) Tie-in NCS
5-Feb-18 2/5/2018
#VALUE! 1640 HU - 5-Sep-17 9/5/2017
5-9-2017 9/5/2017
15 AM-20_3 NCS 4045 0 1 1 1
Tie-in NCS
5-Sep-17 9/5/2017
1199 HU - 6-Dec-17 12/6/2017
6-12-2017 12/6/2017
16 AQ-32_M LMCS 2798 0 2 1 1
Tie-in LMCS
6-Dec-17 12/6/2017
#VALUE! HU - 12-Dec-17 12/12/2017
12-12-2017 12/12/2017
17 AO-30_3 LMCS 2294 0 2 1 1
Tie-in LMCS
12-Dec-17 12/12/2017
#VALUE! HU - 12-Dec-17 12/12/2017
12-12-2017 12/12/2017
18 AR-39_3 SCS 2545 0 7 1 1
Tie-in SCS
12-Dec-17 12/12/2017
#VALUE! 1452 HU - 5-Feb-18 2/5/2018
5-2-2017 2/5/2018
19 INJ-5_M (WI-AP24) UMCS 3291 1 1 1 1
Tie-in UMCS
5-Feb-18 2/5/2018
1872 HU - 21-Feb-18 2/21/2018
21-2-2018 2/21/2018
20 INJ-7_M UMCS 5055 2 3 1 1
Tie-in UMCS
21-Feb-18 2/21/2018
Corridor A 6 39 20 17
Corridor B

Tot. New Flws #1500 10" (m) 52,625


Average 4,078

Launching Receiving
Latest
n Pipeline DGS mt Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 2017-jan 2017-Feb 2017-March 2017-Apr 2017-May 2017-June 2017-July 2017-Aug 2017-Sept 2017-Oct 2017-Nov 2017-Dec Jan-18 Feb-18 Crossing TB Crossing OC Facility & Facility &
Comp.date
Tie-ins Tie-ins
12" Raw gas Pipeline from Hammar IPF to Engineering/Survey/Permits Starting Construction Gas Lines(PPG-H IPF)
21 PPG - 1st Line - Interconnecting pipelines IPF H 10,937 Launching and Receiving Facilities TBD 3 10
PPG
PPG-IPF
12"Gas pipelines PPG-H 1 1
12" Raw gas Pipeline from Hammar IPF to 12"Gas pipelines PPG-H
22 PPG - 2nd Line - Interconnecting pipelines IPF H @ PPG and Hammar IPF
10,937 2857 2857 2500 1823 900 TBD 3 10
PPG
PPG-IPF
6 20
Tot. Raw Gas P/L 12" (m) 21,874
Last Update HOOK UP & GATHERING PLAN FOR NEW WATER INJECTION WELLS 2016 - 2017
3/July/2016
Hook-Up PLAN New WI 2016 Hook-Up PLAN New WI 2017 2018
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan-18 Feb-18
ZB-099 ZB-094 ZB-234 ZB-280 ZB-082 AH-21V AH-19_3 AM-36_M AO-30_3 AI-18
H M NCS H M NCS H M UMCS Z M LMCS Z SCS HM NCS HM NCS ZM LMCS ZM LMCS HM NCS
Starting Mob FL from ZB-247 from Zb-105 from Zb-207 FL existing
0----------> 0.1 km FL 2,9 km FL 3.3km New FL 1,0km FL 7.5km FL 4,7 km FL 5.4 km FL 2,3 km FL 3,0 km
ZB-075 ZB-219 ZB-207 ZB-272 ZB-297 AM-20_3 AQ-32_M AR-39_3 INJ-5
HU PLAN SCHEDULE H M NCS H M UMCS Z M LMCS H M NCS ZM LMCS HM NCS ZM LMCS ZM SCS HM UMCS
2016-2017 FL from ZB-278 FL existing FL existing
with Zb-099 FL 0,2 km FL 4.3 km FL 4,0 km FL 2.8 km FL 2,5 km FL 3,3 km
INJ-7
HM UMCS
CALL OFFs - PHASE 1 Starting Construction Gas Lines(PPG-H IPF)
FL 5,0 km

Zb-99
WI Zb-094 = 65 DD
ZB-219 = 30 DD
WI Zb-234 = 68 DD
New WI lines (Constr+Eng)

