Professional Documents
Culture Documents
BHPOD-CBR-SOS-00001 Capital Benchmarking (Rev 0)
BHPOD-CBR-SOS-00001 Capital Benchmarking (Rev 0)
BHPOD-CBR-SOS-00001 Capital Benchmarking (Rev 0)
Scope of Services
BHPOD-CBR-SOS-00001
Rev Date Reason for revision Originator Checked by Approved by
1 Introduction 3
1.1 Study Background .......................................................................................................................... 3
2 Scope of Services 4
2.1 Overview ........................................................................................................................................ 4
2.2 Scope of Work ................................................................................................................................ 4
2.3 Study Approach .............................................................................................................................. 4
2.4 Scope of Services .......................................................................................................................... 5
2.5 General Exclusions ........................................................................................................................ 8
3 Project Services 9
3.1 Meetings ......................................................................................................................................... 9
3.2 Reporting ........................................................................................................................................ 9
3.3 Invoicing ......................................................................................................................................... 9
3.4 Document Control .......................................................................................................................... 9
3.5 Assurance ...................................................................................................................................... 9
3.6 Request for Information .................................................................................................................. 9
4 Submissions 10
4.1 Submission Format ......................................................................................................................10
4.2 Communications ..........................................................................................................................10
4.3 Closing Date .................................................................................................................................10
TABLES
Table 1.1: Key Dates ................................................................................................................................ 3
Table 4.1: Fee Estimate Structure ..........................................................................................................10
2.1 Overview
The Service Provider shall work collaboratively with the Company to ensure that the scope of services
described below are delivered within the framework of a fit for purpose study with a focus on quality of
information.
Exploration Declines
Surface decline and box cut construction for underground mine access including;
Approximate length, gradient and cross-section.
Box cut and portal construction. (I.e. open excavation, concrete arch supports etc.)
Conveying Systems
Typical conveyor unit rates ($/m) including;
Underground inclined conveyors <2,000m long. (Excluding drive excavation.)
Surface overland conveyors <2,000m long.
Underground switchback and surface transfer points. (Excluding chamber excavation.)
Conveyor capacities 6Mtpa to ~20Mtpa.
Regional Infrastructure
Permanent camp facilities and accommodation including;
Accommodation buildings, cribs, ablutions, laundry, recreational facilities etc.
Reticulation of power, water and sewer.
All-in permanent camp cost. (Including facilities and services described above.)
Accommodation building unit cost. ($/building)
Accommodation building footprint (sqm per building).
Private access roads including;
Heavy vehicle haul roads (unsealed) for off-highway rigid body trucks.
Heavy vehicle haul roads (unsealed) for road trains.
Site access roads (sealed) for approved heavy vehicles and light vehicles.
Typical unit cost of installation. ($/km)
Regional airport including;
Runway, taxiway, aprons, arrivals and departure facilities.
Runway length and aircraft size.
HV Transmission Lines
Overhead high voltage transmission lines including;
Single circuit 132kV and 275kV transmission lines including support structures.
TIC and unit cost of installation. ($/km)
EPCM
Engineering, Procurement and Construction Management costs as a percentage of direct costs
for a suite of recently completed Greenfields and Brownfields mining or complex industrial
projects.
Deliverables
The Service Provider shall produce a single WP001 benchmarking report including;
Approach and methodology.
Graphical presentation of total installed cost / unit cost for each growth capital item. (Refer
typical example below.)
Underground Conveyors
$/mtr
Project C
Project C
Project C
Project A
Project A
Project A
Project B
Project B
Example Only
Raw data that informs the graphical representations within the report stripped of all confidential
information
Discussion (within confidentiality) of each reference project including:
o Project or study date, quality of estimate and build time.
o Specific factors affecting scope, cost (including escalation rates), schedule and
execution strategy.
o Limitations and uncertainty associated with interpretation of benchmark data.
Deliverables
The Service Provider shall produce a single report for WP002 including;
Capital and schedule review approach.
Review key findings and recommendations.
3.1 Meetings
The SP will be responsible for convening a weekly WebEx meeting, minute taking and distribution of
minutes within three (3) working days. Minutes of meetings should be fit for purpose and not more than
1.5 x pages in total including the following;
Issues and concerns.
Key learnings.
Scope, schedule and deliverables progress.
Outstanding requests for information.
Hours and cost summary by resource name.
3.2 Reporting
Weekly meeting minutes are to be utilsed for progress, cost and schedule reporting. There are no other
study reporting requirements associated with executing the scope of services.
3.3 Invoicing
The SP shall prepare and submit monthly invoices with accompanying timesheet information with hours
assigned to individual resources. Receipts must be submitted for all expenses and disbursements
incurred by the SP in undertaking the scope of services.
3.5 Assurance
The SP must ensure that all documentation submitted to the Company has been internally peer reviewed
and quality assured prior to submission to the Company.
Sub-Total $0
Technical Services
Sub-Total $0
Total $0
4.2 Communications
All communications between the Company and the Service Provider are to be directed to the Study
Principal;
Name: Rick D’Agostini
Phone: 0412 46 443