Professional Documents
Culture Documents
21-28,1weekly Report Office Building
21-28,1weekly Report Office Building
21-28,1weekly Report Office Building
JOB DETAILS
⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄
WEATHER
Overall Conditions:
WORK ACCOMPLISHED
TASK STATUS
1- {21/1/2023} tiding up staircase
rebars to be ready for concrete
and lifting every item to next floor On work
for next celling, electrical works
are continued and mechanical
works about to begin
2- {22/1/2023} concreting 10 beams
On work / Done
and the stair case, and
mechanical work begun (core)
3- {23/1/2023} no work, due to cold
none
weather
4- {24/1/2023} lifting plywood items
On work
for next celling, and the core holes
continued working
5- {25/1/2023} mechanical core
On work
continued
⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄
CREW LIST
CREW TYPE CREW NAME CREW NUMBER
SUPERVISOR KANYAW KARWAN 1
Asst. engineer MOHAMMED TAHSEEN 2
⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄
MATERIAL QUANTITIES
# USED
MATERIAL TYPE # REMAINING
Cement 90 23 (50kg)
Steel #12mm 55,175 kg
Steel #10mm 16,155 kg
Steel #16mm 54,440 kg
Blocks (10x40) 750 300
SIGNIFICANT EVENTS
⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄⁄
SAFETY
I, [Mohammed Tahseen], certify that I have completed this weekly construction report and the information
herein is accurate and up-to-date to the best of my knowledge
____________________________________
[28/1/2023]