Professional Documents
Culture Documents
Doka Stronghold in The Middle East
Doka Stronghold in The Middle East
Doka Stronghold in The Middle East
1/2012 ME · www.doka.com
Editorial
Doka News
Doka Training Seminars
Doka Middle East supports fast and
safe assembly and deployment of its
formwork by offering site supervision
and onsite training, plus informative
theoretical seminars.
Dear Customers,
New Innovations
Middle East
Coupled with unparalleled service offerings
Dokaflex 15, Dokadek 30 and Staxo 100 are
unbeatable.
The facts
JoBSiTE Civil Works-Ruwais
GASCO Storage Tank, Pro-
pane & Butane Storage Tank
LoCATioN Ruwais, U.A.E.
CUSToMER Granite Construc-
tion Company
SYSTEMS iN USE Large-area
formwork Top 50 + Crane
Climbing 150F
Energy Demands
Yield 6 LNG Tanks
To meet ever-increasing market demand, Joseph Chacko,
Project Manager,
government-owned and operated Borouge is Granite Construction
Company
executing a multi billion dollar expansion in the city
of Ruwais, a sprawling green oasis 350 km away
from Dubai.
The professional
The Borouge 3 project is a key part of platform on top of the climbing system What impressed us
the Abu Dhabi government strategy for was necessary to enable installation of most was the full-time
growth, tripling production capacity and the reinforcement (rebar). Besides the Doka site supervisor
consolidating the global market posi- forming, Doka supplied expert consul- stationed at our project, and
tion. The project comprises an ethane tancy to ensure that the strict require- the swift logistics in delivering
cracker, polypropylene and polyethylene ment of fair-faced concrete was met to large amounts of material to
our remote site.”
plant, offsites and utilities and marine the satisfaction of the client.
facilities. After completion, total produc-
tion capacity will increase to 4.5 million Safe transfer of concrete pressure
metric tons a year. The construction process for form-
ing the LNG tanks was a single side
Granite Construction looked to Doka’s pouring whereby the contractor erect-
engineering expertise in LNG tanks. ed the steel tank first, followed by a
Practical tip
50 cm reinforced concrete wall against
6 massive tanks it on one side only. Due to the exist- Eliminate the need
in fair-faced concrete
The scope of the build is a total of
ing steel structure, it was possible to
place weldable couplers for sheet walls
for scaffolding
6 LNG tanks, each having a height of on the outer surface of the frame for Providing rebar platforms on
36 m and radius of 35 m. The challenge safe transfer of the concrete pressure the crane-climbing system
for the contractors and Doka was to through the tie-rod system. For this was one of the highlights,
cast 50 cm concrete walls outside the huge petrochemical project a record because these extra plat-
steel tanks. A portion of the total techni- 53,000 weldable couplers for sheet forms saved the client rent-
cal solution deployed by Doka is supply walls were fixed to the steel tanks by al cost and time. The solu-
and installation of a total of 528 brack- the contractors. tion eliminated the need for
ets of the crane climbing system 150F the scaffolding that would
in combination with Large-area form- 100 % Doka formwork otherwise be necessary for
work Top 50. Furthermore, due to the Doka Abu Dhabi was the sole formwork rebar placement.
construction methodology an additional supplier on this project.
6 Doka Xpress
In numbers
FoUNDATioN 5,000 m2 of
formwork with 600 RTU
Top 50 panels & corners
CoRE WALL FoRMWoRk
6,000 m2 of formwork
with 1,100 RTU Doka panels,
2,600 m2 of platforms,
400 sets of platform units
FLooR-SLAB FoRMWoRk
27,500 m2 of floor-slab form-
work set with 220,000 m3 of
shoring towers
The solution
consortium.
The facts
JoBSiTE Sama Beirut
LoCATioN Lebanon
CUSToMER MAN Enterprise
SYSTEMS iN USE Large-
area formwork Top 50,
Dokaflex tables, automatic
climbing formwork SKE50
and SKE100 for CPB
The professional
ity for fast and efficient climbing of the tions. Each shaft cell has it's own auto-
main core wall. A cycle of seven days matic climbing platform - allowing the
was reached easily, taking into consid- time-intensive rebar installation works for MAN Enterprise was
eration how quickly the site crew famil- the next level to start immediately after able to reach the
iarized themselves with the system. curing of concrete - without waiting for project’s requirement
Around 750 m2 of the Large-area form- formwork stripping, cleaning & climbing. because the Doka system
work Top 50 panels were coupled with More than 2,000 m2 of Dokaflex table- used less manpower. We
the SKE system to give the shafts very forms were utilized in order to keep cast- were able to achieve on time
easy forming sequences, and fair faced ing the horizontal elements in step with the pouring of vertical and
concrete as well. the rate of vertical progress. horizontal elements as well.”
