Professional Documents
Culture Documents
Lrs Resistencia Liquid Starter
Lrs Resistencia Liquid Starter
1. GENERAL
4. MAINTENANCE
SPECIFICATION SHEET
Characteristics Specifications
Maximum ambient temperature Type EPM
Maximum dissipation P= Capacity (litres)
Heat exchanger P= Manufacturer CSE Uniserve
Maximum entering water T= Motor power kW
temperature Rotor volts V
Minimum flow rate F= Rotor current A
IP rating of MV enclosure IP Supply volts V
IP rating of LV enclosure IP VA
General IP rating IP Control supply V
Adjustment of starting time (s) VA
Starting time (s) Electrolyte %
Number of consecutive starts from Type
cold
Number of starts h/max Quantity kg
Starting torque Oil (type)
Safety thermostat setting 85°C
Agitator thermostat °C Quantity
Pump thermostat °C Shorting contactor current A
Immersion heater thermostat setting °C Shorting contactor voltage V
Type
Isolating voltage phase/phase kV
Isolating voltage phase/earth kV
Marking
Auxiliary circuits
Single phase power kVA Painting: standard RAL 7032
Three-phase power kVA Other:
Fixing screws Standard
Stainless
Busbar finish Standard
Nickel
Other treatments
Anti-condensation heater
MV enclosure
LV enclosure
Immersion heater kW
1. GENERAL
1.4 Description 6
1.4.1 Electrolytic resistance 6
1.4.1.1 Tank 6
1.4.1.2 Electrodes 7
1.4.1.3 Control 8
1.4.1.4 Electrolyte 9
1.4.2 Enclosures 10
The EPM range of automatic liquid rotor starters is intended for use on large slip ring
and synchronous induction motors.
The range not only ensures excellent starting characteristics with smooth, stepless
acceleration to full load speed, but it can also be used for speed variation, torque control
and plug braking.
The principle employs an electrolytic resistance utilising moving electrodes in an
electrolyte solution.
A large resistance variation is obtained by displacing the electrodes in this solution.
The resistance is shorted out at the end of starting by a shorting contactor (except in case
of speed variation).
The MV enclosure may be supplied as a separate enclosure depending on the rotor data;
details would be provided with each quotation.
LV enclosure
MV enclosure
Electrolytic
resistance
Emptying
valve
Short-circuit contactor
According to IEC Publication 60947-4: AC2.
According to IEC Publication 60470: AC2.
Current type
The current flowing through the main circuits is AC with variable frequency according to
the slip. Its frequency should be lower than 50/60 Hz.
Neutral requirement
Neutral requirement is not applicable for the main circuits. The user may choose the
neutral requirement for the auxiliary circuits.
The unit is adjusted during cimmissioning and should only be serviced by CSE Uniserve
qualified personnel.
Over each EPM is a rating plate which shows the specifications of the unit.
Note: Some configurations require two rating plates.
1.4.1.1 Tank
Protection: IP54.
Capacity and dimensions are a function of the power (See installation manual).
The electrolyte level is monitored by float magnetic system enabling control and
activation of a fault relay with free contacts on the terminal (according to diagrams).
1.4.1.2 Electrodes
The three electrodes are arranged in a line and each comprises a fixed and a
moving electrode. Polypropylene compartmentalisation ensures isolation between
the phases.
The fixed electrodes, situated at the lower end of the isolated compartments, are fed
from an insulated copper bar.
Since this bar does not pass through the wall of the tank, it is impossible for the
electrolyte to leak.
This assembly, common to all three electrodes, constitutes the neutral point.
The low current density, in the order of 1 A per cm2, ensures an extremely long
electrode life.
Fixed
electrode
connection
Polypropylene Isolating
compartment electrode
guide
Moving
electrode
Fixed
electrode
Handwheel
Limit
switches Geared motor (or motor
or servomotor)
Mechanism
holder Worm screw
Fixed electrode
connection
Connection
protection
1.4.1.4 Electrolyte
The cooling of the electrolyte is effected by natural convection and forced circulation
(via the agitator) but in certain applications (permanent slip etc.), it is possible to
augment the heat dissipation by the use of an optional heat exchanger.
Power cable entry is carried out at the base. The cable guide plate of the enclosure
should be drilled during installation. Cables come onthe terminal outputs mounted
on front of the enclosure (see figure 4).
The controls are built-in the LV enclosure. This enclosure lies on the right part of the
MV enclosure. Connecting the control cables is performed at the base through the
back plate to be drilled. Control cables come on the screw terminals (see figure 5).
Protection: IP 54.