ZB-280 =50 DD
ZB-297 tot 75 dd
CORRIDOR A (Zb-297)
AM-36 tot 83 dd Compl. AM-36
WI AH-21 = 100 dd

CORRIDOR B (AH-21) AH-19 tot. 78 dd


AI-18 tot. 66 dd Compl. AI-18
WI AM-20 = 74 DD
WI AQ-32 = 66 DD
WI AO-30 = 60 DD
WI AR-39 = 62 DD
WI-UMCS INJ-7 (FL 5,5 km) = 81
DD
WI-UMCS INJ-5 (FL 3,2 km) = 68 DD
2x12"Gas pipelines PPG-H = 165 DD
CALL OFFs - PHASE 1

(*) Notes:
Zb-099: Current status=Zb-099 is connected to Zb-075 (WSW) by existing FL 6" #1500. Future Config= Zb-075 will be converted to WI well. New 100m connection from NCS to both Zb-099 & Zb-075. Hook-ups & Tie-In to be done.
Zb-094 conversion from Oil Prod. To WI.Well fed by NCS. Well HU, new line and tie-in from Zb-247 well head, to be done
Zb-219: Current configuration=WSW. Future Configuration=WI well - Well HU and tie-in from Zb-278 well head, to be done
Zb-234: Current configuration=WSW. Future Configuration=WI well - Well HU, new line and tie-in from Zb-105 well head, to be done
Zb-280: to be fed by Zb-207. Well HU and line from Zb-207 to Zb-280, to be done
Zb-082: Current configuration=WSW. Future Configuration=WI well - Well HU, Tie-in manifold and flowlines #1500 to be done
Rev 1 A) B) = A+10dd C = B+42dd D) E +D-C Reference to e-mail sent by Operation Mgr. on 20/6/2016 :

Hook-up Hook-up FL Flowlines Well HU Manif. Tie-in


7/4/2016 Wells Drilling Completio HO date date Delays FC2 Remark
(theorical) (Planned) completion km Nos. Nos.
ZFOD Presentation "Water Injection: Status & Way forward updated on 30/5/2016"
MID term actions LINES & Hook-up(planned to be completed before 1st OCT 2016):

Mob 9/1/2016
Survey 9/15/2016
Constr 10/1/2016
Dismantling by Maint. to be
SoW Prex Zb-099 Done 7/15/2016 8/26/2016 11/12/2016 78 Aug-16 11/12/2016 0.10 1 1 plannedW.I. coversion (from #900 HM flowlines and hook up in North Manifold
to #1500)

Dismantling by Maint. to be
SoW Prex Zb-075 7/5/2016 7/15/2016 8/26/2016 11/12/2016 78 Sep-16 (see Zb-099) 0.00 1 0 planned HM flowlines and hook up in North Manifold
W.I. coversion (from WSW)

W.I. conversion from Oil Producer


Zb-094 Done 7/15/2016 8/26/2016 12/17/2016 Aug-16 12/17/2016 2.91 1 0.50 FL connection from Zb-247 HM flowlines and hook up in North Manifold
113
Dismantling by Maint to be
planned - Hook-up after WO Sept flowlines and tie-in to Zb-278 (network flexibility – Upper Manifold)
NU Zb-219 9/30/2016 ### 11/21/2016 12/17/2016 26 Sep-16 12/17/2016 0.15 1 0.50 2016 HM
FL connection from Zb-278

Dismantling by Maint to be
flowlines and tie-in to Zb-108 (network flexibility – Upper Manifold)
NU Zb-234 Done 1/21/2017 Sep-16 1/21/2017 3.30 1 0.50 planned - Hook-up HM
FL connection from Zb-105