10 Doka Xpress
As part of the company’s planned Top 50 was used for all the round col-
The professional
expansion in Oman, the Lulu Hypermar- umns. Framed formwork Frami Xlife
ket in Bowsher extended their building panels were used to construct the walls
With Doka formwork to approximately 30,800 m2 reaching 5 for 7 elevator lifts & staircases. The flex-
materials, ideal solu- storeys high. ibility of Frami Xlife panels is guaranteed
tion, safety and effi- efficient regardless of the complexity of
ciency are guaranteed in pro- optimizing logistics the wall’s shape. Additionally with the
viding valuable support to the for a tight schedule tried and tested Xlife sheet with built-in
construction site. Through Doka Muscat was awarded the contract plywood, longevity is guaranteed for up
this, it helps us increase our in December 2011 to supply the form- to 200 reuse cycles.
productivity and optimal sup- work design and A-Z requirements for
port in the planning phase.” the entire project. To meet the dead- Due to the vast area of floor slab on
lines, the Oman operation ensured that each storey, substantial quantities are
the large volume of rented formwork being used. The total of approximate-
material was supplied right on sched- ly 86,000 m2 of concrete floor slab with
ule. For forming the 770 m reinforced headroom varying between 5.50 and
concrete external walls in the basement, 6.50 m were formed by 9,000 m2 of
The facts Large-area formwork Top 50 in combi- Dokaflex tables and 3,000 m2 of Load-
JoBSiTE Lulu Bowsher Stage nation with Doka supporting construc- bearing towers Staxo 40. These were
2 Extension tion frames was used for the straight shifted quickly and safely to the next
LoCATioN Muscat, Oman and curved 6 m high walls. location with Doka transportation fork
and shifting trolleys. The Dokaflex system
CUSToMER Dolphin Trading &
Investment LLC Maximum flexibility gave full proof of its adaptability when it
SYSTEMS iN USE Large-area
for different column sizes came to forming the curved beams.
formwork Top 50, single- There are 415 reinforced-concrete col-
sided supporting construction umns of varying size on each floor. All For the external façade of the build-
frames, Frami Xlife, Dokaflex the rectangular columns were formed ing, the 11 m high suspended slabs
tables, Dokaflex and Load- with framed formwork Frami Xlife uni- are being shored with Load-bearing
bearing towers Staxo 40 versal panels and Large-area formwork Staxo 40 frames.
October 2012 11
Social Infrastructure
Expansion in Kuwait
The elaborate plans for social infrastructure
in the Middle East include designing and building p Universal Frami Xlife panels are
the most ergonomic and aesthetic hospitals in the ideal for varied cross-sections of
column in a 5 cm grid – including
world. forming special 6 m columns.
By October 2014 Kuwait will welcome a bahani, the biggest anticipated chal- Walid Barakat,
300-bed acute care hospital for Kuwait lenge from the beginning was securing Project Manager
Sayed Hamid
Oil Company in the prominent Ahma- adequate manpower for the job, plus a
Behbahani
di district. The structure's parameters stringent requirement for fair-faced con-
are unique in every way - sensitive to crete.
regional and Islamic principles; reflect
local environmental conditions; incor- Long-standing Doka customer bene-
porate state-of-the-art technology, sus- fits from familiarity and cost efficiency
tainable design; and facilitate a future As a longtime Doka customer, with
expansion of 100 beds. The footprint of proper Doka added value maintenance
the hospital is actually derived from the and the contractor's storage of its own Bashar Dib,
Islamic geometric form of a circle evolv- Doka formwork stock of floor props, tim- Site Engineer
ing into a rotated square into an eight- ber beams and standard steel parts,
sided star. The project boasts the four- cost efficiency on the floor slabs was
storey hospital with a combined area of maximized.
