℄ OF UP MAIN LINE. ℄ OF DN MAIN LINE.

KHANDWA END. 29550 ℄ OF BRIDGE. 2960 4750 2810 UMBRELLA WORK P.B. ITEM NO. 465 OF 2022 - 23
DN RAIL TOP LVL. 100.230 BRIDGE NO. 715/2 UP RAIL TOP LVL. 100.380
ET. END. 1676 NOTES:- FOR JACKETING WORK.
1676
DN PARAPET LVL.100.00 UP PARAPET LVL.99.93 LVL.100.00 DN PARAPET LVL.100.00 1. ALL DIMENSIONS ARE IN mm AND LEVELS ARE IN METERS.
UP PARAPET LVL.99.93 2. PROPOSED WORK SHOWN IN RED.
WING WALL TOP LVL. 99.550 FORMATION LVL. 99.642 (UP) FORMATION LVL. 99.492 (DN) FORMATION LVL. 99.642 (DN)
3. LEVELING COURSE SHALL BE IN 1:3:6.

1850

1850

1850
4. RCC WORK SHALL BE IN M-40 TO BE CHECKED TENDER FROM SCHEDULE.

400

400

400
400

400
5. TEMPORARY SIGNALS SHALL BE PROVIDED AS PER GR 15.09 (i)(d) & SR 15.09 OR GR 15.09(2)b & SR 15.09(2).

3000
EXTRADOS LVL.98.500 EXTRADOS LVL.98.500 6. PRECAUTIONS SHOULD BE FOLLOWED AND SR SHALL BE IMPOSED AS PER BRIDGE MANUAL 1998 PARA 515 DURING

450

450

450

450

450
INTRADOS LVL. 98.050 INTRADOS LVL. 98.050 EXECUTION OF WORK.
TOP SLAB 400 TOP SLAB 400 7. DOWELING WORK FOR BONDING OF EXISTING STRUCTURE AND JACKETING & INTERNING SHOULD BE AS PER
SPRINGING LVL. 97.300 PROP. JACKETING SPRINGING LVL. 97.300 DRAWING NO. G.M.(W) BB/8475 R4. HOLES FOR DOWEL SHOULD BE DRILLED AND NOT MADE BY PAVEMENT BREAKER.
100

400

400
H.F.L. 97.00 300mm. THICK. H.F.L. 97.00 8. BEFORE EXECUTION OF WORK PRIOR INFORMATION TO BE GIVEN TO CONCERN DEPARTMENT VIZ. S&T , TRD,
750 OPERATING ETC. WELL IN ADVANCE.
RL. LVL. 96.430 750 RL. LVL. 96.430 RL. LVL. 96.430 9. NO PLASTERING /CEMENT WASH SHALL BE DONE FOR CONCRETE SURFACE REPAIRS.
PROP. JACKETING PROP. JACKETING PROP. JACKETING PROP. JACKETING PROP. JACKETING 10.DEFECTIVE WORK SHALL BE DEMOLISHED .

3230
300mm. THICK. 300mm. THICK. 300mm. THICK. 300mm. THICK. 300mm. THICK. 11. ALL RCC/ PCC WORK SHALL BE DONE AS PER IR CONCRETE BRIDGE CODE.
2360

PROP. EXTENSION PROP. EXTENSION

2360
400 400 400 400 400 12. JACKETING OF ABUTMENTS AND WING WALLS SHOULD BE DONE UP TO BOTTOM OF EXISTING FOUNDATION.

2360
BY RCC BOX. BY RCC BOX. 13.BEFORE FIXING OF DOWEL BARS CEMENT GROUTING OF ENTIRE MASONARY SHOULD BE DONE AS PER PARA 209(1)
4100 4100 OF IR BRIDGE MANUAL.

150

150
450 1025 450 14.FOR CEMENT GROUTING REFER PARA 209(1) OF IR BRIDGE MANUAL.
BED LVL. 94.070 BED LVL. 94.070 BED LVL. 94.070 BED LVL. 94.070 BED LVL. 94.070 BED LVL. 94.070 15.BEFORE JACKETING DOWEL BARS CONSISTING OF 20 mm.DIA MS/HYSD BARS WITH L- BEND AT THE END MAY BE
100 100 BOTTOM SLAB BOTTOM SLAB FIXED IN THE OLD MASONARY BY DRILLING HOLES OF SUITABLE SIZE TO A DEPTH OF MINIMUM 300 mm. WITH A
2750 2750 2750 2750 2750 2750 2750
SPACING OF 450 mm. HORIZONTALLY AND VERTICALLY.
16.PRIOR PCE SANCTION MUST BE OBTAIN BEFORE EXECUTION OF WORK.

400

400
225 225 17.EXPOSURE CONDITION IS MODERATE.