Zb-207 Done 1/21/2017 Aug-16 existing existing 1 1 Hook-up ZM hook up in Lower Manifold
Hook-up hook up in Lower Manifold (tie-in to Zb-207)
Zb-280 Done 2/25/2017 Nov-16 2/25/2017 1.00 1 0.50 ZM
FL connection from Zb-207
Zb-272 10/9/2016 ### 11/30/2016 2/25/2017 87 Oct-16 2/25/2017 0.13 1 1 Hook-up after WO Oct 2016 HM hook up in North Manifold
Zb-082 9/30/2016 ### 11/21/2016 4/8/2017 138 Oct-16 4/8/2017 0.17 1 1 Hook-up after WO Sept 2016 ZM hook up in South Manifold
Zb-289 Drilled as Oil Producer ZM flowlines and hook up in Lower Manifold
Zb-297 AL-35V 4/6/2017 4/16/2017 5/28/2017 5/28/2017 2/28/2017 4.27 1 1 Pipeline Corridor A ZM flowlines and hook up in Lower Manifold
AH-21_3V 4/6/2017 4/16/2017 5/28/2017 5/28/2017 5/28/2017 7.48 1 1 Pipeline Corridor B
AH-19_3 7/15/2017 7/25/2017 9/5/2017 9/5/2017 5/31/2017 4.71 1 1 Pipeline Corridor B
AM-20_3 7/15/2017 7/25/2017 9/5/2017 9/5/2017 9/5/2017 4.05 1 1
AM-36_M 10/6/2017 ### 11/27/2017 11/27/2017 4/20/2017 5.32 1 1 Pipeline Corridor A
AQ-32_M 10/15/2017 ### 12/6/2017 12/6/2017 12/6/2017 2.80 1 1
AO-30_3 10/21/2017 ### 12/12/2017 12/12/2017 12/12/2017 2.29 1 1
AR-39_3 10/21/2017 ### 12/12/2017 12/12/2017 12/12/2017 2.54 1 1
AI-18_M 12/15/2017 ### 2/5/2018 2/5/2018 5/31/2017 3.06 1 1 Pipeline Corridor B
INJ-5_M (WI-AP2 12/15/2017 ### 2/5/2018 2/5/2018 2/5/2018 3.29 1 1
INJ-7_M 12/31/2017 1/10/2018 2/21/2018 2/21/2018 2/21/2018 5.06 1 1

52.63 20.00 17.00


Notes: Pipelines in corridor(s) to be completed at once
BoQ WI lines Rev.0 4-Jul-2016
Well Elev New flw WELL
Notes Crossing TB Crossing OC Tie-in Manifold
n well DGS mt List of wells (geomatic) 4th July 2016 (msl) Comp.date Hook-UP

Zb-099 and Zb-075 are connected together (WS+WI). Detach the line and
1 Zb-099 HM NCS 100 750846.913 3384441.591 2.067 m 12-Nov-16 tie-in Zb-099 and Zb-075 to NCS (in one common line). The "T" connection 0 0 1 1
would have valves for both direction: 099 and 075

2 Zb-075 HM NCS 0 747821.922 3384351.427 2.292 m existing In common (comingle) with above Zb-099 0 0 1 0
Oil Wells became W.I. (fed by Zb-247). The pipe route is the centerline of
3 Zb-094 (from Zb-247) HM NCS 2912 752012.161 3379264.730 2.5 m 12/17/2016 0 1 1 0.5
seismic NTS. There is a request to enlarg NTS
4 Zb-219 (WI-013) from Zb-278 HM UMCS 150 745540.018 3378601.437 1.992 m 12/17/2016 U/G Tee cold cut on Zb-278 JV flowline 0 0 1 0.5
Flowline built by JV - missing hook-ups (Well and UMCS). there is crossing
5 Zb-234 (WI-P15) from Zb-105 HM UMCS 3300 1/21/2017 1 4 1 0.5
754786.815 3376042.658 2.709 m of high-way (inside existing culvert)
6 Zb-207 (WI-120S) ZM LMCS 0 755061.389 3369595.776 14.799 m existing Existing Flowlines, only hook-ups Well and LMCS 0 0 1 1
7 Zb-280 (WI-O23 Dir) from Zb-207 ZM LMCS 998 755902.928 3369581.663 12.511 m 2/25/2017 connection from Zb-207 0 0 1 0.5

8 Zb-272 (WI-AF15) HM NCS 132 743880.4549 3386199.5033 2.174 2/25/2017 Existing line built by JV. Extension of line (Re-routing) and hook-ups(Well 0 0 1 1
and NCS) to be done

