Report - Belaguru
Report - Belaguru
Sl.
Item Unit Nos. L B D/H Qty Remarks
No.
1. Earth work excavation for Leveling and Lowering the ground Completed
in Ordinary Soil (other than foundation work) and removing the Satisfactorily
excavated earth to a distance not exceeding 50m and lift upto
1.50m and spreading, leveling etc., complete wherever
necessary
Second Bill Cum 1.0 15.00 15.00 0.20 45.00
Third Bill 1.0 15.00 8.00 0.20 24
TOTAL 69.00
2. Earthwork excavation for foundation of buildings, culverts, Completed
water supply, sanitary lines and electrical conduits either in pits Satisfactorily
or in trenches 1 .5m and above in width, in Hard soil not
exceeding 1.5 m. in depth including dressing the bottom and
sides of pits and trenches, stacking the excavated soil clear
from edges of excavation with lead upto 50 m after breaking of
clods complete as per specification
Main Wall Cum 1 10.00 0.75 0.75 5.63
1 8.20 0.75 0.75 4.61
2 6.15 0.75 0.75 6.92
TOTAL 17.16
3. Filling available excavated earth (excluding rock ) in sides of Completed
foundations up to plinth in layers not exceeding 20 cms. in Satisfactorily
depth, compacting each deposited layer by ramming after
watering with lead up to 50 m. and lift upto 1.5 m. including
cost of labour complete as per specification. specification No.
KBS 2.9
Cum 1 25.00 12.00 1.30 390.00
1 16.00 12.00 0.30 57.60
Sl.
Item Unit Nos. L B D/H Qty Remarks
No.
1 15.00 14.00 0.40 84.00
TOTAL 531.60
4. Providing and laying in position plain cement concrete of mix Completed
M7.5 with OPC Cement @ 180kgs, with 40mm and down size Satisfactorily
graded granite metal coarse aggregates @ 0.85Cum and fine
aggregates @ 0.57cum machine mixed, machine mixed,
concrete laid in layers not exceeding 15cms thick, well
compacted , in foundation and plinth, including cost of all
materials, labour, HOM of machinery, curing complete as per
specifications. Specification No. KBS 4.1,4.2
Cum 1 10.00 0.75 0.15 1.13
1 8.20 0.75 0.15 0.92
2 6.15 0.75 0.15 1.38
TOTAL 3.43
5. Providing and constructing granite I trap I basalt size stone Completed
masonry in Foundation with cement mortar 1 :6, stone Satisfactorily
hammerd dressed in courses not less than 20 cms high, bond
stones at two m. apart in each course including cost of
materials, labour, curing complete as per specifications. KBS
5.1 .13
1st flooring Cum 1 10.00 0.60 0.60 3.60
1 8.20 0.60 0.60 2.95
2 6.15 0.60 0.60 4.43
TOTAL 10.98
6. Providing and constructing granite I trap I basalt size stone Completed
masonry in Basement with cement mortar 1:6, stone hammered Satisfactorily
dressed in courses not less than 20 cms high, bond stones at
two m. apart in each course including cost of materials, labour,
curing complete as per specifications. KBS 5.1 .13
Cum 1 10 0.6 0.45 2.70
1 8.2 0.6 0.45 2.21
2 6.15 0.6 0.45 3.32
Deduct -1 0.6 0.4 0.45 -0.11
Sl.
Item Unit Nos. L B D/H Qty Remarks
No.
-1 0.8 0.4 0.45 -0.14
TOTAL 7.98
7. P/L PCC M20 for Plinth Beams Completed
Satisfactorily
Cum 1 10 0.45 0.12 0.54
1 8.2 0.45 0.12 0.44
2 6.15 0.45 0.12 0.66
TOTAL 1.64
8. Providing and removing centering, shuttering, strutting, Completed
propping etc., and removal of form work for Plinth Beams not Satisfactorily
exceeding 1m in depth including cost of all materials, labour
complete as per specification
Cum 2 10 0.15 3.00
TOTAL 9.15
9. Providing and constructing Burnt Brick Masonry with Completed
approved quality of non modular bricks of standard size of Satisfactorily
class designation 50 (table moulded) with cement mortar 1:6
for basement and superstructure including cost of materials,
labor charges scaffolding curing complete as per specifications
Cum 1 10 0.23 1.20 2.76
TOTAL 9.70
Sl.
Item Unit Nos. L B D/H Qty Remarks
No.
10. Providing 15mm thick cement plaster in single coat with Completed
cement mortar 1:4, to Brick masonry I concrete surface Satisfactorily
including rounding off corners wherever required smooth
rendering, : Providing and removing scaffolding, including cost
of materials, labour, curing complete as per specifications.
Sqm 1 10 2 1.20 24.00
1 8.2 2 1.20 19.68
2 6.15 2 1.20 29.52
Pillars 11 0.30 1 1.55 5.12
Design top of wall 19 0.75 0.23 3.28
Basement 2 10.0 0.45 9.00
2 8.20 0.45 7.38
4 6.15 0.45 11.07
Top of wall 1 30.5 0.23 7.02
Deduction -1 0.60 0.40 -0.24
-1 0.80 0.40 -0.32
TOTAL 115.51
11. Providing and finishing external walls in two coats with Completed
waterproof cement paint of approved brand and shade to give Satisfactorily
an even shade after thoroughly brooming the surface t remove
all dirt and loose powdered materials, free from mortar drops
and other foreign matter cost of materials, labour, complete as
per specifications.
Qty Same as External Plastering 115.51
SUB ESTIMATE 2: DECK SLAB
Sl.
Item Unit Nos. L B D/H Qty Remarks
No.
1. Earth work excavation for Leveling and Lowering the ground Completed
in ordinary Soil (other than foundation work) and removing the Satisfactorily
excavated earth to a distance not exceeding 50m and lift upto
1.50m and spreading, leveling etc., complete wherever
necessary
Smashana Office Cum 1 5.00 3.00 0.30 4.50
Temple 1 5.00 3.00 0.30 4.50
Toilet Block 1 6.00 3.00 0.30 5.40
TOTAL 12.18
2. Earthwork excavation by manual means in hard soil involving Completed
an average horizontal throw upto 2 meters and an average lift Satisfactorily
upto 0.5 m, excavated surface leveled and sides neatly dressed,
the disposed earth to be leveled neatly after breaking of clods
complete as per specifications complete as per specifications.
MORTH Chapter 3
Smashana Office Cum 1 1.20 1.65 0.90 1.78
Temple 1 3.00 1.65 0.90 4.46
Toilet Block 1 4.00 1.65 0.90 5.94
TOTAL 12.18
3. Plain cement concrete with crushed stone aggregate 40 m Completed
nominal size mechanically mixed, placed in foundation and Satisfactorily
compacted by vibration including curing for 14 days complete
as per specifications MORTH Specification No. 408
Smashana Office Cum 1 1.20 1.65 0.15 0.30
Temple 1 3.00 1.65 0.15 0.74
Toilet Block 1 4.00 1.65 0.15 0.99
TOTAL 2.03
4. Providing and constructing granite I trap I basalt size stone Completed
masonry in Foundation with cement mortar 1 :6, stone Satisfactorily
hammered dressed in courses not less than 20 ems high, bond
stones at two m. apart in each course including cost of
materials, labour, curing complete as per specifications. KBS
5.1 .13
Sl.
Item Unit Nos. L B D/H Qty Remarks
No.
Smashana Office Cum 2 1.20 0.45 0.60 0.65
Temple 2 3.00 0.45 0.60 1.62
Toilet Block 2 4.00 0.45 0.60 2.16
TOTAL 4.43
5. Providing and laying in position reinforced cement concrete of Completed
nominal mix 1:1.5:3 with 20mm and down size graded granite Satisfactorily
metal, machine mixed, concrete laid in layers not exceeding 15
cms thick, vibrated for all works in foundation plinth and
ground floor level for Footing including attached plasters,
columns, piers, abutments, pillars, posts, struts, butteresses,
string or lacing courses, parapets, coping, bed blocks, anchor
blocks, plain window cills, fillets etc., including cost of
materials, labour, HOM of machinery, curing, complete
Bed for Drain
Smashana Office Cum 1 1.20 1.65 0.15 0.30
Temple 1 3.00 1.65 0.15 0.74
Toilet Block 1 4.00 1.65 0.15 0.99
For slab portion 1 1.17 1.20 0.15 0.21
1 3.60 3.70 0.15 2.00
1 3.75 2.10 0.15 1.18
TOTAL 5.42
6. Providing and Removing Centering, Shuttering, propping etc Completed
and removal of form work for sides and soffits of beams, beam Satisfactorily
launchings, cantilever girders, bressumers and lintels not
exceeding 1m in depth including cost of all materials labou
complete (P.No-14, I.No-4.34) for Roof Slab
For slab portion Sqm 1 1.20 1 0.75 0.90
1 3.00 1 0.75 2.25
1 4.00 1 0.75 3.00
TOTAL 6.15
7. Providing HYSD Steel (cold twisted) reinforcement for RCC Completed
work including straightening, cutting, bending hooking placing Satisfactorily
in position lapping & or welding wherever required tying with
Sl.
