000 NOTES
B C D E
1. ALL DIMENSION ARE IN MILLIMETER. ALL LEVELS ARE IN METER.
(6+6) - Y10 AT 125 C/C 1863 1863 1863 1863

650
B2 2. SEISMIC ZONE: III AND BASIC WIND SPEED: 47M/ SEC.
HOOP BAR & BTM Y8 AT 125 C/C 3. GRADE OF MATERIAL -
13 16 IL115.350 3.1 USE OF CONCRETE M25 FOR THE STAGING AND FOUNDATION (GET THE MIX
HOOP BAR 1000mm Balcony Slab
Y8 AT 125 C/C DESIGN APPROVED BY ENGINEER-IN-CHARGE BEFORE EXECUTION)

650
499
RADIAL BAR AT TOP
3.2 Y DENOTES TMT HIGH YIELD STRENGTH DEFORMED BARS OF GRADE (FE
Y8 AT 70 C/C B/W
500) CONFIRMING TO IS 1786: 2008 WITH ELONGATION MORE THAN 14.5% AND
1 ISA 50X50X6 POSTS

PER SITE CONDITION SPACING


IL120.050 MANUFACTURER SHALL SUPPLY THIS SAME.

OF RINGS IN LAPPING ZONE


LAPPING ZONE OF BARS AS

NOT MORE THAN 100 C/C


2 Y8 AT 190 C/C B/W 3.3 P.C.C. AS PER NIT OR MINIMUM M-15 AND 100MM THICK WITH MINIMUM
B1 16 PROTECTION OF 100MM.
3 - Ø20 G.I.
CAPACITY OF TANK 150 KL 3.4 THE GRADE OF CEMENT SHOULD BE OPC/PPC 43 IN CONCRETE WORK.
PIPE RAILING
7450
4. ACCORDING TO GEO-TECH REPORT OF SITE LOCATION SBC OF SOIL -

R372
3226
AS PER FABRICATOR ASSUMED TANK DIA. Ø 7.450M B1 78.48KN/m2 AT 2.0 M DEPTH.
4050

B1

3850

2550
5
Y8 AT 190 C/C B/W 5. FOUNDATION SHALL BE REST ON GOOD SOIL. IT SHOULD NOT REST ON BLACK
0
95 COTTON SOIL OR ON SOIL HAVING EXPANSIVE PROPERTIES. AFTER
R3 EXCAVATION UP TO GIVEN DEPTH, SOIL STRATA SHALL BE VERIFIED BY SOIL

150
RAILING CONSULTANT AND ENGINEER-IN-CHARGE FOR GIVEN FOUNDATION SYSTEM.
3 EXECUTION SHALL COMMERCE ONLY AFTER APPROVAL FROM SOIL
IL116.000 B2 Y10 AT 150 C/C CONSULTANT AND ENGINEER-IN-CHARGE.
SQ. MESH (IN BTM) 6. CARE SHALL BE TAKEN TO AVOID ACCIDENTAL UPLIFT ON STRUCTURE DURING
IL115.350 CUTOUT FOR INLET OUTLET 1000
OVERFLOW & DRAIN CONSTRUCTION. IF GROUND WATER IS ENCOUNTERED DURING EXECUTION
B1

3226
B1 CONTINUOUS DE-WATERING SHALL BE DONE TO FOUNDATION SYSTEM.
650

ISA 50X50X6 POSTS Y10 AT 150 C/C EXECUTION SHALL COMMERCE ONLY AFTER APPROVAL FROM

650
B/W (IN TOP) SECTION 16-16 Y8 AT 70 C/C B/W ENGINEER-IN-CHARGE AND SOIL CONSULTANT. KEEP FOUNDATION TRENCH IN
IL111.500 DRY CONDITION TILL IT ACHIEVES ITS FULL STRENGTH.
B1 15

450
3 - Ø20 G.I. 7. PROPER STORM WATER DRAINAGE SYSTEM IT BE MAINTAINED AT SITE AND
3850

BR
PIPE RAILING 4 IL111.050 SURROUNDING AREA TO AVOID LOCALIZED TEMPORARY WATER TABLE EFFECT.
450
5 8. ALL OPENINGS AND CUTOUTS IN SLAB SHALL BE LEFT AS PER DRAWING NO