9 Zb-082 HM SCS 170 753463.129 3363609.526 19.215 m 4/8/2017 It was N.U. Producer. To be surveyed to see dismantling of Hus and 0 0 1 1
Flowlines
10 Zb-297 (AL-35V) LMCS 4269 748999.288 3368209.050 4.597 m 2/28/2017 1 5 1 1
11 AM-36_M LMCS 5319 749818.148 3367090.04 4/20/2017 1 6 1 1
12 AH-21_3V NCS 7476 745592.000 3380276.000 5/28/2017 0 4 1 1
13 AH-19_3 NCS 4713 745805.845 3382198 5/31/2017 0 2 1 1
14 AI-18_M NCS 3058 746621.845 3383570.46 5/31/2017 0 1 1 1
15 AM-20_3 NCS 4045 749971.608 3381867.36 9/5/2017 0 1 1 1
16 AQ-32_M LMCS 2798 753787.87 3370923.51 12/6/2017 0 2 1 1
17 AO-30_3 LMCS 2294 751979.447 3372443.61 12/12/2017 0 2 1 1
18 AR-39_3 SCS 2545 754515.12 3365303.82 12/12/2017 0 7 1 1
19 INJ-5_M (WI-AP24) UMCS 3291 751833.852 3378551.53 2/5/2018 1 1 1 1
20 INJ-7_M UMCS 5055 753036.67 3375740.81 2/21/2018 2 3 1 1
Corridor A 6 39 20 17
Corridor B

Well pad covered by NTS confirmed coordinates


Tot. New Flws #1500 10" (m) 52,625 tot. # new flowlines 18
Average 4,078 tot. # exist flowlines 2

Gas lines Notes Crossing TB Crossing OC launching and Tie- Receiving and Tie-in
n Pipeline DGS mt Comp.date in

21 12" Raw gas Pipeline from Hammar IPF to PPG - 1st IPF H 10,937 3 10 1 1
Line - Interconnecting pipelines PPG-IPF PPG

22 12" Raw gas Pipeline from Hammar IPF to PPG - 2nd IPF H 10,937 3 10 1 1
Line - Interconnecting pipelines PPG-IPF PPG
6 20
Tot. New Raw Gas Pipelines 12" (m) 21,874
BoQ WI lines Rev.0 4-Jul-2016 CALL OFFs PHASE 1
CO 4 CO 4 CO 5 CO 6
CO 1 CO 2 CO 3 Tie-in to
n well DGS FLW mt Mob. Flw m Well Hus Nos. TB
Nos
Crossings OC Crossings
Nos
Tie-in Manif.
Nos. existing Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 2017-jan 2017-Feb 2017-March 2017-Apr 2017-May 2017-June 2017-July 2017-Aug Latest
Comp.date
(Opt) (Opt) (Opt) (Opt) (Opt) Flw/Wells
Nos. (Opt)
80 HU - 12-Nov-16 11/12/2016
1
100 12-11-2016 11/12/2016
1 Zb-099 HM NCS 100 0 0

To be QUOTED case by case


Tie-in NCS 11/12/2016
1
12-Nov-16 11/12/2016
1 HU - 12-Nov-16
existing
2 Zb-075 HM NCS 0 0 0
(Existing flw)
11/12/2016
1165 1165 12/17/2016
1 HU - 17-Dec-16
2912 12/17/2016
3 Zb-094 (from Zb-247) HM NCS 2912 0 1 Tie-in 17-12-2016
0.5 Zb-247
#VALUE! 12/17/2016
1 HU - 17-Dec-16
150 12/17/2016
4 Zb-219 (WI-013) from Zb-278 HM UMCS 150 0 0 Tie-in 17-12-2016
0.5 Zb- 278
#VALUE! 1456 1/21/2017
1 HU - 21-Jan-17
3300 1/21/2017
5 Zb-234 (WI-P15) from Zb-105 HM UMCS 3300 1 4 Tie-in 21-1-2017
0.5 Zb- 105
1/21/2017
1
Call OFF Phase 1 <--
HU - 21-Jan-17
Zb-207 (WI-120S) existing
6 ZM LMCS 0 0 0
(existing Flw) Tie-in LMCS
1 21-Jan-17 1/21/2017
499 HU - 25-Feb-17 2/25/2017
1
998 25-2-2017 2/25/2017
7 Zb-280 (WI-O23 Dir) from Zb-207 ZM LMCS 998 0 0 Tie-in
0.5 Zb- 207
HU - 25-Feb-17 2/25/2017
1
132 25-2-2017 2/25/2017
8 Zb-272 (WI-AF15) HM NCS 132 0 0
1 Tie-in NCS
25-Feb-2017 2/25/2017
23 116 31 HU - 8-Apr-17 4/8/2017
1
170 8-4-2017 4/8/2017
9 Zb-082 HM SCS 170 0 0
1 Tie-in SCS
8-Apr-2017 4/8/2017
1708 1594 HU - 28-May-17 5/28/2017
Zb-297 (AL-35V) 1
10 LMCS 4269
4269
1 5
Corridor 3300m 28-2-17 PRESERV. FLW (tbd) 2/28/2017
(Pipeline in Corridor A) Tie-in LMCS
1
PIPELINEs LAID IN THE SAME TRENCH 28-May-2017 5/28/2017
1708 1594 11/27/2017
AM-36_M
11 LMCS 5319
5319
1 6
Corridor 3300m 20-4-17 PRESERVATION FLOWLINE (tbd) 4/20/2017
(Pipeline in Corridor A)
11/27/2017
#VALUE! 2265 HU - 28-May-17 5/28/2017
AH-21_3V 1
7476 28-5-2017 5/28/2017
12 NCS 7476 0 4
(Pipeline in Corridor B) Tie-in NCS
1 28-May-2017 5/28/2017
1400 1400 9/5/2017
AH-19_3
13 NCS 4713
4713
0 2
Corridor 2800m 31-5-2017 PRESERVATION FLOWLINE (tbd) 5/31/2017
(Pipeline in Corridor B) PIPELINEs LAID IN THE SAME TRENCH
9/5/2017
1000 1000 2/5/2018
AI-18_M
14 NCS 3058
3058
0 1
Corridor 2000m 31-5-2017
31-5-2017 PRESERVATION FLOWLINE (tbd) 11
6 5/31/2017
2
(Pipeline in Corridor B) - -2
-
1 2/5/2018
11
2
5-9-2017 21-2-2018
2
MOBILIZATION 1 2
- 12/31/2016
-
31-12-2016 2 2-
0 02
Call Off Q.ty 1 32,597 11 3 23 6 HOLD 1 11
0
7 7
7
Target IGRS Target IGRS Cluster or Stand Surface IGRS Surface IGRS Offset from Demining
GRIDRESERV WELTYPE EASTING NORTHING DGS RESERVOIR STATUS YEAR CODE alone EASTING NORTHING Target TS LA Area TS
AM-29 Dir PRODUCER 750188 3373624 Hammar 3P Grid 2017 3 749713 3372927 843 m
AZ-56 Dir PRODUCER 761888 3349323 Rafidiya 3P Grid 2017 3 762467 3348993 667 m 40000 m²
AI-15 PRODUCER 746588 3386224 Hammar Mishrif 3P Grid 2017 3 746769 3386052 250 m 40000 m²
AK-22 PRODUCER 748388 3379924 Hammar 3P Grid 2017 3 748137 3380194 369 m 20000 m²
AK-23 PRODUCER 748388 3379024 Hammar Mishrif 3P Grid 2017 3 747915 3379114 481 m 20000 m²
AP-36 Dir PRODUCER 752888 3367324 Zubair Mishrif 3P Grid 2017 3 752420 3367065 535 m 5000 m²
AP-42 Dir PRODUCER 752888 3361923 Zubair 3P Grid 2017 3 753893 3362348 1091 m
AQ-43 Dir PRODUCER 753859 3361344 Zubair 3P Grid 2017 3 754437 3360910 723 m
AO-31 PRODUCER 751988 3371824 Hammar Mishrif Grid 2017 2 751920 3371824 68 m
AN-28 (Dir/V) PRODUCER 751088 3374524 Hammar Mishrif Grid 2017 2 750845 3374315 320 m
AN-29 Dir PRODUCER 751088 3373624 Hammar Mishrif Grid 2017 2 750892 3374261 667 m
AO-37 PRODUCER 751988 3366424 Zubair Mishrif Mishrif Grid 2017 2 752584 3365993 735 m
AQ-37 PRODUCER 753788 3366424 Zubair Mishrif Mishrif Grid 2017 2 753347 3366108 542 m 36000 m²
AN-35 PRODUCER 750335 3368644 Zubair Mishrif Mishrif Grid 2017 2 750335 3368644 m
AK-18 INJECTOR 748458.3 3383526 HM NCS Manifold 3P Grid INJ 2017 3 748458.264 3383526.25 m 40000 m²
AL-37 INJECTOR 749287.9 3366424 ZM Manifold 3P Grid INJ 2017 3 749287.86 3366423.5 0m 40000 m²
AH-19 INJECTOR 745805.8 3382198 HM Manifold 3P Grid INJ 2017 3 745805.845 3382198 m
AM-20 INJECTOR 749971.6 3381867 HM manifold 3P Grid INJ 2017 3 749971.608 3381867.36 m
AR-39 INJECTOR 754515.1 3365304 Zubair Manifold 3P Grid INJ 2017 3 754515.12 3365303.82 m 15000 m²
AR-45 INJECTOR 754687.9 3359223 Zubair Manifold 3P Grid INJ 2017 3 754687.884 3359223.48 m 40000 m²
AO-30 INJECTOR 751979.4 3372444 H Manifold 3P Grid INJ 2017 3 751979.447 3372443.61 m
AG-16 INJECTOR 744787.8 3385324 HM Manifold 3P Grid INJ 2017 2 744787.83 3385323.54 m 40000 m²
AQ-32 INJECTOR 753787.9 3370924 LMCS Mishrif Grid INJ 2017 2 753787.87 3370923.51 m 40000 m²
INJ-5 INJECTOR 751833.9 3378552 UMCS Mishrif Grid INJ 2017 2 751833.852 3378551.53 m 40000 m²
INJ-7 INJECTOR 753036.7 3375741 H Manifold Mishrif Grid INJ 2017 2 753036.67 3375740.81 m
AI-18 INJECTOR 746621.8 3383570 HM NCS Manifold Mishrif Grid INJ 2017 2 746621.845 3383570.46 m 40000 m²
AM-36 INJECTOR 749818.1 3367090 ZM Manifold Mishrif Grid INJ 2017 2 749818.148 3367090.04 m 40000 m²
496000 m²

2017 Wells Screening Summary


Total Wells = 27
Stand Alone 10
Grouped 17
Approved Wells 6
Wells with Land Allotment Problems 1 TBC wih committee
Wells Requiring TS Clearance & m² 13 490000 m² @ $217,580 213280
Wells Exceeding Offset Criteria 3 Targets to be investigated
Mishrif Wells 11 6 OP & 5 INJ
3rd Pay 16 8 OP & 8 INJ
GEOs Remarks
Cluster with ZB-198. Scouted MB 22.06.2016 Committee Approved
Cluster with ZB-065.Scouted by MB 24052016. Committee Approved however waiting for LA clearance. TS Demining Required. RESV to investigate TARGET.
To be confirmed by RESV after AH-16 results.TS required 200x200m.
Cluster with ZB-166. Approved location. Extension of TS required 100x200m. Scouted by GS and committee approved 06.06.2016
Cluster with ZB-080. Extension of TS Required 100x200m. RESV to investigate final target
Cluster with ZB-226. Approved location. Extension of TS required 50x100m.Scouted by GS and committee approved 06.06.2016
Cluster with ZB-151B. RESV to investigate final target. To be evalueted near to ZB-255
Cluster with ZB-348. New target received from Dubai 6.6.2016
Cluster with ZB-281.Scouted by GS and committee approved 06.06.2016
Cluster with ZB-284. Scouted by GS and committee approved 06.06.2016. RESV to investigate final target
Cluster with AN-28 & ZB-284. Previous Approved old well AM2710 Dir. Re-scouted by GS 22.06.2016 approved by committee
Cluster with ZB-251 & AO-38. Scoutedby GS and committee approved 06.06.2016. RESV to investigate final target. Same target ZB-263
Partial Failed NTS site. TS required. Proposed Flow line has NTS. RESV to investigate final target
Approved site at AM3213.
Stand Alone well close to NCS Manifold. TS required 200x200m.
Stand Alone well. Flow line corridor has demining clearance
Cluster with ZB-201. Flow line corridor has demining clearance
Cluster with ZB-187
Cluster with ZB-126. Extension of TS required 100x150m
Stand Alone well. TS required 200x200m
Cluster with ZB-148
Stand Alone well. TS required 200x200m
Stand Alone well. TS required 200x200m
Stand Alone well. TS required 200x200m
Cluster with ZB-256.
Possible to use approved location AI1711V 100m E. TS required 200x200m
Possible to use approved location AM3410V ( 15m N). TS required 200x200m

Wells previously approved with LA


LA difficult to acquire and possibly requires large offset. TBC by committee