R1
R2
R3
AG ITATEUR TH 1 85°C
TH 2 40°C
BP
AG ITATO R
Figure 4: MV enclosure
Figure 5: LV enclosure
MV tunnel Contactor
enclosure
Motor 1 and
Coupling Motor 2
Resistance 1 Resistance 2
Cable entry
Cable entry
Motor 2
Motor 1
Normally a water-cooled exchanger is used for this purpose and an adequate supply
of water must be available for this purpose. The volume will vary depending on the
power and the temperature of the cooling water.
For certain speed control applications, the EPM is equipped as standard with a
servomotor and a suitably rated heat exchanger.
2.1 Overview 3
2.1.1 Preliminaries 3
2.1.2 Electrical installation 3
2.1.3 Electrical environment 3
2.1.4 Connections 3
2.1 Overview
2.1.1 Preliminaries
Installation and connection should be carried out with power off and should be
completed and checked bya suitably qualified personnel well acquainted with electrical
safety rules.
2.1.3 Electrical environment
2.1.4 Connections
• Open the EPM enclosures and read the connection diagrams delivered with the unit.
• Perform the control connections using the attached diagrams.
• Connect the starter to the motor rotor.
• Performance of the protection sheaths depends on the adaptation of the packing boxes
and their adaptation to the cables.
The user will have to drill and adapt the gland plate following all the safety
procedures and regulations.
• The unit should be earthed using the terminal provided for this purpose which is
marked with the earth symbol. This earth terminal is located on the MV enclosure.
M V contactor
M V bars
Table 1
For the EPM DUO, the two tanks should be star connected to the same earth.
Table 2 below shows the dimensions and weights for each model of the EPM range,
together with the floor fixing details.
A B C E F G Weight Tank
Type mm mm mm mm mm mm without with capacity
electrolyte electrolyte
EPM 1 1 700 2 000 1 230 856 600 1 620 720 kg 1 720 kg 1 000 litres
EPM 2 2 120 2 000 1 360 950 600 2 060 850 kg 2 350 kg 1 500 litres
EPM 3 2 510 2 290 1 660 1 190 600 2 440 1 230 kg 4 230 kg 3 000 litres
EPM 4 2 950 2 500 1 860 1 410 800 2 850 1 550 kg 6 550 kg 5 000 litres
) Note: The lifting eyes for the EPM 1 are mounted in the floor fixing holes.
The equipment is supplied suitable for use in the specified operating conditions, level
of protection, ambient temperature and other detailed environments (see
specification data).
To ensure correct operation, it is necessary to provide a free area around the EPM.
This space is necessary for two reasons:
- access for maintenance,
- the necessity to provide a sufficiently large volume of air to allow good heat
dissipation.
A space of 600 mm is necessary around the EPM starter to provide access to the
tank (for cover removal) and to avoid a reduction in heat dissipation. A
minimum of1 000 mm clear above the equipment is necessary for the same
reason. It is worthnoting that the contactor enclosure must be removed when
inspecting or replacingthe electrodes.
2.2.5 Warning
The foundation supporting the EPM must be designed to support the weight of the
starter.
The EPM 3 and EPM 4 DUO are delivered with the 2 tanks separated, the
mechanical coupling is supplied loose, as well as the electrical connections.
Assembly is required as follows:
Tunnel
Side E1 Side E2
R ef.E1 R ef.E2
The assembly plan supplied must be strictly adhered to in respect to the markings
shown in figures 2 and 3.
3
1
- The tanks must be firmly fixed to their plinths which must be level (see general
installation recommendations).
- Always refer to the instructions, fit the tunnel to the underside of the enclosures.
- Proceed with the assembly of the 3 copper busbars which connect the resistance
to the shorting contactor.
- Connect the control circuit in accordance with the wire numbers shown on each
terminal.
- Connect the earth circuit on both starters.
Tables 3 and 4 below indicate the weights and dimensions of each EPM DUO and
the floor fixings.
A B C G Weight Tank
Type mm mm mm mm without with capacity
electrolyte electrolyte
EPM 1 DUO 2 760 2 000 1 650 2 140 1 500 kg 3 500 kg 2 000 litres
EPM 2 DUO 2 945 2 000 2 030 2 325 1 800 kg 4 800 kg 3 000 litres
2.3.4 Environment
The equipment is supplied suitable for use in the specified operating conditions, level
of protection, ambient temperature and other detailed environments (see
specification data).
To ensure correct operation, it is necessary to provide a free area around the EPM.
This space is necessary for two reasons:
- access for maintenance,
- the necessity to provide a sufficiently large volume of air to allow good heat
dissipation.
A space of 600 mm is necessary around the EPM starter to provide access to the
tank (for cover removal) and to avoid a reduction in dissipation. A minimum of
1 000 mm clear above the equipment is necessary for the same reason. It is worth
noting that the contactor enclosure must be removed when inspecting or replacing
the electrodes.
2.3.6 Warning
The foundation supporting the EPM must be designed to support the weight of the
starter.
