Professional Documents
Culture Documents
1 - Demand Supply Balancing
1 - Demand Supply Balancing
1
2
3
Electrical Demand and Supply Options
Supply
• Thermal
Demand
– Coal
– Gas
– Lignite • Industrial
– Hybrid • Commercial
• Hydro
• Nuclear • Residential
• Wind • Transportation
• Solar
• Agriculture
• Small Hydro
• Diesel
• Other (Geo, Thermal,
Biomass, OTEC etc. )
• Storage
4
Typical Structure of Power Supply System
Overview of Indian Power Sector
Installed Capacity
MW % of Total
State Sector: 1,05,314 MW (26.7%) Fuel
Total Thermal 2,35,929 59.7%
Central Sector: 98,327 MW (24.9%) 2,03,900 51.6%
Coal
Private Sector: 1,91,434 MW (48.5%) Lignite 1.7%
Annual Peak Load Demand of the Country: 6,620
183 GW Gas 24,900 6.3%
6
Overview of Indian Power Sector
MW % of Total
Fuel
RES (Including Hydro) 1,52,366 38.5%
Hydro 46,512 11.8%
Wind 10.2%
40,101
Solar 50,304 12.7%
BM Power/Cogen 10,176 2.6%
Waste to Energy 434 0.1%
Small Hydro Power 4,840 1.2%
Status as on: Jan, 2022, Source: Ministry of Power website
Peak power demand deficit in the country was almost wiped out in 2020-
21 period. Providing statistics, the ministry said the deficit stood at 0.4 per
cent in 2020-21 compared to 16.6 per cent in 2007-08 and 10.6 per cent
in 2011-12.08-Nov-2021
7
Demand Supply Balancing
▪ What is Electricity Demand and Supply Balancing
Real Power Load-Generation Balance
Reactive Power Load- Generation Balance
Allowed Range
49.90-50.05 Hz
11
Frequency Variations (Indian Grid)
Allowed Range
49.90-50.05 Hz
•Failures at large power plants in France and Spain destabilized the integrated European grid.
•A grid controller data error from the TSO TenneT starts up the pumps at the Goldisthal pumped
hydro plant – even though the necessary power is not available in the grid.
•The normal hourly handoff between large power plants causes a predictable frequency
fluctuation of 0.1 hertz.
•A feed-in shortfall, which can possibly be traced back to the data error. 13
Frequency Control Response
Questions to Answer
14
Demand Supply Balancing
▪ Need for Minute-to-Minute Balancing
▪ Need for organizational structure
▪ Markets, Regulation
▪ Optimization
Various Stake holders in power Supply Chain
15
Major Changes in Power System Operations
in Past Years
16
Various Stake holders in Power Supply Chain
• Generation Companies : GENCOs
(Public, Private, State/Central Government)
• DISCOMS
Public, Private, State/Central Government)
• TRANSCOs
(State/Central Government)
Unit Commitment
Economic Dispatch
Security • Analysing the system parameters like voltage, line power flows,
transformer loading etc. to be within permissible limits or not.
• Planning for the predictive measures: Power flow based analysis
• Real time security assessment and control: Scada based Energy
Management Systems
Optimal Power • Optimal setting of the controls in the system with the objective of
better operation: can be economics, loss reduction, stability
Flow
enhancement etc.
Unit Commitment (UC)
Basics:
• Unit commitment problem states that out of 𝑁𝑔 generating units
available which of them should be committed in order to satisfy the
forecasted demand with the objective of minimum operating
cost/or dependent on the system operators objective.
• The solution involves integer variables i.e. either the unit is ON (1)
or OFF (0) hence difficult to solve.
Thermal
Plants:399
Hydro: 197
Nuclear
Reactors: 22…..
..
Algorithms for UC
• Need for Optimization?
• Heuristics
• Binary coded Algorithms
• Classical Methods like Dynamic Programming, Lagrange
Relaxation
Important factors to be considered in UC
Reserve Requirement
• Spinning reserve
Some generators in the system are synchronized to the grid but are
not generating any power. This is termed as spinning reserve.
Spinning reserves are necessary so that loss of one or more
generating units do not cause a significant loss in system frequency.
• Offline reserves
It consists of generating units which are not connected to grid but
can be brought on-line and synchronized quickly, e.g. pumped
storage.
• Unit on banking
Important factors to be considered in UC
For Thermal Units
• Minimum uptime: Once the unit is turned ON, it should be kept ON
for a minimum amount of time before turning OFF.
3. If H is less than the minimum shutdown time for the unit, keep the
commitment as is and go to the last step; if not, go to the next step.
Priority based Method for UC
Priority List Method (Heuristics): Also known as Merit Order Dispatch
4. Calculate two costs. The first is the sum of the hourly production costs
for the next H hours with the unit up. Then recalculate the same sum for
the unit down and add in the start-up cost for either cooling the unit or
banking it, whichever is less expensive. If there is enough savings from
shutting down the unit, it should be shut down; otherwise, keep it on.
5. Repeat this entire procedure for the next unit on the priority list. If it
is also dropped, go to the next and so forth.
Change in
1. Uncertain generation, load patterns Scheduling
✓ Deregulated Market Operation Practices,
✓ Renewable based Generation Ramp Rates,
Financial
✓ Dynamic Loads like Electric Vehicles
Mechanisms
2. More controllability required
3. Inertial Response
Primary control reserves alone would not be enough to halt the drop, and
reserve power plants could not be started quickly enough.
The French transmission system operator, RTE, sprang into action, issuing
emergency rolling blackout requests to all of France’s 22 large industrial
demand response consumers that reduced power consumption by 1,500
MW.
The utility frequency stabilized and was heading back toward normal levels
at 21:10; by 21:25, the frequency was back to 50 hertz.
34
Delhi’s Load Curve
35
50 Hz_Committee1.pdf (cercind.gov.in)
36
Thank You
37