Professional Documents
Culture Documents
Untitled
Untitled
Uncertainty
y Some scheduling procedures explicitly consider the
uncertainty in activity duration
Stochastic Scheduling y Use probabilistic distribution of activity durations
y a particular activity is assumed to be a random variable that is
Topics distributed in a particular fashion
1. Uncertainty y Beta distribution is often used to characterize activity
2. PERT durations (absolute min and max) three-four parameters
3. Monte Carlo Simulation y Normal distribution is a good approximation (uses two
4. Software and Excel examples parameters)
1
10/10/2013
Example Example
y Consider the nine activity example project shown in Table y Activity duration estimates are follows:
below. Suppose that the project have very uncertain activity
time durations. As a result, project scheduling considering
this uncertainty is desired.
2
10/10/2013
Solution Solution
y CPM calculations : Critical path : A, C, F and I y For example, find the probability of project completion
within 35 days is:
y Sum of the means for the critical activities is 4.0 + 8.0 + 12.0 +
6.0 = 30.0 days,
y Sum of the variances : (0.33)2 + (0.67)2 + (0.67)2 + (0.67)2 =
9 1.44 and the standard deviation is 1.2 days. 10
3
10/10/2013
13 14
4
10/10/2013
Solution Solution
y We will randomly generate values for each of the tasks, then y Probability of Completion Within Specified Time (Months)
calculate the total time to completion ( beta-PERT
distribution is used to generate random values)
y The simulation run 500 times.
y The results describe some of the characteristics of the risk in
the model (Results of MCS shown in the Table)
17 18
Solution Example 2
y The original estimate for the “most likely”, or expected y Given data and the network below for a project, find the
case, was 14 months. probability that the project ends in 20 weeks (use MCS)
y we can see that out of 500 trials using random values,
the total time was 14 months or less in only 34% of the
cases
y It is extremely unlikely that we will ever fall at the
absolute minimum or maximum values
y Based on this information, we might make different
choices when planning the project
y Having more information about risk at the beginning
means we can make a better plan for going forward.
19 20
5
10/10/2013
Example 2 Solution
y Data for Example 2 y 50 simulation runs and summary results of the first 10 runs
21 22
23 24
6
10/10/2013
25 26
7
10/10/2013
29