350

350
150

150
3350 2190 3350 2190 3350 2190 3350 2190 3350 6750 10520 6750 NOTES:- FOR THE PROPOSED EXTENSION OF BARREL LENGTH BY RCC BOX.
33810 1. PREPARATION OF BED BELOW 150MM THICK LEVELING COURSE SHOULD BE BASED ON ACTUAL SITE CONDITION IN
ELEVATION 24020 ORDER TO ACHIEVE THE ADEQUATE BEARING CAPACITY REQUIRED TO WITHSTAND THE FOUNDATION PRESSURE
(SECTION AT A - A') CROSS SECTION GIVEN IN RDSO DRAWING NO. RDSO/B/10155.
2. HSD/TMT BARS CONFIRMING TO IS 1786-2009 SHALL BE USED AS REINFORCEMENT.
33810 (SECTION AT B - B')

B'
750 3300 3300 750 3. DESIGN CRITERIA IS BASED ON FOLLOWING IRS CODES. (i) IRS BRIDGE RULES,
(ii) IRS CONCRETE BRIDGE CODE.
4. LAPPING OF BARS SHOULD BE MINIMIZED AND STAGGERED WHEREVER NECESSARY MINIMUM LENGTH OF LAP
SHALL BE AS GIVEN IN IRS CONCRETE BRIDGE CODE.
5. ALL RCC SURFACE COMING IN CONTACT WITH SOIL SHOULD BE PAINTED WITH BITUMEN OR COALTAR OF APPROVED
QUALITY @ 1.464KG/M2.

FLOW
6. CLEAR COVER FOR REINFORCEMENT BARS SHOULD BE 50MM.

D/S
7. TOLERANCE SHALL BE FOLLOWED AS PER IRS COMPLETE BRIDGE CODE.
℄ OF BRIDGE. 8. M-35 GRADE CONCRETE SHALL BE USED FOR THE SPAN OR HEIGHT OF THE BOX GREATER THAN EQUAL TO 4M,M-30
SITE PLAN
PROP. EXTENSION GRADE CONCRETE SHALL BE USED FOR THE SPAN OR HEIGHT OF THE BOX IS LESS THAN 4M.
(NOT TO SCALE)
751

3
9. FOR INTERMEDIATE SPAN/HEIGHT STRUCTURE DESIGN DETAIL OF IMMEDIATELY HIGHER SPAN/HEIGHTS AS PER
6750

6750
751
BY RCC BOX.
RDSO CONFIGURATION CAN BE ADOPTED.
3

PATHWAY
10. WEEP HOLES SHALL BE OF 75/100 DIA PVC/AC PIPES @1000 C/C ABOVE ,LOW WATER LEVEL IN EARTH RETAINER OF
25MM CLEAR COVER
BOX.
11.FOR REINFORCEMENT DETAILS AND OTHER GENERAL DETAILS PLEASE REFER RDSO/B/10152 AND SERIES.

4100
12.SANCTION OF P.C.E TO BE OBTAINED FOR THE EXECUTION OF WORK.
4100

100
400 400 13.DRAWING SHALL NOT BE SCALED, ONLY WRITTEN DIMENSIONS SHALL BE FOLLOWED.
EXISTING PARAPET
14.MINIMUM GRADE OF RCC WILL BE M-30.
150
15. WEARING COURSE SHALL BE IN M-20.
16.LEVELING COURSE SHALL BE IN 1:3:6.
300
17. TEMPORARY SIGNALS SHALL BE PROVIDED AS PER GRADE 15.09(i)(d) 5 DEG. SR 15.09(2)b AND SR 15.09(2) BEFORE
EXECUTION OF WORK PRIOR INFORMATION TO BE GIVEN TO THE CONCERN DEPARTMENT VIZ, S&T, TRD,OPERATING

450
ETC WELL IN ADVANCE.
2045 1795 18.NO PLASTERING/ CEMENT WASH SHALL BE DONE FOR CONCRETE SURFACE REPAIRS.
DOWEL BARS 19.DEFECTIVE WORK SHALL BE DEMOLISHED.

2810
12Ø @200C/C 20.EXPOSURE CONDITION IS MODERATE.
21. ALL RCC / PCC WORK SHALL BE DONE AS PER RELEVANT IR CONCRETE BRIDGE CODE.
22. PARAPET WALL SHOULD BE DISMANTLE AFTER EXTENSION OF BARREL LENGTH.
℄ OF DN MAIN LINE. ℄ OF DN MAIN LINE. ℄ OF DN MAIN LINE. EXISTING ARCH
b 12Ø@200C/C

10Ø@200C/C

KHANDWA END. ET. END. d1 10Ø@200C/C

24020
4750
10520
d 10Ø
(BANAPURA STN.) (DHARAMKUM STN.) @200C/C
PROP.JACKETING PROP.JACKETING PROP.JACKETING PROP.JACKETING PROP.JACKETING d
300mm. THICK. 300mm. THICK. 300mm. THICK. 300mm. THICK. 300mm. THICK.
a

b 12Ø@200C/C
b 12Ø@200C/C
℄ OF UP MAIN LINE. ℄ OF UP MAIN LINE. ℄ OF UP MAIN LINE.
a 12Ø
@200C/C
100 3350 2190 3350 2190 3350 2190 3350 2190 3450