Item Unit Nos. L B D/H Qty Remarks
No.
binding wire and anchoring to the adjoining members wherever
necessary complete as per design (laps hooks & wastage shall
not be measured & paid) Cost of materials, labour HOM
machinery
RCC Slab 12 Kgs 2 11 1.20 0.89 23.50
12 2 8 1.65 0.89 23.50
12 2 11 3.00 0.89 58.74
12 2 20 1.65 0.89 58.74
12 2 11 4.00 0.89 78.32
12 2 27 1.65 0.89 78.32
TOTAL 321.1
Sl.
Item Unit Nos. L B D/H Qty Remarks
No.
1. Earth work excavation for Leveling and Lowering the ground Completed
in ordinary Soil (other than foundation work) and removing the Satisfactorily
excavated earth to a distance not exceeding 50m and lift upto
1.50m and spreading, leveling etc., complete wherever
necessary
Cum 1 115.00 3.00 0.30 103.50
TOTAL 103.50
2. Earthwork excavation by manual means in hard soil involving
an average horizontal throw upto 2 meters and an average lift
upto 0.5 m, excavated surface leveled and sides neatly dressed,
the disposed earth to be leveled neatly after breaking of clods
complete as per specifications complete as per specifications.
MORTH Chapter 3
Drainage work Cum 1 118.00 0.90 0.90 95.58
TOTAL 95.58
3. Plain cement concrete with crushed stone aggregate 40 m Completed
nominal size mechanically mixed, placed in foundation and Satisfactorily
compacted by vibration including curing for 14 days complete
as per specifications MORTH Specification No. 408
Sl.
Item Unit Nos. L B D/H Qty Remarks
No.
Cum 1 118.00 0.90 0.15 15.93
TOTAL 15.93
4. Providing and laying in position reinforced cement concrete of Completed
nominal mix 1:1.5:3 with 20mm and down size graded granite Satisfactorily
metal, machine mixed, concrete laid in layers not exceeding 15
cms thick, vibrated for all works in foundation plinth and
ground floor level for Footing including attached plasters,
columns, piers, abutments, pillars, posts, struts, butteresses,
string or lacing courses, parapets, coping, bed blocks, anchor
blocks, plain window cills, fillets etc., including cost of
materials, labour, HOM of machinery, curing, complete
Bed for Drain Cum 1 118.00 0.75 0.15 13.28
Side RCC Concrete 2 118.00 0.15 0.60 21.24
TOTAL 34.52
5. Providing and removing centering, shuttering, strutting, Completed
propping etc., and removal of form work for Plinth Beams not Satisfactorily
exceeding 1m in depth including cost of all materials, labour
complete as per specification For Plinth Beam
Side RCC Concrete
Sqm 2 118.00 2 0.60 283.20
wall
TOTAL 283.20
6. Providing HYSD Steel (cold twisted) reinforcement for RCC Completed
work including straightening, cutting, bending hooking placing Satisfactorily
in position lapping & or welding wherever required tying with
binding wire and anchoring to the adjoining members wherever
necessary complete as per design (laps hooks & wastage shall
not be measured & paid) Cost of materials, labour HOM
machinery
Side Drain 10 Kgs 1 787 1.95 0.62 951.08
8 1 13 118.00 0.40 613.60
TOTAL 1564.7
SUB ESTIMATE 4: PIPE CULVERTS
Sl.
Item Unit Nos. L B D/H Qty Remarks
No.
1. Earth work excavation for foundation Of structures Like Completed
culverts, Retaining wall etc, As Per drawing And Technical Satisfactorily
Specification, Including Setting out
For pipe Cum 1 8.00 1.80 1.20 17.28
1 6.00 1.80 1.20 12.96
TOTAL 30.24
2. Plain Cement Concrete M10 mix With Crushed Stone Completed
Aggregates 40mm Nominal Size mechanically mixed PCC M- Satisfactorily
10
For pipe Rmt 1 8.00 1.50 0.15 1.80
1 6.00 1.50 0.15 1.35
TOTAL 3.15
3. P/F 900mm RCC Pipe NP3 as per specification Completed
Satisfactorily
Rmt 1 7.50 7.50
1 5.00 5.00
TOTAL 12.50
4. P/Name Board Completed
Satisfactorily
Nos. 1 1.00 1.00
TOTAL 1.00
Sl.
Item Unit Nos. L B D/H Qty Remarks
No.
1. P/F Burial Chambers with fitting Charges Completed
Satisfactorily
Nos. 2.00
TOTAL 2.00
2. P/F Electrification for Temple and Office Room Completed
Satisfactorily
Nos. 2.00
Sl.
Item Unit Nos. L B D/H Qty Remarks
No.
TOTAL 2.00
3. P/Water Supply and Pipe line Completed
Satisfactorily
Nos. 2.00
TOTAL 2.00
Remarks: This is to certify that the above said work found satisfactory at the time and date of
inspection only.
1
TEST REPORT ON CONCRETE CUBES
Note:
1. Samples are received by the concerned engineer
2. The report shall not be reproduced, except in full, without the written approval of the laboratory.
3. The results indicated above are based on the tests carried out on the samples received in the laboratory.
4. Any Query regarding the report must be reported immediately
2
TEST REPORT ON CONCRETE CUBES
Note:
1. Samples are received by the concerned engineer
2. The report shall not be reproduced, except in full, without the written approval of the laboratory.
3. The results indicated above are based on the tests carried out on the samples received in the laboratory.
4. Any Query regarding the report must be reported immediately
3
TEST REPORT ON CONCRETE CUBES
Note:
1. Samples are received by the concerned engineer
2. The report shall not be reproduced, except in full, without the written approval of the laboratory.
3. The results indicated above are based on the tests carried out on the samples received in the laboratory.
4. Any Query regarding the report must be reported immediately
4
TEST REPORT ON CONCRETE CUBES
Note:
1. Samples are received by the concerned engineer
2. The report shall not be reproduced, except in full, without the written approval of the laboratory.
3. The results indicated above are based on the tests carried out on the samples received in the laboratory.
4. Any Query regarding the report must be reported immediately
1
TEST REPORT ON CONCRETE CUBES
Note:
1. Samples are received by the concerned engineer
2. The report shall not be reproduced, except in full, without the written approval of the laboratory.
3. The results indicated above are based on the tests carried out on the samples received in the laboratory.
4. Any Query regarding the report must be reported immediately
2
TEST REPORT ON CONCRETE CUBES
Note:
1. Samples are received by the concerned engineer
2. The report shall not be reproduced, except in full, without the written approval of the laboratory.
3. The results indicated above are based on the tests carried out on the samples received in the laboratory.
4. Any Query regarding the report must be reported immediately
3
TEST REPORT ON CONCRETE CUBES
Note:
1. Samples are received by the concerned engineer
2. The report shall not be reproduced, except in full, without the written approval of the laboratory.
3. The results indicated above are based on the tests carried out on the samples received in the laboratory.
4. Any Query regarding the report must be reported immediately
TEST REPORT ON COURSE AGGREGATES
IS383-1970 (RA- 2002)
Client : Assistant Executive Engineer, KRIDL, Hosadurga
Agency : A.B.C Technical Consultants and Testing Centre
Name of Work : Revised estimate for providing fencing and COMPOUND
WALL at Belaguru burial ground in Hosadurga Taluk
Reference : AEE/Hosadurga/Thirdpartyinspectionreport2021-22
Date of Testing :
Material : 20 mm Aggregate
Totals Wt. Of Aggregates in gms=5000
Cumulative
Cumulative
Is Sieve Weight Retained Retained Retained
Weight Passing Spec.Limits
Size in mm (gm) Weight in % Weight in
in %
%
40 0 0 0 100 100
20 202 4.0 4 96.0 95-100
10 2743 54.9 58.9 41.1 25-55
4.75 1628 32.6 91.5 8.5 0-10
Physical Properties
Specific Gravity 2.60
Water Absorption 0.25%
Dry rodded Bulk Density 1455 kg/m3
loose rodded Bulk Density 1405 kg/m3
Note:
1. Samples are received by the concerned engineer
2. The report shall not be reproduced, except in full, without the written approval of the
laboratory.
