High-rise buildings
Third / Final
First Fix Second Fix
Fix
Typical Floor
Typical Floor
● Ducting Installation - Supply, Return, Fresh and Extract ● Pipe Connections to FCU
● Dampers Installation - Volume Control, Fire and Smoke ● Bends, Droppers, and Mouthpiece
● Duct Risers
● Duct Insulation
● Chilled Water Piping
● Chilled Water Pipe Riser
● Chilled Water Pipe Test
● Chilled Water Pipe Insulation
● FCU Installation
● Chillers Installation
● Staircase Pressure Fan Installation
● Garbage Exhaust Fan Installation
● Chilled Water Pump Installation
● Expansion Tank & Pressure Unit Installation
● Chemical Dosing Plant Installation
● FAHU Installation
● Duct Connection to FAHU
● Pipe Connection to FAHU
Typical Floor
Building
Building