650
OPENING/ CUTOUT SHALL BE MADE ONCE CONCRETE IS CAST AND SHALL BE

499
Y8 AT 70 C/C B/W VERIFIED BY ENGINEER-IN-CHARGE.
9. STRUCTURAL DESIGNER IS NOT RESPONSIBLE ANY DEVIATION ON SITE WITH
IL111.500
13 15 1000mm Balcony Slab RESPECT TO THIS DRAWING AND UNWANTED ACCIDENT IN ANY CASE.
450

150
IL111.050 VERIFICATION OF REINFORCEMENT ON SITE WILL BE PROVIDED IF

PER SITE CONDITION SPACING


OF RINGS IN LAPPING ZONE
LAPPING ZONE OF BARS AS
CONTRACTOR OR AGENCY SPECIFICALLY ASKED FOR. BUT RESPONSIBILITY

NOT MORE THAN 100 C/C


COLUMN REGARDING CORRECT & SOUND CONSTRUCTION SHALL SOLELY REST WITH
Ø 450MM R/F DETAIL OF BOTTOM SLAB (200 THK) (M-25) CONTRACTOR/ AGENCY, ENGINEER-IN-CHARGE AND CONCERN DEPARTMENT.
1000 10. STRUCTURAL DESIGNER HAS NO LEGAL LIABILITY.

3850

2550
Y10 AT 150 C/C (IN TOP) (B/W) Y10 AT 150 C/C (IN TOP) (B/W) 11. CORRELATE ALL LEVELS, OPENING CLEAR DIMENSION WITH DRAWING ANY
3850

Y8 AT 125 C/C (IN TOP) (B/W) Y8 AT 190 C/C B/W AMBIGUITY SHALL BE BROUGHT TO THE NOTICE OF DESIGNER BEFORE
SECTION 15-15

200
300 300 300 EXECUTION.
12. DEVELOPMENT LENGTH -
BRACE BEAM 12.1 IN COLUMN, BEAM AND FOUNDATION = 50 DB

650

650

650
300X450 (TYP.) 12.2 VERTICAL AND OTHER = 50 DB
IL107.200
150
450

IL106.750 13. LD* = LD + 10 DB WHERE DB IS DIAMETER OF BAR.


(6+6)Y10 AT 125 C/C Y10 AT 150 C/C 14. IN CASE OF ANY DISCREPANCY IN THE DRAWING CONTACT STRUCTURAL
HOOP BAR TOP & BTM SQ. MESH (IN BTM) DESIGNER BEFORE EXECUTION.

650
Y8 AT 70 C/C B/W 15. NOT MORE THAN 50 % OF AREA OF STEEL BARS SHALL BE SPLICED AT ANYONE
IL107.200 SECTION.
SECTION 13-13 16. FOR NUMBER OF BAR ROUND UP THE VALUE UP TO NEAREST DIGIT WITH

450
3850

BR RESPECT TO SPACING AND LENGTH.


IL106.750
17. ANCHORAGE OF ZINCLUME WATER TANK SHALL BE CONFIRMED BY TANK
MANUFACTURES.

650
450 450 Y8 AT 70 C/C B/W
BRACE BEAM GL 100.000
300X450 (TYP.) CENTERING
IL102.900
HOOP-4-16 (TH.)
450

3900.8 (ARC) 18. THE CENTERING FOR STRUCTURAL MEMBERS SHALL NOT BE REMOVED
IL102.450

2L-Y10 AT 100 C/C


BEFORE CONCRETE SHALL ARCHIVED A CUBE CRUSHING STRENGTH AT 7 DAYS
C1 4 - Y16 (TH.) C1 450 Y8 AT 190 C/C B/W AGE ATLEAST 68% OF ITS FINAL CUBE CRUSHING STRENGTH. IN NORMAL
CASED WHERE OPC IS USED FORMS MAY GENERALLY BE REMOVED AFTER THE
FOLLOWING PERIOD.
18.1 SLAB: SPANING UP TO 45M - 7 DAYS SPANING UP TO 6M - 14 DAYS.
2000

3850

2550
3800

650
650

650
11 12 18.2 BEAMS SOFIT: WITH PROPES LEFT UNDER 7 DAYS.
IL100.000 GL100.000 18.3 COLUMN: 24 HOURS.
18.4 VERTICAL SIDE OF BEAMS: 48 HOURS. THE NUMBER OF PROPES & THEIR
SIZES SHALL BE SUCH THAT SO AS TO ABLE TO CARRY THE FULL DEAD LOAD
PLINTH PROTECTION
IL 98.650 HOOP-4-Y16 (TH.) OF STRUCTURAL MEMBERS & ALSO THE LOAD DUE TO THE CONCRETING &
300 300 300 300 OTHER CONSTRUCTION OPERATION. SITE-IN-CHARGE WILL BE FULL
IL 98.000 SECTION 11-11 RESPONSIBLE FOR THE SAME.
LEGENDS
ELEVATION A-A HOOP-4-Y16 (TH.)