3. The results indicated above are based on the tests carried out on the samples received
in the laboratory.
4. Any Query regarding the report must be reported immediately
TEST REPORT ON COURSE AGGREGATES
IS 383-1970 (RA- 2002)
Client : Assistant Executive Engineer, KRIDL, Hosadurga
Agency : A.B.C Technical Consultants and Testing Centre
Name of Work : Revised estimate for providing fencing and COMPOUND
WALL at Belaguru burial ground in Hosadurga Taluk
Reference : AEE/Hosdurga/Thirdpartyinspectionreport2021-22
Date of Testing :
Material : 40mm (Course Aggregates)
Total Wt. Of Aggregates in gms=15000
Cumulative Cumulative
Is Sieve Size Weight Retained
Retained Weight Passing Spec.Limits
in mm Retained (gm) Weight in %
Weight in % in %
80 0 0 0 100 100
40 256 1.71 1.71 98.29 95-100
20 8732 58.21 59.92 40.08 30-70
10 3173 21.15 81.07 18.93 10-35
4.75 2476 16.51 97.58 2.42 0-5
Physical Properties
Specific Gravity 2.62
Water Absorption 0.20%
Dry rodded Bulk Density 1500kg/m3
loose rodded Bulk Density 1450 kg/m3
Note:
1. Samples are received by the concerned engineer
2. The report shall not be reproduced, except in full, without the written approval of the
laboratory.
3. The results indicated above are based on the tests carried out on the samples received
in the laboratory.
4. Any Query regarding the report must be reported immediately
TEST REPORT ON FINE AGGREGATES (SAND)
IS383-1970 (RA- 2002)
Client : Assistant Executive Engineer, KRIDL, Hosadurga
Agency : A.B.C Technical Consultants and Testing Centre
Name of Work : Revised estimate for providing fencing and COMPOUND
WALL at Belaguru burial ground in Hosadurga Taluk
Reference : AEE/Hosadurga/Thirdpartyinspectionreport2021-22
Date of Testing :
Material : Sand
Total Wt. of Aggregates in gms=1500
Cumulative
Cumulative
Is Sieve Size Weight Retained Retained Retained Spec.Limits
Weight Passing
in mm (gm) Weight in % Weight in For Zone-II
in %
%
10 0 0 0 100 100
4.75 79 5.27 5.27 94.7 90-100
2.36 143 9.53 14.80 85.2 75-100
1.18 281 18.73 33.53 66.5 55-90
600 Micron 283 18.87 52.40 47.6 35-59
300 Micron 394 26.27 78.67 21.3 8-30
150 Micron 278 18.53 97.20 2.8 0-10
Physical Properties
Specific Gravity 2.58
Water Absorption 3.26%
Dry rodded Bulk Density 1600kg/m3
loose rodded Bulk Density 1565 kg/m3
Note:
1. Samples are received by the concerned engineer
2. The report shall not be reproduced, except in full, without the written approval of the
laboratory.
3. The results indicated above are based on the tests carried out on the samples received
in the laboratory.
4. Any Query regarding the report must be reported immediately
TEST REPORT ON CEMENT
3 Initial Setting Time 128 minutes Should not be less than 30 minutes
4 Final Setting Time 404 minutes Should not be more than 600 minutes
Note:
1. Samples are received by the concerned engineer
2. The report shall not be reproduced, except in full, without the written approval of the laboratory.
3. The results indicated above are based on the tests carried out on the samples received in the laboratory.
4. Any Query regarding the report must be reported immediately
STEEL
TENSILE STRENGTH
Nominal
Mass per 0.20% proof Tensile Elongation,
Sl. Size
Brand meter stress / yield Strength Percent on
No. (Dia in
(Kg/meter) stress (N/mm2) guage length
mm)
(N/mm2)
1 Fe500 8mm 0.402 518 565 18
Sir,
Sub: Submission of third party inspection reports & Material Testing reports.
Respected Sir,
With reference to the above cited subject I am herewith submitting the Third party
inspection reports and bill for the work of Revised estimate for providing fencing and
COMPOUND WALL at Belaguru burial ground in Hosadurga Taluk, Estimated Cost
is Rs. 20.00 Lakhs, Work code: 102692, Scheme: SWD.
Yours faithfully
INVOICE BILL
Sl.
DESCRIPTION CHARGES
No.
Prepared by : (Sign):-
Declaration