Professional Documents
Culture Documents
Financial Proposal - 2units
Financial Proposal - 2units
Financial Proposal - 2units
in 1,000 USD
Tendered Alternative
Item
Total Local Foreign Total Local Foreign
1 GENERAL ITEMS and INFRASTRUCTURES 155,415.24 55,949.50 99,465.74 160,170.01 57,661.22 102,508.79
1.2 Contractor's General items 91,339.90 32,882.37 58,457.53 91,339.90 32,882.37 58,457.53
1.3 Facilities for the Employer camp and offices (Logistic support ) 16,740.56 6,026.61 10,713.95 16,748.26 6,029.38 10,718.88
3.1 Excavation Dam site 2,312.22 832.39 1,479.83 3,927.57 1,413.93 2,513.64
3.2 Diversion And Bottom outlet 12,031.33 4,331.29 7,700.04 14,413.44 5,188.84 9,224.60
5.2 Surge Chamber Headrace 10,070.18 3,625.26 6,444.92 7,599.97 2,735.98 4,863.99
1/32
in 1,000 USD
Tendered Alternative
Item
Total Local Foreign Total Local Foreign
5.5 Surge Chamber Tailrace 9,036.88 3,253.26 5,783.62 11,400.97 4,104.34 7,296.63
6.1 Main Access Tunnel 4,740.80 1,706.68 3,034.12 8,543.79 3,075.76 5,468.03
6.3 Power Station And Transformer Cavern 2,075.86 747.30 1,328.56 6,310.91 2,271.93 4,038.98
6.6 Cable Tunnel And Culvert 1,339.88 482.36 857.52 15,081.85 5,429.47 9,652.38
7 HYDROMECHANICAL PLANT AND EQUIPMENT 20,961.67 4,192.34 16,769.33 20,961.67 4,192.34 16,769.33
7.1 Diversion & Bottom outlet 6,887.97 1,377.59 5,510.38 6,887.97 1,377.59 5,510.38
7.3 Headrace & penstock 7,879.06 1,575.81 6,303.25 7,879.06 1,575.81 6,303.25
2/32
in 1,000 USD
Tendered Alternative
Item
Total Local Foreign Total Local Foreign
8.5 33kv Power Supply (Local Supply) 10,718.27 1,607.73 9,110.54 10,718.27 535.91 10,182.35
14 Provisional sum 5% of the 16km underground tunnel bid price. 5,788.13 2,083.73 3,704.40 4,988.00 1,795.68 3,192.32
15 VAT taxes 15% of the Bid price. 88,435.38 28,015.42 60,419.96 90,841.23 27,780.00 63,061.22
3/32
SCHEDULE 1D- UNIT RATES, PRICES AND BILL OF ESTIMATED QUANTITIES
The Bidder to fill the unit rates and prices in the attached Bill Of Estimated Quantity only for the purpose of Bid evaluation and to be used in case the Employer wishes to instruct additional
works.
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
1000 USD 1000 USD 1000 USD 1000 USD 1000 USD 1000 USD
1 GENERAL ITEMS and INFRASTRUCTURES 155,415.24 55,949.50 99,465.74 160,170.01 57,661.22 102,508.79
1.1 Access Road 47,334.78 17,040.52 30,294.26 52,081.85 18,749.47 33,332.38
1.1.1 Permanent access road km 55 46445.93 16,720.53 29,725.40 56.86 48,016.65 17,285.99 30,730.66
1.1.2 Temporary access road km 8 702.14 252.77 449.37 14.94 1,311.24 472.05 839.19
1.2.5 Power supply system LS 1 4556.07 1,640.19 2,915.88 1 4,556.07 1,640.19 2,915.88
1.2.6 Temporary houses LS 1 4548.29 1,637.38 2,910.91 1 4,548.29 1,637.38 2,910.91
4/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
Facilities for the Employer camp and offices
1.3 16,740.56 6,026.61 10,713.95 16,748.26 6,029.38 10,718.88
(Logistic support )
1.3.1 Employer's camp, office service building 9,376.99 3,375.73 6,001.26 9,384.69 3,378.50 6,006.19
1.3.1.1 Service Building m² 2900 2233.49 804.06 1,429.43 2,910.00 2,241.19 806.83 1,434.36
1.3.1.2 House For the Employer representative m² 1936 1378.1 496.12 881.98 1,936.00 1,378.10 496.12 881.98
1.3.1.3 House For the Employer m² 4824 3433.86 1,236.19 2,197.67 4,824.00 3,433.86 1,236.19 2,197.67
Internal Infrastructure (Water, Electric,
1.3.1.4 LS 1 1981.46 713.33 1,268.13 1 1,981.46 713.33 1,268.13
Road Sewerage, Fence, Parking Area
1.3.1.5 House furniture and utilities LS 1 350.08 126.03 224.05 1 350.08 126.03 224.05
1.3.2 Office furniture and office equipment 1,671.96 601.90 1,070.06 1,671.96 601.90 1,070.06
1.3.2.1 Furniture LS 1 136.06 48.98 87.08 1 136.06 48.98 87.08
1.3.3.2 Renovate Building to handover LS 1 210.05 75.62 134.43 1 210.05 75.62 134.43
1.3.4 Vehicle 3,989.49 1,436.22 2,553.27 3,989.49 1,436.22 2,553.27
1.3.4.1 Provision of Vehicle LS 1 2869.24 1,032.93 1,836.31 1 2,869.24 1,032.93 1,836.31
1.3.4.2 Operation & Maintenance of Vehicle Months 48 1120.25 403.29 716.96 48 1,120.25 403.29 716.96
5/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
Consumables for all housing, offices,
1.3.5 Months 48 263.54 94.87 168.67 48 263.54 94.87 168.67
canteen
Man
1.3.6 Driver and unskilled labours 4000 1026.88 369.68 657.20 4000 1,026.88 369.68 657.20
month
2 SITE AND RESERVOIR 7,394.32 2,661.95 4,732.37 7,394.32 2,661.95 4,732.37
2.1 Compensation (general) Ha 10 583.47 210.05 373.42 10 583.47 210.05 373.42
2.2 Site Clearing, easy Ha 600 4263.44 1,534.84 2,728.60 600 4,263.44 1,534.84 2,728.60
2.3 Site Clearing, medium vegetation Ha 130 1439.29 518.14 921.15 130 1,439.29 518.14 921.15
2.4 Site Clearing, heavy vegetation Ha 70 1108.12 398.92 709.20 70 1,108.12 398.92 709.20
3 DAM 112,796.17 40,606.64 72,189.53 120,155.12 43,255.87 76,899.25
3.1 EXCAVATION DAMSITE 2,312.22 832.39 1,479.83 3,927.57 1,413.93 2,513.64
3.1.1 Clearing and grubbing m² 81200 131.54 47.35 84.19 118,120.25 191.35 68.89 122.46
3.1.6 Rock excavation dam foundation m³ 60000 921 331.56 589.44 211,669.30 3,249.12 1,169.68 2,079.44
3.1.7 Excavation of tunnel lm 150.00 209.39 75.38 134.01
DIVERSION AND
3.2 12,031.33 4,331.29 7,700.04 14,413.44 5,188.84 9,224.60
BOTTOMOUTLET
3.2.1 Impermeable material m² 666 3.71 1.34 2.37
6/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
3.2.6 Reinforcement steel ton 1873 3978.17 1,432.14 2,546.03
3.2.7 Rock bolt 5m, d28 pcs 7200 588.46 211.85 376.61
3.2.8 Rock bolt 4m, d22 pcs 4600 265.6 95.62 169.98
3.2.9 Shotcrete C20 m³ 3660 1449.07 521.67 927.40
3.2.10 Wire mesh ton 50 106.2 38.23 67.97
3.2.11 Soft excavation m³ 6,950.25 21.82 7.86 13.96
7/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
3.3.3 Impermeable material m² 7200 40.11 14.44 25.67
3.3.15 Rock block for slope protection m³ 2,680.00 89.08 32.07 57.01
3.3.16 Cofferdam demolition m³ 40,948.00 161.34 58.08 103.26
3.4.3 Grout curtain m² 13750 656.43 236.31 420.12 32,739.42 1,562.98 562.67 1,000.31
3.4.4 Rockbolts grouted, L =4M m³ 3000 173.22 62.36 110.86 3,569.50 206.10 74.20 131.90
3.4.5 Asphalt core m³ 17640 13347.83 4,805.22 8,542.61 22,237.20 16,826.44 6,057.52 10,768.92
Filter fill, crushed rock,(D=0-60MM, T
3.4.6 m³ 88200 2655.7 956.05 1,699.65 110,446.09 3,325.53 1,197.19 2,128.34
= 1.5M)
3.4.7 Transition fill (D=0-200mm, T-4.0M) m³ 235200 3756.14 1,352.21 2,403.93 240,468.54 3,840.28 1,382.50 2,457.78
8/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
3.4.8 Rock fill (D=0-0.3m) m³ 500000 7585 2,730.60 4,854.40 500,000.00 7,585.00 2,730.60 4,854.40
3.4.9 Rockfill Drainage layer(D=0.03-0.2M) m³ 187830 2967.72 1,068.38 1,899.34 301,237.78 4,759.56 1,713.44 3,046.12
3.4.10 Rock fill Type B (D=0.1.0m) m³ 2126000 25023.02 9,008.29 16,014.73 1,892,427.52 22,273.87 8,018.59 14,255.28
3.4.11 Rip-Rap toe protection m³ 33275 439.89 158.36 281.53 63,639.38 841.31 302.87 538.44
3.4.12 Rip-Rap Slope protection m³ 129197 4463.77 1,606.96 2,856.81 38,230.83 1,320.88 475.52 845.36
3.4.13 Dam safety monitor Ls 1 1400.32 504.12 896.20 1.00 1,400.32 504.12 896.20
3.4.14 Wire mesh ton 20 42.48 15.29 27.19 20.00 42.48 15.29 27.19
3.4.15 Shot crete with mesh c20, 10cm ton 180 65.96 23.75 42.21 180.00 65.96 23.75 42.21
3.4.16 Rock bolt 5m, d28 pcs 680 55.58 20.01 35.57 680.00 55.58 20.01 35.57
3.4.17 Reinforcement ton 760 1614.2 581.11 1,033.09 485.63 1,031.45 371.32 660.13
3.4.18 Consolidation grouting m 800 86.26 31.05 55.21 2,805.00 302.44 108.88 193.56
3.5.1 Clearing and grubbing m² 307 0.5 0.18 0.32 43,673.70 70.75 25.47 45.28
3.5.2 Stripping of topsoil m² 14000 17.08 6.15 10.93 21,836.85 26.64 9.59 17.05
3.5.3 Soft excavation (easy) m² 28000 26.32 9.48 16.84 127,827.26 120.16 43.26 76.90
3.5.4 Rock excavation (normal) m³ 240000 3309.6 1,191.46 2,118.14 488,068.04 6,730.46 2,422.97 4,307.49
3.5.5 Impermeable material m² 3111 17.33 6.24 11.09 -
3.5.6 Excavation of tunnel lm 300 418.8 150.77 268.03 100.00 139.60 50.26 89.34
3.5.7 Plain vertical formwork m² 5900 -
9/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
3.5.9 Curved formwork m² 500 -
3.5.10 Structural concrete C35 outdoor m³ 32000 10004.16 3,601.50 6,402.66 35,998.20 11,254.12 4,051.48 7,202.64
3.5.11 Reinforcement steel ton 1200 2548.74 917.55 1,631.19 1,031.94 2,191.79 789.04 1,402.75
3.5.12 Grout curtain m² 2250 107.42 38.67 68.75 -
3.5.13 Concrete bridge, one lane (span <15m) lm 35 235.19 84.67 150.52 48.00 322.55 116.12 206.43
3.5.14 Shotcrete m³ 1000 366.45 131.92 234.53 7,264.95 2,662.24 958.41 1,703.83
3.5.15 Wire mesh ton 13 27.61 9.94 17.67 318.57 676.63 243.59 433.04
3.5.16 Consolidation grouting m 21700 2339.7 842.29 1,497.41 23,343.60 2,516.91 906.09 1,610.82
3.5.17 Rock bolt 5m, d28 pcs 23000 1879.81 676.73 1,203.08 6,777.75 553.95 199.42 354.53
4 INTAKE 7,701.57 2,772.58 4,928.99 7,271.45 2,617.73 4,653.72
4.1 Clearing and grubbing m² 3850 6.23 2.24 3.99 5,440.28 8.81 3.17 5.64
4.4 Rock excavation (normal) m³ 35000 558.6 201.10 357.50 64,995.71 1,037.33 373.44 663.89
4.5 Grout curtain m² 100 4.77 1.72 3.05 -
4.13 Structural concrete C35 outdoor m³ 17000 4539.17 1,634.10 2,905.07 12,459.11 3,326.71 1,197.62 2,129.09
10/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
4.14 Reinforcement steel ton 1200 2548.74 917.55 1,631.19 872.14 1,852.38 666.86 1,185.52
5.1.7 Shotcrete with fiber, behind face m³ 13000 6754.66 2,431.68 4,322.98 4,440.47 2,307.22 830.60 1,476.62
5.1.8 Shotcrete m³ 143 55.89 20.12 35.77 2,823.13 1,103.31 397.19 706.12
5.1.12 Rockbolts grouted, 5m d25 pcs 10000 746.7 268.81 477.89 12,643.40 944.08 339.87 604.21
5.1.13 Consolidation grouting m 36000 2830.38 1,018.94 1,811.44 1,364.00 107.24 38.61 68.63
5.1.14 Reinforcement steel ton 2800 5947.07 2,140.95 3,806.12 496.23 1,053.97 379.43 674.54
11/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
5.1.15 Steel Ribs ton 73.33 208.08 74.91 133.17
5.2.14 Rockbolts grouted, L=3m No 1730 68.55 24.68 43.87 214.50 8.50 3.06 5.44
5.2.15 Spiling rockbolt, L=6m grouted No 865 81.08 29.19 51.89 3,582.70 335.81 120.89 214.92
5.2.16 Shotcrete with fibers m³ 2550 1300.79 468.28 832.51 1,170.27 596.97 214.91 382.06
5.2.17 Shotcrete m³ 1100 421.79 151.84 269.95 72.97 27.98 10.07 17.91
5.2.18 Consolidation grouting m 7800 613.24 220.77 392.47 2,983.20 234.54 84.43 150.11
12/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
5.2.20 Waterstop m 711.54 23.87 8.59 15.28
5.3.4 Rockbolts grouted, L=3m No 160 6.34 2.28 4.06 728.20 28.87 10.39 18.48
5.3.5 Plain vertical formwork UG m² 81 -
5.3.6 Plain curved formwork UG m² 82 -
5.3.7 Concrete in tunnel lining C35 m³ 155 49.76 17.91 31.85 -
5.3.8 Reinforcement steel ton 84 178.41 64.23 114.18 -
5.3.13 Curtain grouting m 1200 198.36 71.41 126.95 594.00 98.19 35.35 62.84
5.3.14 Joint grouting m² 556.17 12.14 4.37 7.77
5.4.4 Rockbolts grouted, L=3m No 90 3.57 1.29 2.28 191.40 7.59 2.73 4.86
13/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
5.4.5 Plain vertical formwork UG m² 720 -
5.5 SURGE CHAMBER TAILRACE 9,036.88 3,253.26 5,783.62 11,400.97 4,104.34 7,296.63
5.5.1 Excavation of tunnel m³ 138,609.46 7,367.09 2,652.15 4,714.94
5.5.2 Excavation of tunnel A=50m², lm 320 1047.95 377.26 670.69 -
5.5.3 Excavation of tunnel A=25m², lm 70 151.61 54.58 97.03 -
5.5.4 Excavation of cavern. Top soil m³ 28000 1488.2 535.75 952.45 -
14/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
5.5.17 Waterstop m 506.02 16.97 6.11 10.86
5.6.4 Rockbolts grouted, L=4 m No 2260 85.79 30.88 54.91 36,940.00 1,402.24 504.81 897.43
5.6.5 Spilling rockbolt, L=6m grouted No 1130 105.91 38.13 67.78 -
5.6.6 Cement grouting ton 200 314.49 113.22 201.27 -
5.6.7 Rockbolts grouted, 5m d25 pcs 13000 970.71 349.46 621.25 -
5.6.8 Reinforcement steel ton 2900 6159.45 2,217.40 3,942.05 2,193.96 4,659.86 1,677.55 2,982.31
5.6.9 Consolidation grouting m 43000 3380.67 1,217.04 2,163.63 15,822.40 1,243.96 447.83 796.13
5.6.10 Concrete in tunnel lining C35 m³ 12,174.18 4,036.71 1,453.22 2,583.49
5.6.11 Steel Ribs ton 73.71 150.23 54.08 96.15
5.6.12 Steel support ton 312.42 679.29 244.54 434.75
5.7.3 Soft excavation (easy) m³ 60000 158.41 57.03 101.38 20,840.00 55.02 19.81 35.21
5.7.4 Rock excavation (normal) m³ 55000 609.4 219.38 390.02 83,360.00 923.63 332.51 591.12
5.7.5 Stabilizing rock slopes m² 120 8.4 3.02 5.38 120.00 8.40 3.02 5.38
15/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
5.7.6 Shotcrete with fiber m³ 140 71.3 25.67 45.63 702.00 357.50 128.70 228.80
5.7.12 Fences, parking lots etc. LS 1 70.02 25.21 44.81 1.00 70.02 25.21 44.81
5.7.13 Masonry m³ 900 122.37 44.05 78.32
5.7.14 Consolidation grouting m 1,177.00 126.90 45.68 81.22
5.7.15 Coarse Filter m³ 2,085.00 57.19 20.59 36.60
6 POWERSTATION 24,805.86 8,930.11 15,875.75 45,114.61 16,241.26 28,873.35
6.1 MAIN ACCESS TUNNEL 4,740.80 1,706.68 3,034.12 8,543.79 3,075.76 5,468.03
6.1.1 Excavation of tunnel A=50m², lm 1150 3766.06 1,355.78 2,410.28 1,515.95 4,964.48 1,787.21 3,177.27
6.1.2 Excavation of tunnel A= 12m² lm 115.64 183.34 66.00 117.34
6.1.3 Shotcrete with fibers m³ 1150 586.28 211.06 375.22 1,412.57 720.14 259.25 460.89
6.1.4 Rockbolts grouted, L=4 m No 2875 165.37 59.53 105.84 7,876.00 453.03 163.09 289.94
6.1.5 Rockbolts grouted, L=2 m No 329.00 8.65 3.11 5.54
6.1.11 Reinforcement steel ton 23 48.85 17.59 31.26 115.41 245.13 88.25 156.88
16/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
6.1.12 Asphalt surfacing m² 8625 68.03 24.49 43.54 -
6.2.12 Concrete in tunnel lining C35 m³ 204 83.85 30.19 53.66 1,549.66 636.93 229.29 407.64
6.2.13 Reinforcement steel ton 20 42.48 15.29 27.19 92.98 197.48 71.09 126.39
17/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
6.2.15 Shotcrete with fibers m³ 1,209.18 617.69 222.37 395.32
6.3.12 Rockbolts grouted, L=4 m No 721 41.47 14.93 26.54 322.00 18.52 6.67 11.85
6.3.13 Rockbolts grouted, L=6 m No 240 22.41 8.07 14.34 876.00 81.81 29.45 52.36