Tables 5 and 6 below show the weights and dimensions for each EPM and heat
exchanger together with the floor fixing details. Consult the data sheet for details on
the heat exchanger.
A B C D E F Weight Tank
Type mm mm mm mm mm mm without with capacity
max. electrolyte electrolyte
EPM 1 E 2 000 2 000 1 640 856 600 1 920 870 kg 1 870 kg 1 000 litres
EPM 2 E 2 410 2 000 1 735 950 600 2 350 1 000 kg 2 500 kg 1 500 litres
EPM 3 E 2 840 2 290 2 025 1 190 600 2 770 1 480 kg 4 480 kg 3 000 litres
EPM 4 E 3 270 2 500 2 245 1 410 800 3 180 1 800 kg 6 800 kg 5 000 litres
Exchanger type 1 2 3 4 5 6 7 8 9 10
I 36 350 350 350 400 400 520 520 520 520
J 420 420 420 420 420 420 420 420 420 420
K 175 337 627 1128 1139 1851 462 661 862 1162
L 429 591 881 1382 1370 2083 835 1035 1235 1535
Ø 140 140 140 140 200 200 285 285 285 285
NOTE: The commissioning commences after the EPM has been installed (see
installation instructions). For the DUO, in particular, all the operations described are
carried out only when the assembly of the starter is complete.
1) Check that the details on the rating plate correspond with those on the motor for which
the starter is to be used.
2) Power connections
Connect the cables from the rotor of the motor to the terminals marked R1, R2 and
R3 on the shorting contactor.
Check tightness of the bolts on the copper connections.
3) Control connections
4) Earthing
The equipment should be earthed via the terminal provided for this purpose.
The electrode drive motor may be, depending on the application, either a geared
motor, servomotor, or a motor whose speed is controlled by an inverter.
a) Set the handwheel in position.
b) Remove the wooden blocks which support the electrodes.
Handwheel
Figure 1
Blocks Moving electrode
carrier
Use the handwheel on the top of the electrode drive motor to bring the moving
electrode carrier to the intermediate position.
7) Before filling the tank, carry out the following operations carefully:
Ensure that the drain tap is fully closed.
If the EPM is fitted with a heat exchanger:
- Check that the electrolyte circulation valves are open on the heat exchanger.
- Check the cooling water circulation in the heat exchanger.
Precautions
Handling and storage
Use a well-ventilated room, away from reactive substances, such as acid, zinc,
quicklime, aluminium.
Protections
- Protect against inhalation (use a mask for protection from dust).
- Hands should be protected using gloves made of Neoprene or Rubber.
- Eyes should be protected by wearing goggles.
- Skin should be protected by wearing suitable clothes.
The user must follow the legislative, regulation and administrative procedures
related tosafety and protection concerning the human health and environment.
a) Untighten the fixing screws and remove the long cover. This operation
requires two operators to remove the long cover.
c) Fill the tank to approximately half way up the isolating compartments. Use
distilled water above 20°C (the electrolyte dissolves better in warm solution).
e) Fill a plastic container (polyvinyl) with 15 litres of warm water (30°C to 40°C).
the level of the tank with distilled water (observe the level
attached to the tank). During this operation, set the agitator
in service to ensure that the electrolyte is dissolved
completely.
c) If the starting torque is too weak: add electrolytic solution using the electrolyte
ADJUSTMENT DOSE, operation 2 from item 9.
d) If the starting torque is too high: empty some of the electrolyte and top up to the
level mark with water.
When the correct adjustment is obtained, tighten the fixing screws of the cover.
a) Check the operation of the agitator (or pump) which should operate at 40°C as
specified in the technical brochure.
b) Check the thermostat setting and the overload relay for the agitator (or pump)
motor.
c) Check the impeller drive and, if necessary the tightness of the connection
between the motor shaft and the impeller rod. If the EPM is fitted with a heat
exchanger, check the motor/pump drive and the effective circulation of the cooling
water.
d) If the EPM is fitted with an antifrost heater, check the setting of the thermostat and
its operation. The operating point is at + 5°C.
e) Exceeding the starting duty: the starting frequency is shown on the rating plate.
f) Check that the starting time is the same as that shown on the rating plate.
g) Ensure that the shorting contactor is operating properly: check each pole of the
contactor.
h) Check the tightness of all connections on the busbars and cables to the rotor of
the motor.
NOTE: The electrolyte overheat thermostat is factory set at 85°C and must not be
altered.
3.2.2 Failure of the moving electrode descent mechanism (electrode drive motor)
a) Check the connections of the motor windings and the supply voltage.
b) Check the connections to the motor terminals and the overload relay.
c) Check the mechanical coupling between the electrode drive motor and the worm
drive of the moving electrodes.
d) Check:
- continuity of the control circuit,
- control circuit supply voltage is present,
- the coil supply voltage.
