ID Task Task Name Duration Start Finish % Complete

Mode Half 2, 2021 Half 1, 2022 Half 2, 2022 Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025
1 Ansamblu rezidential NOVUM VIILOR-bloc A 154 days Mon 11/10/21 Thu 07/04/22 88%
2 anunt incepere lucrari Primarie Sector 5 3 days Mon 18/10/21 Wed 20/10/21 100%
3 anunt incepere lucrari ISC 3 days Wed 20/10/21 Fri 22/10/21 100%
4 proces verbal trasare limita proprietate 1 day Mon 08/11/21 Mon 08/11/21 100%
5 Organizarea de santier 94 days Mon 11/10/21 Thu 27/01/22 100%
57 Infrastructura 100 days Mon 08/11/21 Thu 03/03/22 100%
58 sapatura plot -4.25- 4.95 faza 1 21 days Mon 08/11/21 Wed 01/12/21 100%
70 sapatura plot -5.25 faza 1 31 days Fri 03/12/21 Fri 07/01/22 100%
83 armare radier zona bloc A zona -4.25- 4.95 24 days Mon 22/11/21 Sat 18/12/21 100%
93 instalatii radier zona bloc A 26 days Wed 24/11/21 Thu 23/12/21 100%
103 cofrare radier zona bloc A ( inclusiv base) 5 days Thu 16/12/21 Tue 21/12/21 100%
106 radier zona bloc A si parcare subterana 50 days Mon 22/11/21 Tue 18/01/22 100%
134 Verticale subsol parcare subterana 53 days Tue 21/12/21 Sat 19/02/22 100%
154 Placa peste subsol corp A si parcare subterana 16 days Mon 14/02/22 Thu 03/03/22 100%
164 Lucrari de incinta 39 days Mon 31/01/22 Wed 16/03/22 92%
178 Hidroizolatie pereti subsol 27 days Mon 14/02/22 Wed 16/03/22 100%
187 Bransament apa-canal faza 1 (interior proprietate)20 days Mon 21/02/22 Tue 15/03/22 4%
197 Suprastructura 32 days Wed 02/03/22 Thu 07/04/22 48%
198 Verticale parter bloc A 11 days Wed 02/03/22 Mon 14/03/22 94%
203 Umplutura pamant bloc A si parcare subterana 19 days Mon 07/03/22 Mon 28/03/22 0%
206 Placa peste parter corp A 13 days Wed 09/03/22 Wed 23/03/22 93%
207 cofrare placa si grinzi si scara P_ E1 10 days Wed 09/03/22 Sat 19/03/22 100%
208 comanda fier grinzi 1 day Mon 14/03/22 Mon 14/03/22 100%
209 aprovizionare fier grinzi 1 day Thu 17/03/22 Thu 17/03/22 100%
210 armare grinzi 1 day Fri 18/03/22 Fri 18/03/22 100%
211 armare placa -plasa inferioara 1 day Fri 18/03/22 Fri 18/03/22 100%
212 armare placa -plasa superioara si scara P_ E1
1 day Mon 21/03/22 Mon 21/03/22 90%
213 betonare placa 1 day Wed 23/03/22 Wed 23/03/22 0%
214 Verticale etaj 1-bloc A 20 days Wed 16/03/22 Thu 07/04/22 8%
215 lansare comanda 2 days Wed 16/03/22 Thu 17/03/22 100%
216 aprovizionare fier 2 days Thu 24/03/22 Fri 25/03/22 0%
217 realizare carcase 3 days Sat 26/03/22 Tue 29/03/22 0%
218 montaj elemente verticale 2 days Sat 26/03/22 Mon 28/03/22 0%
219 prelungire impamantare 1 day Tue 29/03/22 Tue 29/03/22 0%
220 cofrare verticale 7 days Tue 29/03/22 Tue 05/04/22 0%
221 betonare verticale 7 days Thu 31/03/22 Thu 07/04/22 0%