JOB DETAILS
⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄
WEATHER
Overall Conditions:
WORK ACCOMPLISHED
TASK STATUS
1- {11/12/2022} wooding board for 12 On work
columns out of 24 at the first floor
2- {11/12/2020} measuring area for
concreting all the building (beam Done (first floor)
and column roof and stair cases)
3- {12/12/2022} concreting 14 beams
Done (first floor)
at first floor
4- {12/12/2022} Cleaning the ground
side of the building for the pump Done
and concrete trucks (jarmud)
5- {12/12/2022} Lifting 7 ballet of
Ponza block to first floor, and done
putting the rest to ground floor
6- {15/12/2022} removing the
plywood’s and preparing for the done (first floor)
next columns
⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄
MATERIAL QUANTITIES
# USED
MATERIAL TYPE # REMAINING
Cement 30 (25kg)
Steel #12mm 55,175 kg
Steel #10mm 16,155 kg
Steel #16mm 42,440 kg
blocks 1200
⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄
MATERIAL DELIVERIES
TYPE # SCHEDULED ARRIVAL
Cement mortar 12𝑚3 11/12/2022-Sunday- afternoon
blocks 1200 11/12/2022-Sunday-afternoon
Ponza block 34 ballets 12/12/2022-monday-afternoon
⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄
SAFETY
I, [Mohammed Tahseen], certify that I have completed this daily construction report and the information
herein is accurate and up-to-date to the best of my knowledge
_______________________________________
[17/12/2022]