18/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
6.3.14 Cement grouting ton 30 47.17 16.98 30.19 -
6.3.15 Rock bolts grouted, φ28mm,5m pcs. 224.00 18.31 6.59 11.72
6.3.16 Rock bolts grouted, φ40mm,L=10m pcs. 224.00 78.02 28.09 49.93
6.3.17 Prestressed anchor rope ,L=20m,100t pcs. 76.00 466.14 167.81 298.33
6.4.4 Reinforcement steel ton 1920 4077.99 1,468.08 2,609.91 1,521.00 3,230.53 1,162.99 2,067.54
6.4.5 Grouted dowels for anchoring 25mm m 2000 28.76 10.35 18.41 -
6.4.8 Plastering, Painting walls & ceiling m² 11000 134.13 48.29 85.84 -
6.4.9 Steel doors No 40 40.65 14.63 26.02 -
6.4.14 Steel structure ton 50 190.69 68.65 122.04 70.00 266.96 96.11 170.85
19/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
6.5.1 Clearing and grubbing m² 3850 6.24 2.25 3.99
20/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
6.6.7 Excavation of tunnel A=25m², lm 1,099.21 2,380.66 857.04 1,523.62
6.6.18 Concrete for bottom slab C25 m³ 1,189.98 328.47 118.25 210.22
6.6.19 Steel Ribs ton 3,714.07 10,538.90 3,794.00 6,744.90
6.6.20 Backfill grouting m² 903.45 48.83 17.58 31.25
6.6.21 Consolidation grouting m 2,534.40 199.25 71.73 127.52
Culvert
6.6.1 Clearing and grubbing m² 850 1.38 0.50 0.88
6.6.2 Soft excavation (easy) m² 340 0.9 0.32 0.58
21/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
6.6.17 Structural concrete C35 outdoor m³ 390 112.52 40.51 72.01
7.1.4 Trash rack for Bottom outlet . LS 1 942.69 188.54 754.15 1 942.69 188.54 754.15
7.1.5 Auxiliary equipment LS 1 413.38 82.68 330.70 1 413.38 82.68 330.70
Sliding gate for Diversion tunnel with
7.1.6 LS 1 1
embedded parts
7.1.7 Hoist for service gate of Bottom outlet. LS 1 2909.02 581.80 2,327.22 1 2,909.02 581.80 2,327.22
7.2 Intake HSS 4,694.43 938.89 3,755.54 4,694.43 938.89 3,755.54
Stop logs for intake with embedded
7.2.1 LS 1 2849.51 569.90 2,279.61 1 2,849.51 569.90 2,279.61
parts
7.2.2 Trash rack LS 1 257.1 51.42 205.68 1 257.10 51.42 205.68
7.2.3 Trash rack manual cleaner LS 1 1
7.2.4 Wheel Roller gate for Intake LS 1 178.54 35.71 142.83 1 178.54 35.71 142.83
7.2.5 Hydraulic hoist for Intake gate LS 1 1409.28 281.86 1,127.42 1 1,409.28 281.86 1,127.42
7.3 Headrace & penstock 7,879.06 1,575.81 6,303.25 7,879.06 1,575.81 6,303.25
7.3.1 Adit gate with embedded parts LS 1 493.25 98.65 394.60 1 493.25 98.65 394.60
7.3.2 Rock trap rack
22/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
7.4.1 Sliding gate with embedded parts LS 2 669.88 133.98 535.90 2 669.88 133.98 535.90
8.1.1 Turbines and valves LS 1 8573.76 1,286.06 7,287.70 1 8,573.76 428.69 8,145.07
Main inlet valve with hydraulic control
8.1.2 LS 1 6287.55 943.13 5,344.42 1 6,287.55 314.38 5,973.18
system
8.1.3 Governor sys. PID electrohydrauilic LS 1 649.64 97.45 552.19 1 649.64 32.48 617.16
8.1.4 Powerhouse crane 290t/20ton LS 1 1864.89 279.73 1,585.16 1 1,864.89 93.24 1,771.65
8.1.5 Cooling water system LS 1 1345.28 201.79 1,143.49 1 1,345.28 67.26 1,278.01
8.1.6 Compressed air system LS 1 414.83 62.22 352.61 1 414.83 20.74 394.08
8.1.7 Drainage and dewatering system LS 1 611.13 91.67 519.46 1 611.13 30.56 580.58
8.1.8 Hydraulic oil system LS 1 106.53 15.98 90.55 1 106.53 5.33 101.20
8.1.9 Mobile oil treatment plant LS 1 78.16 11.72 66.44 1 78.16 3.91 74.25
8.1.10 Spare parts LS 1 1164.6 174.69 989.91 1 1,164.60 58.23 1,106.37
23/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
Neutral point equipment for generator
8.2.3 and main transformer ( isolation switch, LS 1 238.05 35.71 202.34 1 238.05 11.90 226.15
arrestor, discharge gap etc)
Computer monitoring system for power
8.2.4 LS 1 1437.44 215.62 1,221.82 1 1,437.44 71.87 1,365.56
station
8.2.5 Auxiliary .cables & earthing LS 1 4896.19 734.43 4,161.76 1 4,896.19 244.81 4,651.38
8.2.6 Control and Protection equipment LS 1 1281.08 192.16 1,088.92 1 1,281.08 64.05 1,217.03
8.2.7 Station service Transformers LS 1 190.51 28.58 161.93 1 190.51 9.53 180.98
8.2.8 Other electrical LS 1 2970.79 445.62 2,525.17 1 2,970.79 148.54 2,822.25
Current transformers generator outlet and
8.2.9 LS 1 86.04 12.91 73.13 1 86.04 4.30 81.74
neutral point
8.2.10 Voltage transformer for generator outlet LS 1 426.23 63.93 362.30 1 426.23 21.31 404.92
SF6 breaker generator outlet 24kv,
8.2.11 LS 1 1064.15 159.62 904.53 1 1,064.15 53.21 1,010.94
1000A
PT arrestor, Excitation transformer,
8.2.12 LS 1 473.05 70.96 402.09 1 473.05 23.65 449.40
vacuum breaker
Phase isolated bus bar 20KV,8000A and
8.2.13 m 1200 2195.4 329.31 1,866.09
1000A
Phase isolated bus bar 20KV,7000A and
m 500 914.75 45.74 869.02
1000A
8.2.14 Spare parts and service tools LS 1 952.86 142.93 809.93 1 952.86 47.64 905.21
8.2.15 Mobile oil treatment plant LS 1 52.11 7.82 44.29 1 52.11 2.61 49.50
8.3.3 Cooling system incl. Piping LS 1 391.39 58.71 332.68 1 391.39 19.57 371.82
8.3.4 Automatic control system LS 1 87.93 13.19 74.74 1 87.93 4.40 83.53
24/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
8.4.1 33 kV Swithcyard LS 1 1076.27 161.44 914.83 1 1,076.27 53.81 1,022.45
8.4.2 33kv Switchyard civil LS 1 652.32 234.84 417.48 1 652.32 234.84 417.48
8.4.3 Fences LS 1 29.18 10.50 18.68 1 29.18 10.50 18.68
33kv POWER SUPPLY (local
8.5 10,718.27 1,607.73 9,110.54 10,718.27 535.91 10,182.35
supply)
8.5.1 33kV Transmission line double circuit LS 1 8432.62 1,264.89 7,167.73 1 8,432.62 421.63 8,010.99
9.1 Civil works for mini hydro LS 1 1357.58 488.73 868.85 1 1,357.58 488.73 868.85
9.2 Mini hydro plant and equipment LS 1 1378.11 206.72 1,171.39 1 1,378.11 68.91 1,309.20
12.1 Engineering and design LS 1 9861.66 1,972.33 7,889.33 1 9,861.66 1,972.33 7,889.33
25/32
( In 1,000USD)
Tendered Alternative
Item
Description Unit Total Local Foreign. Total Local Foreign.
no. QTY QTY
cost cost cost cost cost cost
Provisional sum 5% of the 16km
13 LS 1 5788.13 2,083.73 3,704.40 1 4,988.00 1,795.68 3,192.32
underground tunnel bid price.
Total 589,569.18 212,244.90 377,324.28 605,608.21 218,018.96 387,589.25
26/32
SHEDULES – 2D :
SCHEDULE OF PRICES FOR EMPLOYER‘S FACILITIES TO BE PROVIDED BY THE CONTRACTOR
The Bidder shall complete the following schedule of prices for all work covered by Logistical Support for Employer.
( In 1,000USD)
Table -1
No. Description Unit Qty Total Local Foreign.
Employer‘s facilities
1 Provision of Building 9,384.69 3378.49 6006.2
1.1 Service Building 2,241.19 806.83 1434.36
27/32
Table -1
2 For all House For the Employer representative LS 1 62.96 22.67 40.29
28/32
Table -1
2 All House For the Employer representative Month 48.5 30.98 11.15 19.83
3 All House For the Employer Month 48.5 77.18 27.78 49.4
2 All House For Employer representative Mont 48.5 32.52 11.71 20.81
3 All House For Employer Mont 48.5 81.04 29.17 51.87
5 Consumables for all housing, offices, canteen month 48 263.54 94.87 168.67
man.
6 Driver and unskilled labor 4000 1,026.88 369.68 657.2
month
Provisional and contingency budget to be
7 taken out 5% of the contract price offered by 1 Set
the Contractor
Total 16,748.26 6029.37 10718.89
29/32
SCHEDULE 3D - LIST OF FACILITY & SERVICES FOR THE EMPLOYER
( In 1,000USD)
1.5 Vehicle Operation & maintenance Land Cruiser 276000 Km 77.57 27.93 49.64
1.6 Vehicle Operation & maintenance Hi-Lux Pickup 2760000 Km 775.69 279.25 496.44
1.7 Vehicle Operation & maintenance Sedan type 300000 Km 84.31 30.35 53.96
2 Offices
3.1 Furniture
Managerial Desks With Computer Side Tables
3.1.1 8 No 9.34 3.36 5.98
Separate Drawers
3.1.2 High Back Chair 8 No 1.68 0.60 1.08
Office Desks With Computer Side Tables
3.1.3 50 No 46.68 16.80 29.88
Separate Drawers
3.1.4 Medium Back Chair 50 No 7.00 2.52 4.48
3.2 Equipment
Laptop Computers With Operating System,
3.2.1 4 No 6.35 2.29 4.06
Antivirus And MS Office Software;
Desktop Computers With UPS And With
3.2.2 Operating System, Antivirus And MS Office 26 No 30.34 10.92 19.42
Software;
3.2.3 Printers Laser Jet A4 (Black & White); 10 No 8.17 2.94 5.23
30/32
No Description Qty Unit Total Local Foreign
31/32
Schedule of Prices for 230 kv and 400kv Transmission Line
( In 1,000USD)
Transformers 150MVA,
8.2.2 LS 1 3976.3 596.45 3379.85
15KV/230KV (ODWF or OFWF)
Transformers 150MVA,
8.2.2 LS 1 5,617.45 842.62 4,774.83
15KV/400KV (ODWF or OFWF)
8.6 SWITCHYARD 7,149.02 2,573.65 4,575.37 23,434.47 4,483.15 18,897.81
8.6.2 Stand by Diesel generator LS 1 218.83 78.78 140.05 1 218.83 8.27 157.05
8.6.2 Switchyard civil work LS 1 2174.38 782.78 1,391.60 1 4,698.40 1,691.42 3,006.98
8.6.2 Fences LS 1 87.53 31.51 56.02 1 28.01 10.08 17.93
10 TRANSMISSIOON LINES 20,422.69 3,063.40 17,359.29 29,920.00 4,488.00 25,432.00
32/32