NOTE: The starting sequence of the motor is correct if the moving electrodes are in
the raised position when the starter is energised.
4. MAINTENANCE
All maintenance operations relating to the electrical systems (MV contactor housing, LV
enclosure or motors) or moving mechanical parts (electrode system) should be carried out
with the supply disconnected. Particularly, opening of the MV and LV enclosure doors
should only be carried out with the security interlocks in place and operational.
c Check the tightness of all the connections: copper, cables and control circuits.
d Ensure that the short circuit contactor operates correctly. Check each pole of the
contactor: both fixed and moving contacts and the braids.
22
60
30
61
60 Geared motor plate gland plate
C
61 Motor screw coupling
4 27
Figure 1: Motor
20
A
Agitator
support 55
plate
Plate se
62
Motor/propeller axis
coupling
28
Guide
29
Figure 2: Agitator
Break
valves Electrical
connection
Pump motor
assembly
Connection
rings Assembly
fixing devices
d Level switch:
- Untighten the fixing screws from the worm drive cover 5 or unlock the bolts.
- Using the handwheel, bring the electrode control arm 17 to the low position.
- Block the assembly using 2 blocks.
- Remove the electrode drive motor 22 .
- Untighten the locking rings from the top and end ball thrust bearings C and D
(figure 1).
- Uncouple the worm drive nut 25 from the moving electrode control arm 17 .
- Lift the worm screw 27 vertically by turning to uncouple the worm drive nut.
- To remantle, operate as above in the reverse way.
A Handwheel 22 63 64 17
5
8
Figure 4
Changing the electrode system is an important operation. It is necessary to shut down and
immobilise the starter for several days.
In the case where the electrolyte is not reused, it is necessary to neutralise it, either
in the tank or by sending it to a specialist. Emptying is carried out by opening the
valve at the base of the tank. It is necessary to use a pump to remove the electrolyte
from the 3 isolated tanks.
Note: To disassemble the fixed and moving electrodes it is necessary to raise the electrical
enclosures by 300 mm. A wedge should be used between the bases of the enclosures and
the top of the tank to hold them in this position.
2 Dismantle mechanism cover: remove worm drive cover which is fixed either with
clips or screws.
We access the worm screw ensuring electrode moving. Dismantle the 4 electrode
cover plates made of PVC 63 and 64 by untightening the screws (figure 4).
3 MV and LV enclosures.
Remove the fixing devices from the enclosure inside the MV enclosure, access via
the doors or removable panels.
Remove the fixing devices from the isolating tubes 31 (figure 5).
Remove the connections supplying the current 65 (figure 5).
Lift the enclosure of 3 cm towards the front.
Lift the assembly of 300 mm and raise the electrode motor. Proceed to the
enclosure bottom and top blockings.
Remove the connection shrouds.
37
31
R1
R2
R3
65
Current supply
Enclosure fixing devices
Figure 5
4.4.2.3 Emptying and rinsing the tank and the 3 isolating tanks before disassembly
Move the electrodes to low position and insert a block between each moving and
fixed electrode.
- In the worm drive cover, undo the 6 screws B located in the U iron neutral point
support.
- Untighten the 6 hexagonal rods 24 from the moving electrodes.
- Undo fixing of the moving electrode guide support 44 . Undo the 6 nuts.
- Remove the guide support 32 , electrodes in place. Undo the 3 screws located
inside the U iron.
- Remove the moving electrode guides. Remove the moving electrodes.
B 37 17
Sheath
Neutral
point
support
24
31
44
39
32
16
15
C
A 23 33 34 35
a Fit connection bars 37 and fixed electrodes 15 to the support 31 using bolts and
Nylon locking nuts.
d Fit the fixed electrode assemblies in the blocks using nuts and locking nuts.
e Paste extension connection shrouds using silicone AS 310 LOCTITE, CSE Uniserve
partnumber: C 00029-000.
l Using the handwheel, raise or lower the moving electrodes manually. Penetration of
the electrodes should be of 40 mm approximately.
s Assemble the thermostat sheath, the level detector plate and the optional probe.
t Connect the control circuit cable, three-phase circuit, signalling circuit, thermostat,
level detector, optional probe and geared motor or motor or servomotor.
v Tighten the PE nuts inside the mechanism cover, link between LV enclosure and
mechanism cover.
a Movement of the electrodes: with the help of the handwheel situated on the top of
the geared motor bring the moving electrode carrier to the intermediate position.
When the supply is energised, the moving assembly should return to the up
position, if not reverse two phases.
b Mounting of the 4 PVC plates on the mechanism top.
e Security controls: thermostats, level detectors, top and bottom limit switches.
Maintenance explained above also applies to EPM DUO with the differences following: