DSI‐5000008451 CALL 

OFF 03 CALL OFF 03

A1.1 - Water Injection Wellhead area hook up - WI-WEL-002 - 10" pipe 11 OPT. SoW WI 11 OPT. SoW WI
PRICE BREAKDOWN SCHEDULE -LUMP SUM PRICE (LS) WELL HEAD  WELL HEAD 
ITEM L0 ITEM L1 ITEM L2 ITEM L3 Description
PREFAB INST. w/o ELE/INS
0.0 PROJECT MANAGEMENT AND SUPPORT ACTIVITIES
0.0a Project Management $8,591.40 $13,364.40
0.0b Support Activity $5,727.60 $8,909.60
1.0 ENGINEERING
1.0a Survey $7,955.00
1.0b Civil Plot‐Plan/Layouts and Details $7,955.00

1.0c Piping Plot Plan/Welding Map/Isometric/Piping Layouts $13,258.34

1.0d E&I Layouts/wiring diagrams $10,606.67

1.0e Detailed bill of material $7,955.00


1.0f As Built documentation $3,022.90
2.0 MATERIAL SUPPLY
2.0a Material Take off $15,910.00
2.0b Purchase Order Placed $42,426.68
2.0c Material on Site $47,730.01
3.0 INSTALLATION
3.0a Civil and Structural Works
3.0a.01 Valve Pit, piping supports and foundation for CP Test post
3.0a.01.01 Prefabrication a.m. items 3.0a.1 $18,561.67
3.0a.01.02 Installation a.m. items 3.0a.1 $18,561.68
3.0a.02 cable trench for Electr cable and FOC from well pad's fence (flowline end) to LER
3.0a.03 cable trench and manholes from LER to WHCP and Xmas Tree, LER
3.0a.04 foundation for WHCP and Filters $18,561.67
3.0a.05 Installation of Platform and walkway (within Xmas Tree, including the Junction Box and field 
Instruments supports)
3.0a.05.01 Prefabrication $18,561.67

3.0a.05.02 Installation $18,561.67

3.0a.06 Installation of cellar grating

3.0a.06.01 Prefabrication $18,561.67

3.0a.06.02 Installation $18,561.67


3.0a.07 Earthing/Grounding
3.0a.07.01 Earthing System. Installation and Connection of earth electrodes, earthing groundbeds,  $12,993.17
system earthing, including bonding of all electrical equipment, skids and structure

3.0a.07.02 Earthing system for LER 
3.0b Piping, Equipment and Painting Works

3.0b.01 Piping pre‐fabrication welding/PWHT/NDT/painting $64,965.85


3.0b.02 Piping and equipment(filters) erection at field (welding/PWHT/NDT/coating) $83,527.52

3.0b.03 Cleaning $9,280.84


3.0b.04 Hydrotest/dewatering $18,561.66
3.0b.05 Reinstatement $9,280.84
3.0c Electrical and I&C Works

3.0c.01 Laying LV Electrical cable from end of flowline to LER (in cable trench 3.0a.02)
3.0c.02 Laying FOC from end of flowstation to LER (in cable trench 3.0a.02)
3.0c.03 Laying LV cable from LER to WHCP (in cable trench 3.0a.03)
3.0c.04 Laying LV cable from LER to Field Instruments PT and TT, Ultrasonic Flowmeter and remote 
Junction box (in cable trench 3.0a.03)
3.0c.05 Laying I/O cables from Field Instruments PT, TT, Ultrasonic flowmeter and remote Junction 
box to LER (in cable trench 3.0a.03)
3.0c.06 Laying I/O cables from WHCP to LER (in cable trench 3.0a.03)

3.0c.07 Installation of Containeraized E&I Substation (LER)
3.0c.08 Cabling hook‐up LV cable to LV Switchgear (inside LER)
3.0c.09 lay FOC cable inside LER and left it, coiled. under the pavement of TC room
3.0c.10 Cabling, hook‐up of El. Cable from LER LV switchgear to Field Instr (i.e. PT, TT & Ultrasonic 
Flowmeter, and remote Junction box)
3.0c.11 Cabling, hook‐up of El. and instr. Cables from LER LV switchgear to WHCP
3.0c.12 Cabling, hook‐up of CP
3.0d Mechanical Completion dossier
3.0d.01 Mechanical/Civil/Field Instr. And cables $70,163.12
3.0d.02 LER
3.0e Final  Mechanical Hook‐up and tie‐ins $74,246.68
4.0 PRE‐COMMISSIONING, COMMISSIONING AND START UP
4.0a Mechanical Pre‐commissioning $21,213.34
4.0b Instrument calibration $10,606.67
4.0c Electrical Pre commissioning
4.0c.01 $4,242.67
Earthing ‐  testing of earth electrodes, earthing groundbeds,
system earthing, including bonding of all electrical equipment, skids and structure`

4.0c.02 Pre commissioning for Field Instruments (PT, TT, FM, FOC etc..)‐ Megger test and OTDR

4.0c.03 Electrical Pre commissioning for LER and its equipments (HVAC, F&G, LV Switchgears, UPS 
and batteries)
4.0c.04 Electrical Pre commissioning for external equipment installed by Contractor or by Other and 
fed by LER (WHCP)
4.0c.05 Cathodic Protection pre‐commissioning $2,121.33
4.0d COMMISSIONING & START‐UP
4.0d.01 Mechanical $26,516.67
4.0d.02 LER

TOTAL  PRICE $288,766.56 $442,298.10