2960
d1 10Ø@200C/C d1 10Ø@200C/C
2750 300 300 ` b
2750 300 2750 300 2750 300 2750 1795 d1
2045 PROP. JACKETING FOR PARAPET WALL. 300
29550
(NOT TO SCALE)

450
15
100 00 00 100
1025

3350 15

400
4100

4100

400
TOP OF PARAPET WALL
RL. LVL. 100.00
6750

6750
3

751
PROP. EXTENSION 3550
751

1850
BY RCC BOX.

400
400
FLOW

RL. LVL. 98.150


U/S

29719 2750 R.L. 97.750


RAILWAY LAND BOUNDARY
PROP. REINFORCEMENT DETAIL FOR JACKETING OF PIER.
(NOT TO SCALE)
OHE MAST NO.
715
PROP. EXTENSION ℄ OF BRIDGE NO. 715
2
BY RCC BOX.

450
8

17000
OHE MAST NO.

3830
750 3300 25710 3300 750

4980
715

B
33810 10
A PLAN A'
℄ OF DN MAIN LINE.
DOWEL BARS 150 WEARING COURSE. ET. END.

4750
BED LVL. 94.070 KHANDWA END. (DHARAMKUNDI STN.)
(BANAPURA STN.)
R.L. 93.920 ℄ OF UP MAIN LINE.
25MMCLEAR COVER 150 R.L. 93.520
R.L. 93.170
150 BASE COURSE.

400
200 SAND FILLING.

18000
a 12Ø@ 200C/C CEMENT GROUTING
3850
ELEVATION OF PROP. RCC BOX. (UP&DN) OHE MAST NO. PROP. EXTENSION OHE MAST NO.
20mm. MS DOWEL
715 BY RCC BOX. 715
7 RAILWAY LAND BOUNDARY 9
0
30

SITE PLAN

100
b 12Ø@200C/C
(NOT TO SCALE)
238
50MM CLEAR COVER

50MM CLEAR COVER


WEST CENTRAL RAILWAY
d 10Ø@200C/C DIVISION :- BHOPAL SECTION :- KNW - ET.
GROUT PIPE 25MMØ
300mm. MINIMUM.
PROP. DETAILS JACKETING OF DOWEL
(NOT TO SCALE) PROPOSED INTERNING & JACKETING AND EXTENSTION OF
GROUT PIPE 25MMØ
d1 10Ø @200C/C
GROUT PIPE 25MMØ BARREL LENGTH OF EXIST. ARCH BRIDGE NO. 715/2 (SPAN
G.L. 94.070
5/3.350M.) AT K.M. 715/08-10.
900

CH
G.L. 93.170
(GENERAL ARRANGEMENT DRAWING)
900

EXIST. SPAN
ML
G.L. 92.270
d SCALE:- 1:100
TRIAL PIT DETAIL
DIVISION'S APPROVAL HQ'S APPROVAL
a d1 (NOT TO SCALE)
b a CBE/JBP
300MM. DRM/BPL
SPECIFIC CERTIFICATE :-
( SAURABH BANDOPADHYAYA) ( O.P.TANWAR )
1. IT IS CERTIFIED THAT BEFORE PREPARATION OF GAD DETAILED INSPECTION OF SITE HAS BEEN CARRIED OUT AND ALL RELEVANT FACTORS HAVE BEEN CONSIDERED WHILE
25MMCLEAR COVER 50MM CLEAR COVER d FINALIZING CONSTRUCTION SCHEME FOR BRIDGE. PROPOSED SCHEME.
d1 ADRM (O & I) / BPL
2. IT IS CERTIFIED THAT THERE WILL BE NO DIFFICULTY IN EXECUTION OF THE WORK WITH the Proposed Scheme.
( Y.K.SAXENA) DY.CE(BR)/DESIGN/JBP ( SUDHIR PARIHAR )

25MMCLEAR COVER SR. DEN(Co)/BPL


( A.K.TOMAR ) AXEN(BR)/DESIGN/JBP (C.P. MANDLOI)
b
Sr. DEN (S) BPL
ADEN (M) ET.
SR. DOM/BPL
( NIREESH RAJPUT )

300 300
ADEN - ET SSE(D) BR
PROP. REINFORCEMENT DETAILS FOR INTERNING & JACKETING. SR. DEN (S) BPL
(SHYAM NAGAR) ( S.N. MISHRA )
(NOT TO SCALE) ( ABHISHEK MISHRA)

SSE / W / ET SSE(D)
(ABHISHEK GUPTA) (NARESH DUBEY) DIVISION DRG No. DRM / W / BPL / R- HQ'S DRG No. GM(W)/

You might also like