Professional Documents
Culture Documents
Ts 02780 Culvert Inspection Risk Assessment Technical Manual
Ts 02780 Culvert Inspection Risk Assessment Technical Manual
1 Background
TS 02780:1.0 references AS/NZS ISO 31000:2009 Risk management – Principles and
guidelines for risk assessment. With the publication of latest version, all references to
AS/NZS ISO 31000:2009 is now replaced with AS ISO 31000:2018 Risk management -
Guidelines.
2 Amendment to TS 02780:1.0
The sections in TS 02780:1.0 Technical Manual for Culvert Inspection and Risk Assessment -
Road are to be amended as follows:
The Manual is based on the approach suggested in AS ISO 31000:2018, Risk management –
Guidelines.
This Manual provides a systematic set of instructions that allow TfNSW to apply
AS ISO 31000:2018 to culvert risk management. The following sections outline this approach.
Authorisation:
Remove the blue colour box before the image is inserted, select the blue shape,
then right click and choose – Format Shape. Choose No fill on the Fill tab.
Resize and position the image as required.
Title: Technical Manual for culvert inspection and risk assessment – Road
For queries regarding this document, please email Transport for NSW Asset Management Branch
at standards@transport.nsw.gov.au or visit www.transport.nsw.gov.au
Contents
1 Introduction ............................................................................................................................. 1
1.1 Structure of the Manual..................................................................................................... 1
1.2 The Culvert Management Framework ............................................................................... 2
1.3 Inspection and Risk Assessment Approach ...................................................................... 3
1.4 Personnel Roles ............................................................................................................... 3
1.5 Definitions ......................................................................................................................... 3
1.6 Training ............................................................................................................................ 4
1.6.1 General training goals ........................................................................................... 4
1.6.2 Specific training goals ............................................................................................ 4
1.6.3 Other Training Requirements ................................................................................ 5
2 Inspection Planning and Overview ........................................................................................ 6
2.1 Inspector Responsibilities ................................................................................................. 6
2.2 Risk Assessor Responsibilities ......................................................................................... 6
2.3 Available Information ........................................................................................................ 6
2.3.1 Essential Information for Inspection and Risk Assessment .................................... 6
2.3.2 Additional Information ............................................................................................ 6
2.4 Safety on Site ................................................................................................................... 7
2.4.1 Safety around Traffic ............................................................................................. 7
2.4.2 Confined Spaces ................................................................................................... 7
2.4.3 Difficult Access ...................................................................................................... 7
2.5 Planning Checklist ............................................................................................................ 8
2.6 Field Equipment Checklist ................................................................................................ 8
2.6.1 Inspection equipment ............................................................................................ 8
2.6.2 Safety equipment................................................................................................... 9
2.6.3 Bush clearing equipment ....................................................................................... 9
2.6.4 Equipment check ................................................................................................... 9
2.7 Stage One – Culvert Inspection ........................................................................................ 9
2.8 Stage Two - Risk Assessment ........................................................................................ 10
3 Culvert Data Collection (CDC) Application.......................................................................... 11
3.1 Culvert Data.................................................................................................................... 11
3.1.1 Pre-existing Culvert Information........................................................................... 11
3.1.2 New Inspection Information ................................................................................. 11
3.2 Culvert Selection............................................................................................................. 11
3.2.1 Main Screen ........................................................................................................ 11
3.2.2 Culvert Selection ................................................................................................. 12
Technical Manual Culvert Inspection and Risk Assessment – February 2022 iii
Version 1.0 UNCONTROLLED WHEN PRINTED
Technical Manual Culvert Inspection and Risk Assessment – February 2022 vii
Version 1.0 UNCONTROLLED WHEN PRINTED
List of Figures
Figure 1 Culvert Management Framework ...................................................................................... 2
Figure 2 Culvert with junction pits - one culvert ............................................................................. 14
Figure 3 Culverts in a Network ...................................................................................................... 15
Figure 4 Roadside and Actual Locations ....................................................................................... 33
Figure 5 Left, Right or Centre ........................................................................................................ 34
Figure 6 Marking at roadside ........................................................................................................ 35
Figure 7 Depth of Cover ................................................................................................................ 36
Figure 8 Culvert too short.............................................................................................................. 36
Figure 9 Grates ............................................................................................................................. 37
Figure 10 Flood gates ................................................................................................................... 38
Figure 11 Tidal flows ..................................................................................................................... 38
Figure 12 Example Sketch ............................................................................................................ 83
Figure 13 AS/NZS ISO 31000 Risk Management Process ............................................................ 87
Figure 14 Risk Assessment Flowchart .......................................................................................... 89
Figure 15 Embankment example .................................................................................................. 95
Figure 16 Cut slope example ........................................................................................................ 95
Figure 17 Structural collapse of the barrel ................................................................................... 104
Figure 18 Instability caused by afflux .......................................................................................... 108
Figure 19 Instability due to leakage / headwall collapse / undermining........................................ 112
Figure 20 Piping failure modes.................................................................................................... 121
Figure 21 Erosion by overtopping flows (fill example) ................................................................. 131
Figure 22 Erosion by overtopping flows (cut and fill example) ..................................................... 131
Figure 23 Cross Catchment Flooding (a) .................................................................................... 135
Figure 24 Cross Catchment Flooding (b) .................................................................................... 135
Figure 25 Temporal Probability based on traffic volume .............................................................. 146
Figure 26 Example RoadLoc Diagrams....................................................................................... 158
Figure 27 Segment marking example.......................................................................................... 158
List of Tables
Table 1 Culvert Purpose ............................................................................................................... 21
Table 2 Road Condition ................................................................................................................ 27
Table 3 Inlet / Outlet Flow ............................................................................................................. 39
Table 4 Inlet / Outlet Adverse Conditions ...................................................................................... 41
Table 5 Culvert Type..................................................................................................................... 51
Table 6 Barrel or cell construction ................................................................................................. 52
Table 7 Culvert Joints ................................................................................................................... 56
Table 8 Box Culvert Type.............................................................................................................. 57
Table 9 Lining Type ...................................................................................................................... 60
Table 10 Lining Materials .............................................................................................................. 61
Table 11 Barrel Flow ..................................................................................................................... 64
Table 12 Structure Condition ........................................................................................................ 67
Table 13 Pit Attributes ................................................................................................................... 76
Table 14 Pit Types ........................................................................................................................ 77
Table 15 Photograph Examples .................................................................................................... 80
Table 16 Routine maintenance ..................................................................................................... 85
Table 17 Risk Screening / Hazard Relationship ............................................................................ 91
Table 18 Likelihood Factor Values ................................................................................................ 93
Table 19 Culvert Risk Level .......................................................................................................... 98
Table 20 ARL Descriptions ........................................................................................................... 99
Table 21 SC-1.1 Failure Likelihood Range .................................................................................. 105
Technical Manual Culvert Inspection and Risk Assessment – February 2022 viii
Version 1.0 UNCONTROLLED WHEN PRINTED
1 Introduction
Transport for NSW (TfNSW) have an established framework for the long-term management of
culverts across the TfNSW road network. The culvert management framework consists of two key
components:
• Collection of culvert inventory, condition and initial risk screening – Inspection.
• Conducting a detailed risk assessment of culverts if an assessment is required – Risk
Assessment.
This work is being undertaken as part of ongoing asset management works to ensure safety and road
network availability. The information collected will provide TfNSW with improved knowledge of
potential culvert risks and allow for priority programming of repair works.
Subsequent re-inspections and re-assessments are called up where necessary to manage culverts
which have been identified as requiring ongoing monitoring until defects are treated or culverts are
replaced. The inspection frequency cycle is nominated in the TfNSW Technical Procedure ILC-AM-
TP1-603 Culvert Asset Management.
Where re-inspection and re-assessment are required, the Inspection and Risk Assessment
components will typically be combined and performed as one process in the field as described in this
document.
Circumstances may exist however where either the Inspection or the Risk Assessment will be
completed as a stand-alone process.
Finalisation
Section 15 Inspection and Assessment Completion
Information
Section 16 Supplementary Information
Section 17 Glossary
Section 18 Index
• A central database of all culvert location and condition data, developed as a module of the Road
Asset Management System (RAMS).
1.5 Definitions
The following definitions are pertinent to the culvert inspection process. For a full list of definitions
refer to the Glossary.
• Inspection – a field inspection of a culvert involving collecting and/or verifying inventory data and
reporting on general condition items including the Risk Screening Checklist. Conducted by a
TfNSW certified Inspector or Risk Assessor.
• Risk Screening – conducted during the Inspection stage, involving rating certain defects as either
Urgent, Advanced, Visible or Nil – if items are Urgent or Advanced, then a Risk Assessment is
required.
1.6 Training
Inspectors and Risk Assessors must be trained, assessed, and certified by TfNSW in the inspection
and risk assessment process described in this document. Their details will be entered in the database
as able to conduct either inspection only or both inspection and risk assessment.
Inspector
Training of Inspectors will be undertaken in a two day workshop and consists of training, assessing
and certifying Inspectors in the Inspection process only.
Risk Assessor
Training of Risk Assessors will be undertaken in a four day workshop. Training consists of training,
assessing and certifying Assessors in the:
• Inspection process.
• Risk Assessment process.
Once issued with an Assessor number, each Assessor is certified to undertake Inspection and Risk
Assessment of culverts.
In this document, references to Inspectors, Inspector Training or Training also includes Risk
Assessors.
− maintenance issues that, if identified early, can prevent the eventual failure of a culvert or
embankment
• Familiarising Inspectors with the use of required equipment such as:
− data capture devices
− CDC application
− cameras and lighting – quality and consistency of images
• Describing the risk assessment theory, and the generation of an Assessed Risk Level (ARL).
• Instilling consistency in undertaking Risk Assessments.
• Ensuring that the limitations of this inspection process are known. For example, restrictions may
apply when inspecting a culvert –culvert barrels are considered a “confined space”.
• Describing common rehabilitation methods and their application.
• Undertaking worked examples of the Risk Assessment process – a primary goal being to develop
a system of uniformity amongst trainees.
• Slope Numbers for slopes on the section of road – available from the Project Manager from the
Road Slope Management System (RSMS).
• Bridge Numbers for any bridge sized culverts on the section of road - available from the Project
Manager from the Bridge Information System (BIS).
• Hydraulic information, where available, including design flow, catchment size, rainfall data.
• Pavement status and pavement works information.
1. An assessment must be made as to whether a safe inspection is possible. For instance, the
culvert may be on a steep embankment and rope access may be required.
2. If deemed safe, then proceed with caution.
3. If any external equipment is required to access a culvert (e.g. rope and harness), the Inspector
must be suitably trained with that equipment prior to use.
4. If deemed unsafe to proceed, then a note should be made on the General tab of CDC in the
Culvert Comment box with wording such as “Culvert unable to be inspected – rope and harness
required” or similar.
• Complete the Risk Screening checklist. This will determine whether a Risk Assessment will be
required for that culvert.
• Complete the list of photographs and make a site sketch if needed to show access routes and
identify concerns.
• If you find a culvert that has not been recorded or inspected previously, then start a NEW culvert
record, fill in all required details including location and complete the inspection as described
above. Ensure to notify the TfNSW Project Manager of its existence and location.
• If the culvert is in a condition requiring urgent attention – contact the TfNSW Project Manager.
The “Select Culvert” button should be clicked; this will open the following screen.
From here, the process below can be followed to correctly select the culvert that you will be
inspecting.
4 Culvert Features
2) A series of short longitudinal culverts can be considered a single culvert with intermediate
pits, provided the maximum overall length from inlet to outlet is <50 m, the culvert has uniform
size and construction along its length, and minor invert level changes (<100 mm) at the
intermediate pits.
Transverse and longitudinal culverts should always be separate culverts (except where the
longitudinal pipe is very short and simply joining two adjacent pits).
5 Inspection
What to record:
• If the culvert has an existing number, ensure it matches with your current location.
• For new culverts, the Project Manager will have supplied available culvert numbers.
5.2.2 Region
About the data:
• This is a mandatory field
• Regions are as follows:
− Northern
− Hunter
− Western
− Southern
− Southwest
− Sydney North
− Sydney West
− Sydney South
What to record:
• The region name will be shown in CDC and cannot be changed for an existing culvert.
• For a new culvert, the Region is selected in the Setup form.
What to record:
• There is no need to record any data.
What to record:
• Unless advised otherwise by the Project Manager, do not complete this field.
• If there is a Bridge Number for the culvert, you must enter it in this field in the form BN1234. An
inspection is not required.
What to record:
• The date will automatically populate with the date at which you opened a new inspection form.
5.2.6 Inspectors
About the data:
• There are fields to enable identification of up to two Inspectors.
• Entry of at least one Inspector is mandatory.
• Only certified inspectors can be entered here.
What to record:
• Select certified Inspector name/s from the drop down box.
• If a name is not available, check with your project manager that you have the latest available
reference data.
• The second field remains blank if only one Inspector is certified.
What to record:
• A comment should be added regarding location, access, and non-critical issues.
• Comments may include:
− Proximity or distance to intersection, landmarks or distinctive features, e.g. “near State Creek”
or “100 metres south of Anzac Bridge
− Any specific access requirements, difficulty, equipment or restrictions, e.g. “Access on opposite
carriageway, access requires permission from house 100 metres north of road”
What to record:
• Where the speed limit is already shown in CDC, check that the value is correct. If the value is not
already shown or is incorrect, select the appropriate speed limit from the drop down box.
What to record:
• It is mandatory to select type from Table 1.
• Select the main purpose if more than one seems to apply.
• Culverts that are classified as bridge structures do not require inspection or risk assessment. If a
culvert of this type is identified during an Inspection, discontinue the Inspection and notify the
Project Manager.
Table 1 Culvert Purpose
Stock/Fauna Access Culvert Stock / fauna access culverts are built for
stock / fauna passage under busy roads
Stock / fauna access culverts are
classified as bridge structures and do not
require inspection or risk assessment
What to record:
• Select one or more of the fill types.
• If ‘Other’ is selected, provide a description. A selection can be made from the drop down box or
entered using text (up to 200 characters). “Natural Fill” is not an adequate description – indicate
the type of soil in the local area that would have been used.
• If the pavement or kerb is constructed directly on top of the culvert, indicate the fill material either
side.
If plans are not available for a culvert, the Inspector may be able to source the information in the field.
Occasionally design data is marked on the culvert. If data is on the culvert, copy it into the relevant
section on the form.
Plan Number, Pipe / Box Number
• These are mandatory if plans are available.
• The two items are optional text fields (of up to 50 characters in total).
• The plan number and sheet number are located at the bottom right of each plan.
• The pipe / box number (depending on type of culvert) may be located in tabular format or adjacent
to the drainage line on a drainage plan sheet. Older plans will simply refer to the culvert chainage.
Capacity Description
• This describes the design capacity of the culvert.
• This item is an optional text field of up to 200 characters.
• The capacity description will be located in a tabular format on a drainage plan sheet. It is only
occasionally present.
Discharge
• This is the discharge volume in cubic metres per second.
• This item is mandatory if drainage plans are available and is a numeric field.
• Discharge rate is usually presented in a table within the set of Design plans.
• Discharge should be stated in cubic metres per second (cu m/s).
Construction / Reconstruction Date
• These are the dates on which the culvert was constructed and underwent major reconstruction.
• These items are optional date fields with format dd/mm/yyyy (e.g. 25/03/2014).
Reconstruction Comments
• This describes the latest major reconstruction of the culvert.
• This item is an optional text field of up to 20 characters.
What to record:
• Enter the plan and sheet number, separated by a comma.
• Enter the pipe or box number.
• Enter the capacity description as found.
• Enter the discharge rate number. Ensure litres per second is converted to cubic metres per
second by dividing by 1,000 (1,000 L/s = 1 cu m/s). If older units are used, record the discharge
rate and units in the Capacity Description box.
• Enter the construction or reconstruction date if known. Enter 1 January as the date to enter year
only.
• Enter a brief description of major reconstruction work, if any and if known.
What to do:
The Inspector should consider potential issues associated with the culvert. For instance – is the
immediate catchment for the culvert large, with only a small diameter culvert? How does its situation
compare to its designed / intended performance / capacity?
What to record
• Enter comments as appropriate.
• Select the check box for History of water flow over road where the following apply:
− An observed high water mark above the top of barrel on the headwall, embankment, other
structures or trees
− Flood indication markers are present
− Culvert submerged
− Evidence of debris flowing over road or above the top of the barrel
− Debris found under guardrail indicating possible water flow over road
− Local historical information from Project Manager or residents
What to do:
• The Inspector should make site observations of adverse structural indications on the surface of the
roadway, including:
− Pavement cracks parallel or perpendicular to the culvert centreline. This could indicate
embankment instability. If cracking extends through travelled lanes, notify the Project Manager
immediately
− Frequent patching, crack sealing, potholing or pothole patches. Significant potholes should be
reported to the Project Manager immediately
− Guardrail sag (vertically or horizontally). This could indicate embankment instability
− Depressions in the road surface. This could indicate embankment instability, piping or culvert
structure collapse
• Provide photographs of all adverse features and a sketch (if necessary) showing location,
dimensions and widths / depths.
What to record:
• Enter a comment about adverse conditions. Describe location and extent of faults and damage.
• A selection can be made from the drop down box or entered using text (up to 200 characters).
• If condition is good, write “Good”.
• Table 2 below details relevant road condition items to be aware of when inspecting the culvert.
Table 2 Road Condition
Condition and Example Photograph What to Record
Visible Up to 50 mm depression
Locate the inlet / outlet and complete the relevant items. Items at both locations are similar, with some
extra items for the outlet.
Using CDC, pressing the “Find” button beside the location coordinates will direct you to that location
using an internal or connected GPS unit.
If a culvert cannot be located in the field after a reasonable amount of time is spent looking (nominally
30 minutes), then note this in the Culvert Comment box with wording such as “Culvert could not be
located” and notify the Project Manager.
Be alert for culverts that may not have been located during previous inventory or inspections and are
not shown on design plans. If you do find such a culvert, notify the Project Manager. They may
request that you create a “New culvert” record, and inspect / assess in accordance with this manual.
5.5.1 Location
Roadside and Actual Location
What to do:
• Set the GPS unit to the right datum (WGS84) and display setting (decimal degrees).
• Obtain and record Actual (mandatory) and Roadside (where applicable) readings for the inlet and
outlet. Using CDC this can be done using:
− Manual entry of the data from an external GPS device into the fields
− Record – automatically enters the latitude / longitude of the current location into the data box
using internal or connected GPS device
− Copy From – allows you to copy coordinates from another location on this culvert (such as a pit
already recorded) or on another culvert (such as the outlet of an adjoining culvert that flows
into this one – requires you to know the other culvert number)
What to record:
• Record coordinates for the inlet and outlet.
• If coordinates have already been entered, check they are correct.
• Entry of the “Actual” position (at the structure) is mandatory.
• The “Roadside” position (on the roadside shoulder above the line of the culvert) is to be entered if
the actual inlet / outlet are greater than 10 m from the roadside, See Figure 4.
Side of Carriageway
What to do:
• Select Left, Right or Centre as appropriate.
Marked at Roadside
What to do:
• Look for evidence of markers indicating the existence of the culvert inlet / outlet at the side of the
roadway.
• Guideposts and painted marks on guard rail are two common markers for culvert locations.
• Discuss roadside marking requirements with the Project Manager. If roadside marking is not
present, but is feasible and is required, the Inspector is to mark the roadside in accordance with
the Project Manager’s instructions.
What to record:
• Tick the box if the culvert is marked at the roadside.
5.5.2 Details
Depth of cover
What to do:
• Measure or estimate the depth of cover.
What to record:
• Enter the depth of cover in metres (values up to 99.9).
Is the culvert long enough?
What to do:
• Inspect the entire culvert and surrounds to determine whether the culvert is long enough.
What to record:
• If the culvert does have sufficient length, the associated check box must be selected for both the
inlet and the outlet. If only one is selected, then the culvert as a whole will be recorded as not long
enough.
Grates
What to do:
• Inspect the entire culvert and surrounds to determine whether there are grates at the inlet and / or
outlet.
What to record:
• If grates are present at the inlet or outlet, the associated check box must be selected and the
culvert as a whole will be recorded as having grates. Do not record the presence of grates
associated with intermediate pits.
Ropes access
What to do:
• Inspect the entire culvert and surrounds to determine whether ropes access is required.
What to record:
• If ropes access is required for safe access to the inlet or outlet, the associated check box must be
selected and the culvert as a whole will be recorded as requiring rope access.
Flood gates
What to do:
• Inspect the culvert outlet and surrounds to determine whether flood gates are present.
What to record:
• If floodgates are installed at the culvert outlet, the associated check box must be selected.
Tidal flows
What to do:
• Inspect the culvert outlet and surrounds to determine whether the culvert is subject to tidal flows.
What to record:
• If the culvert outlet experiences tidal flows from the ocean or an estuary, the associated check box
must be selected.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 38
Version 1.0 UNCONTROLLED WHEN PRINTED
What to do:
An estimate should be made of how blocked the flow is at the inlet and outlet.
What to record:
Select the appropriate inlet / outlet flow.
Condition Description
Damaged Drainage Blanket • Drainage blankets (geotextile, growth mat, rock
filled mattresses) protect the channel against
scour
• Mark this item if maintenance is required or if
there is damage to the structure
Boulder Trap Full / Compromised • Grates are used to stop boulders from entering the
culvert however these need to be cleaned out at
regular maintenance intervals
• On the outlet, sediment traps, energy dissipaters
and trash racks also require maintenance
• Mark this item if maintenance is required or if there
is damage to the structure
Other Structures in Drainage Line • Large pieces of timber or other materials may cause
drainage channels and culverts to become blocked
• Example structures are utilities ducts, farmer’s stock
gates, propping inside the culvert, guardrail posts
piercing the culvert
• If the structure is far enough from the culvert (and
won’t move from that position) such that it won’t
create a blockage it doesn’t need to be recorded
• Make a note of what the structure is in the General
comments field
Condition Description
Headwall missing / damaged • Record if the headwall / wingwall has either not
Wingwall missing / damaged been installed during construction or has fallen /
been washed away over time
• If the culvert was built without headwalls or
wingwalls make a note in the General comments
field
• Record if the headwall / wingwall has damage such
as cracking, tilting or dislocation
What to do:
• Make site observations of adverse conditions inside and around the culvert inlet and outlet.
• If any of the listed adverse conditions are identified, ensure that adequate photographs are taken
to enable follow up assessment.
What to record:
• Where listed adverse conditions are observed, the associated check box should be checked.
Each of the adverse condition items has options of Yes (ticked), No (clear) and Not entered
(greyed out).
• If an adverse condition is not applicable (for example, there is no drainage blanket to be
damaged), the associated check box should be marked as No (clear).
• If other significant adverse conditions exist which aren’t covered by these or the risk screening
items, note them in the General comments box.
Severity Description
Level
Urgent > 2 mm deep water is flowing in culvert
and all is lost or enters pipe not from inlet
/ outlet
Advanced Water is flowing in culvert and noticeable
amount is lost or enters pipe not from inlet
/ outlet OR if culvert dry, water stains in
culvert start or stop at joints/voids
• Batter slump is an example of deteriorating batter. The toe of the embankment may have been
eroded, and the batter slumps downward, sometimes forming a bulge at the base, which may
cover the inlet.
• Embankment erosion can occur due to lack of vegetation, or a slope that is too steep.
• This is an optional text field, of up to 200 characters.
What to do:
• The Inspector should make site observations of adverse batter conditions, including:
− Slump
− Erosion
− Scour
− Sinkholes or voids
− Evidence of piping.
• Note the general condition of the batter on both inlet and outlet sides.
• Inspect the embankment either side of the culvert for any signs of erosion. Damaged or blocked
inlets can lead to flows over the roadside at some distance from the culvert.
• Provide an approximate distance from the culvert to the batter slump.
• Provide photographs that allow overall assessment of the batter condition.
What to record:
• Enter observations about any adverse batter conditions including estimated size / extent, location
and proximity to the culvert.
• If the batter is in good condition, enter “Good”.
• If there is no batter, enter “No batter” or “Urban”.
Holes or cavities in the fill around the inlet / outlet or above the culvert
5.7 Barrel
The barrel(s) of the culvert should be assessed from both the inlet and the outlet. This ensures that
any changes in barrel type or size through the culvert are detected. If the inlet and outlet are at
noticeably different directions, and the bend can’t be seen from the inlet or outlet, note this in the
General comments.
Culvert Type
What to record:
• Select one culvert type (mandatory).
Barrel or Cell Construction
Steel Reinforced Concrete • Steel reinforced concrete pipe (RCP) is the most
prevalent form of concrete culvert
• Steel reinforced concrete pipe is generally supplied
in 2.4 m lengths
• This pipe will have a lifting lug on the upper inside
of the pipe
• When hit with a hammer it will have a “clink” sound
• Box culverts are typically steel reinforced concrete
Fibre Reinforced Concrete • The Inspector may notice the fibre in the concrete if
the surface has been damaged
• Fibre reinforced pipe does not have a lifting lug
inside the pipe
• Fibre reinforced pipe is generally in 4 metre long
segments, and is thinner walled than steel
reinforced concrete pipe
• When hit with a hammer it will have a “thud” sound
• If the pipe was installed before 1988 it is most likely
an asbestos pipe, and should be recorded as such.
Spiral Wound Steel / Aluminium Pipe • Spiral wound steel pipes are corrugated metal
pipes with interlocking or welded seam along the
pipe. This seam is visible from the inside of the
pipe
• Joins are bands wrapped around the outside of the
join between each pipe section
• To determine whether aluminium, use judgement,
or else a magnet – aluminium is not magnetic
Multi-Plate Corrugated Steel / • Bolts / nuts will be visible where the adjacent plates
Aluminium join
• Alternatively, on older, smaller pipes there may be
interlocking fingers of steel in a clam shell
construction
• To determine whether aluminium, use judgement,
or else a magnet – aluminium is not magnetic
Corrugated Plastic Pipe • These pipes are manufactured using High Density
Polyethylene (HDPE)
• Wall thickness will vary but is generally thin
Stone or Masonry Barrel • Stone barrels are built from irregular non uniform
stone blocks that may be stacked dry or joined
together with mud and mortar
What to record:
• Select one barrel cell construction type (mandatory).
Culvert Joints
Butt – Unsealed Pipe Joint • The difference between an unsealed pipe joint and
sealed pipe joint can be hard to see. Pipes are laid
next to each other with no interlocking at the joints
• This can result in misaligned pipes, allowing the
ingress of embankment material
Butt – Sealed Pipe Joint • Pipes are laid next to each other with no
interlocking at the joints. However, an external
band is wrapped around the joint to prevent loss of
bedding material into the pipe
Spigot & Socket – Rubber Ring Joint • Pipes are joined together via spigot-socket
interlocking mechanism. The rubber ring joint is
wrapped around the spigot surface and it prevents
water seepage when the pipe is operating under
pressurized conditions
• The inlet may have the socket end visible
• Rubber rings are sometimes visible protruding or
hanging down into the barrel (this is a joint defect)
Spigot & Socket – Grouted Joint • As for above, however the joints are grouted with a
cement based material
• Note: the grout in the photo to the left is obviously
deteriorated
Other – tick box • These fields are to be used when the culvert
Other – description jointing is not any of the above four types. If
selected, a description is required
• Examples are flange joints in concrete pipes, butt
with external collar joints on FRC pipes, and
overlapping finger joints in steel pipes
What to record:
• Select one or more joint type/s (mandatory). If uncertain whether butt joints are Butt – sealed or
Butt – unsealed, tick Butt – unsealed.
• During the inspection if it is noticed that joints have separated to a degree whereby water or
embankment fill is penetrating into the joint, this should be noted, photographed, and should be
assessed correctly in the condition and risk screening sections of the form.
Box Culvert Type
Pre-cast Crown with Cast in Situ Base • Individual sections of the culvert sides and top will
Slab be noticeable
• Inside top corners will have haunches
• The base slab will be continuous with no obvious
jointing between sections of culvert
• Note: the base slab may show expansion joints
Pre-cast Box with Pre-cast Floor • Individual sections of the culvert sides, top and
floor will be noticeable
• Inside top corners will have haunches
• The base will have regular joints
Multi-cell Box with Link Slabs • Multi-cell box culverts with link slabs are identified
by the presence of a link slab joining two pre-cast
box culverts
• A minimum of 3 cells is required for this type
• If the link slab is over an inverted crown unit then
select Other type
Link slab
Other – tick box • These fields are to be used when the box type is
Other – description not any of the above types, for example inverted
crown units with precast slab over
What to record:
• Select one or more box culvert type/s (mandatory where “Box” has been selected under culvert
type).
Lining
Invert Only Lined • Invert lined with concrete to protect the pipe against
water carrying stones and abrasive materials or
corrosion at low flows
• Lining might be concrete with or without reinforcing
Fully Lined • Fully lined culverts are lined around the full inside
circumference of the barrel
What to record:
• Select one or more lining type (mandatory).
Lining Material
Reinforced Concrete / Fibre • Smooth concrete lining of the invert (floor) to prevent
Reinforced Concrete Lining corrosion and abrasion
• Fibre reinforced concrete may be difficult to
determine. If lining is damaged, fibres may be visible
• Fibres made of steel or plastic can be used in
shotcrete which can then be smoothed and these
may be visible on the surface
Coal Tar / Hazardous Lining • Hazardous lining may be asbestos lined concrete
pipe. If the lining is damaged and fibres are present
it may be asbestos – do not disturb
What to record:
• Where a lining is present, select one or more lining material (mandatory).
Barrel Dimensions
What to do
• Culvert length (overall) can be measured using a “Disto” laser measuring device in metres.
• The number of cells / barrel are counted.
• Cells/barrels are to be lettered A, B, C… in order, in the prescribed direction. The associated
cell/barrel letter must be marked above each barrel.
• Pipe inside diameter is measured in millimetres. Precast pipes are manufactured in standard sizes
in 75 or 150 mm increments –round the diameter to the nearest standard size.
• Cell, barrel, or arch width (culverts other than pipes) is measured in millimetres. Precast box units
are manufactured in standard widths in 150 or 300 mm increments – round the actual width of a
precast box to the nearest standard size.
• Cell, barrel, or arch height (culverts other than pipes) is measured in millimetres. Precast box units
are manufactured in standard heights in 150 or 300 mm increments –round the actual height of a
precast box to the nearest standard size.
• Length of cell (between joints) is measured in millimetres. Precast units are manufactured in
standard lengths of 1220 or 2440 mm –round the actual length of a precast box to the standard
size. Adopt full culvert length for continuous culverts such as metal, plastic or brick culverts.
What to record:
• Culvert dimensions as follows:
− Culvert length (overall). Enter up to three digits and one decimal digit
− Number of barrels. Enter up to three digits. Range 1 – 300. Ensure photographs are taken for
every cell / barrel
− Pipe inside diameter. Enter up to four digits. Range 75 – 9999. This is mandatory where “pipe”
has been selected under culvert type.
− Cell, barrel or arch width (culverts other than pipes). Enter up to four digits. This is mandatory
where “box” or “arch” has been selected under culvert type
− Cell, barrel or arch height (culverts other than pipes). Enter up to four digits. This is mandatory
where “box” or “arch” has been selected under culvert type
− Length of cell (between joints)
• If the inlet and outlet are at noticeably different directions, and the bend can’t be seen from the
inlet or outlet, note this in the General comments.
Barrel Flow
What to do:
• An estimate should be made of how blocked the flow is within the barrel of the culvert, choosing a
value that represents the worst condition.
What to record:
• Select the appropriate barrel flow.
Barrel Adverse Conditions
About the data:
The presence of adverse conditions within the barrel should be identified. These fields are desirable,
and each should be completed where possible.
Joint Damage • Separated joints leave a void above the culvert and
can potentially contribute to road subsidence
• Look for embankment material or water seeping
through joints – both at the top and bottom of the
culvert
During this inspection is there water • Whether or not there is any water trapped in the
in the culvert? culvert during the inspection. This could result from
vertical movement of a culvert section or blockages
inside or outside the culvert
• Is water running through the culvert? Is water
ponded?
• The concern is whether it is there
What to do:
• Make site observations of adverse conditions inside the culvert barrel from both the inlet, outlet
and any intermediate pits.
• If any of the listed adverse conditions are identified, ensure that adequate photographs are taken
to enable follow up assessment.
What to record:
• Where listed adverse conditions are observed, the associated check box should be checked. Each
of the adverse condition items has options of Yes (ticked), No (clear) and Not entered (greyed
out).
• If an adverse condition is not applicable, the associated check box should be marked as No
(clear).
• If other significant defects exist which aren’t covered by these or the risk screening items, note
them in the General comments box.
Nil No spalling
Bowing of culvert
Geometry change
Evidence of water being lost out of joints or other defects in the pipe
Metal, plastic, brick, stone, terracotta, masonry, timber, composite, or barrel type classified as
“other”
5.8 Pits
This section is for recording drainage pit structures located along the culvert.
Sometimes a pit may be the inlet or outlet of the culvert – if so it should be captured as per the Inlet /
Outlet requirements in this guideline as well as a pit.
Median Pit • Pits that are integral to the median kerb and
have no additional grate in the pavement (may
have a concrete lid or a grate on the raised
median)
5.9 Documents
This section is used to record the file name and a descriptive caption for each photo that you have
taken. If you have also scanned any images or documents that are relevant to this culvert then also
list them.
5.9.1 Photographs
Photos should be taken at each stage of the inspection as it is undertaken to identify the culvert, show
its general condition, and to highlight specific defects.
Each photo must have its filename and caption listed in the table.
Inspectors must take photographs of the following:
• The road surface along the line of the culvert.
• The inlet showing enough information to later identify it, understand the culvert layout and the
catchment leading to the inlet. Include the batter slope to road level. Use more than one photo if
necessary.
• The outlet, as for the inlet, showing the streamline leading away from the outlet.
• The barrel, showing the internal condition from both the inlet and outlet ends of each cell.
• Each pit, as for the inlet.
• Each defect that is identified / recorded, clearly highlighting the defect. The defect being shown
needs to be noted in the caption. More than one defect can be shown in a photo it they are clearly
seen and each one noted.
Taking Photographs
• When taking photographs inside the culvert barrel, the camera should be angled towards the wall
of the barrel. This will allow the illuminated wall to occupy the larger area on the photograph.
Shining a high-powered torch straight down the barrel will give better lighting over a longer
distance than using the camera flash alone.
• In detail photos, include an object to help show scale – e.g. a tape measure, pen, or mobile
phone.
• When taking photographs external to the culvert, include enough surroundings in the photograph
to allow an overall assessment of the culvert to be made.
Table 15 Photograph Examples
Example Photographs Description
• The same culvert photographed using flash
(above) and using a powerful torch (below).
The torch provides much better lighting at
further distances
5.9.2 Sketches
It is sometimes useful to make a sketch of the site to fully describe issues and indicate some
significant features. An example sketch is shown below. Sketches must be scanned as JPEG files
and added to the list.
Figure 12 Example Sketch
Clean Drainage Pit If pit or grate is blocked preventing water draining away
Concrete Repairs (of cracks, spalls etc) Epoxy or concrete repairs to damaged concrete pipes
A quantity of work should be provided to assist in planning, along with a comment of any special
equipment that may be required.
The timeframe to be recorded is the time within which the work needs to be carried out before that
action will no longer be viable or effective. Timeframe options are:
• <1 month
• 1-6 months
• 7-12 months
• 1-2 years
• 2 years
What to record:
• Select the check box beside a required maintenance activity.
• Record the quantity of work in the units shown.
• Select a timeframe within which the work needs to be carried out in order for this activity to be
effective.
• If needed, add a description of what needs doing, special equipment etc.
• Clearing the tick box for an activity will delete all other items for that activity.
• All the routine maintenance activities are ultimately combined into a single text field, with a
maximum length of 255 characters. The number of characters remaining in this field is displayed
at the right of the “Other” box.
• Any maintenance required that isn’t covered by the options provided can be listed in the “Other”
box, including “Nil” if no maintenance is required.
6 Risk Assessment
This Manual provides a systematic set of instructions that allow TfNSW to apply AS/NZS ISO
31000:2009 to culvert risk management. The following sections outline this approach.
Culvert Risk Assessment, as outlined in this Manual, corresponds to the AS/NZS ISO 31000:2009
processes inside the box titled “Risk assessment” in the above diagram (with references to clauses in
the Standard).
To complete the picture above:
• Establishing the context is assisted by the collection of an inventory of culverts. Existing data
undertaken in accordance with the Culvert Inventory Collection Guideline has been collected for
most culverts. Inspection procedures to update existing data or else provide the inventory data if
not yet completed will include a first stage risk screening to identify the subset of culverts to be
assessed for risk.
• Risk treatment process will follow evaluation.
• Monitoring and review continues the risk management cycle.
• Communication and consultation is ongoing.
6.5.2 Consequences
Secondly, the possible effects of the hazard on each element – the consequences – have to be
assessed. The consequence analysis is based on the procedure in the TfNSW Slope Risk Analysis
Guideline.
Consequences are expressed separately for:
• Loss of life (road users or people located down slope of road embankments).
• Damage to property and consequential (social/economic impact) effects:
− Road closure (defined in terms of sub-network ranking and including any resulting user
costs)
− Infrastructure or property damage and consequential costs (excluding those arising from the
road closure itself, if it occurs)
− Repair costs (to restore the road to its pre-failure condition and/or to repair or replace the
culvert structure)
For consequences associated with slope risk and culvert risk, the added costs related to legal
matters following serious failures are not included in the risk analysis procedure.
The form covers each of the four steps outlined in the Risk Assessment Flowchart in Figure 14,
described in further detail as follows.
7.3.1 ARL
The ARL tab (shown above) summarises the major aspects of the risk level.
Status
When the assessment is completed, “Assessment Completed OK” should be selected from the
dropdown list. Other options provide reasons for not completing a risk assessment.
Assessor(s)
The drop down box allows selection of the Inspector(s) conducting the risk assessment. It is
mandatory to enter at least one Assessor.
Risk
Select vulnerable or low to indicate the likelihood of the culvert deteriorating further – refer to the
following table.
Table 19 Culvert Risk Level
Term Description
Vulnerable The culvert is likely to deteriorate further under normal to moderate
events. Preventative maintenance (if possible) is required to avoid this
Low The culvert is unlikely to deteriorate further except under extreme events
Additionally you can tick Urgent to highlight a culvert where there is a high likelihood of imminent
failure causing death or injury (should already be an ARL1).
ARL
The system generated ARL from the ARL Calculation screen will be selected.
If in the engineering judgement of the Assessor the ARL should be different to that generated by
the system then it is possible to override the generated ARL. A comment must be included noting
the particular aspects that lead to this conclusion.
The Assessor Override should be used in preference to unwarranted modification of likelihood
factors to get the desired result, as identifying where the system value is not appropriate allows for
ongoing refinement of the system.
Table 20 provides a guide to how the different ARLs may be used to determine treatment priorities.
This can be used to test the validity of the calculated ARL.
Table 20 ARL Descriptions
ARL 1 p = 0.1 A very high risk to life. Place in the current year’s program as
a higher priority than previously planned works. Rehabilitate to
(1 in 10 years)
remove the risk to life and where possible renew 100 year life
ARL 2 p = 0.01 A high risk to life. Include in next year’s rehabilitation program.
Rehabilitate to remove risk to life and where possible renew
(1 in 100 years)
100 year life
ARL 4 p = 0.0001 A low risk to life. Place in the rehabilitation program in a way
that optimises treatment cost and culvert life. Rehabilitation
(1 in 10,000 years)
options may include low cost preventative works in the short
term to prevent deterioration to a higher risk level or higher
cost renewal works to be applied when further deterioration
occurs, with emphasis on prevention
Inspection Dates
The Inspection Frequency Cycle (IFC) is based on the ARL and determines when the next
inspection is due.
If in the opinion of the Assessor, or if requested by the Project Manager, a follow up inspection
should be carried out at a different interval then it is possible to enter an override date. A comment
should be included noting the reasons for overriding the date.
Always Inspect after a Major Event
Check this item when there is a high risk of further deterioration or blockage during a major rainfall
event.
Internal Barrel Inspection performed
Check this item if the assessment has included information from a man entry or CCTV inspection
of the barrel.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 99
Version 1.0 UNCONTROLLED WHEN PRINTED
This tab is used to recommend the maintenance, remediation or rehabilitation actions required to
mitigate the risks identified in the risk assessment. Appropriate actions can be entered under each
of five categories
• Further Investigation Required
• Routine Maintenance
• Rehabilitation – Pipe
• Rehabilitation – Non Pipe
• Other – Assessment
Action groups shown in red indicate they have sub group actions. Double click on the Action title to
open the Group Cost Details screen described below. The value in the Cost column for these
action groups are the total of those entered on the details screen and can’t be edited here. A
comment for the action group as a whole can be entered.
Action groups shown in black (Rehabilitation – Non Pipe and Other) do not have sub groups. Enter
a comment about what work is recommended and the estimated cost for these actions directly on
the Actions/Costs tab.
Further Investigation Required
This allows items such as CCTV, additional inspections or assessments to be requested. Items
can be accompanied by a suggested cost and a comment as to why they have been
recommended.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 100
Version 1.0 UNCONTROLLED WHEN PRINTED
Routine Maintenance
Routine maintenance activities are actions that will enable the culvert to operate at its optimal
performance and extend the life of the culvert. Maintenance is recommended in the inspection
process as outlined in detail in Section 5.10.1.
If the Assessor considers the maintenance activities recorded in the inspection to be appropriate
then they should also be recorded here, along with any additional recommended maintenance.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 101
Version 1.0 UNCONTROLLED WHEN PRINTED
Rehabilitation – Pipe
This section allows the recommendation of more substantial repairs to pipe culverts than routine
maintenance.
This screen provides a summary line for Pipe Rehabilitation, along with other items that are
required in conjunction with pipe rehabilitation works. Details of the ancillary items should be
entered here, but Pipe Rehabilitation work should be entered on the next screen.
Pipe Rehabilitation
This screen is opened by double clicking the red “Pipe Rehabilitation” item on the previous screen.
Dimensions of the culvert are shown at the top of the screen and are used to automatically
generate a cost for the different rehabilitation methods. This can be overridden if the Assessor
considers the automatically generated cost to be inappropriate.
Select the appropriate rehabilitation methods. Indicate the order in which these options should be
considered. Enter the number of years within which this treatment needs to be carried out before
this action will no longer be viable or effective.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 102
Version 1.0 UNCONTROLLED WHEN PRINTED
Use this screen to enter any comments thought appropriate for each culvert. Example comments
include:
• Describing why you believe the culvert deserves the ranking you gave it.
• Constraints or limitations to the Risk Assessment.
• Any relevant information that should be passed on that doesn’t have other relevant location to
do so.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 103
Version 1.0 UNCONTROLLED WHEN PRINTED
Structural collapse of a culvert could occur due to structural overload of the culvert (e.g.
inadequate design) or to deterioration of the culvert leading to loss of strength (e.g. corrosion of
metal pipes, corrosion of reinforcing steel). Collapse of the culvert barrel could subsequently lead
to development of a void or depression on the road surface. See Figure 17.
Factors
The factors that could contribute to the collapse of the culvert barrel include:
• Culvert type (e.g. reinforced concrete pipes, either butt jointed, spigot and socket, with or
without banding on joints, corrugated metal pipes spirally wound or not, etc).
• Culvert condition – e.g. evidence of corrosion of steel elements, longitudinal cracking of
concrete, corrosion/scour of the invert.
• Loss of supporting material.
• Traffic loads higher than design values.
The factors that could contribute to a void or settlement at the road surface include:
• Depth of cover.
• Nature of the fill material.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 104
Version 1.0 UNCONTROLLED WHEN PRINTED
Consequences
The failure mechanism typically develops over time; however a certain rainfall event may trigger a
failure. The potential consequences of this failure mechanism include:
• Void/sinkhole on the road surface causing an accident.
• Repair costs.
• Road closure.
RC Box, Failed or Culvert roof has collapsed or is badly 0.9 - 1.0 Will occur
RC Pipe Failure is deformed with extensive cracking of this year
Imminent the concrete pipe/box section
Metal Failed or Culvert roof has collapsed or is badly 0.9 - 1.0 Will occur
(Steel Arch, Failure is deformed (e.g. buckling or large this year
Steel Pipe) Imminent deformation of the steel section,
>40% deformed/blocked).
Misalignment/settlement >20 mm
Technical Manual Culvert Inspection and Risk Assessment – February 2022 105
Version 1.0 UNCONTROLLED WHEN PRINTED
Other (e.g. Failed or Culvert roof has collapsed or is badly 0.9 - 1.0 Will occur
masonry, Failure is deformed (e.g. large deformation of this year
timber, Imminent the section, >40%, collapsed roof)
plastic)
Technical Manual Culvert Inspection and Risk Assessment – February 2022 106
Version 1.0 UNCONTROLLED WHEN PRINTED
Relative depth of Nature of majority of materials overlying the culvert Likelihood range
cover over structure
culvert
Shallow depth Any materials - collapse of culvert would likely lead to 0.5 - 0.9
(less than dia. of subsidence at the road surface
culvert)
Moderate depth Erodible materials (e.g. sand, silty sand, decomposed 0.2 – 0.5
(1 to 2 x dia. of granite, poorly compacted soils)
culvert)
Moderately erodible materials (e.g. compacted clayey 0.05 – 0.1
soils)
Deep depth Erodible materials (e.g. sand, silty sand, decomposed 0.05 – 0.2
(greater than 2 x granite, poorly compacted soils)
dia. of culvert)
Moderately erodible materials (e.g. compacted clayey 0.01 – 0.05
soils)
Table Notes
• Voids: Consider the ability of the road pavement to bridge across voids in assessing the
potential for a void affecting the road surface.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 107
Version 1.0 UNCONTROLLED WHEN PRINTED
This failure mechanism involves damming of water on the upstream side due to insufficient
hydraulic capacity, or blockage of the inlet by debris or vegetation. Stored water may lead to
saturation of fill and/or increase in pore pressure in the embankment, contributing to slope
instability on the downstream side.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 108
Version 1.0 UNCONTROLLED WHEN PRINTED
Factors
The factors contributing to the ponding of water on the upstream side of the culvert include:
• Hydraulic capacity of the culvert.
• Current level of blockage of the culvert.
• Material upstream with the potential to block the inlet or barrel of the culvert.
The factors contributing to instability of the embankment given storage of water are dependent on
• Location of the road embankment (e.g. a steep slope).
• Embankment material and compaction.
• Foundation material – potential for low strength materials and strain weakening materials.
• Embankment condition and downstream slopes.
Consequences
The potential consequences of this failure type include:
• Void in the road causing an accident/loss of life.
• Debris flow causing loss of life or damage down slope of the failure.
• Repair costs.
• Road closure.
Likelihood of Likelihood of
Likelihood of
Likelihood storm event culvert blockage
= ( , ) x
instability of road
of failure max exceeding or insufficient
embankment
SI-1 capacity hydraulic capacity
(table SI-1.3)
(table SI-1.1 ) (table SI-1.2)
Technical Manual Culvert Inspection and Risk Assessment – February 2022 109
Version 1.0 UNCONTROLLED WHEN PRINTED
Grates, structures or vegetation in the line of the culvert will reduce the effective size of
the culvert opening.
Trash racks, boulder protection, etc may mitigate blockage potential of debris if adequate
bypass capacity is provided.
Mobility of site material Examples Existing Blockage Likelihood Range
that is larger than the
culvert opening
0-25% Negligible
Table Notes
Culverts can perform very differently in moderate and extreme storm events. Generally silty
materials build up and block culverts in numerous moderate events but can be flushed out in
extreme storm events. Heavily treed or boulder lined gullies generally remain clear in all but
extreme events, when they are likely to block due to the large debris size.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 110
Version 1.0 UNCONTROLLED WHEN PRINTED
Circumstantial evidence of deep Three or more high risk factors 0.2 - 0.5
seated movement or slumping are present
(e.g. longitudinal cracks on road
One or two high risk factors are 0.05 - 0.2
pavement, settlement of road
present
edge/verge)
No high risk factors are present 0.01 - 0.05
Table Notes
High risk factors include:
• Geological environment (e.g. embankment founded on colluvial soils, basaltic clays, soft soil).
(Colluvial: a combination of soil and rock typically formed by gravity flow).
• Low strength materials in the embankment or foundation.
• High pore pressures in the embankment or foundation.
• Embankment founded on steep slopes (above likelihoods should be revised for steep slopes).
• Water observed coming out of the embankment fill or toe of the slope.
• Steep downstream batter.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 111
Version 1.0 UNCONTROLLED WHEN PRINTED
This failure mechanism involves instability from water leaking out of the culvert leading to
saturation of fill or foundation materials below the culvert. Leakage may occur through open joints
caused by separation of pipe segments due to soil creep or differential settlement, or deterioration
of the culvert. This may be observed by settlement at the road surface, stepping of the culvert, or
movement of the road embankment.
Factors
The factors that could contribute to this failure are related to both leakage out of the culvert and
slope instability.
The factors contributing to the leakage out of the culvert include:
• Condition of the culvert – joint condition, pipe separation through settlement or other, culvert
deterioration (corrosion of invert).
The factors contributing to instability of the embankment given leakage out of the culvert:
• Scour undermining the toe.
• Observed condition of the embankment – evidence of instability, slumping.
• Embankment material and compaction.
• Foundation material – potential for low strength materials and strain weakening materials.
• Downstream slope, e.g. localised slumping.
Consequences
The potential consequences of this failure type include:
• Void in the road causing an accident.
• Debris flow causing loss of life or damage down slope of the failure.
• Repair costs.
• Road closure.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 112
Version 1.0 UNCONTROLLED WHEN PRINTED
Technical Manual Culvert Inspection and Risk Assessment – February 2022 113
Version 1.0 UNCONTROLLED WHEN PRINTED
Circumstantial evidence of deep Three or more high risk factors 0.2 – 0.5
seated movement or slumping (e.g. are present
longitudinal cracks on road pavement,
One or two high risk factors are 0.05 – 0.2
settlement of road edge/verge)
present
No high risk factors are present 0.01 – 0.05
Table Notes
High risk factors include
• low strength materials in the embankment or foundation.
• high pore pressures in the embankment or foundation.
• embankment founded on steep slopes.
• water observed coming out of the embankment fill or toe of the slope.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 114
Version 1.0 UNCONTROLLED WHEN PRINTED
Factors
The factors contributing to the collapse of the headwall include:
• Depth of soil at road embankment.
• Traffic loads higher than design values.
• The amount of erosion caused by nesting animals, poor compaction, etc.
• Additional lanes providing a squeeze-point at this location.
The factors contributing to a headwall collapse resulting in pavement collapse include:
• The distance from the headwall to the edge line (EL).
Consequences
The potential consequences for this failure type include:
• Collapse of headwall and loss of pavement.
• Repair costs.
• Road closure.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 115
Version 1.0 UNCONTROLLED WHEN PRINTED
Technical Manual Culvert Inspection and Risk Assessment – February 2022 116
Version 1.0 UNCONTROLLED WHEN PRINTED
Factors
The factors contributing to outlet or inlet erosion include:
• Energy dissipation measures at the inlet or outlet.
• Erosion protection measures at the inlet or outlet.
• Evidence of scour at the inlet or outlet.
• Water energy – grade and roughness.
Consequences
The potential consequences for this failure type include:
• Void in road causing accident.
• Repair costs.
• Road closure.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 117
Version 1.0 UNCONTROLLED WHEN PRINTED
Technical Manual Culvert Inspection and Risk Assessment – February 2022 118
Version 1.0 UNCONTROLLED WHEN PRINTED
Technical Manual Culvert Inspection and Risk Assessment – February 2022 119
Version 1.0 UNCONTROLLED WHEN PRINTED
Table Notes
High risk factors include:
• Low strength materials in the embankment or foundation.
• High pore pressures in the embankment or foundation.
• Embankment founded on steep slopes.
• Water observed coming out of the embankment fill or toe of the slope.
• Steep downslope batter slopes.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 120
Version 1.0 UNCONTROLLED WHEN PRINTED
Technical Manual Culvert Inspection and Risk Assessment – February 2022 121
Version 1.0 UNCONTROLLED WHEN PRINTED
Factors
The factors that could contribute to piping erosion into the culvert include:
• Culvert type.
• Condition of joints, evidence of cracks/corrosion through which groundwater could enter.
• Surrounding soil conditions – sandy soils are more susceptible to erosion.
• A source of seepage into the culvert (e.g. a high groundwater table).
The factors that could contribute to a void or settlement at the road surface include:
• Depth of cover.
• Nature of the fill material.
Consequences
The potential consequences of this failure type include:
• Void/sinkhole in road causing accident.
• Collapse and blockage of culvert requiring repair – repair costs.
• Road closure.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 122
Version 1.0 UNCONTROLLED WHEN PRINTED
Technical Manual Culvert Inspection and Risk Assessment – February 2022 123
Version 1.0 UNCONTROLLED WHEN PRINTED
Table Notes
• Voids: Consider the ability of the road pavement to bridge across voids in assessing the
potential for a void affecting the road surface.
• Collapse: If the culvert has collapsed or is near failure and sinkholes, subsidence or cracking
are evident in the overlying road surface, then adopt a final likelihood value of 0.9.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 124
Version 1.0 UNCONTROLLED WHEN PRINTED
Factors
Factors contributing to afflux include:
• Hydraulic capacity of the culvert.
• Potential for blockage at the inlet.
Factors contributing to the potential for piping through the surrounding soil materials include:
• Embankment material and compaction – poorly compacted sandy soils are the most
vulnerable, well compacted clayey soils are least vulnerable.
• Hydraulic gradient for seepage through the embankment.
• Duration of ponding of water – afflux caused by blockage at the inlet is more likely to be stored
for longer periods of time.
Consequences
The potential consequences for this failure type include:
• Void in road caused by embankment failure or sinkhole.
• Debris flow causing loss of life or property damage down slope of the road embankment.
• Repair costs.
• Road closure.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 125
Version 1.0 UNCONTROLLED WHEN PRINTED
Technical Manual Culvert Inspection and Risk Assessment – February 2022 126
Version 1.0 UNCONTROLLED WHEN PRINTED
Table Notes
High risk factors for internal erosion and piping are:
• Erodible soils around the outside of the culvert (e.g. dispersive soils, silty sands, poorly graded
fine sand or silt). Dispersive Soils: typically unstable soils which lose structure in water.
• Culvert barrel is thin walled metal pipe.
• Open joints or other open defects (e.g. corrosion/abrasion) in the culvert barrel with seepage
into or out of the culvert.
• Poorly compacted soils around the outside of the culvert.
• High seepage gradients along the outside of the culvert (Height of fill above pipe / Length of
pipe >0.2 for blocked culvert condition).
Technical Manual Culvert Inspection and Risk Assessment – February 2022 127
Version 1.0 UNCONTROLLED WHEN PRINTED
Factors
The factors contributing to piping due to culvert leakage include:
• Embankment material and compaction – poorly compacted sandy soils are the most
vulnerable, well compacted clayey soils are least vulnerable. Dispersive soils (typically unstable
soils which lose structure in water) are also vulnerable.
• Culvert type – thin walled metal pipes are more prone to holes resulting in leakage.
• Velocity of flow within the culvert.
• Condition of joints, evidence of cracks/corrosion/seepage.
The factors that could contribute to a void or settlement at the road surface include:
• Depth of cover.
• Nature of the fill material.
Consequences
The potential consequences for this failure type include:
• Void in road caused by embankment failure or sinkhole.
• Debris flow causing loss of life or property damage down slope of the road embankment.
• Repair costs.
• Road closure.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 128
Version 1.0 UNCONTROLLED WHEN PRINTED
Technical Manual Culvert Inspection and Risk Assessment – February 2022 129
Version 1.0 UNCONTROLLED WHEN PRINTED
Shallow depth (less than Any materials – erosion of material into the culvert 0.2 – 0.5
dia. of culvert) would likely lead to subsidence at the road surface
Moderate depth (1 to 2 x Erodible materials (e.g. sand, silty sand, 0.05 – 0.2
dia. of culvert) decomposed granite, poorly compacted soils)
Moderately erodible materials (e.g. compacted 0.01 – 0.05
clayey soils)
Erosion resistant materials (e.g. rockfill, 0.002 – 0.01
compacted high plasticity clays)
Deep depth (greater than Erodible materials (e.g. sand, silty sand, 0.01 – 0.05
2 x dia. of culvert) decomposed granite, poorly compacted soils)
Moderately erodible materials (e.g. compacted 0.001 – 0.005
clayey soils)
Erosion resistant materials (e.g. rockfill, Negligible to
compacted high plasticity clays) 0.001
Table Notes
• Voids: Consider the ability of the road pavement to bridge across voids in assessing the
potential for a void affecting the road surface.
• Collapse: If the culvert has collapsed or is near failure and sinkholes, subsidence or cracking is
evident in the overlying road surface, then adopt a final likelihood value of 0.9.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 130
Version 1.0 UNCONTROLLED WHEN PRINTED
Technical Manual Culvert Inspection and Risk Assessment – February 2022 131
Version 1.0 UNCONTROLLED WHEN PRINTED
This hazard involves the erosion of the downstream side of a road embankment due to flows over
the road surface caused by blockage or insufficient capacity of the culvert. This can lead to a void
on the edge of the road embankment, or complete washout of the road embankment.
Consideration needs to be given to the storage capacity of the “dam” created by the blocked
culvert and the presence of bypass routes that will allow floodwater to be diverted without
overtopping the road. A large storage capacity or clear bypass routes will result in a negligible
likelihood of this hazard occurring. A moderate storage capacity or potential bypass routes will
justify reducing the likelihood factors recommended in the tables below.
Water on the road may also lead to damage to the road pavement surface and accidents.
Factors
Factors contributing to flow over the road embankment include:
• Hydraulic capacity of culvert.
• Potential for blockage at inlet.
• Storage capacity of the “dam” created by the road embankment.
• Presence of bypass routes other than overtopping.
Factors contributing to an embankment failure by overtopping flows include:
• Embankment geometry – gully line concentrating flows.
• Surface cover on slope (vegetation).
• Slope of embankment.
• Amount of water and its velocity.
Consequences
The potential consequences for this failure type include:
• Damage to road pavement.
• Void in road caused by embankment failure or sinkhole.
• Debris flow causing loss of life or property damage downstream.
• Water washing cars away.
• Repair costs.
• Road closure.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 132
Version 1.0 UNCONTROLLED WHEN PRINTED
Technical Manual Culvert Inspection and Risk Assessment – February 2022 133
Version 1.0 UNCONTROLLED WHEN PRINTED
Technical Manual Culvert Inspection and Risk Assessment – February 2022 134
Version 1.0 UNCONTROLLED WHEN PRINTED
Technical Manual Culvert Inspection and Risk Assessment – February 2022 135
Version 1.0 UNCONTROLLED WHEN PRINTED
Factors
The factors contributing to the redirection of flows include:
• Hydraulic capacity of the culvert.
• Potential for blockage.
• Geometry of road embankment (and opportunity for water to dissipate).
The factors contributing to the flooding of properties in other catchments include:
• The presence of properties in low lying areas.
Consequences
The potential consequences for this failure type include:
• Property damage/injury or loss of life.
• Repair costs.
• Road closure.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 136
Version 1.0 UNCONTROLLED WHEN PRINTED
Table Notes
For this table, only identify obstructions that cannot be flushed by high flows i.e. not silts or leaf
debris.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 137
Version 1.0 UNCONTROLLED WHEN PRINTED
Cross catchment flows are likely to flow through low lying third party 0.9 – 1.0
properties (e.g. houses, caravan parks, industrial buildings, etc)
Cross catchment flows are likely to flow through low lying third party 0.1 – 0.5
properties (e.g. houses, caravan parks, industrial buildings, etc), but
the structures are unlikely to be affected by the flows
Cross catchment flows may affect third party properties but the 0.01 – 0.05
dwellings are very unlikely to be affected by the flows
Technical Manual Culvert Inspection and Risk Assessment – February 2022 138
Version 1.0 UNCONTROLLED WHEN PRINTED
Technical Manual Culvert Inspection and Risk Assessment – February 2022 139
Version 1.0 UNCONTROLLED WHEN PRINTED
Technical Manual Culvert Inspection and Risk Assessment – February 2022 140
Version 1.0 UNCONTROLLED WHEN PRINTED
* For the purposes of the risk analysis, a vulnerability rating of V5 is allocated. In some cases this
may lead to an excessively conservative risk outcome. If these circumstances apply, consideration
should be given to ruling these hazards out.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 141
Version 1.0 UNCONTROLLED WHEN PRINTED
Technical Manual Culvert Inspection and Risk Assessment – February 2022 142
Version 1.0 UNCONTROLLED WHEN PRINTED
− Deep culverts have greater potential for the sudden appearance of a void due to slope
instability, but are more likely to have a slow forming void as a result of collapse or piping
These different factors can be classified according to the following tables.
Table 49 Pavement Material
Pavement Material Description
Weak Unbound granular pavements on low trafficked roads
Strong Bound or unbound granular pavements on moderate to high trafficked
roads
Deep AC Pavements with more than 100 mm of asphalt
Concrete All pavements with concrete layers. Under thin asphalt, these can often
be identified by regular transverse cracks.
Table 51 Depth
Depth Description
Shallow Less than cell width/ diameter of culvert
Medium 1 to 2 times cell width/ diameter of culvert
Deep Greater than 2 times cell width/ diameter of culvert
Double click on any of the void type boxes and a screen will open where the Fill Material, Culvert
Depth and Pavement Type are entered. These will be used to determine the void type for each of
the hazard types according to Table 52 below.
The void type is automatically combined with the Speed Limit according to Table 48 above to
determine the Vulnerability Rating for each of the hazard types.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 143
Version 1.0 UNCONTROLLED WHEN PRINTED
Technical Manual Culvert Inspection and Risk Assessment – February 2022 144
Version 1.0 UNCONTROLLED WHEN PRINTED
Road Users
The temporal probability for road users is based on the traffic volume at the site. If the hazard is
likely to present itself in the road shoulder rather than the travel lane, a traffic volume of 1% of the
lane traffic volume can be used.
in many cases additional information such as the proportion of heavy vehicles and in some cases
the traffic distributions (by lane, day or hour). The AADT is the total volume the road carries in both
directions and for the purposes of the Risk Assessment has to be converted to vehicles/lane/day.
The volume of traffic carried by any road will normally change through the day, and in different
ways for the different directions of travel (e.g. most roads carry the majority of their traffic in the
daylight hours and there are commonly peaks in different directions in the morning and evening).
There are often changes in patterns on weekends or seasonally, particularly in rural areas. The
AADT averages across all of these variations. It means that AADT cannot be guessed with any
great precision from a short period of observation. At most, an impression of the traffic being
carried may be obtained.
AADT data is used by CDC to automatically determine temporal probability in accordance with the
following figure.
Figure 25 Temporal Probability based on traffic volume
Technical Manual Culvert Inspection and Risk Assessment – February 2022 146
Version 1.0 UNCONTROLLED WHEN PRINTED
Technical Manual Culvert Inspection and Risk Assessment – February 2022 147
Version 1.0 UNCONTROLLED WHEN PRINTED
by reference to the analysis detailed in Bunce et al (1997). The need for this may also depend on
the effectiveness of possible safety responses.
There have been two cases in recent years of rapid embankment failure above occupied buildings,
leading to multiple fatalities. One involved a rail embankment (Coledale), the second a road
embankment (Thredbo), with both cases leading to extended Coronial inquests. A C1
consequence class would be derived for embankment instability on steep slopes above habitation,
if the hazard is expected to cause complete or partial collapse of the occupied buildings. This is
relevant should the entire road embankment fail and affect any downstream occupied buildings.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 148
Version 1.0 UNCONTROLLED WHEN PRINTED
Technical Manual Culvert Inspection and Risk Assessment – February 2022 149
Version 1.0 UNCONTROLLED WHEN PRINTED
Notes
The definitions listed above under each consequence class are not exhaustive and are meant to
be illustrative rather than definitive in the area of financial and economic costs (the cost base is
year 2012 dollars).
Advice on Sub-Network rankings can be obtained from TfNSW Regional Offices. This part of the
consequence rating definitions is intended to express the indirect costs of a hazard, such as the
cost of traffic management, disruption; extra fuel used and lost time due to route changes. It does
not include the repair costs, which are listed separately. Nor does it include the potential cost to
people (or organisations) other than road users, which are also considered separately.
Where there are multiple consequences, the total should be considered, as it may increase the
consequence class above that derived from the individual effects.
The consequence classes used for loss of life are not equivalent in economic terms to those for the
damage to property and consequential effects, reflecting the lower tolerance which exists in society
for loss of life compared to financial losses.
Partial Closure
This means that the road is closed to traffic in one direction and either:
• The traffic in one direction has to take an alternate route, or;
• The traffic in both directions has to be controlled to allow alternating one-way flows. This may
require the construction of earthworks and temporary pavements (for instance, to cross the
median in dual carriageway roads or to allow traffic to use the road shoulder for an extended
period).
If the closure affects:
• Only one lane of a multilane road (dual or single carriageway), or;
• Only the shoulder of the road.
Then the costs of closure will normally be small and may be taken not to affect the outcome of the
risk assessment. The assessment should be based on the repair costs or other economic
consequences.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 150
Version 1.0 UNCONTROLLED WHEN PRINTED
Where no viable failure mechanism exists, the Assessed Risk Level is deemed to be negligible and
is allocated a rating of ARL5.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 151
Version 1.0 UNCONTROLLED WHEN PRINTED
Technical Manual Culvert Inspection and Risk Assessment – February 2022 152
Version 1.0 UNCONTROLLED WHEN PRINTED
Technical Manual Culvert Inspection and Risk Assessment – February 2022 153
Version 1.0 UNCONTROLLED WHEN PRINTED
16 Additional Information
Deterioration
Deterioration refers to the ability of a material to resist corrosion and abrasion. Corrosion is the
deterioration of metal due to electrochemical or chemical reactions. Culverts are subject to
corrosion in certain aggressive environments.
Abrasion is the wearing away of culvert materials by the erosive action of bedload carried in the
stream. Abrasion is generally most serious in steep areas where high flow rates carry sand and
rocks that wear away the culvert invert. Abrasion can also accelerate corrosion by wearing away
protective coatings.
Corrosion and abrasion of culverts can be a serious problem with adverse effects on structural
performance. Damage due to corrosion and abrasion is a common cause for culvert replacement.
It is important to recognise that thin walled flexible pipes gain most of their compressive strength
through composite action with the surrounding backfill, so even small losses of the surrounding
backfill can have severe impacts on the structural capacity of the culvert. If thin walled culverts can
be accessed, then tapping the walls is a very effective measure of contact between the
surrounding backfill and the internal wall. If hollow sections are found then replacing the material
surrounding the culvert using grouting techniques should be given high priority
Concrete inverts are usually slabs on ground. Invert slabs provide protection against erosion and
undercutting, and are also used to improve hydraulic efficiency. In metal culverts, concrete inverts
are sometimes used in circular or other shapes, to protect the metal from severe abrasive or
severe corrosive action. Concrete invert slabs should be checked for undermining and damage
such as spalls, open cracks, and missing portions. The significance of damage will depend upon its
effect on the footings and corrugated metal.
The inspection should include visual observations of metal corrosion and abrasion. A geologist's
pick-hammer can be used to scrape off heavy deposits of rust and scale permitting better
observation of the metal. Protective coatings should be examined for abrasion damage, tearing,
cracking, and removal.
Cracking
Cracking may occur in most culvert materials and can indicate overloading resulting in small
(localized) failures in shear, flexure, or simply damage during installation.
In metal barrel structures, cracking may occur along bolt holes of longitudinal seams and can be
serious if allowed to progress. These cracks are most serious when accompanied by significant
deflection, distortion, and other conditions indicative of backfill or soil problems.
In concrete structures, reinforcing steel is designed to assume some of the imposed loads.
Therefore, small hairline cracks (widths less than 0.3 mm) are expected and are not cause for
alarm. The location of cracking in concrete structures can indicate the type of problems being
experienced.
In concrete pipe:
• Longitudinal cracks at the 3, 6, 9, and 12 o’clock positions indicate flexural cracking caused by
poor side support.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 154
Version 1.0 UNCONTROLLED WHEN PRINTED
• Longitudinal cracking in the invert at the 5 and 7 o’clock positions indicate shear cracking
caused by poor haunch support.
• Cracking at the 11 and 1 o’clock positions may be the result of shear forces from above the
structure.
• Transverse cracks may also occur and are usually the result of non-uniform bedding or fill
material causing point loads on the pipe.
Plastic pipe materials may experience splits. A split (rip, tear, or crack) is any separation in the wall
material other than at a designed joint.
Metal culverts
A critical area for the inspection of long span metal culverts is at the 2 o’clock and 10 o’clock
locations. An inward bulge at these locations may indicate potential failure of the structure. When
distortion or curve flattening is apparent, the extent of the flattened area, in terms of arc length,
length of culvert affected, and the location of the flattened area should be described in the risk
assessment comments. The length of the chord across the flattened area and the middle ordinate
of the chord should be measured and recorded.
Arch culverts
Arches are fixed on concrete footings, usually below or at the springline. The springline is a line
connecting the outermost points on the sides of a culvert. This difference between pipes and
arches means that an arch tends to deflect differently during the placement of backfill. Backfill
forces tend to flatten the arch sides and peak its top because the springline cannot move inward
like the wall of a round pipe. As a result, important shape factors to look for in an arch are:
• Flattened sides.
• Peaked crown.
• Flattened top arc.
Another important shape factor in arches is symmetry. If the arch was erected with the base
channels not square to the centreline, it can cause a racking of the cross section. A racked cross-
section is one that is not symmetrical about the centreline of the culvert. One side tends to flatten;
the other side tends to curve more while the crown moves laterally and possibly upward. If these
distortions are not corrected before backfilling the arch, they usually get worse as backfill is placed.
Plastic pipes
There are several definitions that are unique to describing shape defects in plastic pipe:
• Deflection - deviation from original design shape without the formation of sharp peaks or valley.
• Buckling - a bend, warp or crumpling. The following are forms of buckling:
− Hinging - yielding due to excessive bending moment in the pipe wall. Pipe wall exhibits a
sharp crease pointed inward or outward. Hinges usually form at the 3 o’clock and 9 o’clock
positions
− Wall Crushing - yielding in the wall produced by excessive compressive stresses. Pipe wall
exhibits a wrinkled effect
− Dimpling - a wavy or waffling pattern in the inner wall of the pipe due to local instability
Technical Manual Culvert Inspection and Risk Assessment – February 2022 155
Version 1.0 UNCONTROLLED WHEN PRINTED
16.1.4 Headwalls
The Assessor should look for evidence of deterioration, settlement, undercutting and signs of
failure of headwalls, endwalls and wingwalls.
Headwalls, endwalls, or wingwalls are designed to retain the embankment, prevent the water from
undermining the culvert ends, prevent piping around the culvert, and improve the hydraulic
capacity of the culvert. All headwalls, endwalls, or wingwalls are to be checked for:
• Deterioration.
• Settlement.
• Undercutting and signs of failure.
End treatments should be inspected in a similar manner to any other structural component. Their
effectiveness can directly affect the performance of the culvert.
Check for evidence of scour or undermining around footings and at inlet and outlet of culvert.
Stone end treatment types use wingwalls to retain the embankment around the opening. Check
stone masonry piers for mortar cracks, water and vegetation in the cracks, and for spalled, split,
loose, or missing stones. Wingwalls should be inspected to ensure they are in proper vertical
alignment. Wingwalls may be tilted due to settlement, slides, or scour.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 156
Version 1.0 UNCONTROLLED WHEN PRINTED
16.1.7 Pavement
Key factors to look for in the inspection of the road pavement include sag, cracking and settlement.
Review the culvert’s pavement maintenance history if available.
Defects in the pavement may be indicators of possible structural or hydraulic problems in the
culvert. The pavement should be inspected for the following conditions:
• Sag in roadway or guardrail.
• Cracks in pavement.
• Pavement patches or evidence that roadway has settled.
The roadway should be examined for sudden dips, cracks, and sags in the pavement. These
usually indicate excessive deflection of the culvert or inadequate compaction of the backfill
material. New pavement can temporarily hide problems. It is advisable for the Assessor to check
maintenance records to assess the age of the present overlay.
It is important to note that not all defects in the pavement are due to an adverse effect from the
culvert. Deterioration of the pavement may be due to excessive traffic and no other reason.
16.2 RoadLoc
Roadloc is TfNSW’s Linear Referencing system used to locate all assets along the road network. It
is the key link to other location information from the RAMS database. The reference consists of
four parts:
• Road Number: a 7 digit number, including preceding zeros.
• Link Number: sections along the road, each with a 4 digit number, which increases in the
prescribed direction.
• Carriageway Code: see below.
• Offset along Link: distance from the start of the link to the current location in kilometres to 3
decimal places (the nearest metre).
Prescribed Direction
• Each road has a “prescribed” direction, typically away from the Capital city or away from the
coast. (The opposite direction is called the “Counter” direction). Link numbers and Segment
numbers increase in the prescribed direction.
• Left and Right of the carriageway are always determined by facing in the prescribed direction,
not the direction of traffic flow.
Carriageway Code
Carriageway code is required to be understood for purposes of determining left or right of
carriageway.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 157
Version 1.0 UNCONTROLLED WHEN PRINTED
Figure 26 below shows a representation of a road with sections of A, B and C Carriageway code.
This is described below:
• Carriageway A - If the road is undivided road there is a single Carriageway and its code is A.
• Carriageway B - If the road is divided with a centre median there is a separate code for each
carriageway. The carriageway code along the prescribed direction is B.
• Carriageway C - If the carriageway is opposite to the prescribed direction, the code is C.
There are other less common Carriageway Codes you might see – these are mostly for ramps
between roads. The Carriageway also has a version number, but that is not needed here, as you
are always inspecting the latest version.
Figure 26 Example RoadLoc Diagrams
Technical Manual Culvert Inspection and Risk Assessment – February 2022 158
Version 1.0 UNCONTROLLED WHEN PRINTED
17 Glossary
Table 58 Glossary
Term Definition
Abrasion Wearing or grinding away of material by water laden with sand, gravel,
stones or other abrasive material
Afflux A raised water level at the inlet to a culvert due to insufficient capacity or
blockage
Aggradation Deposition of materials in culverts or stream beds (compare with
Degradation)
Culvert Failure A culvert is considered to have failed when it is no longer fit for purpose.
This could be due to structural collapse, either complete or partial, due to
corrosion, deterioration or when water is leaking out of or into the culvert,
or when the hydraulic area is reduced by more than 50%.
Technical Manual Culvert Inspection and Risk Assessment – February 2022 159
Version 1.0 UNCONTROLLED WHEN PRINTED
Term Definition
Debris Any material, including floating timber materials and other trash,
suspended sediment, or bed load
Foundation The in situ material beneath the pipe and pipe bedding material
Grade /Gradient The longitudinal slope of the channel as a ratio of the drop in elevation to
the distance
Hairline Cracks Very small cracks that form in the surface of a pipe due to tension caused
by loading
Headwall A structure placed at the inlet and outlet of a culvert to protect the
embankment slopes, anchor the culvert and prevent undercutting
Homogeneous A common wall between culverts
Inlet Control A culvert operates with inlet control when the flow capacity is controlled at
the entrance by the depth of headwater and the entrance geometry
Invert The bottom or lowest point of the internal surface of the transverse cross
section of a culvert. Opposite to Crown
Joint A connection between two culvert sections made either with or without the
use of additional parts
Technical Manual Culvert Inspection and Risk Assessment – February 2022 160
Version 1.0 UNCONTROLLED WHEN PRINTED
Term Definition
Piping A process of subsurface erosion in which surface runoff flows along the
outside of a culvert and with sufficient hydraulic gradient erodes and
carries away material from around or beneath the culvert
Ponding Water backed upstream of a culvert
Standing water within the barrel of a culvert
Prescribed Generally, East from Sydney, South from Sydney, North from Sydney,
direction West from Sydney
RAMS Road Asset Management System
Reinforced A concrete pipe designed with either steel or fibre reinforcement as a
Concrete Pipe composite structure
Rigid Pipe A pipe with a high resistance to bending
Risk Analysis Systematic process to understand the nature of and to deduce the level of
risk
Provides the basis for risk evaluation and decisions about risk treatment
Risk Assessment The process of risk analysis and risk evaluation
Risk Evaluation The stage at which value judgements enter the decision process, explicitly
or implicitly, by consideration of the importance of the estimated risks and
the associated social, environmental and economic consequences, in
order to identify a range of alternatives for managing the risks
Risk Management The complete process of risk assessment and risk control
Risk Rating The level of risk posed by culvert damage to roads/assets. It is also a
reflection of the level of damage that might be reasonably incurred by the
asset as a result of the possible damage
RoadLoc TfNSW Road Location identifier. RoadLoc uses the Linear Referencing
System
Scour Erosion of material causing rutting or washing away of the embankment or
area downstream of the outlet
Technical Manual Culvert Inspection and Risk Assessment – February 2022 161
Version 1.0 UNCONTROLLED WHEN PRINTED
Term Definition
Spall Flakes of a material that are broken off a larger solid body, which can be
produced by a variety of mechanisms, such as projectile impact,
corrosion, weathering, cavitation
Vegetation A general term for the plant life of a region; it refers to the ground cover
life forms, structure, spatial extent or any other specific botanical or
geographic characteristics
Technical Manual Culvert Inspection and Risk Assessment – February 2022 162
Version 1.0 UNCONTROLLED WHEN PRINTED