The professionals
80,000 m2 plus construction of five two-
storey residential buildings for medical For the retaining walls and special struc-
staff with a combined area of approxi- ture walls, plus the special shaped walls Our engagement with
mately 10,000 m2. the flexible Large-area formwork Top 50 Doka resulted in the
was used for speed, partly because in accurate solution for
Securing manpower Kuwait, the crew is well used to work- maximum effectiveness of the
For all forming operations commenc- ing with this system. For casting all systems deployed, combined
ing in February 2011, Doka Kuwait was standard columns including the special with strict cost control and
the exclusive formwork partner. Working requirement of 6 m columns, Frami Xlife overcoming any manpower
with main contractor Sayed Hamid Beh- column formwork was used. resource issues.”
The facts
JoBSiTE
New Ahmadi Hospital Project
LoCATioN Ahmadi, Kuwait
CUSToMER
Sayed Hamid Behbahani
SYSTEMS iN USE Large-area
formwork Top 50, framed
formwork Frami Xlife, Doka
birch plywood for fair-faced
concrete, Eco 20 floor props,
H20 timber beams
t A combination of readily
available material from Doka
kuwait's yard and contractor-
owned material benchmarks
efficiency.
12 Doka Xpress
The Formwork
That Adapts by Itself
Doka has scored yet another sales success by
winning the formwork contract for the 555 m Lotte
World Tower.
The facts The client, Lotte Construction, rated the gapless enclosure of the under-con-
Doka concept as the “technically most struction storeys has to adapt to the
HEiGHT555 m sophisticated and best-quality formwork decreasing circumference automatically,
Seoul
CiTY solution”, as it adapts more or less “on i.e. without needing any time-consum-
USE Mixed use its own” to the many changes in cross- ing modifications. To achieve this, the
PECULiARiTY section. Quite apart from the core’s enor- entire Xclimb 60 solution (screens and
Many cross-section changes mous height, then, its complex shape platforms) can be adjusted to the struc-
ARCHiTECT presents another set of highly challeng- ture with 1 m telescopic areas on both
Kohn Pedersen Fox ing requirements. In front elevation view, ends. Thus the width of the screens can
FLooRS 123 the core breaks down into three sec- be modified within a range of 3 to 5 m.
CoNTRACToR tions which are roughly equal in height The screen will be delivered in the next
Lotte Construction but which are completely different geo- few months.
metrically. From August 2011, the Doka
climbing formwork system SKE100 will Column formwork
be setting the pace on this CIP concrete with own rebar crane
core as well, raising some 2,500 m² of Gigantic CIP concrete pillars, known as
The solution Large-area formwork Top 50 and three ‘mega-columns’, run up the outsides of
concrete placing booms with the aid of the structure. Between the first and last
The Doka climbing form-
work system SKE100 is rais- 144 automatic climbers SKE100. casting steps, their quadratic cross-sec-
ing some 2,500 m² of Large- tion tapers from 3.50 m to 2.00 m. The
area formwork Top 50 and Telescopic protection screen self-climbing solution ‘SKE50 plus’ is
three concrete placing booms on rollers used here in conjunction with ‘Top 50’
with the aid of 144 automatic To enable the slab-forming work in the Large-area formwork elements. To
climbers SKE100. There is also top four storeys of the rising core to speed up the construction workflow
a telescopic protection screen take place under optimum safety con- still further, each column will have its
Xclimb 60 in use that adapts ditions, sheltered from the weather, the own crane for lifting in the rebar. These
automatically to the many self-climbing Doka protection screen cranes are ‘climbed’ together with the
changes in cross-section. Xclimb 60 is to be fielded here. This formwork solution.
October 2012 13
Doka Formwork
Service Management
Khalid Mehmood,
Project Manager
Ghulam Rasool
The solution
16,000 m3 of Load-bearing
towers Staxo 100 form the full
four spans of the bridge. The
preassembly team has fab-
ricated 1,200 m2 of Top 50
panels, which Doka’s onsite
assembly team are erecting
using spindles and a special
suspended solution to speed
up and simplify handling and
repositioning. At the outset,
Load-bearing tower Staxo 40
is utilized for forming the top
and cantilever slabs.
October 2012 15
The facts
JoBSiTE
Sabah Al-Salem University,
College of Arts and Education
THE CUSToMER
Arabtec Construction LLC
Joint Venture Combined
Group Contracting Company
LoCATioN Shidadiyah, Kuwait
SYSTEMS iN USE
Load-bearing towers
Staxo 40, Large-area form-
work Top 50, Dokaflex
for Education
One side of the building wall
features a prism shape finish,
which necessitated the cast-
ing of inclined columns vary-
ing from 62 to 70 degrees. As
a key part of the design, Doka
successfully met the require-
ments with the flexible Large-
Located south-west of Kuwait City is a six area Formwork Top 50 plus
cantilever brackets to help
million square meter plot allocated to the Univer- climb the formwork.
sity City, whose mission is to integrate facilities of
health, science and humanities into one campus. Awni El-Baraqouni,
Deputy Project
Director, JV Arabtec
& Combined Group
The vision is to develop world class edu- area formwork Top 50. Columns of dif-
cational facilities equipped with the most ferent sizes were easily formed with
advance Resources for human talent and Large-area formwork Top 50 as well
future development in the country. as retaining walls. For single height
slabs, Dokaflex slab system was used.
Four colleges supplied by Doka To ensure the highest level of safety Dr. Abdulaziz
Al Hosamy,
Doka is supplying initially for the first required by the client, certain floors of Project Director,
educational building whereby the con- drop-beam design were supported with JV Arabtec &
tractors are using both new and exist- a combination of Staxo 40 and additional Combined Group
ing Doka stocks for the University City Eurex top floor props.
which will be completed in 2015. The
first building to be constructed was the Staxo 40 scores in kuwait The professionals
College of Arts for Men. The plan is to The fast and safe Load-bearing tow-
optimize cost-effectiveness and reduce er Staxo 40 gave structural support for Due to the sheer mag-
the amount of total material required by shoring heights of approximately 7.5 m. nitude of the project,
shifting and reusing formwork in vari- The site management were extremely we are extremely hap-
py to work with professionals
ous sequential zones. Contractors did happy with the fast result of the Staxo
who recommended the cor-
not hesitate because they were confi- system, especially because it was light-
rect system, offered round-
dent that any additional material required er with an ergonomic H shaped frame, the-clock support, available
would be supplied to the site on sched- faster to erect by just two laborers for supply of material, and the
ule from Doka’s Shuwaik warehouse. one tower and with few separate com- exact training required. We
ponents. Entire towers were swiftly and were very happy to be intro-
Basement heights of the building were safely moved by crane, due to the sys- duced to Staxo 40 which
7.2 m with a single casting of Large- tem's crane safe connections. saved us a lot of time.”
16 Doka Xpress
In Brief
News, dates, media, awards
t Ralf Bürger,
Managing
Director Doka
Qatar WLL
Global competence center support for Doka & Dubai Municipality held a form-
t karl tunneling projects work safety seminar
Heinz Riedl,
Managing
Director Doka TUNNELiNG CHALLENGES DokA SAFETY oN WoRLD HSE DAY
Gulf FZE Every single project is unique and calls Dubai Municipality teamed up with
for custom-tailored services. No matter Doka Gulf FZE to present new safety
which tunnel-building method you use, innovations in formwork systems which
the Doka formwork experts will work comprehensively address all aspects
with you to find the right solution. of material quality and construction
jobsite safety. The event held at Dubai
ANoTHER HiGH-RiSE EXPERT Municipality on May 1, 2012, was
The gecko, like Doka, is synonymous for entitled “360 Degree Formwork Safety
its abilities in safe and fast climbing. Symposium”.
For more info stay tuned to
www.youtube.com/doka for the
“gecko experience”.
Impressum: Doka Xpress is a publication of the international Doka Group. Publisher: Doka GmbH, Josef Umdasch Platz 1, A 3300 Amstetten, Austria.
Editor-in-chief: Sonali Maheshwary. Layout design: Como GmbH, Linz, Austria
In some cases the site photos show the situation during formwork assembly and are therefore not always complete from the point of view of safety.
Doka Gulf Doka Emirates Doka Qatar Doka kuwait Doka Lebanon
Dubai Sharjah Qatar Kuwat Lebanon
Tel. +971 4 870 8700 Tel. +971 6 556 2801 Tel. +974 4 4500 628 Tel. +965 24 82 24 62 Tel. +961 1 612 569
emirates@doka.com sharjah@doka.com qatar@doka.com kuwait@doka.com lebanon@doka.com
Doka Emirates Doka Saudi Arabia Doka Muscat Doka Bahrain Doka Jordan
Abu Dhabi Jeddah Oman Bahrain Jordan
Tel. +971 2 676 5855 Tel. +966 2 669 1008 Tel. +968 244 844 45 Tel. +973 17 402 810 Tel. +962 6 554 5586
abu-dhabi@doka.com jeddah@doka.com oman@doka.com bahrain@doka.com jordan@doka.com