650
11 12 I E/F EACH FACE V SB STAIR BEAM
Y8 AT 70 C/C B/W
14 (HOOPS) Y8 AT 100C/C (OUTSIDE)

4 - Y16 (TH.)
13 (HOOPS) Y8 AT 100C/C (INSIDE)

2L-Y10 AT 100 C/C


IL102.900
A B C D E 450 II C/C CENTRE TO CENTRE VI TYP TYPICAL

450
1863 1863 1863 1863
RAFT BEAM RB-3 (450X650) (M-25) BR
IL102.450 III R/F REINFORCEMENT VII TB TIE BEAM

IV RB RING BEAM VIII BTM BOTTOM

650
650
GL100.000 Y8 AT 70 C/C B/W
499

CLEAR COVER
CENTERLINE OF COLUMN
188 - Y10 AT 125C/C

1 I TOP SURFACE OF BTM SLAB 30 VII STAIR BEAMS (BRACKETS) 30


RADIAL BARS

2 HOOP-4-Y16 (EX.) Y8 AT 190 C/C B/W


HOOP-4-Y16 (TH.) II BTM SURFACE OF BTM SLAB 30 VIII SIDE COVER BEAM 25

III TOP SURFACE OF BTM SLAB 30 IX SIDE COVER FOOTING 40


0

SECTION 12-12
5
R395

72

2500
3800
IV BTM SURFACE OF BTM SLAB 30 X STAIRCASE WAIST SLAB 25
3226

R3
R53

5 00 V COLUMN 40 XI ANNULAR RAFT 50


R3
25

IL 100.000
2000

VI BRACE BEAM 30 XII BALCONY BOTH SURFACES 30

3 14
RB - 3 450X650
M/S VINDHYA TELELINKS LIMITED
14 R23
0 0
INNER PROJECTION -13 Y8 AT 100 C/C HOOPS GAJA ENGINEERING PVT.LTD JV
OUTER PROJECTION - 14- Y8 AT 100 C/C HOOPS
3226

650
EXECUTIVE DIRECTOR
CLIENT : AGENCY : IVPS INFRA PVT. LTD.
STATE WATER & SANITATION MISSION HAMAMI GANGE & RURAL WATER SUPPLY
188 - Y10 AT 125C/C RADIAL BARS IL 98.650 Y8 AT 70 C/C B/W DEPARTMENT GOVERNMENT OF UTTAR PRADESH LUKHNOW UTTAR PRADESH 13/123, Manash Nagar, Bara, Rewa (M.P.)
650

226501

DETAIL AS PER
425

SECTION 14-14 DESIGNING OF WATER TANK STRUCTURE CONSISTING OF STRUCTURE FRAME AND A PLATE
100 250

IL 98.000 FORM TO RECEIVE PREFABRICATED ZINCLUME WATER TANK AT GRAMPANCHYAT


4 MAHIPALPUR, BLOCK SHIVRAJPUR, DIST. KANPUR NAGAR, STATE UTTAR PRADESH
5
1375 450 1200 DETAIL OF COLUMN (M-25) ALUM ZINC TANK OF CAPCITY 150 KL AT 16M STAGING AT GRAMPANCHAYAT
499

MAHIPALPUR, BLOCK SHIVRAJPUR, DIST. KANPUR NAGAR, STATE UTTAR PRADESH


SECTION 14-14
DRAWING NO. IVPS/VTL/KNPR/150KL/16M/02-R0 (SHEET NO. 1/2)
R/F DETAILS OF RAFT SLAB S. NO TYPE COLUMN
TIES STARTING ENDING
AT CENTRE AT JUNCTION LEVEL LEVEL
8-Y20

GENERAL PLAN OF RAFT SLAB (IL 98.00) 1. COLUMN (CI) (M-25) Y8 AT 190 C/C Y8 AT 70 C/C IL 98.000 IL 116.000
UPTO 650
450