21-28,1weekly Report Office Building

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

Company office

Darwaza city {3}

Construction weekly Report


Prepared by: [ENG. Mohammed Tahseen]
Date: [ 21/1/2023]
⁄ ⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄

JOB DETAILS

Project Name: company Office


Job Type: construction Job Number: 1

⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄
WEATHER

Overall Conditions:

❏ Sunny ❏ Raining ❏ Fog


❏ Cloudy ❏ Thunderstorm ❏ Frost
❏ Partially cloudy ❏ Snow ❏ Wind

Wind speed: 13 mph


⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄

WORK ACCOMPLISHED
TASK STATUS
1- {21/1/2023} tiding up staircase
rebars to be ready for concrete
and lifting every item to next floor On work
for next celling, electrical works
are continued and mechanical
works about to begin
2- {22/1/2023} concreting 10 beams
On work / Done
and the stair case, and
mechanical work begun (core)
3- {23/1/2023} no work, due to cold
none
weather
4- {24/1/2023} lifting plywood items
On work
for next celling, and the core holes
continued working
5- {25/1/2023} mechanical core
On work
continued

CONSTRUCTION WEEKLY REPORT


6- {26/1/2023} mechanical core
continued, creating formworks for
the beams for the surrounding On work
beams with elevation for water
sewerage.

⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄
CREW LIST
CREW TYPE CREW NAME CREW NUMBER
SUPERVISOR KANYAW KARWAN 1
Asst. engineer MOHAMMED TAHSEEN 2

⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄
MATERIAL QUANTITIES
# USED
MATERIAL TYPE # REMAINING

Cement 90 23 (50kg)
Steel #12mm 55,175 kg
Steel #10mm 16,155 kg
Steel #16mm 54,440 kg
Blocks (10x40) 750 300

Concreting till ground floor 214,16 𝑚3

Concreting till first floor 198.21 𝑚3

Ponza block 5730 102


Blocks(20x40) 2250 300

Aggregate size for concreting 2 𝑚3

CONSTRUCTION WEEKLY REPORT


⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄
MATERIAL DELIVERIES
TYPE # SCHEDULED ARRIVAL
𝑚3 22/1/2023-monday-afternoon

SIGNIFICANT EVENTS

EVENT TYPE DESCRIPTION POTENTIAL DELAY

Concreting all columns to start


concrete
next celling [no]

⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄
SAFETY

Was a site inspection performed today?


❏ Yes
❏ No
Were there any safety incidents?

{23/1/2023} no work, due to cold weather

Mohammed Tahseen 28/1/2023

I, [Mohammed Tahseen], certify that I have completed this weekly construction report and the information
herein is accurate and up-to-date to the best of my knowledge

____________________________________
[28/1/2023]

CONSTRUCTION WEEKLY REPORT